DESIGN OF SUBSURFACE
DRAINAGE SYSTEM
SUBSURFACE DRAINAGE
Drains laid deep in the
ground
and covered
Fig: Subsurface drainage system-sectional view
Placed at suitable depth and grade
below the ground surface
Lowers the capillary surface and
water table
Aerates the root zone
1.Advantages of Subsurface Drains
Provides aeration to root zone
Improves soil structure and
maintains soil temperature
Avails land for early cultivation
Facilitates easy movement of farm
machines
Removes undesirable salts from
root zone
Decreases chances of flood hazards
Occupies no surface land
Small capacity drains are required
Less maintenance cost compared to
surface drains
2. Disadvantages of subsurface drains
Require high initial cost
Requires steeper gradient
Repair works are costly and
inconvenient
Only seepage water is removed
Construction is difficult
3. Subsurface drainage methods
Tile drains
Mole drains
Drainage wells
Deep open drains
Combination of tile and
mole drains
4. Investigations for subsurface drainage
Topographic map of the area
Data of soil physiochemical properties
Position of ground water table and its
fluctuation
Quality of groundwater
Logs of soil and subsurface material
Crops to be grown and their drainage
requirements
Irrigation practices and their
requirements
5. Groundwater studies for planning
subsurface drainage
3 parameters:
oDepth and fluctuation of groundwater
table
oQuality of groundwater
oHydraulic conductivity of the subsoil
material
DESIGN OF TILE DRAINAGE SYSTEM
Consists of :
1. Layout of the system
2. Depth and spacing of the drain
3. Size and grade of the tile lines
4. Material of tiles
5. Envelope materials and accessory
structures
6. Installation of tile drains
1. Layout of tile drainage system
Drainage system comprises of laterals,
main drains and an outlet
Laterals
Main drains
Outlet
Different layouts of tile drainage
system:
a) Natural system
b) Parallel system
c) Herringbone system
d) Grid iron system
e) Random system
f) Intercepting system
g) Double system
h) Grouping system
i) Composite system
j) Zig zag system
k) Sink hole system
a) Natural system:
b) Parallel system: c) Herringbone system:
d) Grid iron system: e) Random system:
f) Intercepting system:
g) Double system: h) Grouping system:
i) Composite system: j) Zigzag system:
2. Depth and spacing of tile drains
 Depth and spacing are closely inter related
 Depends on:
Texture of soil
Hydraulic conductivity
Types of crops grown
Extend of surface drainage
Outlet conditions
Topography of land
Salt content of soil
Agronomic practices
 Drain depth: From ground surface to the
bottom of the tile, usually 1-1.5m
 Tiles are placed above impermeable layer,
if any
 Deeper the drain, wider the spacing, lesser
the number of drains required
 Drain spacing-
’Hooghouts drain spacing formula’
S2 = 4K/R [H2-2hd+2Hd-h2]
where,
d- Depth to the impermeable layer
from the drain bottom
h- Height of water in the drain
H-Height of water in midway between 2
drains
S- Drain spacing
D-Distance from the impermeable layer to the
maximum height of water between the
drains
K- Hydraulic conductivity
R- Replenishment rate
3. Size and grade of the tile drains
 Drains are designed based on
Manning's formula
 Drains are laid on longitudinal slope:
0.05-3%
 Working grade: 0.2%
 Size of tiles pipes: 30-90cm long,
10-15cm diameter
Diameter of tile drains,
d = 5.3(Dc)0.375 A0.375 S-0.1875
where,
d- Internal diameter of tile drain, cm
Dc – Drainage coefficient, cm/day
A-Drainage area, ha
S- Hydraulic gradient or tile grade, m/m
4. Material of tiles
 Clay, Concrete, PVC/Plastic pipes, Bituminous fibre or
steel
 Pipe material should be:
Resistant to weathering and freezing
Have high density
Have sufficient strength to withstand static and
dynamic loads
Have uniformity in shape and wall thickness
5. Envelope materials and accessory
structures
a) Envelope materials:
 Materials that cover the drains placed
in less pervious strata
 Gravel, coarse sand etc.
 Prevents inflow of soil into the drains
 Increases effective drain diameter
Coarsest material
is placed
immediately
over the tile
Minimum thickness
of envelope: 7.5cm
Recommendations for gravel envelope
(USBR):
For uniform soils,
D50 of envelope/D50 of soil = 5 to 10
For graded soils,
D50 of envelope/ D50 of soil = 12 to 58
b) Manholes and sedimentation basins:
 Vertical structures
 Installed at regular intervals along the
tile lines
 Constructed by concrete or brick
masonry
 Helps in cleaning and inspection
A man can enter and
work within it
Placed about 60 cm
below ground surface
Covered by
concrete block
c) Inlet to tile drains:
 Allows water into the drain
 Two types:
 Blind inlet- cheaper but chances of
clogging
 Surface inlet- have provisions to
prevent the trash
entering into the drains but costly
Fig: Blind inlet
Fig: Surface inlet
d) Outlet for drains:
 Water from tile drains are discharged into
big size surface drains
 Either by gravity or pumping
 Gravity outlet- invert level of tile drain is
higher than fully supply level of surface
drain
 Pump outlet- bed level of the outlet is
higher tan the discharging tile drain
e) Installation of tile drains:
 Consists of:
 Excavation of a trench
 Laying the tile at predetermined grade,
depth and spacing
 Putting the envelope material and
backfilling the soil
 Installation of tile should start from out let
MULTIPLE WELL SYSTEM
MULTIPLE WELL SYSTEM
Multiple wells are installed in a common
area of influence
Cone of depressions overlap each other
Results in increased drawdown in each well
Provides more drainage effect
Fig: Multiple well system
Wells are arranged in various patterns
Isolated groups or continuous pattern
Suction lines of each well is connected
to a common pump
Krishna Gopal Samanta- Design of Sub Surface Drainage System.pptx

More Related Content

Similar to Krishna Gopal Samanta- Design of Sub Surface Drainage System.pptx

10-CE 408 Lining &Design of channel.pptx
10-CE 408 Lining &Design of  channel.pptx10-CE 408 Lining &Design of  channel.pptx
10-CE 408 Lining &Design of channel.pptx
HuzaifaZafar15
 
Drainage
DrainageDrainage
Drainage
Aamir Qaisrani
 
To be presented
To be presentedTo be presented
To be presented
Manas Thapa
 
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
VATSAL PATEL
 
chapt 6.pptx
chapt 6.pptxchapt 6.pptx
chapt 6.pptx
HCCTAndTechnologycom
 
Dewatering
DewateringDewatering
Dewatering
JNTUK
 
Dewatering.pptx
Dewatering.pptxDewatering.pptx
Dewatering.pptx
nileshsurti
 
Dewatering process and control in building projects
Dewatering process and control in building projectsDewatering process and control in building projects
Dewatering process and control in building projects
Umar Faruk
 
Storm drainage design
Storm drainage designStorm drainage design
Storm drainage design
dobariya axit
 
Drainage engineering presentation work done
Drainage engineering presentation work doneDrainage engineering presentation work done
Drainage engineering presentation work done
pavik13
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
Sravan Muguda
 
Module 5: Highway Drainage and Highway Economics
Module 5: Highway Drainage and Highway EconomicsModule 5: Highway Drainage and Highway Economics
Module 5: Highway Drainage and Highway Economics
DhananjayM6
 
Water logging.pptx
Water logging.pptxWater logging.pptx
Water logging.pptx
Emaan Sharma
 
dewateringtechniques 2.pptx
dewateringtechniques 2.pptxdewateringtechniques 2.pptx
dewateringtechniques 2.pptx
CarolTumaneng
 
BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4
Shree Swami atmanand saraswati inst. of technology, surat
 
Drainage Engineering (Drainage and design of drainage systems)
Drainage Engineering (Drainage and design of drainage systems)Drainage Engineering (Drainage and design of drainage systems)
Drainage Engineering (Drainage and design of drainage systems)
Latif Hyder Wadho
 
drainage-engineering-ppt.pdf
drainage-engineering-ppt.pdfdrainage-engineering-ppt.pdf
drainage-engineering-ppt.pdf
PkSong
 
Chapter Four -4 Highway Drainage slide.pdf
Chapter Four -4 Highway Drainage slide.pdfChapter Four -4 Highway Drainage slide.pdf
Chapter Four -4 Highway Drainage slide.pdf
rajundauliya
 
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
nik kin
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
ajinkya gaikwad
 

Similar to Krishna Gopal Samanta- Design of Sub Surface Drainage System.pptx (20)

10-CE 408 Lining &Design of channel.pptx
10-CE 408 Lining &Design of  channel.pptx10-CE 408 Lining &Design of  channel.pptx
10-CE 408 Lining &Design of channel.pptx
 
Drainage
DrainageDrainage
Drainage
 
To be presented
To be presentedTo be presented
To be presented
 
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
 
chapt 6.pptx
chapt 6.pptxchapt 6.pptx
chapt 6.pptx
 
Dewatering
DewateringDewatering
Dewatering
 
Dewatering.pptx
Dewatering.pptxDewatering.pptx
Dewatering.pptx
 
Dewatering process and control in building projects
Dewatering process and control in building projectsDewatering process and control in building projects
Dewatering process and control in building projects
 
Storm drainage design
Storm drainage designStorm drainage design
Storm drainage design
 
Drainage engineering presentation work done
Drainage engineering presentation work doneDrainage engineering presentation work done
Drainage engineering presentation work done
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Module 5: Highway Drainage and Highway Economics
Module 5: Highway Drainage and Highway EconomicsModule 5: Highway Drainage and Highway Economics
Module 5: Highway Drainage and Highway Economics
 
Water logging.pptx
Water logging.pptxWater logging.pptx
Water logging.pptx
 
dewateringtechniques 2.pptx
dewateringtechniques 2.pptxdewateringtechniques 2.pptx
dewateringtechniques 2.pptx
 
BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4
 
Drainage Engineering (Drainage and design of drainage systems)
Drainage Engineering (Drainage and design of drainage systems)Drainage Engineering (Drainage and design of drainage systems)
Drainage Engineering (Drainage and design of drainage systems)
 
drainage-engineering-ppt.pdf
drainage-engineering-ppt.pdfdrainage-engineering-ppt.pdf
drainage-engineering-ppt.pdf
 
Chapter Four -4 Highway Drainage slide.pdf
Chapter Four -4 Highway Drainage slide.pdfChapter Four -4 Highway Drainage slide.pdf
Chapter Four -4 Highway Drainage slide.pdf
 
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 

Recently uploaded

A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
DharmaBanothu
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
upoux
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理
uqyfuc
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
nedcocy
 
5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf
AlvianRamadhani5
 
Accident detection system project report.pdf
Accident detection system project report.pdfAccident detection system project report.pdf
Accident detection system project report.pdf
Kamal Acharya
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
ijaia
 
P5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civilP5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civil
AnasAhmadNoor
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
PreethaV16
 
Bituminous road construction project based learning report
Bituminous road construction project based learning reportBituminous road construction project based learning report
Bituminous road construction project based learning report
CE19KaushlendraKumar
 
openshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoinopenshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoin
snaprevwdev
 
DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...
DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...
DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...
OKORIE1
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
ijseajournal
 
Impartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 StandardImpartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 Standard
MuhammadJazib15
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
felixwold
 
Digital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptxDigital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptx
aryanpankaj78
 
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICSUNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
vmspraneeth
 

Recently uploaded (20)

A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
 
5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf
 
Accident detection system project report.pdf
Accident detection system project report.pdfAccident detection system project report.pdf
Accident detection system project report.pdf
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
P5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civilP5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civil
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
 
Bituminous road construction project based learning report
Bituminous road construction project based learning reportBituminous road construction project based learning report
Bituminous road construction project based learning report
 
openshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoinopenshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoin
 
DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...
DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...
DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
 
Impartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 StandardImpartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 Standard
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
 
Digital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptxDigital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptx
 
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICSUNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
 

Krishna Gopal Samanta- Design of Sub Surface Drainage System.pptx

  • 1. WELCOME Camellia Institute of Technology & Management KRISHNA GOPAL SAMANTA Roll No. : 25701322035 B.Tech in Civil Engineering Sem: 5th Year : 2023
  • 3. SUBSURFACE DRAINAGE Drains laid deep in the ground and covered
  • 4. Fig: Subsurface drainage system-sectional view
  • 5. Placed at suitable depth and grade below the ground surface Lowers the capillary surface and water table Aerates the root zone
  • 6. 1.Advantages of Subsurface Drains Provides aeration to root zone Improves soil structure and maintains soil temperature Avails land for early cultivation Facilitates easy movement of farm machines
  • 7. Removes undesirable salts from root zone Decreases chances of flood hazards Occupies no surface land Small capacity drains are required Less maintenance cost compared to surface drains
  • 8. 2. Disadvantages of subsurface drains Require high initial cost Requires steeper gradient Repair works are costly and inconvenient Only seepage water is removed Construction is difficult
  • 9. 3. Subsurface drainage methods Tile drains Mole drains Drainage wells Deep open drains Combination of tile and mole drains
  • 10. 4. Investigations for subsurface drainage Topographic map of the area Data of soil physiochemical properties Position of ground water table and its fluctuation Quality of groundwater
  • 11. Logs of soil and subsurface material Crops to be grown and their drainage requirements Irrigation practices and their requirements
  • 12. 5. Groundwater studies for planning subsurface drainage 3 parameters: oDepth and fluctuation of groundwater table oQuality of groundwater oHydraulic conductivity of the subsoil material
  • 13. DESIGN OF TILE DRAINAGE SYSTEM Consists of : 1. Layout of the system 2. Depth and spacing of the drain 3. Size and grade of the tile lines 4. Material of tiles 5. Envelope materials and accessory structures 6. Installation of tile drains
  • 14. 1. Layout of tile drainage system Drainage system comprises of laterals, main drains and an outlet Laterals Main drains Outlet
  • 15. Different layouts of tile drainage system: a) Natural system b) Parallel system c) Herringbone system d) Grid iron system e) Random system
  • 16. f) Intercepting system g) Double system h) Grouping system i) Composite system j) Zig zag system k) Sink hole system
  • 18. b) Parallel system: c) Herringbone system:
  • 19. d) Grid iron system: e) Random system:
  • 21. g) Double system: h) Grouping system:
  • 22. i) Composite system: j) Zigzag system:
  • 23. 2. Depth and spacing of tile drains  Depth and spacing are closely inter related  Depends on: Texture of soil Hydraulic conductivity Types of crops grown Extend of surface drainage
  • 24. Outlet conditions Topography of land Salt content of soil Agronomic practices  Drain depth: From ground surface to the bottom of the tile, usually 1-1.5m  Tiles are placed above impermeable layer, if any
  • 25.  Deeper the drain, wider the spacing, lesser the number of drains required  Drain spacing- ’Hooghouts drain spacing formula’ S2 = 4K/R [H2-2hd+2Hd-h2] where, d- Depth to the impermeable layer from the drain bottom h- Height of water in the drain
  • 26. H-Height of water in midway between 2 drains S- Drain spacing D-Distance from the impermeable layer to the maximum height of water between the drains K- Hydraulic conductivity R- Replenishment rate
  • 27. 3. Size and grade of the tile drains  Drains are designed based on Manning's formula  Drains are laid on longitudinal slope: 0.05-3%  Working grade: 0.2%  Size of tiles pipes: 30-90cm long, 10-15cm diameter
  • 28. Diameter of tile drains, d = 5.3(Dc)0.375 A0.375 S-0.1875 where, d- Internal diameter of tile drain, cm Dc – Drainage coefficient, cm/day A-Drainage area, ha S- Hydraulic gradient or tile grade, m/m
  • 29. 4. Material of tiles  Clay, Concrete, PVC/Plastic pipes, Bituminous fibre or steel  Pipe material should be: Resistant to weathering and freezing Have high density Have sufficient strength to withstand static and dynamic loads Have uniformity in shape and wall thickness
  • 30. 5. Envelope materials and accessory structures a) Envelope materials:  Materials that cover the drains placed in less pervious strata  Gravel, coarse sand etc.  Prevents inflow of soil into the drains  Increases effective drain diameter
  • 31. Coarsest material is placed immediately over the tile Minimum thickness of envelope: 7.5cm
  • 32. Recommendations for gravel envelope (USBR): For uniform soils, D50 of envelope/D50 of soil = 5 to 10 For graded soils, D50 of envelope/ D50 of soil = 12 to 58
  • 33. b) Manholes and sedimentation basins:  Vertical structures  Installed at regular intervals along the tile lines  Constructed by concrete or brick masonry  Helps in cleaning and inspection
  • 34. A man can enter and work within it Placed about 60 cm below ground surface Covered by concrete block
  • 35. c) Inlet to tile drains:  Allows water into the drain  Two types:  Blind inlet- cheaper but chances of clogging  Surface inlet- have provisions to prevent the trash entering into the drains but costly
  • 36. Fig: Blind inlet Fig: Surface inlet
  • 37. d) Outlet for drains:  Water from tile drains are discharged into big size surface drains  Either by gravity or pumping  Gravity outlet- invert level of tile drain is higher than fully supply level of surface drain  Pump outlet- bed level of the outlet is higher tan the discharging tile drain
  • 38. e) Installation of tile drains:  Consists of:  Excavation of a trench  Laying the tile at predetermined grade, depth and spacing  Putting the envelope material and backfilling the soil  Installation of tile should start from out let
  • 39.
  • 41. MULTIPLE WELL SYSTEM Multiple wells are installed in a common area of influence Cone of depressions overlap each other Results in increased drawdown in each well Provides more drainage effect
  • 43. Wells are arranged in various patterns Isolated groups or continuous pattern Suction lines of each well is connected to a common pump