© Steve TennantConsultancy Ltd2010 1
Asia  Nuclear  Construction  
Conference
Learning  Lessons  From  Past  Capex  
Projects:  Coal  Plant  &  Billion  Dollar  
Infrastructure  Case  Study
By  Steve  Tennant  FRICS,  FCInstCES,  MAIB
Learning Lessons From Past
CAPEX Projects
Presentation  Review
§ Introduction  and  non  Nuclear  Apology
§ Current  challenges  that  Asia  New  Build  
is  facing
§ Lessons  I  have  learnt  from  past  
construction  projects
§ Construction  management  technologies  
&  best  practices
© Steve TennantConsultancy Ltd2010 2
Learning Lessons From Past
CAPEX Projects
Presentation  Review
§ Control  of  complex  builds  in  sometimes  
unpredictable  environments
§ Suggestions  to  reduce  time  and  risk  
exposure  on  your  next  billion  dollar  
project
© Steve TennantConsultancy Ltd2010 3
Learning Lessons From Past
CAPEX Projects
Introduction  &  Apology
§ An  Apology?
§ Qualifications  to  present?
© Steve TennantConsultancy Ltd2010 4
Learning Lessons From Past
CAPEX Projects
© Steve TennantConsultancy Ltd2010 5
Power Reclamation Metro Highway Dredging
Learning Lessons From Past
CAPEX Projects
© Steve TennantConsultancy Ltd2010 6
Integrated  
Gaming  Resort
BOT  
Concession
Tunnel Harbour  
Crossing
Container  
Port
Learning Lessons From Past
CAPEX Projects
Current  Challenges – Asia  New  Build
§ Standard  Challenges
§ Need  Political  &  Project  Champions
§ Finance
§ Regulatory
§ NIMBY  
© Steve TennantConsultancy Ltd2010 7
Learning Lessons From Past
CAPEX Projects
Current  Challenges – Asia  New  Build
§ Current  Challenges
§ Political  Control  of  Nuclear  Technology
§ Proven  Experience  in  Project  Delivery
§ Selection  of  Operational  Technology
§ Operational  Expertise
© Steve TennantConsultancy Ltd2010 8
Learning Lessons From Past
CAPEX Projects
Current  Challenges – Asia  New  Build
§ Current  Situation
§ “Asia  is  the  main  region  in  the  world  where  
electricity  generating  capacity  and  
specifically  nuclear  power  is  growing  
significantly”    -­ World  Nuclear  Association
© Steve TennantConsultancy Ltd2010 9
Learning Lessons From Past
CAPEX Projects
Current  Challenges – Asia  New  Build
§ Current  Situation
§ In  East  and  South  Asia  there  are  112  
nuclear  power  reactors  in  operation,  37  
under  construction  and  firm  plans  to  build  a  
further  84  (at  April  2010). Many  more  are  
proposed.”  -­ World  Nuclear  Association
© Steve TennantConsultancy Ltd2010 10
Learning Lessons From Past
CAPEX Projects
© Steve TennantConsultancy Ltd2001 11
Learning Lessons From Past
CAPEX Projects
Current  Challenges – Asia  New  Build
§ Current  Situation  -­ outside  Asia
§ USA  approves  2  new  sites  after  30  year  
hiatus
§ UK  approves  8  new  sites  after  15  year  
hiatus
§ Russia  domestic  &  export  sites
§ France  domestic  &  export  sites
§ +  others
© Steve TennantConsultancy Ltd2010 12
Learning Lessons From Past
CAPEX Projects
Current  Challenges – Asia  New  Build
§ Where  will  the  Builders  come  from?
§ USA?
§ Canada?
§ Russia?
§ France?
§ Japan?
§ China?
§ South  Korea?
© Steve TennantConsultancy Ltd2010 13
Impact of Nuclear
Technology Export
Restrictions?
Learning Lessons From Past
CAPEX Projects
Current  Challenges – Asia  New  Build
§ The  Key  Challenge
§ Sourcing  experienced  human  resources  
you  trust  and  can  communicate  with
• Nuclear  boom?
• Infrastructure  boom  in  Asia
• Competition  for  human  resources  between  
countries  and  projects
• Not  just  management,  but  supervisors  &  
tradesmen
© Steve TennantConsultancy Ltd2010 14
Learning Lessons From Past
CAPEX Projects
Lessons  that  I  have  learnt
§ Bad  news  flows  upwards  very  slowly
§ Collaboration  not  Confrontation
§ We  expect  Problems
§ We  do  not  like  Surprises
§ The  Client  wants  to  change  his  Mind,  
but  not  his  Budget  or  Completion  Dates
© Steve TennantConsultancy Ltd2010 15
Learning Lessons From Past
CAPEX Projects
Lessons  that  I  have  learnt
“  I  want  the  World’s  best  5  year  old  
railway,  delivered  to  me”
Russell  Black  Projects  Director  (Retired  2009)
MTR  Corporation  Limited    
© Steve TennantConsultancy Ltd2010 16
Learning Lessons From Past
CAPEX Projects
Construction  Management  &  Practices
§ Use  of  BIM
§ Use  of  IPS  &  Programme  Payment  
Milestones
§ Owner’s  pro-­active  Project  Management  
Team  or  Alliance  /  Construction  Management
§ Use  of  OCIP
© Steve TennantConsultancy Ltd2010 17
Learning Lessons From Past
CAPEX Projects
Construction  Management  &  Practices
§ Use  of  a  Project  Collaboration  and  online  
Project  Management  System
§ Use  of  Dispute  Resolution  Adviser
§ Use  of  Risk  Management
© Steve TennantConsultancy Ltd2010 18
Learning Lessons From Past
CAPEX Projects
Construction  Management  &  Practices
§ Use  of  BIM  -­ Building  Information  Modeling  
§ produces  and  manages  all  building-­related  data  
for  a  given  project  using  multi-­dimensional,  real-­
time,  dynamic  building  modeling  software  that  
generates  an  integrated,  digital  representation  
which  can  be  shared  by  multiple  project  partners.
§ The  building  information  model  is  a  central  
database  of  project  information  for  the  entire  
building  life  cycle,  from  design  and  construction  to  
operation.
© Steve TennantConsultancy Ltd2010 19
Learning Lessons From Past
CAPEX Projects
Construction  Management  &  Practices
§ Use  of  BIM  -­ Building  Information  Modeling  
§ Streamlines  communication  and  collaboration  between  
project  partners
§ Errors  are  detected  more  rapidly  and  can  be  corrected  prior  
to  fabrication  and/or  construction,  thus  avoiding  costly  
modifications
§ Provides  the  status  of  each  building  component
§ Estimates,  simulations,  planning  and  energy  analyses  are  
much  more  accurate
§ Pre-­construction  simulation  of  building  performance
§ I  have  used  Intelibuild as  BIM  service  provider
© Steve TennantConsultancy Ltd2010 20
Revit  Structure  – BIM  Model
Combined  Building  Services
MHS  B7  ULD  Paths  vs  ARC  Walls MHS  B7  ULD  Paths  vs  ARC  Walls
MHS  C7  ULD  Paths  vs  ARC  Walls MHS  C7  ULD  Paths  vs  ARC  Walls
Clash  Detection  
Learning Lessons From Past
CAPEX Projects
Construction  Management  &  Practices
§ Use  of  IPS  &  Programme  Payment  
Milestones
§ Interim  Payment  System  – Contractor  proposes  
his  required  monthly  cash  flow  with  his  tender.
§ Contractor  gets  paid  if  he  achieves  Programme  
Payment  Milestones
§ Facility  for  adjustment  due  to  missing  Payment  
Milestones  or  change  to  approved  Programme
§ Reduce  disputes  on  interim  payment
© Steve TennantConsultancy Ltd2010 24
Learning Lessons From Past
CAPEX Projects
Construction  Management  &  Practices
§ Owner’s  pro-­active  Project  Management  
Team  or  Alliance  /  Construction  Management
§ Direct  Ownership  of  Project,  speed  up  
decision  making
§ Split  works  into  smaller  packages,  eg City  
of  Dreams  US$3b,  700  +  works  contracts,  
increased  ability  to  accommodate  change.
§ Transparency  of  cost  and  time
© Steve TennantConsultancy Ltd2010 25
Learning Lessons From Past
CAPEX Projects
Construction  Management  &  Practices
§ Owner’s  pro-­active  Project  Management  
Team  or  Alliance  /  Construction  Management
§ Owner  needs  to  be  hands  on,  he  is  going  
to  operate  Project  afterwards
§ Owner  is  Contractor  or  Contractor  is  part  of  
Owner’s  team
§ Contractor  paid  fee  plus  shared  gain  /  pain
§ Project  is  managed,  not  fought  over
© Steve TennantConsultancy Ltd2010 26
Learning Lessons From Past
CAPEX Projects
Construction  Management  &  Practices
§ Use  of  OCIP  -­ Owner  Controlled  Insurance  Programme
§ Owner  insures  at  least  Works  &  Third  Party  
Liability
§ Economies  of  scale  by  buying  directly
§ Contractors  still  liable  for  deductibles,  
exclusions  and  risk  of  policy  coverage
§ Owner  can  assign  benefit  of  insurance  to  
Lenders  and  effect  DSU,  if  required  
© Steve TennantConsultancy Ltd2010 27
Learning Lessons From Past
CAPEX Projects
Construction  Management  &  Practices
§ Use  of  OCIP  -­ Owner  Controlled  Insurance  Programme
§ Policy  known  to  be  in  place  and  coverage  
effective  at  project  commencement
§ Waiver  of  cross  liabilities  between  co-­
insureds
§ Broadest  form  of  wording  generally  
available
§ Employer  must  keep  deductibles  affordable    
© Steve TennantConsultancy Ltd2010 28
Learning Lessons From Past
CAPEX Projects
Construction  Management  &  Practices
§ Use  of  a  Project  Collaboration  and  online  
Project  Management  System
§ secure  and  easy-­to-­use  system,  
§ accessed  by  all  project  participants  to  capture,  
manage,  track  and  protect  critical  information.  
RFIs,  approvals,  drawings,  tenders
§ handles  all  project  data  and  all  formal  project  
communication  with  other  parties.
© Steve TennantConsultancy Ltd2010 29
Learning Lessons From Past
CAPEX Projects
Construction  Management  &  Practices
§ Use  of  a  Project  Collaboration  and  online  
Project  Management  System
§ Paid  for  by  Employer
§ Used  free  of  charge  by  all  project  participants  in  
any  tier,  in  any  location
§ Auditable  with  complete  document  tracking  and  
history
§ No  excuse  for  not  having  current  information  
§ Systems  I  have  used;;  Aconex,  Incite
© Steve TennantConsultancy Ltd2010 30
Learning Lessons From Past
CAPEX Projects
Construction  Management  &  Practices
§ Use  of  Dispute  Resolution  Adviser
§ An  individual  person,  jointly  appointed  and  paid  for  
at  beginning  of  contract
§ Proactively  seeks  to  avoid  disputes  with  a  “D”
§ A  friend  to  the  Project  who  attends  progress  
meetings,  commercial  and  other  meetings.
§ Contractor,  Owner,  Consultants  or  Sub-­
Contractors  can  refer  matters  to  him
§ Can  only  suggest  or  recommend,  cannot  make  a  
contractual  decision  
© Steve TennantConsultancy Ltd2010 31
Learning Lessons From Past
CAPEX Projects
Construction  Management  &  Practices
§ Use  of  Risk  Management
§ Use  a  formal  documented  Risk  Management  
system  that:
• Starts  with  the  Design  Consultants
• Gets  handed  over  to  and  updated  by  the  Contractor
• And  is  handed  over  to  the  Operator
§ Evaluates  the  likelihood  and  consequences  of  a  
risk  occurring  so  that  you:
• Avoid,  Mitigate,  Transfer  or  Accept  the  risk
© Steve TennantConsultancy Ltd2010 32
Learning Lessons From Past
CAPEX Projects
Control  of  complex  builds  in  sometimes  
unpredictable  environments
§ Flexibility,  a  must
§ “…The  best-­laid  schemes  o'  mice  an'  men
Gang  aft  agley…”  From  To  a  Mouse  Robert  Burns  in  1785
§ “…  The  best  laid  schemes  of  mice  and  men
Go  often  askew…”  From  To  a  Mouse  Robert  Burns  in  1785
§ Unpredictability  creates  opportunity  for  risk  or  
reward
• City  Hall  MRT  Collapse
© Steve TennantConsultancy Ltd2010 33
Learning Lessons From Past
CAPEX Projects
Suggestions  to  reduce  time  and  risk  
exposure  on  your  next  billion  dollar  
project
§ You  have  seen  only  some  of  the  things  I  
keep  in  my  tool  box
§ Find  out  what  your  Project  Manager  
keeps  in  his!
§ Something  to  think  about  on  the  next  
slide
© Steve TennantConsultancy Ltd2010 34
Learning Lessons From Past
CAPEX Projects
© Steve TennantConsultancy Ltd2010 35
Dr. George Jergeas
PEng.Professor of
Project Management
University of
Calgary, Alberta.
April 2007
Learning Lessons From Past
CAPEX Projects
THE  END
© Steve TennantConsultancy Ltd2010 36

Learning Lessons From Past Capex Projects

  • 1.
    © Steve TennantConsultancyLtd2010 1 Asia  Nuclear  Construction   Conference Learning  Lessons  From  Past  Capex   Projects:  Coal  Plant  &  Billion  Dollar   Infrastructure  Case  Study By  Steve  Tennant  FRICS,  FCInstCES,  MAIB
  • 2.
    Learning Lessons FromPast CAPEX Projects Presentation  Review § Introduction  and  non  Nuclear  Apology § Current  challenges  that  Asia  New  Build   is  facing § Lessons  I  have  learnt  from  past   construction  projects § Construction  management  technologies   &  best  practices © Steve TennantConsultancy Ltd2010 2
  • 3.
    Learning Lessons FromPast CAPEX Projects Presentation  Review § Control  of  complex  builds  in  sometimes   unpredictable  environments § Suggestions  to  reduce  time  and  risk   exposure  on  your  next  billion  dollar   project © Steve TennantConsultancy Ltd2010 3
  • 4.
    Learning Lessons FromPast CAPEX Projects Introduction  &  Apology § An  Apology? § Qualifications  to  present? © Steve TennantConsultancy Ltd2010 4
  • 5.
    Learning Lessons FromPast CAPEX Projects © Steve TennantConsultancy Ltd2010 5 Power Reclamation Metro Highway Dredging
  • 6.
    Learning Lessons FromPast CAPEX Projects © Steve TennantConsultancy Ltd2010 6 Integrated   Gaming  Resort BOT   Concession Tunnel Harbour   Crossing Container   Port
  • 7.
    Learning Lessons FromPast CAPEX Projects Current  Challenges – Asia  New  Build § Standard  Challenges § Need  Political  &  Project  Champions § Finance § Regulatory § NIMBY   © Steve TennantConsultancy Ltd2010 7
  • 8.
    Learning Lessons FromPast CAPEX Projects Current  Challenges – Asia  New  Build § Current  Challenges § Political  Control  of  Nuclear  Technology § Proven  Experience  in  Project  Delivery § Selection  of  Operational  Technology § Operational  Expertise © Steve TennantConsultancy Ltd2010 8
  • 9.
    Learning Lessons FromPast CAPEX Projects Current  Challenges – Asia  New  Build § Current  Situation § “Asia  is  the  main  region  in  the  world  where   electricity  generating  capacity  and   specifically  nuclear  power  is  growing   significantly”    -­ World  Nuclear  Association © Steve TennantConsultancy Ltd2010 9
  • 10.
    Learning Lessons FromPast CAPEX Projects Current  Challenges – Asia  New  Build § Current  Situation § In  East  and  South  Asia  there  are  112   nuclear  power  reactors  in  operation,  37   under  construction  and  firm  plans  to  build  a   further  84  (at  April  2010). Many  more  are   proposed.”  -­ World  Nuclear  Association © Steve TennantConsultancy Ltd2010 10
  • 11.
    Learning Lessons FromPast CAPEX Projects © Steve TennantConsultancy Ltd2001 11
  • 12.
    Learning Lessons FromPast CAPEX Projects Current  Challenges – Asia  New  Build § Current  Situation  -­ outside  Asia § USA  approves  2  new  sites  after  30  year   hiatus § UK  approves  8  new  sites  after  15  year   hiatus § Russia  domestic  &  export  sites § France  domestic  &  export  sites § +  others © Steve TennantConsultancy Ltd2010 12
  • 13.
    Learning Lessons FromPast CAPEX Projects Current  Challenges – Asia  New  Build § Where  will  the  Builders  come  from? § USA? § Canada? § Russia? § France? § Japan? § China? § South  Korea? © Steve TennantConsultancy Ltd2010 13 Impact of Nuclear Technology Export Restrictions?
  • 14.
    Learning Lessons FromPast CAPEX Projects Current  Challenges – Asia  New  Build § The  Key  Challenge § Sourcing  experienced  human  resources   you  trust  and  can  communicate  with • Nuclear  boom? • Infrastructure  boom  in  Asia • Competition  for  human  resources  between   countries  and  projects • Not  just  management,  but  supervisors  &   tradesmen © Steve TennantConsultancy Ltd2010 14
  • 15.
    Learning Lessons FromPast CAPEX Projects Lessons  that  I  have  learnt § Bad  news  flows  upwards  very  slowly § Collaboration  not  Confrontation § We  expect  Problems § We  do  not  like  Surprises § The  Client  wants  to  change  his  Mind,   but  not  his  Budget  or  Completion  Dates © Steve TennantConsultancy Ltd2010 15
  • 16.
    Learning Lessons FromPast CAPEX Projects Lessons  that  I  have  learnt “  I  want  the  World’s  best  5  year  old   railway,  delivered  to  me” Russell  Black  Projects  Director  (Retired  2009) MTR  Corporation  Limited     © Steve TennantConsultancy Ltd2010 16
  • 17.
    Learning Lessons FromPast CAPEX Projects Construction  Management  &  Practices § Use  of  BIM § Use  of  IPS  &  Programme  Payment   Milestones § Owner’s  pro-­active  Project  Management   Team  or  Alliance  /  Construction  Management § Use  of  OCIP © Steve TennantConsultancy Ltd2010 17
  • 18.
    Learning Lessons FromPast CAPEX Projects Construction  Management  &  Practices § Use  of  a  Project  Collaboration  and  online   Project  Management  System § Use  of  Dispute  Resolution  Adviser § Use  of  Risk  Management © Steve TennantConsultancy Ltd2010 18
  • 19.
    Learning Lessons FromPast CAPEX Projects Construction  Management  &  Practices § Use  of  BIM  -­ Building  Information  Modeling   § produces  and  manages  all  building-­related  data   for  a  given  project  using  multi-­dimensional,  real-­ time,  dynamic  building  modeling  software  that   generates  an  integrated,  digital  representation   which  can  be  shared  by  multiple  project  partners. § The  building  information  model  is  a  central   database  of  project  information  for  the  entire   building  life  cycle,  from  design  and  construction  to   operation. © Steve TennantConsultancy Ltd2010 19
  • 20.
    Learning Lessons FromPast CAPEX Projects Construction  Management  &  Practices § Use  of  BIM  -­ Building  Information  Modeling   § Streamlines  communication  and  collaboration  between   project  partners § Errors  are  detected  more  rapidly  and  can  be  corrected  prior   to  fabrication  and/or  construction,  thus  avoiding  costly   modifications § Provides  the  status  of  each  building  component § Estimates,  simulations,  planning  and  energy  analyses  are   much  more  accurate § Pre-­construction  simulation  of  building  performance § I  have  used  Intelibuild as  BIM  service  provider © Steve TennantConsultancy Ltd2010 20
  • 21.
  • 22.
  • 23.
    MHS  B7  ULD Paths  vs  ARC  Walls MHS  B7  ULD  Paths  vs  ARC  Walls MHS  C7  ULD  Paths  vs  ARC  Walls MHS  C7  ULD  Paths  vs  ARC  Walls Clash  Detection  
  • 24.
    Learning Lessons FromPast CAPEX Projects Construction  Management  &  Practices § Use  of  IPS  &  Programme  Payment   Milestones § Interim  Payment  System  – Contractor  proposes   his  required  monthly  cash  flow  with  his  tender. § Contractor  gets  paid  if  he  achieves  Programme   Payment  Milestones § Facility  for  adjustment  due  to  missing  Payment   Milestones  or  change  to  approved  Programme § Reduce  disputes  on  interim  payment © Steve TennantConsultancy Ltd2010 24
  • 25.
    Learning Lessons FromPast CAPEX Projects Construction  Management  &  Practices § Owner’s  pro-­active  Project  Management   Team  or  Alliance  /  Construction  Management § Direct  Ownership  of  Project,  speed  up   decision  making § Split  works  into  smaller  packages,  eg City   of  Dreams  US$3b,  700  +  works  contracts,   increased  ability  to  accommodate  change. § Transparency  of  cost  and  time © Steve TennantConsultancy Ltd2010 25
  • 26.
    Learning Lessons FromPast CAPEX Projects Construction  Management  &  Practices § Owner’s  pro-­active  Project  Management   Team  or  Alliance  /  Construction  Management § Owner  needs  to  be  hands  on,  he  is  going   to  operate  Project  afterwards § Owner  is  Contractor  or  Contractor  is  part  of   Owner’s  team § Contractor  paid  fee  plus  shared  gain  /  pain § Project  is  managed,  not  fought  over © Steve TennantConsultancy Ltd2010 26
  • 27.
    Learning Lessons FromPast CAPEX Projects Construction  Management  &  Practices § Use  of  OCIP  -­ Owner  Controlled  Insurance  Programme § Owner  insures  at  least  Works  &  Third  Party   Liability § Economies  of  scale  by  buying  directly § Contractors  still  liable  for  deductibles,   exclusions  and  risk  of  policy  coverage § Owner  can  assign  benefit  of  insurance  to   Lenders  and  effect  DSU,  if  required   © Steve TennantConsultancy Ltd2010 27
  • 28.
    Learning Lessons FromPast CAPEX Projects Construction  Management  &  Practices § Use  of  OCIP  -­ Owner  Controlled  Insurance  Programme § Policy  known  to  be  in  place  and  coverage   effective  at  project  commencement § Waiver  of  cross  liabilities  between  co-­ insureds § Broadest  form  of  wording  generally   available § Employer  must  keep  deductibles  affordable     © Steve TennantConsultancy Ltd2010 28
  • 29.
    Learning Lessons FromPast CAPEX Projects Construction  Management  &  Practices § Use  of  a  Project  Collaboration  and  online   Project  Management  System § secure  and  easy-­to-­use  system,   § accessed  by  all  project  participants  to  capture,   manage,  track  and  protect  critical  information.   RFIs,  approvals,  drawings,  tenders § handles  all  project  data  and  all  formal  project   communication  with  other  parties. © Steve TennantConsultancy Ltd2010 29
  • 30.
    Learning Lessons FromPast CAPEX Projects Construction  Management  &  Practices § Use  of  a  Project  Collaboration  and  online   Project  Management  System § Paid  for  by  Employer § Used  free  of  charge  by  all  project  participants  in   any  tier,  in  any  location § Auditable  with  complete  document  tracking  and   history § No  excuse  for  not  having  current  information   § Systems  I  have  used;;  Aconex,  Incite © Steve TennantConsultancy Ltd2010 30
  • 31.
    Learning Lessons FromPast CAPEX Projects Construction  Management  &  Practices § Use  of  Dispute  Resolution  Adviser § An  individual  person,  jointly  appointed  and  paid  for   at  beginning  of  contract § Proactively  seeks  to  avoid  disputes  with  a  “D” § A  friend  to  the  Project  who  attends  progress   meetings,  commercial  and  other  meetings. § Contractor,  Owner,  Consultants  or  Sub-­ Contractors  can  refer  matters  to  him § Can  only  suggest  or  recommend,  cannot  make  a   contractual  decision   © Steve TennantConsultancy Ltd2010 31
  • 32.
    Learning Lessons FromPast CAPEX Projects Construction  Management  &  Practices § Use  of  Risk  Management § Use  a  formal  documented  Risk  Management   system  that: • Starts  with  the  Design  Consultants • Gets  handed  over  to  and  updated  by  the  Contractor • And  is  handed  over  to  the  Operator § Evaluates  the  likelihood  and  consequences  of  a   risk  occurring  so  that  you: • Avoid,  Mitigate,  Transfer  or  Accept  the  risk © Steve TennantConsultancy Ltd2010 32
  • 33.
    Learning Lessons FromPast CAPEX Projects Control  of  complex  builds  in  sometimes   unpredictable  environments § Flexibility,  a  must § “…The  best-­laid  schemes  o'  mice  an'  men Gang  aft  agley…”  From  To  a  Mouse  Robert  Burns  in  1785 § “…  The  best  laid  schemes  of  mice  and  men Go  often  askew…”  From  To  a  Mouse  Robert  Burns  in  1785 § Unpredictability  creates  opportunity  for  risk  or   reward • City  Hall  MRT  Collapse © Steve TennantConsultancy Ltd2010 33
  • 34.
    Learning Lessons FromPast CAPEX Projects Suggestions  to  reduce  time  and  risk   exposure  on  your  next  billion  dollar   project § You  have  seen  only  some  of  the  things  I   keep  in  my  tool  box § Find  out  what  your  Project  Manager   keeps  in  his! § Something  to  think  about  on  the  next   slide © Steve TennantConsultancy Ltd2010 34
  • 35.
    Learning Lessons FromPast CAPEX Projects © Steve TennantConsultancy Ltd2010 35 Dr. George Jergeas PEng.Professor of Project Management University of Calgary, Alberta. April 2007
  • 36.
    Learning Lessons FromPast CAPEX Projects THE  END © Steve TennantConsultancy Ltd2010 36