SlideShare a Scribd company logo
A
A
A
A
A
A
Float > 50 Days Float between 0 & 50 Days OR > 50 with declining float Float < 0 Trend - Positive Trend - Unchanged / Improving Trend - Negative No Impact Program Impact
PROJEK MASS TRANSIT LEMBAH KELANG - JAJARAN SUNGAI BULOH - KAJANG
GADANG ENGINEERING (M) SDN. BHD. : V2 - KOTA DAMANSARA STATION TO DATARAN SUNWAY
STATION
July-16
SCHEDULE SUMMARY KEY EVENTS STATUS HIGHLIGHTS & ISSUES OF CONCERN OVERALL STATUS OF V2
Float
Trend
Prog.
Impact
Progress Highlights
● Baseline Programme Rev. 07a submitted on 12th May 2015
Award Date 10-Jul-12
Item Date
Description DPS Date
Forecast /
Actual (A)
Var.
(Days)
Issues / Areas of Concern :
Completion Date 29-Sep-16
Commence 1st Bored Pile -
Preliminaries Load Test
5-Nov-12 22-Oct-12 14
Notice to Proceed 26-Jul-12
Commence Utilities Relocation - KD25
17-Jan-13 17-Jan-13 0
Baseline Programme
Problem :
Cause :
Consequence :
Action :
NIL
OVERALL PROGRESS (Rev.07a) Commence 1st Pile Cap - KD25 9-Feb-13
Overall Works Progress 99.71 97.86 1.85 Excavation at underpass 7-Feb-15
Item
this period
(Rev.07a)
last period
(Rev.07a)
Variance
Commence 1st Column - KD25
12-Mar-13 25-Mar-13
18-Jan-13 22
25-Aug-16
-13
-131
PRINCIPAL ACTIVITIES STATUS RISK MANAGEMENT :
Construction Complete 100 99.71 -0.29 Practical Completion 29-Feb-16
Delayed for Enternal works at Station
Slow work by sub-contractor
Delay impact to follow on works - overall station completion
Gadang to ensure any delays are mitigated by additional working hours or extra equipment
Item
Planned
(%)
Actual
(%)
Variance
SBG Launcing Pier KD25-DS07 17-Dec-14 21-Feb-15 -66
25-Feb-15 -49 Construction
Problem :
Cause :
Consequence :
Action :
Piling (No) 622 622 0
Principal Activity Planned qty Actual qty Variance
Pier (Nos) 140 140 0
Pilecap (Nos) 152 152 0
Box Girder Erection (span) 124 124 0
Pier Heads (Nos) 140 140 0
SAFETY, HEALTH & ENVIRONMENT OVERALL PROGRESS % S-CURVE SPI & EV TRENDS
Land Type
Land Date
Required
Forecast /
Actual
Trend
Item No. Trend
Government w/o encum' 10-Jul-12 31-Mar-12 (A) Major Incidents 0
Private w/o encum' 29-Sep-12 29-Sep-12 Stop work orders from PDP 0
Government w/ encum' 27-Jul-12 27-Jul-12 Notices from DOE or DOSH 0
People receiving SHE induction 0
Tool Box Talk 70
Private w/ encum' 31-Dec-12 31-Dec-12 NCR overdue for closure 10
PROJECT STATUS SUMMARY
CRITICAL PATH TOTAL FLOAT
CRITICAL PATH
LAND AQUISITION
File:D:MRTV2Monthly Report 31 July 2016KVMRT Dashboard V2 July 16.xlsxKVMRT Aug 16

More Related Content

Similar to KVMRT Dashboard V2 July 16.pdf

Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
WaqarHussain183
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust
 
Stockley Xmas 14 - Possession Workshop 25092014
Stockley Xmas 14 - Possession Workshop 25092014Stockley Xmas 14 - Possession Workshop 25092014
Stockley Xmas 14 - Possession Workshop 25092014
Thomas Ingrey
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
FaisalGulzar19
 
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust
 
Torkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfTorkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdf
SajidMumtazGurmani
 
SISCO - Presentation SABIC
SISCO - Presentation SABICSISCO - Presentation SABIC
SISCO - Presentation SABIC
Kochumon Mathew MBA,PGDEM,BBA
 
B12
B12B12
Manish Engineering Works
Manish Engineering WorksManish Engineering Works
Manish Engineering Works
lakeweekendresort
 
CONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATIONCONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATION
cyberyogi07
 
HKIS windows analysis delay-------------
HKIS windows analysis delay-------------HKIS windows analysis delay-------------
HKIS windows analysis delay-------------
engmts19861
 
SISCO - Presentation
SISCO - PresentationSISCO - Presentation
SISCO - Presentation
Talal Bayoumi CCNA, MCSE
 
Power Point BLCC End of year Review
Power Point BLCC End of year ReviewPower Point BLCC End of year Review
Power Point BLCC End of year Review
Tom Atkinson
 
Power Point BLCC End of year Review
Power Point BLCC End of year ReviewPower Point BLCC End of year Review
Power Point BLCC End of year Review
Tom Atkinson
 
Project Quality control Progress .pptx
Project Quality control  Progress .pptxProject Quality control  Progress .pptx
Project Quality control Progress .pptx
DILIP KUMAR M.Tech (ACT)
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust
 
Curriculum Vitae of M Holloway
Curriculum Vitae of M HollowayCurriculum Vitae of M Holloway
Curriculum Vitae of M Holloway
manuela holloway
 
AIWSP presentation SCM 3 11.09.2018 (1).ppt
AIWSP presentation SCM 3  11.09.2018 (1).pptAIWSP presentation SCM 3  11.09.2018 (1).ppt
AIWSP presentation SCM 3 11.09.2018 (1).ppt
Rajabdeen Amjath
 
15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...
15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...
15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...
Environmental Protection Agency, Ireland
 
Al Qasr Mall presentation
Al Qasr Mall presentationAl Qasr Mall presentation
Al Qasr Mall presentation
Mamdouh Attia
 

Similar to KVMRT Dashboard V2 July 16.pdf (20)

Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
Stockley Xmas 14 - Possession Workshop 25092014
Stockley Xmas 14 - Possession Workshop 25092014Stockley Xmas 14 - Possession Workshop 25092014
Stockley Xmas 14 - Possession Workshop 25092014
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
 
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
 
Torkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfTorkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdf
 
SISCO - Presentation SABIC
SISCO - Presentation SABICSISCO - Presentation SABIC
SISCO - Presentation SABIC
 
B12
B12B12
B12
 
Manish Engineering Works
Manish Engineering WorksManish Engineering Works
Manish Engineering Works
 
CONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATIONCONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATION
 
HKIS windows analysis delay-------------
HKIS windows analysis delay-------------HKIS windows analysis delay-------------
HKIS windows analysis delay-------------
 
SISCO - Presentation
SISCO - PresentationSISCO - Presentation
SISCO - Presentation
 
Power Point BLCC End of year Review
Power Point BLCC End of year ReviewPower Point BLCC End of year Review
Power Point BLCC End of year Review
 
Power Point BLCC End of year Review
Power Point BLCC End of year ReviewPower Point BLCC End of year Review
Power Point BLCC End of year Review
 
Project Quality control Progress .pptx
Project Quality control  Progress .pptxProject Quality control  Progress .pptx
Project Quality control Progress .pptx
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
Curriculum Vitae of M Holloway
Curriculum Vitae of M HollowayCurriculum Vitae of M Holloway
Curriculum Vitae of M Holloway
 
AIWSP presentation SCM 3 11.09.2018 (1).ppt
AIWSP presentation SCM 3  11.09.2018 (1).pptAIWSP presentation SCM 3  11.09.2018 (1).ppt
AIWSP presentation SCM 3 11.09.2018 (1).ppt
 
15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...
15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...
15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...
 
Al Qasr Mall presentation
Al Qasr Mall presentationAl Qasr Mall presentation
Al Qasr Mall presentation
 

Recently uploaded

22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
enizeyimana36
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
mamamaam477
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 

Recently uploaded (20)

22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 

KVMRT Dashboard V2 July 16.pdf

  • 1. A A A A A A Float > 50 Days Float between 0 & 50 Days OR > 50 with declining float Float < 0 Trend - Positive Trend - Unchanged / Improving Trend - Negative No Impact Program Impact PROJEK MASS TRANSIT LEMBAH KELANG - JAJARAN SUNGAI BULOH - KAJANG GADANG ENGINEERING (M) SDN. BHD. : V2 - KOTA DAMANSARA STATION TO DATARAN SUNWAY STATION July-16 SCHEDULE SUMMARY KEY EVENTS STATUS HIGHLIGHTS & ISSUES OF CONCERN OVERALL STATUS OF V2 Float Trend Prog. Impact Progress Highlights ● Baseline Programme Rev. 07a submitted on 12th May 2015 Award Date 10-Jul-12 Item Date Description DPS Date Forecast / Actual (A) Var. (Days) Issues / Areas of Concern : Completion Date 29-Sep-16 Commence 1st Bored Pile - Preliminaries Load Test 5-Nov-12 22-Oct-12 14 Notice to Proceed 26-Jul-12 Commence Utilities Relocation - KD25 17-Jan-13 17-Jan-13 0 Baseline Programme Problem : Cause : Consequence : Action : NIL OVERALL PROGRESS (Rev.07a) Commence 1st Pile Cap - KD25 9-Feb-13 Overall Works Progress 99.71 97.86 1.85 Excavation at underpass 7-Feb-15 Item this period (Rev.07a) last period (Rev.07a) Variance Commence 1st Column - KD25 12-Mar-13 25-Mar-13 18-Jan-13 22 25-Aug-16 -13 -131 PRINCIPAL ACTIVITIES STATUS RISK MANAGEMENT : Construction Complete 100 99.71 -0.29 Practical Completion 29-Feb-16 Delayed for Enternal works at Station Slow work by sub-contractor Delay impact to follow on works - overall station completion Gadang to ensure any delays are mitigated by additional working hours or extra equipment Item Planned (%) Actual (%) Variance SBG Launcing Pier KD25-DS07 17-Dec-14 21-Feb-15 -66 25-Feb-15 -49 Construction Problem : Cause : Consequence : Action : Piling (No) 622 622 0 Principal Activity Planned qty Actual qty Variance Pier (Nos) 140 140 0 Pilecap (Nos) 152 152 0 Box Girder Erection (span) 124 124 0 Pier Heads (Nos) 140 140 0 SAFETY, HEALTH & ENVIRONMENT OVERALL PROGRESS % S-CURVE SPI & EV TRENDS Land Type Land Date Required Forecast / Actual Trend Item No. Trend Government w/o encum' 10-Jul-12 31-Mar-12 (A) Major Incidents 0 Private w/o encum' 29-Sep-12 29-Sep-12 Stop work orders from PDP 0 Government w/ encum' 27-Jul-12 27-Jul-12 Notices from DOE or DOSH 0 People receiving SHE induction 0 Tool Box Talk 70 Private w/ encum' 31-Dec-12 31-Dec-12 NCR overdue for closure 10 PROJECT STATUS SUMMARY CRITICAL PATH TOTAL FLOAT CRITICAL PATH LAND AQUISITION File:D:MRTV2Monthly Report 31 July 2016KVMRT Dashboard V2 July 16.xlsxKVMRT Aug 16