MANAGED SOLUTIONS, INC.

                 Technical Relocation Services




                                                                                                                                                                                             1
Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
PROFESSIONAL SERVICES
                      Desktop & Laptop Disconnect / Reconnect

                                          Datacenter Racking & Cabling

                                                  Technical Lab Relocations

                                Certified California E-Waste Recycler

                                                   IT Asset Inventory Services

                                                                                                                                                                                             2
Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
PROFESSIONALISM ON EVERY LEVEL
             When working with Managed Solutions you can count on a higher
             level of Professionalism as our services are always provided with the
             following…


                         Experienced Technical Project Managers

                                   Skill Tested & Capable Technicians

                                Easily Identifiable Uniformed Teams

                          Industry Standard Best Practice Services
                                                                                                                                                                                              3
 Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
DESKTOP & LAPTOP RELOCATIONS
        From small start-up companies to enterprise organizations with
        thousands of employees, Managed Solutions has the skills, experience
        and resources to support your office or campus relocation.

                          Dedicated Project Management
                          Pre-Move Planning & Preparation
                          Asset Inventory Services
                          Anti-Static Computer Bags & Monitor Screen Covers
                          Pre-Move Inventory and Desktop Diagramming
                          Disconnect & Reconnect of Desktops & Laptops
                          Phone Disconnect & Reconnect
                          Velcro Cable Management
                          Post-Move Inventory Verification & QA
                          Printer Mapping
                          Post Move support
                          Weekly IMAC (Internal Moves, Adds & Changes)

                                                                                                                                                                                              4
 Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
DESKTOP & LAPTOP RELOCATIONS




             Pre-Move Inventory                                                                                                 Disconnect & Bag




               Monitor Protection                                                                                                 Reconnect & QA
                                                                                                                                                                                              5
 Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
PRE-MOVE USER INVENTORY


                     Visit Each                                                 IT Asset                                                   Make,
                     Employee                                                                                                             Model &
                                                                               Inventory                                                   Serial



                      Review &                                                Upload to                                                      Snap
                      Prepare                                                 Database                                                      Picture




                                                                                                                                                                                             6
Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
DATACENTER & LAB RELOCATIONS
        Whether supporting your office infrastructure from the closet turned
        server room, have a floor-to-ceiling, wall-to-wall datacenter with
        thousands of systems or multiple labs, Managed Solutions is the right
        choice for your relocation.
                          Dedicated Project Management
                          Last Down, First Up Server Relocation Planning & Execution
                          Asset Inventory Services
                          Minimized Downtime Approach to Relocations
                          Destination Rack Visio Elevations
                          I/O, Port & Cable Labeling
                          Destination Cart Inventory Process
                          Blanket Wrap, Anti-Static Bubble & Shrink Wrap
                          Disconnect & Reconnect of Servers & Switches
                          GPS Tracked & Air-Ride Vehicles
                          Rack & Stack & Rail Installations
                          Real Time Server Readiness Information
                          Velcro Cable Management
                          Post-Move Inventory Verification & QA                                                                                                                              7
 Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
DATACENTER - BUILD OUT




           Rack & Cabinet Installations                                                                                   Server & Switch Move




                Server Configuration                                                                                         Cable Management
                                                                                                                                                                                             8
Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
INTERNATIONAL EXPERIENCE


                                                                       Scotland

                                                                                                                                    Beijing




                                                                                                                                   Singapore




    - Beijing - 3,500 System Datacenter Relocation

            - Singapore - 950 System Datacenter Relocation

                       - Scotland - 500 System Datacenter Relocation

                                                                                                                                                                                             9
Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
NEXT STEPS
             Scope of Work Identification

                      Operations Team Introduction

                                Relocation Project Planning

                                         Execution of Relocation

                                                   Post Relocation Support
                                                                                                                                                                                             10
Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
QUESTIONS & ANSWERS




                                                                                                                                                                                             11
Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com

Managed Solutions Professional Services Presentation

  • 1.
    MANAGED SOLUTIONS, INC. Technical Relocation Services 1 Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
  • 2.
    PROFESSIONAL SERVICES Desktop & Laptop Disconnect / Reconnect Datacenter Racking & Cabling Technical Lab Relocations Certified California E-Waste Recycler IT Asset Inventory Services 2 Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
  • 3.
    PROFESSIONALISM ON EVERYLEVEL When working with Managed Solutions you can count on a higher level of Professionalism as our services are always provided with the following… Experienced Technical Project Managers Skill Tested & Capable Technicians Easily Identifiable Uniformed Teams Industry Standard Best Practice Services 3 Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
  • 4.
    DESKTOP & LAPTOPRELOCATIONS From small start-up companies to enterprise organizations with thousands of employees, Managed Solutions has the skills, experience and resources to support your office or campus relocation.  Dedicated Project Management  Pre-Move Planning & Preparation  Asset Inventory Services  Anti-Static Computer Bags & Monitor Screen Covers  Pre-Move Inventory and Desktop Diagramming  Disconnect & Reconnect of Desktops & Laptops  Phone Disconnect & Reconnect  Velcro Cable Management  Post-Move Inventory Verification & QA  Printer Mapping  Post Move support  Weekly IMAC (Internal Moves, Adds & Changes) 4 Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
  • 5.
    DESKTOP & LAPTOPRELOCATIONS Pre-Move Inventory Disconnect & Bag Monitor Protection Reconnect & QA 5 Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
  • 6.
    PRE-MOVE USER INVENTORY Visit Each IT Asset Make, Employee Model & Inventory Serial Review & Upload to Snap Prepare Database Picture 6 Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
  • 7.
    DATACENTER & LABRELOCATIONS Whether supporting your office infrastructure from the closet turned server room, have a floor-to-ceiling, wall-to-wall datacenter with thousands of systems or multiple labs, Managed Solutions is the right choice for your relocation.  Dedicated Project Management  Last Down, First Up Server Relocation Planning & Execution  Asset Inventory Services  Minimized Downtime Approach to Relocations  Destination Rack Visio Elevations  I/O, Port & Cable Labeling  Destination Cart Inventory Process  Blanket Wrap, Anti-Static Bubble & Shrink Wrap  Disconnect & Reconnect of Servers & Switches  GPS Tracked & Air-Ride Vehicles  Rack & Stack & Rail Installations  Real Time Server Readiness Information  Velcro Cable Management  Post-Move Inventory Verification & QA 7 Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
  • 8.
    DATACENTER - BUILDOUT Rack & Cabinet Installations Server & Switch Move Server Configuration Cable Management 8 Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
  • 9.
    INTERNATIONAL EXPERIENCE Scotland Beijing Singapore - Beijing - 3,500 System Datacenter Relocation - Singapore - 950 System Datacenter Relocation - Scotland - 500 System Datacenter Relocation 9 Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
  • 10.
    NEXT STEPS Scope of Work Identification Operations Team Introduction Relocation Project Planning Execution of Relocation Post Relocation Support 10 Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com
  • 11.
    QUESTIONS & ANSWERS 11 Shawn Robert Martin – Strategic Business Development - Managed Solutions, Inc. - 927 Wrigley Way – Milpitas, California 95035 - Mobile: 925-808-1907 – Website: www.managedsolutionsit.com