by Team LawBond 007
June 2015
An Exclusive
Interview With
SR Bernard Lo
Personal
Experience
Project
Involvement
Life Advice
Content
What is a quantity surveyor…………………….. 1
Interviewee Profile……………………………… 2
Company Profile………………………………… 3
Stages of Project………………………………… 4-5
Project Example…………………………………. 6-7
Task on Different Stages of Construction……… 8-10
Team Profile……………………………………… 11
What is a
Quantity Surveyor ?
A quantity surveyor (QS) is a professional working within
the construction industry concerned with construction costs and
contracts. They are the ECONOMIST in the construction indus-
try. As a quantity surveyor are responsible for the cost of any
building project from initial esti-
mates, right through to the final
acquisition of materials. Surveying
jobs and their associated roles are
varied but focused on providing
clients value for money while ad-
hering to the strict regulations
which govern every aspect of the
construction industry.
The day to day responsibilities of include roles inside the office,
on the construction site or in meetings with clients and other
project personnel.
“You can't get single things
without any single effort and
effort is depend other quality
and quantity of your desire.”
– Prakash Adhikari
1
2
QuantityQuantityQuantityQuantity
SurveyorSurveyorSurveyorSurveyor
of the Monthof the Monthof the Monthof the Month
Sr Bernard Lo is the Director of his company, Pe-
runding KK Bina Sdn. Bhd and is
a Registered Quantity Surveyor with the Board of Quantity
Surveyors Malaysia as well as a Full Corporate Member of The Institution of Surveyors Malaysia.
He graduated from Robert Gordon Institute of Technology Aberdeen, U.K and during
that time as a student he worked as a trainee Quantity Surveyor at a company called GD Walfords
(CQS) Partners in London. After graduating in the year 1990, Sr Bernard Lo worked in one of the
largest construction cost consultancy practice in Malaysia which was Juru Ukur Bahan Malaysia as a
Project Executive/Quantity Surveyor from the year 1990 till 1994. He then worked as a Senior
Quantity Surveyor in PQS Setia Konsult until Dec 2005 and in the following year his partner and
he made their company Perunding KK Bina Sdn. Bhd.
Sr Bernard Lo has experience in the Property Development and Construction Industry
for over 25 years until to date. His responsibilities as a Director Quantity Surveyor in his company
is to directly involve and personally attend to government and private projects undertaken by the
Firm from Inception to Finalisation of Project Account.
SR BERNARD LO
“World is NEVER sufficient for QS
even the economic down there is
always a way QS is required.”
—SR Bernard Lo
PERUNDING KK BINA SDN. BHD.
Lot 28, 2nd Floor, Block F,
Damai Plaza Phase IV,
88300 Kota Kinabalu,
Sabah.
Tel : 088 - 263720
Fax : 088 – 268720
About the
Company Profile
Perunding KK Bina Sdn Bhd. (“the
Firm”) was established in Malaysia on
26th
August 2008 with the Board of
Quantity Surveyors Malaysia (Lembaga
Juruukur Bahan Malaysia). The Firm
was previously practicing under the
name of Perunding KK Bina which had
been established since 1st
January
2006. The firm is also registered with
Kementerian Kewangan Malaysia.
Perunding KK Bina provides services
in the Property Development and
Construction Industry such as : -
1) Feasibility Studies.
2) Analysis and Preparation of
3) Financial Proposal.
4) Preliminary Estimate and Cost
Plan.
5) Bills of Quantities, Tender Docu-
ment and Contract Document.
6) Interim Valuation of Works.
7) Final Account.
8) Other Assignments in Relate to
the Construction Industry.
3
BIG PROJECT
5
Project title:
Construction of Dewan Kuliah
Pusat ke-2 dan Bangunan Pusat
Pengajian Pasca Siswazah di Uni-
versiti Malaysia Sabah
Client:
Kementerian Pengajian Tinggi Ba-
hagian Pembangunan
User:
Universiti Malaysia Sabah
Project director:
Pengarah Cawangan Kerja
Pengajian Tinggi
Project contractor:
Variasi Baru SDN. BHD
Contract sum:
Section 1 – RM 70 million
Section 2 – RM 91.6 million
Commencement:
17th
November 2006
Completion date:
Section 1 – 20th
February 2011
Section 2 – 15th
May 2011
6
Introducing
Dewan Kuliah Pusat ke-2 and
Bangunan Pusat Pengajian Pasca Siswazah
SMALL PROJECT
7
Project title:
CONSTRUCTION OF OFFICE, STORE AND GARAGE
FOR PERTUBUHAN PELADANG KAWASAN (PPK)
NABAWAN
Client:
LEMBAGA PERTUBUHAN PELADANG SABAH
Project Contractor:
ILHAMSAMA SDN. BHD.
Possession Date :
01 DECEMBER 2010
Completion Date:
15 FEBRUARY 2012
Besides big projects, Perunding KK Bina SDN. BHD. also works
on small projects for other companies and LEMBAGA PERTUB-
UHAN PELADANG SABAH is one of them. PERTUBUHAN
PELADANG KAWASAN (PPK) NABAWAN is actually one of the
farmers’ organization in Malaysia. The current project which taken by
Perunding KK Bina SDN. BHD. is located in Kota Kinabalu, Sabah.
1) The date of tender is on 30 AUG 2010 and after the tender sub-
mitted there will be an interview with the client.
2) In this construction, the value of work to be executed including
materials and goods is within RM1000.
3) Perunding KK Bina SDN. BHD. will get the Letter of Ac-
ceptance from his client if he is successful to get approved.
BEFORE CONSTRUCTION
1. Meeting with client and consultant team
2. Architect come out with design and proposal
3. Construction area is decided
4. Survey the site to make sure the boundary and working area
5. Preparation of list of materials
6. Act as go between contractor and government
7. Receive approval, which is Letter of Award (LOA)
8. Prepare contract document with everything inside pre-
construction (specification, condition of contract, performance
bond, insurance, term of payment)
9. Signing of client and contractor
8
DURING
CONSTRUCTION
1. When changes occur, time and cost may be affected. QS will sub-
mit a variation order (VO) to claim the cost and notice to claim
extension of time.
2. Manage relation and project between contractor and government
3. Be professional especially in payment
4. Visit construction site to ensure work is done according to con-
tract and schedule
5. Make recommendation of payment with professional chop of QS
and other professional consultant
9
AFTER CONSTRUCTION
1. Preparation of Certified of Practical Completion (CPC) by architect
2. Completion of all necessary documents
3. Preparation of final account
4. Adjust and cost according to architect’s drawings and instruction
5. QS will issue Statement of Final Account for all the party to sign and confirm
the Final Account
6. QS will submit claim to release money retention
7. The changes of cost throughout this project is minimum
10
11
ICI MAGAZINE

ICI MAGAZINE

  • 1.
    by Team LawBond007 June 2015 An Exclusive Interview With SR Bernard Lo Personal Experience Project Involvement Life Advice
  • 2.
    Content What is aquantity surveyor…………………….. 1 Interviewee Profile……………………………… 2 Company Profile………………………………… 3 Stages of Project………………………………… 4-5 Project Example…………………………………. 6-7 Task on Different Stages of Construction……… 8-10 Team Profile……………………………………… 11
  • 3.
    What is a QuantitySurveyor ? A quantity surveyor (QS) is a professional working within the construction industry concerned with construction costs and contracts. They are the ECONOMIST in the construction indus- try. As a quantity surveyor are responsible for the cost of any building project from initial esti- mates, right through to the final acquisition of materials. Surveying jobs and their associated roles are varied but focused on providing clients value for money while ad- hering to the strict regulations which govern every aspect of the construction industry. The day to day responsibilities of include roles inside the office, on the construction site or in meetings with clients and other project personnel. “You can't get single things without any single effort and effort is depend other quality and quantity of your desire.” – Prakash Adhikari 1
  • 4.
    2 QuantityQuantityQuantityQuantity SurveyorSurveyorSurveyorSurveyor of the Monthofthe Monthof the Monthof the Month Sr Bernard Lo is the Director of his company, Pe- runding KK Bina Sdn. Bhd and is a Registered Quantity Surveyor with the Board of Quantity Surveyors Malaysia as well as a Full Corporate Member of The Institution of Surveyors Malaysia. He graduated from Robert Gordon Institute of Technology Aberdeen, U.K and during that time as a student he worked as a trainee Quantity Surveyor at a company called GD Walfords (CQS) Partners in London. After graduating in the year 1990, Sr Bernard Lo worked in one of the largest construction cost consultancy practice in Malaysia which was Juru Ukur Bahan Malaysia as a Project Executive/Quantity Surveyor from the year 1990 till 1994. He then worked as a Senior Quantity Surveyor in PQS Setia Konsult until Dec 2005 and in the following year his partner and he made their company Perunding KK Bina Sdn. Bhd. Sr Bernard Lo has experience in the Property Development and Construction Industry for over 25 years until to date. His responsibilities as a Director Quantity Surveyor in his company is to directly involve and personally attend to government and private projects undertaken by the Firm from Inception to Finalisation of Project Account. SR BERNARD LO “World is NEVER sufficient for QS even the economic down there is always a way QS is required.” —SR Bernard Lo
  • 5.
    PERUNDING KK BINASDN. BHD. Lot 28, 2nd Floor, Block F, Damai Plaza Phase IV, 88300 Kota Kinabalu, Sabah. Tel : 088 - 263720 Fax : 088 – 268720 About the Company Profile Perunding KK Bina Sdn Bhd. (“the Firm”) was established in Malaysia on 26th August 2008 with the Board of Quantity Surveyors Malaysia (Lembaga Juruukur Bahan Malaysia). The Firm was previously practicing under the name of Perunding KK Bina which had been established since 1st January 2006. The firm is also registered with Kementerian Kewangan Malaysia. Perunding KK Bina provides services in the Property Development and Construction Industry such as : - 1) Feasibility Studies. 2) Analysis and Preparation of 3) Financial Proposal. 4) Preliminary Estimate and Cost Plan. 5) Bills of Quantities, Tender Docu- ment and Contract Document. 6) Interim Valuation of Works. 7) Final Account. 8) Other Assignments in Relate to the Construction Industry. 3
  • 6.
    BIG PROJECT 5 Project title: Constructionof Dewan Kuliah Pusat ke-2 dan Bangunan Pusat Pengajian Pasca Siswazah di Uni- versiti Malaysia Sabah Client: Kementerian Pengajian Tinggi Ba- hagian Pembangunan User: Universiti Malaysia Sabah Project director: Pengarah Cawangan Kerja Pengajian Tinggi Project contractor: Variasi Baru SDN. BHD Contract sum: Section 1 – RM 70 million Section 2 – RM 91.6 million Commencement: 17th November 2006 Completion date: Section 1 – 20th February 2011 Section 2 – 15th May 2011
  • 7.
    6 Introducing Dewan Kuliah Pusatke-2 and Bangunan Pusat Pengajian Pasca Siswazah
  • 8.
    SMALL PROJECT 7 Project title: CONSTRUCTIONOF OFFICE, STORE AND GARAGE FOR PERTUBUHAN PELADANG KAWASAN (PPK) NABAWAN Client: LEMBAGA PERTUBUHAN PELADANG SABAH Project Contractor: ILHAMSAMA SDN. BHD. Possession Date : 01 DECEMBER 2010 Completion Date: 15 FEBRUARY 2012 Besides big projects, Perunding KK Bina SDN. BHD. also works on small projects for other companies and LEMBAGA PERTUB- UHAN PELADANG SABAH is one of them. PERTUBUHAN PELADANG KAWASAN (PPK) NABAWAN is actually one of the farmers’ organization in Malaysia. The current project which taken by Perunding KK Bina SDN. BHD. is located in Kota Kinabalu, Sabah. 1) The date of tender is on 30 AUG 2010 and after the tender sub- mitted there will be an interview with the client. 2) In this construction, the value of work to be executed including materials and goods is within RM1000. 3) Perunding KK Bina SDN. BHD. will get the Letter of Ac- ceptance from his client if he is successful to get approved.
  • 9.
    BEFORE CONSTRUCTION 1. Meetingwith client and consultant team 2. Architect come out with design and proposal 3. Construction area is decided 4. Survey the site to make sure the boundary and working area 5. Preparation of list of materials 6. Act as go between contractor and government 7. Receive approval, which is Letter of Award (LOA) 8. Prepare contract document with everything inside pre- construction (specification, condition of contract, performance bond, insurance, term of payment) 9. Signing of client and contractor 8
  • 10.
    DURING CONSTRUCTION 1. When changesoccur, time and cost may be affected. QS will sub- mit a variation order (VO) to claim the cost and notice to claim extension of time. 2. Manage relation and project between contractor and government 3. Be professional especially in payment 4. Visit construction site to ensure work is done according to con- tract and schedule 5. Make recommendation of payment with professional chop of QS and other professional consultant 9
  • 11.
    AFTER CONSTRUCTION 1. Preparationof Certified of Practical Completion (CPC) by architect 2. Completion of all necessary documents 3. Preparation of final account 4. Adjust and cost according to architect’s drawings and instruction 5. QS will issue Statement of Final Account for all the party to sign and confirm the Final Account 6. QS will submit claim to release money retention 7. The changes of cost throughout this project is minimum 10
  • 12.