Call Girl Gurgaon Saloni 9711199012 Independent Escort Service Gurgaon
HVRA for healthcare facility
1. HAZARD , VULNERABILITY, RISK
ASSESSMENT(HVRA) FOR HEALTHCARE
FACILITIES DR LEE OI WAH
MD (UKM)
2. HVRA
• Hazard (H)
• Vulnerability (V)
• Risk (R)
• Concept of HVRA
• Purpose of HVRA
• Tools for HVRA
• Methodology to conduct HVRA
3. HAZARD (H)
Definition
A source or situation with the potential for harm in terms of
human injury or ill health, damage to property, damage to the
environment or a combination of these.
(ILO- OSHMS : 2001, MS OSHMS 1722 : 2003)
4. CATEGORIES OF POTENTIAL HEALTHCARE
HAZARDS
• Naturally occurring events
• Human related events
• Technologic events
• Hazardous materials events
5. HAZARD IDENTIFICATION
• Hazard identification—the process of recognizing that a
hazard exists and defining its characteristics.
7. RISK(R)
Definition
Probability or likelihood of harm occurring in relation to a
particular hazard & the magnitude or severity of harm.
• Risk—the chance of injury or loss as defined as a measure
of the probability [likelihood] and severity of an adverse
effect to health, property, the environment, or other things of
value.
• Risk analysis—the systematic use of information to identify
hazards and to estimate the chance for and severity of, injury or
loss to individuals or populations, property, the environment, or
other things of value
8. RISK ASSESSMENT
The risk of an event is assessed based on:
Threat to life and/or health
Disruption of services
Damage or failure possibilities
Loss of community trust
Financial impact and legal issues
American Society of Healthcare Engineering 2001
9. HVRA
• The Joint Commission, previously called the Joint
Commission of Accreditation of Healthcare Organizations
(JCAHO), requests an HVRA for organizations to
determine the focus of their emergency planning
• However,there is no specific tool nor method defined
10. PURPOSE OF HVRA
• The HVA is a tool used to evaluate the potential risks for a
facility
• It is not an evaluation of the potential for evacuation
• However, risks identified in the process may focus the
organization toward the need to mitigate and prepare for
circumstances that could include evacuation
• The purpose is a prioritization process that will result in a
risk assessment for “all hazards”.
• The focus is on organization planning and resources and
/or the determine that no action may be required. This is
an organization decision
11. WHY IS HVRA IMPORTANT ?
• Preparedness efforts, plans and resources are directly related
to the organization’s HVRA
• Engineering controls may occur as a result of HVRA thus
reducing risk for the work force
• Safety factors are considered
• Process promotes understanding of current resources that may
not have been known beyond the “expert”
• When a risk is identified in the HVRA that would potentially
result in an evacuation, the organization should focus on issues
that could impact the need to evacuate or to mitigate the risk.
Examples:
– Routes
– Locations
– Personal Protective Equipment (PPE)
– Communication to employees with special needs
– Special situations - management of family on site
12. MODELS FOR HVRA
• There are a number of models for an HVA.
• Two well known models are from
– American Society of Healthcare Engineering (ASHE)
– Kaiser Foundation (Kaiser Permanente)
• Both models can be adjusted to fit the organization.
• Security organizations and other vendors also market
HVA tools
14. PRINCIPLES OF KAISER 2001
• Based on mathematical formulas that are embedded in
the document (Excell tool-kit)
• The factors considered in the assessment includes the
assumption that the risk occurs at the worst possible time
and with a full patient census
• Threat events considered are:
- natural events
- human events
- technological events
- HAZMAT events
15. PRINCIPLES OF KAISER 2001
• 5 worksheets covering 4 groups of threats and summary
• Need to complete all worksheets (natural , technological ,
human and HAZMAT)
• The summary section will automatically provide your
specific and overall relative threat.
16.
17.
18.
19.
20.
21. KAISER PERMANENTE MODEL
• Kaiser model also includes the listed variables :
– Probability
– Human, property and business impacts, each
considered as a separate issue
– Response factors (preparedness , internal response &
external response)
22. PROBABILITY
Issues to consider for probability include, but not limited to :
Known risk
Historical data
Manufacturer / vendor statistics
Subjective evaluation / best estimate
Local Emergency Planning Committee input
23. MEASURE OF PROBABILITY
SCORE LIKELIHOOD OF OCCURENCE
0
(N/A)
Almost never happen before or in future
1
(Low)
Occasional or slight chance (little recorded
historical evidence and return interval of 10-30 years
is possible)
2
(Moderate)
Moderate (historical record with a frequency of 3 –
10 years)
3
(High)
Frequent ( have a high number of recorded or
anecdotal evidence , occurring every year )
25. HUMAN IMPACT
Issues to consider for human impact include , but are not
limited to :
Potential for staff death or injury
Patential for patient /visitor death or injury
Emotional / psychological impact
Local cultural norms
26. MEASURE OF HUMAN IMPACT (FATALITY)
SCORE NO OF FATALITY
0
(N/A)
No deaths or non-applicable
1
(Low)
Less than 5 deaths
2
(Moderate)
5-10 deaths
3
(High)
More than 10 deaths
27. MEASURE OF HUMAN IMPACT (INJURY)
SCORE NO OF INJURY
0
(N/A)
No injury or non-applicable
1
(Low)
Less than 10 injuries
2
(Moderate)
10-30 injuries
3
(High)
More than 30 injuries
28. PROPERTY IMPACT
Issues to consider for property impact include , but not
limited to :
Cost to replace
Cost to set up temporary replacement
Cost to repair
Time to recover
Environmental impact
29. MEASURE OF PROPERTY DAMAGE
SCORE EXTENT OF PROPERTY DAMAGE
0
(N/A)
No property damage or non-applicable
1
(Low)
Localized damage
2
(Moderate)
Localized severe damage (extending within a district
or community)
3
(High)
Widespread & severe damage (extending beyond a
single district)
30. MEASURE OF ENVIRONMENTAL IMPACT
SCORE EXTENT OF ENVIRONMENTAL IMPACT
0
(N/A)
Minimal impact or non-applicable
1
(Low)
Localized impact
2
(Moderate)
Localized severe impact (extending within a
district or community)
3
(High)
Widespread & severe impact (extending beyond
a single district)
31. BUSINESS IMPACT
Issues to consider for business impact include , but not
limited to :
Business interruption
Employees unable to report to work
Customers unable to reach facility
Company in violation of contractual agreements
Company in violation of statutory standards
Imposition of fines and penalties or legal costs
Interruption of critical supplies
Interruption of product distribution
Reputation and public image
Financial impact / burden
32. MEASURE OF BUSINESS IMPACT –
CLOSURE OF FACILITIES
SCORE EXTENT & DURATION OF CLOSURE
0
(N/A)
No evacuation or non-applicable
1
(Low)
Temporary relocation/ closure ( less than 24 hrs)
2
(Moderate)
Temporary relocation/ closure ( more than 24
hrs but less than 14 days)
3
(High)
Long term disruption or closure more than 14
days
33. MEASURE OF BUSINESS IMPACT – DISRUPTION OF
LIFELINES (WATER, GAS, POWER ETC)
SCORE DURATION OF DISRUPTION
0
(N/A)
No disruption or non-applicable
1
(Low)
Interruption (less than 24 hrs)
2
(Moderate)
Interruption ( 24 hrs – 72 hrs)
3
(High)
Interruption (more than 72 hrs)
34. RESPONSE
Issues to consider for response include , but not limited to :
Time to marshall an on-scene response
Scope of response capability / staff training
On-site support resources / supplies
Estimated severity & duration of the incidence
Historical evaluation of response success
Local Emergency Planning Committee input
35. PREPAREDNESS
Issues to consider for preparedness include, but not limited
to :
Status of current plan
Frequency of drills
Training status
Insurance
Availability of alternate sources for critical supplies /
services
36. MEASURE OF PREPAREDNESS –IAP/ CP
SCORE AVAILABILITY OF IAP/CP
0 Non-applicable
3
(Low)
IAP/CP available but outdated
2
(Moderate)
IAP / CP available and updated & communicated
to all staffs
1
(High)
IAP /CP available, up to date , communicated and
tested .
37. MEASURE OF PREPAREDNESS –TRAINING
OF STAFFS & DRILLS
SCORE TRAINING PROGRAMS & DRILLS
0 Non-applicable
3
(Low)
No structured programme or Training given in form
of briefing & orientation programme
2
(Moderate)
Annual Table-top exercise , evacuation exercise or
live drills involving only internal staffs
1
(High)
Annual Table-top exercise , evacuation exercise or
drills involving internal staffs and other agencies
38. INTERNAL RESOURCES
Issues to consider for internal resources include , but are not
limited to :
Types of supplies on hand / will they meet need?
Volumes of supplies on hand / will they meet need?
Staff availability & training
Coordination with MOB’s
Availability of back-up systems
Internal resources ability to withstand disasters /
survivability
39. MEASURE OF INTERNAL RESPONSE -
SUPPLIES
SCORE AVAILABILITY OF RESOURCES
0 Non-applicable
3
(Low)
Supplies not available
2
(Moderate)
Supplies available but unable to meet needs
1
(High)
Supplies available and able to meet needs
40. MEASURE OF INTERNAL RESPONSE –
BACK-UP SYSTEM
SCORE AVAILABILITY OF BACK-UP SYSTEM
0 Non-applicable
3
(Low)
No back-up system
2
(Moderate)
Back-up system unable to meet needs
1
(High)
Back-up system able to meet needs
41. EXTERNAL RESOURCES
Issues to consider for external resources include, but are not
limited to :
Types of agreements with community agencies / drills
Coordination with local and state agencies
Coordination with proximal health care facilities
Coordination with treatment specific facilities
City / County EMS services capabilities
Community volunteers / training
Vendor pre-incident response plans / contracts
Other community resources
42. MEASURE OF EXTERNAL RESPONSE – AGREEMENT
& COORDINATION WITH OTHER AGENCIES
SCORE AVAILABILITY OF AGREEMENT &
COORDINATION WITH OTHER AGENCIES
0 Non-applicable
3
(Low)
No standing agreement , no standing order for
dispatch or coordination with external agencies
2
(Moderate)
Existing mutual understanding to dispatch and
coordination
1
(High)
Formal agreement and well –documented SOP for
activation , dispatching and coordination with
external agencies
43. MEASURE OF EXTERNAL RESPONSE-VENDOR PRE-
INCIDENT RESPONSE PLANS & CONTRACT
SCORE AVAILABILITY OF VENDOR PRE-INCIDENT
RESPONSE PLANS & CONTRACT
0 Non-applicable
3
(Low)
No existing vendor pre-incident response plan or
contingency plan
2
(Moderate)
Existing vendor pre-incident response plan or
contingency plan
1
(High)
Existing vendor pre-incident response plan or
contingency plan plus additional back-up
contingency plan/contract with 3rd party providers