Quality Control Plan
(QC-FO-28)
QCP No.: 67-1401-15*1016
Quality Control Plan for Helical Submerged Arc Welded Pipes
Client : … Project Spec. : …
QCP No. : 67-1401-15*1016 Customer : ‫ﺷﺮﮐﺖ‬
‫ﺳﺎز‬ ‫ﭘﻨﺎه‬
‫ا‬
‫ﯾ‬
‫ﺮان‬
Pipe Size(mm) : 1016*15 (OD*Thk) Steel Grade : X60(API-5L 2018)
Date of Issue : 2023.02.15(1401.11.26) Ref. Standard : ASTM-A252(2010)
Scope:This quality control plan defines the process of manufacturing, inspection and repair of Spiral Submerged Arc Welded Pipes piles.
Abbreviations
I (Inspection): Manufacturer indicate any inspection point of the process to assure conformance of the given requirements.
W (Witness Point): client’s inspector to be informed 3 day before starting the task and may proceed with past the witness point, if the client's inspector is not available.
R (Review Document): It is surveillance of a document for the purpose of verifying that an activity conforms the established requirements.
H (Hold Point): Client’s Inspector to be informed 3 working day before starting the task and work shall not be done without witness of Client’s Inspector.
SW(Spot witness): Witness is non- mandatory;the Manufacture shall inform employer incpectorthe start of activity date.the imployer inspector will arrenge to random inspection at
least part of ongoing activity
KSE : Kowsar Sanat Espadana/PNS:Panahsaz IRAN(Client)/TPA:GL(Inspector)/NIOEC:(OWNER)
Note: According to our production scheduled plan, these pipes will be produced in Kowsar Sanat Espadana Factory.
Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
Quality Control Plan
(QC-FO-28)
QCP No.: 67-1401-15*1016
1-Steel Coil Inspection and Testing
Document
Responsibility
Inspection Stage
Testing
Frequency
Measuring
Device
Reference
Standard
Acceptance Criteria
Task Name
Description
NIOEC
TPA/PNS
KSE
Mill Test
Certificate
Raw Material
Inspector
R
R
R
Each Coil
Review
API 5L(2018)
EN 10204(2004) Type 3.1
Certificate
Control
(1-1)
Material
inspection
Report
Raw Material
Inspector
R
W
I
Each Coil
Visual
ASTM A635(2004)
Section 13.1
1 Tag attached to each coil
Marking
(1-2)
Visual
Inspection
Report
Raw Material
Inspector
R
W
I
Each Coil
Visual
ASTM A700(1999)
4 Radial &
2 circumferential belt
Bundling
Report
Raw Material
Inspector
R
W
I
Each Coil
Visual
ASTM A635(2004)
Section 9
Coils shall be free of defect, oxide, scale
& oil
Surface
Inspection
Report
Raw Material
Inspector
R
W
I
Each Coil
Ultrasonic
Thickness meter
ASTM A635(1998)
Table A1.2
Min. : 14.7 mm
Max. : 15.3 mm
Thickness
(1-3)
Dimensional
Inspection
Report
Raw Material
Inspector
R
W
I
Each Coil
Steel Tape
Meter
DIN 1016(1986)
Section 5.7
Maximum 60 mm From One Side
Telescopic
Report
Raw Material
Inspector
R
W
I
2 Point of
Each Coil
Steel Tape
Meter
ASTM A635(2004)
Table A1.3
Min. : 1500 mm
Max. : 1538 mm
Width
Mill Test
Certificate
Manufacturer’
s Laboratory
R
R
R
Each Heat
…
API 5L(2018)
Table 4
Max: C:0.25% - Mn:1.4%
P:0.03% -S:0.03%- Nb+V+Ti:0.15%
Chemical
Analysis
(1-4)
Chemical
Properties
Only MTC
Manufacturer’
s Laboratory
R
R
R
Each Heat
…
API 5L(2018)
Table 6
YS: Min. 415 MPa
UTS:Min. 520 MPa
Tensile Test
(1-5)
Mechanical
Properties
…
…
…
…
…
…
…
…
Charpy
V-Notch
Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
Quality Control Plan
(QC-FO-28)
QCP No.: 67-1401-15*1016
2-Welding Material Inspection and Testing
Document
Responsibility
Inspection Stage
Testing
Frequency
Measuring
Device
Reference
Standard
Acceptance Criteria
Task Name
Description
NIOEC
TPA/PNS
KSE
Report
Raw Material
Inspector
SW
W
I
Each Pack
Visual
AWS-A5.1(2001)
Section 23 , 24
Shall be suitably packaged
and marked
Marking & Packaging
(2-1)
Shielded Metal
Arc Welding
Electrodes
Report
Raw Material
Inspector
SW
W
I
3 Electrode
of Each Lot
Caliper &
Visual
AWS-A5.1(2001)
Table 12 , Sec 20
Shall be free of defects
Diameter ,Length &
Covering
Mill Test
Certificate
Raw Material
Inspector
R
R
R
Each Lot
Review
AWS-A5.01 &
AWS-A5.1(2001)
EN 10204(2005) Type 3.1
Certificate Control
Mill Test
Certificate
Manufacturer’
s Laboratory
R
R
R
Each Lot
…
AWS-A5.1(2001)
Table 7
Max.: V:0.08%-Si:0.75%
Ni:0.3%-Cr:0.2% -Mo:0.3% -
Mn:1.6%
Weld Metal Analysis
Mill Test
Certificate
Manufacturer’
s Laboratory
R
R
R
Each Lot
…
AWS-A5.1(2001)
Table 3
Average Min.
27 J at -29 °C
Impact Test
Mill Test
Certificate
Manufacturer’
s Laboratory
R
R
R
Each Lot
…
AWS-A5.1(2001)
Table 2
YS: Min 399
UTS: Min 482 MPa
E%: Min: 22%
Tension Test
Report
Raw Material
Inspector
SW
W
I
Each Reel
Visual
AWS-A5.18(2001)
Section 21 , 22
Shall be suitably packaged
and marked
Marking & Packaging
(2-2)
Gas Metal Arc
Welding Wires
Report
Raw Material
Inspector
SW
W
I
Each Reel
Caliper &
Visual
AWS-A5.18(2001)
Section 16 , 17.4
Suitable coating
Diameter & Copper Coating
Mill Test
Certificate
Raw Material
Inspector
R
R
R
Each Lot
Review
AWS-A5.01 &
AWS-A5.18(2001)
EN 10204(2005) Type 3.1
Certificate Control
Mill Test
Certificate
Manufacturer’
s Laboratory
R
R
R
Each Lot
…
AWS-A5.18(2001)
Table 1
C:0.06-0.15%
Si:0.8-1.15%
Mn:1.4-1.85%
Wire Analysis
Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
Quality Control Plan
(QC-FO-28)
QCP No.: 67-1401-15*1016
2-Welding Material Inspection and Testing
Document
Responsibility
Inspection Stage
Testing
Frequency
Measuring
Device
Reference
Standard
Acceptance Criteria
Task Name
Description
NIOEC
TPA/PNS
KSE
Report
Raw Material
Inspector
SW
SW
I
Each Reel
Visual
AWS-A5.17(2001)
Section 16.7 , 17.4
Shall be suitably marked
Marking
(2-3)
Submerged Arc
Welding Wire &
Flux
Report
Raw Material
Inspector
SW
SW
I
Each Reel
Visual
AWS-A5.17(2001)
Section 16.6 , 17.3
Suitable Package
Packaging
Report
Raw Material
Inspector
SW
SW
I
Each Reel
Caliper
AWS-A5.17(2001)
Table 8M
Specified: ±0.06 mm
Wire
Diameter
Report
Raw Material
Inspector
SW
SW
I
Each Reel
Visual
AWS-A5.17(2001)
Section 16.2.4
Suitable Coating
Wire Copper
Coating
Mill Test
Certificate
Raw Material
Inspector
R
R
R
Each Lot
Review
AWS-A5.01 & AWS-
A5.17(2001)
EN 10204(2005) Type 3.1
Certificate
Control
Mill Test
Certificate
Manufacturer’s
Laboratory
R
R
R
Each Lot
…
AWS-A5.17(2001)
Table 1
C:0.06-0.15%
Si: Max 0.1%
Mn:0.8-1.25%
Wire
Analysis
Report
Raw Material
Inspector
SW
W
I
Each Lot
Sieve Shaker
DIN 760(1996)
Section 5
According to order & supplier
certificate
Flux Particle
Size
Mill Test
Certificate
Manufacturer’s
Laboratory
R
R
R
Each Lot
…
AWS-A5.17(2001)
Table 5M
YS: Min 400
UTS: 480-660 MPa
E%: Min: 22%
Weld Metal
Tension Test
Mill Test
Certificate
Manufacturer’s
Laboratory
R
R
R
Each Lot
…
AWS-A5.17(2001)
Table 6M
Average Min.
27 J at -40 °C
Weld Metal
Impact Test
Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
Quality Control Plan
(QC-FO-28)
QCP No.: 67-1401-15*1016
3-Pipe Production Process
Document
Responsibility
Inspection Stage
Frequency
Reference Standard
Acceptance Criteria
Task Name
Description
NIOEC
TPA/PNS
KSE
Report
Production
Department
SW
W
I
Each Pipe
AWWA-C200(2017)
…
Coil Longitudinal
Edge Trimming
(3-1)
Coil Preparation
Report
Production
Department
SW
W
I
Each Pipe
AWWA-C200(2017)
…
Pipe Forming
(3-2)
Pipe Production
Report
Production
Department
SW
W
I
Each Pipe
AWWA-C200(2017)
…
Pipe Cutting
Report
Production
Department
SW
W
I
Each Skelp End Weld
AWWA-C200(2017)
…
Skelp End Weld
Report
Production
Department
SW
W
I
Defected Pipes
ASME Section IX(2019)
…
SMAW & GMAW
(3-3)
Repair Welding
Report
Production
Department
SW
W
I
Each Pipe
ASME Section IX(2019)
…
Inside & Outside
(3-4)
Spiral Weld Seam
(SAW)
Report
Production
Department
SW
W
I
Each Skelp End Weld
ASME Section IX(2019)
…
Inside & Outside
Outside
(3-5)
Skelp End Weld
Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
Quality Control Plan
(QC-FO-28)
QCP No.: 67-1401-15*1016
4-Products Destructive Tests
Document
Responsibility
Inspection Stage
Testing Frequency
Measuring
Device
Reference
Standard
Acceptance Criteria
Task Name
Description
NIOEC
TPA/PNS
KSE
Report
First set of
mecanical
propertice in
3th party
labratory
SW
W
I
One tension test shall be
made on one length or
fraction thereof of each
size, or one piece of skelp
representing
each lot of 200 lengths or
fraction thereof of each
size
SANTAM
600 KN
ASTM-A252(2010)
Section 16.1
UTS: Min. 520 MPa
Transverse Weld
Tensile Test
(4-1)
Mechanical
Properties
Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
Quality Control Plan
(QC-FO-28)
QCP No.: 67-1401-15*1016
5-Products Non Destructive Inspection & Testing
Document
Responsibility
Inspection Stage
Testing Frequency
Measuring
Device
Reference
Standard
Acceptance Criteria
Task Name
Description
NIOEC
TPA/
PNS
KSE
Report
Level II VT
Man
SW
W
I
1- Whole of inside &
outside pipe body &
weld seam of each pipe
2-After repair
Cambridge &
V-Wack Gage
ASTM-A252(2010)
Section 14.1
The finished pipe piles shall
be reasonably straight and
shall not contain
imperfections in such
number or of such
character as to render the
pipe unsuitable for pipe piles.
VT Defect
(5-1)
Visual Inspection
Report
Hydro test
operator
R
W
I
Only pipes Have T-Joint
(Min 20% of all pipes)
Hydro tester
AWWA-C200(2017)
Section 5.2.1
Any leak at pressure:
P=15 (Bar)
Holding Time : (30 Sec)
Hydrostatic
Test
(5-2)
Hydrostatic Test
Report
Level II UT
Man
SW
W
I
3 Time per shift
Ultrasonic Flaw
Detector
ASME Section V
Article 5 (2019)
Echo height from 3 mm hole
set on 80% CRT & Threshold
on 50% of CRT
Calibration
(5-3)
Online Ultrasonic
Test
Report
Level II UT
Man
SW
W
I
100% of weld seam
each pipe
Ultrasonic Flaw
Detector
ASME Section VIII
Division 1(2019)
Threshold set on 50% of CRT
Test
Report
Level II UT
Man
SW
W
I
3 Time per shift
Ultrasonic Flaw
Detector
ASME Section V
Article 5 (2019)
…
Calibration
(5-4)
Manual Ultrasonic
Test Report
Level II UT
Man
SW
H
I
1-UT online indication
2-Skelp end weld
3-After repair
Ultrasonic Flaw
Detector
ASME Section VIII
Division 1(2019)
Appendix 12
Paragraph 12-3
1- Crack , LOF , LOP shall be
rejected.
2-any response that exceed
reference level and length
greater 6 mm shall be
consider as defect.
Test
Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
Quality Control Plan
(QC-FO-28)
QCP No.: 67-1401-15*1016
6-Products Final Inspection
Document
Responsibility
Inspection Stage
Testing
Frequency
Measuring
Device
Reference
Standard
Acceptance Criteria
Task Name
Description
NIOEC
TPA/PNS
KSE
Report
Final Inspector
SW
W
I
A & B End of Each
Pipe
Circumference
Meter
ASTM-A252(2010)
Section 12.2
Min.: 3160 mm
Max.: 3224 mm
Circumference
of Pipe End
(6-1)
Visual & Dimensional
Inspection
Report
Final Inspector
SW
W
I
Each Pipe
Ultrasonic
Thickness meter
ASTM-A252(2010)
Section 12.3
Min.: 13.125 mm
Thickness of
Pipe Body
Report
Final Inspector
SW
W
I
Each Pipe
Steel Tape
Meter
ASTM-A252(2010)
Section 13.1
Specified: 12000 ±25.4 mm
Single random lengths:4.88
to 7.62 mm, incl
Double random lengths:
over 7.62 m with minimum
average 10.67 m
Length
Report
Final Inspector
SW
W
I
A & B End of Each
Pipe
Steel Tape
Meter
API-5L(2018)
Table 10
Max.: 2% Outside Diameter
Out of
Roundness
Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
Quality Control Plan
(QC-FO-28)
QCP No.: 67-1401-15*1016
6-Products Final Inspection
Document
Responsibility
Inspection Stage
Testing
Frequency
Measuring
Device
Reference
Standard
Acceptance Criteria
Task Name
Description
NIOEC
TPA/PNS
KSE
Report
Final
Inspector
SW
W
I
Each Pipe
Cambridge &
V-Wack Gage
API -5L(2018)
Max.: 4.5 mm
Height of Weld
Reinforcement
(6-2)
Visual &
Dimensional
Inspection
Report
Final
Inspector
SW
W
I
A & B End of
Each Pipe
Cambridge &
Caliper
ASTM-
A252(2010)
Section 15.1
Angle:30°+5°
Bevel Angle &
…
Final
Inspector
SW
W
I
Each Pipe
Visual
ASTM-
A252(2010)
Section 22.1
Each length of pipe pile shall be legibly
marked by stenciling, stamping, or rolling
to show manufacturer brand,the outside
diameter, nominal wall thickness
Marking
…
Final
Inspector
SW
W
I
Each Pipe
Visual
AWWA-
C200(2017)
Sec 6.2
Pipe shall be loaded & handled with
proper equipment and in a manner to
prevent damage.
Handling &
Loading
Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
Quality Control Plan
(QC-FO-28)
QCP No.: 67-1401-15*1016
7-Documents & Records
Document
Responsibility
Inspection Stage
Task Name
Description
NIOEC
TPA/PNS
KSE
-
Pipe History
System
R
H
I
1. Visual Inspection Report
2. Hydrostatic test procedure
3. UT online & Manual UT test procedure
4. Final Inspection Report
5. NDT Personnel Qualification
6. Welder Qualification
7. Equipment & Instrument Calibration Certificates
8. Raw Material Certificates
9. Destructive Test Report
10. Hydrostatic Test Report
11. Pipe Specification
12. MPS
13. WPS
14. PQR
15. QCP
(7-1)
Final Book
Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant

More Related Content

Similar to Aproved QCP.pdf

INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdfINSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
Teddy Setiady
 
03c-eil-mr-3002-dd1059.pdf
03c-eil-mr-3002-dd1059.pdf03c-eil-mr-3002-dd1059.pdf
03c-eil-mr-3002-dd1059.pdf
AnonymousbIe9JSMphs
 
Resume of QA QC-Welding Engineer with 5+ years of exp
Resume of QA QC-Welding Engineer with 5+ years of expResume of QA QC-Welding Engineer with 5+ years of exp
Resume of QA QC-Welding Engineer with 5+ years of expVijay Raghavan
 
ARAVINTH(CV Aramco Approved)
ARAVINTH(CV Aramco Approved)ARAVINTH(CV Aramco Approved)
ARAVINTH(CV Aramco Approved)Aravinth Jai
 
Veerasekar api inspectorresume
Veerasekar api inspectorresumeVeerasekar api inspectorresume
Veerasekar api inspectorresume
kalyanasundaram veerasekaran
 
Veerasekar api inspectorresume
Veerasekar api inspectorresumeVeerasekar api inspectorresume
Veerasekar api inspectorresume
kalyanasundaram veerasekaran
 
Overview of Proc Process (Presented to SA).ppt
Overview of Proc Process (Presented to SA).pptOverview of Proc Process (Presented to SA).ppt
Overview of Proc Process (Presented to SA).ppt
israr740008
 
mohamed daowod cv
mohamed daowod cvmohamed daowod cv
mohamed daowod cv
MOHAMED DAOWOD
 
ANSI C12.1 Overview and Current Events
ANSI C12.1 Overview and Current EventsANSI C12.1 Overview and Current Events
ANSI C12.1 Overview and Current Events
TESCO - The Eastern Specialty Company
 
Txmer quality plan 2
Txmer quality plan 2Txmer quality plan 2
Txmer quality plan 2
Naresh Raju
 
2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)
2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)
2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)Rajeev Kumar
 
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
Tonni Bruce
 
Aramco Approved Welding Inspector Resume
Aramco Approved Welding Inspector ResumeAramco Approved Welding Inspector Resume
Aramco Approved Welding Inspector Resume
Robin Parayil
 
How to view the material certificate part 1
How to view the material certificate part 1How to view the material certificate part 1
How to view the material certificate part 1
Mohamed Farouk
 

Similar to Aproved QCP.pdf (20)

INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdfINSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
 
shan resume 2015.1.1
shan resume 2015.1.1shan resume 2015.1.1
shan resume 2015.1.1
 
03c-eil-mr-3002-dd1059.pdf
03c-eil-mr-3002-dd1059.pdf03c-eil-mr-3002-dd1059.pdf
03c-eil-mr-3002-dd1059.pdf
 
NONG YAO PROJECT SUBSEA VALVE Rev 0
NONG YAO PROJECT SUBSEA VALVE Rev 0NONG YAO PROJECT SUBSEA VALVE Rev 0
NONG YAO PROJECT SUBSEA VALVE Rev 0
 
Resume of QA QC-Welding Engineer with 5+ years of exp
Resume of QA QC-Welding Engineer with 5+ years of expResume of QA QC-Welding Engineer with 5+ years of exp
Resume of QA QC-Welding Engineer with 5+ years of exp
 
ARAVINTH(CV Aramco Approved)
ARAVINTH(CV Aramco Approved)ARAVINTH(CV Aramco Approved)
ARAVINTH(CV Aramco Approved)
 
Veerasekar api inspectorresume
Veerasekar api inspectorresumeVeerasekar api inspectorresume
Veerasekar api inspectorresume
 
Veerasekar api inspectorresume
Veerasekar api inspectorresumeVeerasekar api inspectorresume
Veerasekar api inspectorresume
 
R.Krishna Raj Sr. QC_Inspector-19-04-16
R.Krishna Raj Sr. QC_Inspector-19-04-16R.Krishna Raj Sr. QC_Inspector-19-04-16
R.Krishna Raj Sr. QC_Inspector-19-04-16
 
Overview of Proc Process (Presented to SA).ppt
Overview of Proc Process (Presented to SA).pptOverview of Proc Process (Presented to SA).ppt
Overview of Proc Process (Presented to SA).ppt
 
mohamed daowod cv
mohamed daowod cvmohamed daowod cv
mohamed daowod cv
 
Phairat-CV(2015)
Phairat-CV(2015)Phairat-CV(2015)
Phairat-CV(2015)
 
kiruba new resume
kiruba new resumekiruba new resume
kiruba new resume
 
ANSI C12.1 Overview and Current Events
ANSI C12.1 Overview and Current EventsANSI C12.1 Overview and Current Events
ANSI C12.1 Overview and Current Events
 
Txmer quality plan 2
Txmer quality plan 2Txmer quality plan 2
Txmer quality plan 2
 
2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)
2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)
2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)
 
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
 
Aramco Approved Welding Inspector Resume
Aramco Approved Welding Inspector ResumeAramco Approved Welding Inspector Resume
Aramco Approved Welding Inspector Resume
 
AMJResume.doc
AMJResume.docAMJResume.doc
AMJResume.doc
 
How to view the material certificate part 1
How to view the material certificate part 1How to view the material certificate part 1
How to view the material certificate part 1
 

Recently uploaded

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 

Recently uploaded (20)

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 

Aproved QCP.pdf

  • 1. Quality Control Plan (QC-FO-28) QCP No.: 67-1401-15*1016 Quality Control Plan for Helical Submerged Arc Welded Pipes Client : … Project Spec. : … QCP No. : 67-1401-15*1016 Customer : ‫ﺷﺮﮐﺖ‬ ‫ﺳﺎز‬ ‫ﭘﻨﺎه‬ ‫ا‬ ‫ﯾ‬ ‫ﺮان‬ Pipe Size(mm) : 1016*15 (OD*Thk) Steel Grade : X60(API-5L 2018) Date of Issue : 2023.02.15(1401.11.26) Ref. Standard : ASTM-A252(2010) Scope:This quality control plan defines the process of manufacturing, inspection and repair of Spiral Submerged Arc Welded Pipes piles. Abbreviations I (Inspection): Manufacturer indicate any inspection point of the process to assure conformance of the given requirements. W (Witness Point): client’s inspector to be informed 3 day before starting the task and may proceed with past the witness point, if the client's inspector is not available. R (Review Document): It is surveillance of a document for the purpose of verifying that an activity conforms the established requirements. H (Hold Point): Client’s Inspector to be informed 3 working day before starting the task and work shall not be done without witness of Client’s Inspector. SW(Spot witness): Witness is non- mandatory;the Manufacture shall inform employer incpectorthe start of activity date.the imployer inspector will arrenge to random inspection at least part of ongoing activity KSE : Kowsar Sanat Espadana/PNS:Panahsaz IRAN(Client)/TPA:GL(Inspector)/NIOEC:(OWNER) Note: According to our production scheduled plan, these pipes will be produced in Kowsar Sanat Espadana Factory. Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
  • 2. Quality Control Plan (QC-FO-28) QCP No.: 67-1401-15*1016 1-Steel Coil Inspection and Testing Document Responsibility Inspection Stage Testing Frequency Measuring Device Reference Standard Acceptance Criteria Task Name Description NIOEC TPA/PNS KSE Mill Test Certificate Raw Material Inspector R R R Each Coil Review API 5L(2018) EN 10204(2004) Type 3.1 Certificate Control (1-1) Material inspection Report Raw Material Inspector R W I Each Coil Visual ASTM A635(2004) Section 13.1 1 Tag attached to each coil Marking (1-2) Visual Inspection Report Raw Material Inspector R W I Each Coil Visual ASTM A700(1999) 4 Radial & 2 circumferential belt Bundling Report Raw Material Inspector R W I Each Coil Visual ASTM A635(2004) Section 9 Coils shall be free of defect, oxide, scale & oil Surface Inspection Report Raw Material Inspector R W I Each Coil Ultrasonic Thickness meter ASTM A635(1998) Table A1.2 Min. : 14.7 mm Max. : 15.3 mm Thickness (1-3) Dimensional Inspection Report Raw Material Inspector R W I Each Coil Steel Tape Meter DIN 1016(1986) Section 5.7 Maximum 60 mm From One Side Telescopic Report Raw Material Inspector R W I 2 Point of Each Coil Steel Tape Meter ASTM A635(2004) Table A1.3 Min. : 1500 mm Max. : 1538 mm Width Mill Test Certificate Manufacturer’ s Laboratory R R R Each Heat … API 5L(2018) Table 4 Max: C:0.25% - Mn:1.4% P:0.03% -S:0.03%- Nb+V+Ti:0.15% Chemical Analysis (1-4) Chemical Properties Only MTC Manufacturer’ s Laboratory R R R Each Heat … API 5L(2018) Table 6 YS: Min. 415 MPa UTS:Min. 520 MPa Tensile Test (1-5) Mechanical Properties … … … … … … … … Charpy V-Notch Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
  • 3. Quality Control Plan (QC-FO-28) QCP No.: 67-1401-15*1016 2-Welding Material Inspection and Testing Document Responsibility Inspection Stage Testing Frequency Measuring Device Reference Standard Acceptance Criteria Task Name Description NIOEC TPA/PNS KSE Report Raw Material Inspector SW W I Each Pack Visual AWS-A5.1(2001) Section 23 , 24 Shall be suitably packaged and marked Marking & Packaging (2-1) Shielded Metal Arc Welding Electrodes Report Raw Material Inspector SW W I 3 Electrode of Each Lot Caliper & Visual AWS-A5.1(2001) Table 12 , Sec 20 Shall be free of defects Diameter ,Length & Covering Mill Test Certificate Raw Material Inspector R R R Each Lot Review AWS-A5.01 & AWS-A5.1(2001) EN 10204(2005) Type 3.1 Certificate Control Mill Test Certificate Manufacturer’ s Laboratory R R R Each Lot … AWS-A5.1(2001) Table 7 Max.: V:0.08%-Si:0.75% Ni:0.3%-Cr:0.2% -Mo:0.3% - Mn:1.6% Weld Metal Analysis Mill Test Certificate Manufacturer’ s Laboratory R R R Each Lot … AWS-A5.1(2001) Table 3 Average Min. 27 J at -29 °C Impact Test Mill Test Certificate Manufacturer’ s Laboratory R R R Each Lot … AWS-A5.1(2001) Table 2 YS: Min 399 UTS: Min 482 MPa E%: Min: 22% Tension Test Report Raw Material Inspector SW W I Each Reel Visual AWS-A5.18(2001) Section 21 , 22 Shall be suitably packaged and marked Marking & Packaging (2-2) Gas Metal Arc Welding Wires Report Raw Material Inspector SW W I Each Reel Caliper & Visual AWS-A5.18(2001) Section 16 , 17.4 Suitable coating Diameter & Copper Coating Mill Test Certificate Raw Material Inspector R R R Each Lot Review AWS-A5.01 & AWS-A5.18(2001) EN 10204(2005) Type 3.1 Certificate Control Mill Test Certificate Manufacturer’ s Laboratory R R R Each Lot … AWS-A5.18(2001) Table 1 C:0.06-0.15% Si:0.8-1.15% Mn:1.4-1.85% Wire Analysis Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
  • 4. Quality Control Plan (QC-FO-28) QCP No.: 67-1401-15*1016 2-Welding Material Inspection and Testing Document Responsibility Inspection Stage Testing Frequency Measuring Device Reference Standard Acceptance Criteria Task Name Description NIOEC TPA/PNS KSE Report Raw Material Inspector SW SW I Each Reel Visual AWS-A5.17(2001) Section 16.7 , 17.4 Shall be suitably marked Marking (2-3) Submerged Arc Welding Wire & Flux Report Raw Material Inspector SW SW I Each Reel Visual AWS-A5.17(2001) Section 16.6 , 17.3 Suitable Package Packaging Report Raw Material Inspector SW SW I Each Reel Caliper AWS-A5.17(2001) Table 8M Specified: ±0.06 mm Wire Diameter Report Raw Material Inspector SW SW I Each Reel Visual AWS-A5.17(2001) Section 16.2.4 Suitable Coating Wire Copper Coating Mill Test Certificate Raw Material Inspector R R R Each Lot Review AWS-A5.01 & AWS- A5.17(2001) EN 10204(2005) Type 3.1 Certificate Control Mill Test Certificate Manufacturer’s Laboratory R R R Each Lot … AWS-A5.17(2001) Table 1 C:0.06-0.15% Si: Max 0.1% Mn:0.8-1.25% Wire Analysis Report Raw Material Inspector SW W I Each Lot Sieve Shaker DIN 760(1996) Section 5 According to order & supplier certificate Flux Particle Size Mill Test Certificate Manufacturer’s Laboratory R R R Each Lot … AWS-A5.17(2001) Table 5M YS: Min 400 UTS: 480-660 MPa E%: Min: 22% Weld Metal Tension Test Mill Test Certificate Manufacturer’s Laboratory R R R Each Lot … AWS-A5.17(2001) Table 6M Average Min. 27 J at -40 °C Weld Metal Impact Test Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
  • 5. Quality Control Plan (QC-FO-28) QCP No.: 67-1401-15*1016 3-Pipe Production Process Document Responsibility Inspection Stage Frequency Reference Standard Acceptance Criteria Task Name Description NIOEC TPA/PNS KSE Report Production Department SW W I Each Pipe AWWA-C200(2017) … Coil Longitudinal Edge Trimming (3-1) Coil Preparation Report Production Department SW W I Each Pipe AWWA-C200(2017) … Pipe Forming (3-2) Pipe Production Report Production Department SW W I Each Pipe AWWA-C200(2017) … Pipe Cutting Report Production Department SW W I Each Skelp End Weld AWWA-C200(2017) … Skelp End Weld Report Production Department SW W I Defected Pipes ASME Section IX(2019) … SMAW & GMAW (3-3) Repair Welding Report Production Department SW W I Each Pipe ASME Section IX(2019) … Inside & Outside (3-4) Spiral Weld Seam (SAW) Report Production Department SW W I Each Skelp End Weld ASME Section IX(2019) … Inside & Outside Outside (3-5) Skelp End Weld Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
  • 6. Quality Control Plan (QC-FO-28) QCP No.: 67-1401-15*1016 4-Products Destructive Tests Document Responsibility Inspection Stage Testing Frequency Measuring Device Reference Standard Acceptance Criteria Task Name Description NIOEC TPA/PNS KSE Report First set of mecanical propertice in 3th party labratory SW W I One tension test shall be made on one length or fraction thereof of each size, or one piece of skelp representing each lot of 200 lengths or fraction thereof of each size SANTAM 600 KN ASTM-A252(2010) Section 16.1 UTS: Min. 520 MPa Transverse Weld Tensile Test (4-1) Mechanical Properties Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
  • 7. Quality Control Plan (QC-FO-28) QCP No.: 67-1401-15*1016 5-Products Non Destructive Inspection & Testing Document Responsibility Inspection Stage Testing Frequency Measuring Device Reference Standard Acceptance Criteria Task Name Description NIOEC TPA/ PNS KSE Report Level II VT Man SW W I 1- Whole of inside & outside pipe body & weld seam of each pipe 2-After repair Cambridge & V-Wack Gage ASTM-A252(2010) Section 14.1 The finished pipe piles shall be reasonably straight and shall not contain imperfections in such number or of such character as to render the pipe unsuitable for pipe piles. VT Defect (5-1) Visual Inspection Report Hydro test operator R W I Only pipes Have T-Joint (Min 20% of all pipes) Hydro tester AWWA-C200(2017) Section 5.2.1 Any leak at pressure: P=15 (Bar) Holding Time : (30 Sec) Hydrostatic Test (5-2) Hydrostatic Test Report Level II UT Man SW W I 3 Time per shift Ultrasonic Flaw Detector ASME Section V Article 5 (2019) Echo height from 3 mm hole set on 80% CRT & Threshold on 50% of CRT Calibration (5-3) Online Ultrasonic Test Report Level II UT Man SW W I 100% of weld seam each pipe Ultrasonic Flaw Detector ASME Section VIII Division 1(2019) Threshold set on 50% of CRT Test Report Level II UT Man SW W I 3 Time per shift Ultrasonic Flaw Detector ASME Section V Article 5 (2019) … Calibration (5-4) Manual Ultrasonic Test Report Level II UT Man SW H I 1-UT online indication 2-Skelp end weld 3-After repair Ultrasonic Flaw Detector ASME Section VIII Division 1(2019) Appendix 12 Paragraph 12-3 1- Crack , LOF , LOP shall be rejected. 2-any response that exceed reference level and length greater 6 mm shall be consider as defect. Test Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
  • 8. Quality Control Plan (QC-FO-28) QCP No.: 67-1401-15*1016 6-Products Final Inspection Document Responsibility Inspection Stage Testing Frequency Measuring Device Reference Standard Acceptance Criteria Task Name Description NIOEC TPA/PNS KSE Report Final Inspector SW W I A & B End of Each Pipe Circumference Meter ASTM-A252(2010) Section 12.2 Min.: 3160 mm Max.: 3224 mm Circumference of Pipe End (6-1) Visual & Dimensional Inspection Report Final Inspector SW W I Each Pipe Ultrasonic Thickness meter ASTM-A252(2010) Section 12.3 Min.: 13.125 mm Thickness of Pipe Body Report Final Inspector SW W I Each Pipe Steel Tape Meter ASTM-A252(2010) Section 13.1 Specified: 12000 ±25.4 mm Single random lengths:4.88 to 7.62 mm, incl Double random lengths: over 7.62 m with minimum average 10.67 m Length Report Final Inspector SW W I A & B End of Each Pipe Steel Tape Meter API-5L(2018) Table 10 Max.: 2% Outside Diameter Out of Roundness Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
  • 9. Quality Control Plan (QC-FO-28) QCP No.: 67-1401-15*1016 6-Products Final Inspection Document Responsibility Inspection Stage Testing Frequency Measuring Device Reference Standard Acceptance Criteria Task Name Description NIOEC TPA/PNS KSE Report Final Inspector SW W I Each Pipe Cambridge & V-Wack Gage API -5L(2018) Max.: 4.5 mm Height of Weld Reinforcement (6-2) Visual & Dimensional Inspection Report Final Inspector SW W I A & B End of Each Pipe Cambridge & Caliper ASTM- A252(2010) Section 15.1 Angle:30°+5° Bevel Angle & … Final Inspector SW W I Each Pipe Visual ASTM- A252(2010) Section 22.1 Each length of pipe pile shall be legibly marked by stenciling, stamping, or rolling to show manufacturer brand,the outside diameter, nominal wall thickness Marking … Final Inspector SW W I Each Pipe Visual AWWA- C200(2017) Sec 6.2 Pipe shall be loaded & handled with proper equipment and in a manner to prevent damage. Handling & Loading Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant
  • 10. Quality Control Plan (QC-FO-28) QCP No.: 67-1401-15*1016 7-Documents & Records Document Responsibility Inspection Stage Task Name Description NIOEC TPA/PNS KSE - Pipe History System R H I 1. Visual Inspection Report 2. Hydrostatic test procedure 3. UT online & Manual UT test procedure 4. Final Inspection Report 5. NDT Personnel Qualification 6. Welder Qualification 7. Equipment & Instrument Calibration Certificates 8. Raw Material Certificates 9. Destructive Test Report 10. Hydrostatic Test Report 11. Pipe Specification 12. MPS 13. WPS 14. PQR 15. QCP (7-1) Final Book Manufacturer’s QC Manager : Mehdi Ghorbani Client’s Inspector Client’s Consultant