SlideShare a Scribd company logo
Gaurav Kumar Singh Rajput
Roll no- 15
Gaurav Kumar Singh Rajput
Roll No- 15
HAZARD ASSESSMENT
METHODOLOGY FOR LIQUID
HYDROCARBON TANK
Gaurav Kumar Singh Rajput
Roll No- 15
S8
School Of Engineering
PRESENTATION OUTLINE-
1. Tank fire accident scenario
2. Failure cause of tank accident
3. Jaipur fire
4. Barton solvent chemical plant
5. Preventive and protective measure
6. potential process and non-process hazard
7. Risk assessment flow diagram
8. Risk calculation
9. Discussion of methodology
10. References
Tank fire accident scenarios-
 Rim seal fire
 Spill on roof fire
 Full surface fire
 Bund or dyke wall
 Pontoon explosion
 Boilover
Failure cause of tank accident-
1. Operational error
 Tank overfilling
 Valves left open accidently
 Vent closed during loading unloading
2. Equipment/instrument failure
 Floating roof sunk
 Level indicator
 Discharge valve rupture
 Rusted vent valve
3. Lightning
 Poor grounding
4. Static electricity
 Damage seal
 Poor grounding
 Poor bonding
 Fluid transfer
5. Maintenance error
 Welding/cutting
 Circuit shortcut
 Non explosive-proof equipment used
6. Tank crack/rupture
 Poor soldering
 Corrosion
 Distortion/buckling
7. Piping rupture/leak
 Valve leaking
 Pump leak
 Cut accidentally
8. Safety supporting system
 Insufficient tank cooling
 electric power loss
 Firefighter water loss
9. Miscellaneous
 Earthquake
 Arson
 Extreme weather
Jaipur Fire
Jaipur IOC Terminal (oct 2009)
11 people lost their life
Fire in 11 tank, fire continue for 11 days
Cause-
 Basic operation procedure was not followed
 No control room
 Delay in emergency response team
 ESD from control room was not available
Recommendations-
 Engineering related
 Operation related
 Training related
 Procurement related
 Management related
By M.B Lal committee
Standard operating sequence Likely sequence
1. Ensure MOV and HOV are
closed
2. Reverse the position of
hammer blind valve
3. Open the HOV
4. Open MOV
1. MOV opened first
2. Hammer blind valve opened
3. Leakage started
Barton Solvents Chemical Plant Accident
Barton solvent chemical plant Kansas (July 2007)
Evacuation of 6000 residents, destroyed the tank farm
Cause-
 Faulty design of level gauge.
 The tank contained an ignitable vapour-air mixture in its head
space.
 Stop-start filling, air in transfer pipe, sediment and water.
Recommendations-
 Add inert gas to the head space
 Avoid loose linkage
 Anti static additives
 Reduce fluid pumping velocity
 Require additional manufacture guidance
 By pass conductor
Preventive and protection measure-
1. Design
 Follow engineering standard and regulations
 Modification in design
 Dyke, Bund
2. Maintenance
 Routine inspection
 Periodic proof testing
 Use proper equipment
 Use explosion-proof tools
3. Equipment
 Follow engineering standard
 Lightning protection system
 ROSOV
 Temperature monitoring device
4. Safety supporting system
 Fire detection and alarm system
 Fire fighting system
 Tank cooling system
 Emergency response plan
 CCTV equipment
5. Miscellaneous
 Safeguarding
 Good house keeping/No smoking
 Protection from DOMINO effect, areal electrical
power lines, extreme weather, mechanical stress
and vehicle bumping.
POTENTIAL PROCESS AND NON-PROCESS
HAZARD-
RISK ASSESSMENT FLOW DIAGRAM-
RISK CALCULATION-
 Risk due to hazard at storage tank terminal and its
surrounding is composed of summation of all risk
given no escalation of event of undesired event and
all risk given an escalation.
Risk= Risk/ No Escalation + Risk/ Escalation
The result of the quantitative risk analysis are commonly represented by
the following parameter-
1. Individual risk
2. Societal risk
-Individual risk is the risk that an individual remaining at a
particular spot would face from the plant facility.
The individual risk value is a frequency of fatality usually
chance per million per year and represent on ALARP
triangle.
-Societal risk is the risk on number of people who might
be affected by hazardous incident and represent on F-N
(Frequency-Number curve) curve .
Risk Analysis
Qualitative Risk
Analysis
Quantitative Risk
Analysis
ALARP Triangle
F-N Curve
DISCUSSION OF METHODOLOGY-
 All expert practitioner place great importance to an
integrated automatic system for overfilling protection.
 The protection against lightning is considered vital.
 A rim seal fire is considered as the most frequent fire
for floating roof tank.
 Venting devices placed on the top of the fixed roof
tank should be regularly checked.
 The sinking of the floating roof must be avoided.
 Reduce the all possibility of Boilover.
 Regular maintenance and inspection should be done
and their report should be maintain.
 Good drainage facility to avoid flooding in tank farm
area.
 High inlet temperature of the fuel is not considered
a probable accident cause.
 The non existence of specific safety measure, like
an obligatory cooling system, in the that the tank
farm have been built prior to the actually existing
regulation.
 Qualitative and quantitative risk assessment should
be conducted time to time.
 Layer of protection analysis should be done before
QRA.
References-
 A hazard assessment methodology for large liquid hydrocarbon fuel
tanks, C.D. Argyropoulos, M.N. Christolis, Z. Nivolianitou, N.C. Markatos.
 Barton Solvents Flammable Liquid Explosion and Fire, CSB report.
http://www.csb.gov/barton-solvents-flammable-liquid-explosion-and-fire/
 Jaipur Terminal Fire of 29.10.2009. http://www.hrdp-
idrm.in/live/hrdpmp/hrdpmaster/idrm/content/e6547/e6546/e32086/e3208
7/eventReport32415/MbLalreportonJaipurFire.Mr.Roy.ppt
 U.S. Chemical Safety Board. (2009). Cited at December, 5, 2011,
available at http://www.csb.gov/investigation/detail.aspx?SID=87
 A novel approach for Risk Assessment of Large Oil Storage Tanks Ali
Sari, Ph.D,. P.E. GenesisOilandGas.com
 A Holistic Risk Assessment Method For Storage Tank Terminals
Considering Domino Effects Triggered by Natural Hazards. ALI SARI,
PH.D,. P.E.

More Related Content

What's hot

Safety tips for lpg tank installation
Safety tips for lpg tank installationSafety tips for lpg tank installation
Safety tips for lpg tank installation
lpgbnhgastank
 
Gas engineering
Gas engineeringGas engineering
Gas engineering
Zin Eddine Dadach
 
Lpg safety
Lpg safetyLpg safety
Lpg safety
JAISINHSAMPAT
 
Basic Fire Fighting Training
Basic Fire Fighting TrainingBasic Fire Fighting Training
Basic Fire Fighting TrainingChristian Escaler
 
Classification of hazardous area for lighting
Classification of hazardous area   for lightingClassification of hazardous area   for lighting
Classification of hazardous area for lightingHarendra Vishwakarma
 
Fire prevention
Fire preventionFire prevention
Fire prevention
KitizaMerchant
 
Smpv(u) rules 2016-18
Smpv(u) rules  2016-18Smpv(u) rules  2016-18
Smpv(u) rules 2016-18
Abhishek Padiyar
 
OISD.ppt
OISD.pptOISD.ppt
OISD.ppt
SanjayQaz1
 
The basic of safety for petrochemicals industries 1
The basic of safety for petrochemicals industries 1The basic of safety for petrochemicals industries 1
The basic of safety for petrochemicals industries 1Anand Dhouni
 
D33 1 explosion protection_final-web
D33 1 explosion protection_final-webD33 1 explosion protection_final-web
D33 1 explosion protection_final-web
Dir Jan
 
Fire fighting equipments
Fire fighting equipmentsFire fighting equipments
Fire fighting equipments
Simran Dhingra
 
Hazards in steel plant and their control, By B C das
Hazards in steel plant and their control, By B C dasHazards in steel plant and their control, By B C das
Hazards in steel plant and their control, By B C das
Bimal Chandra Das
 
HEALT & SAFETY IN THE OIL & GAS INDUSTRY
HEALT & SAFETY IN THE OIL & GAS INDUSTRYHEALT & SAFETY IN THE OIL & GAS INDUSTRY
HEALT & SAFETY IN THE OIL & GAS INDUSTRY
Alex TX
 
High Expansion Foam System
High Expansion Foam SystemHigh Expansion Foam System
High Expansion Foam System
REDEMPTO
 
Hazardous Area Classification
Hazardous Area ClassificationHazardous Area Classification
Hazardous Area Classification
Gaurav Singh Rajput
 
Human Factors in Barrier Thinking
Human Factors in Barrier ThinkingHuman Factors in Barrier Thinking
Human Factors in Barrier Thinking
Society of Petroleum Engineers
 

What's hot (20)

Fire pumps
Fire pumpsFire pumps
Fire pumps
 
Safety tips for lpg tank installation
Safety tips for lpg tank installationSafety tips for lpg tank installation
Safety tips for lpg tank installation
 
Safety In Gas Cutting.
Safety In Gas Cutting.Safety In Gas Cutting.
Safety In Gas Cutting.
 
Gas engineering
Gas engineeringGas engineering
Gas engineering
 
Lpg safety
Lpg safetyLpg safety
Lpg safety
 
Basic Fire Fighting Training
Basic Fire Fighting TrainingBasic Fire Fighting Training
Basic Fire Fighting Training
 
Classification of hazardous area for lighting
Classification of hazardous area   for lightingClassification of hazardous area   for lighting
Classification of hazardous area for lighting
 
Cl2safehandling
Cl2safehandlingCl2safehandling
Cl2safehandling
 
Fire prevention
Fire preventionFire prevention
Fire prevention
 
Smpv(u) rules 2016-18
Smpv(u) rules  2016-18Smpv(u) rules  2016-18
Smpv(u) rules 2016-18
 
OISD.ppt
OISD.pptOISD.ppt
OISD.ppt
 
The basic of safety for petrochemicals industries 1
The basic of safety for petrochemicals industries 1The basic of safety for petrochemicals industries 1
The basic of safety for petrochemicals industries 1
 
D33 1 explosion protection_final-web
D33 1 explosion protection_final-webD33 1 explosion protection_final-web
D33 1 explosion protection_final-web
 
Fire fighting equipments
Fire fighting equipmentsFire fighting equipments
Fire fighting equipments
 
H2 Safety
H2 SafetyH2 Safety
H2 Safety
 
Hazards in steel plant and their control, By B C das
Hazards in steel plant and their control, By B C dasHazards in steel plant and their control, By B C das
Hazards in steel plant and their control, By B C das
 
HEALT & SAFETY IN THE OIL & GAS INDUSTRY
HEALT & SAFETY IN THE OIL & GAS INDUSTRYHEALT & SAFETY IN THE OIL & GAS INDUSTRY
HEALT & SAFETY IN THE OIL & GAS INDUSTRY
 
High Expansion Foam System
High Expansion Foam SystemHigh Expansion Foam System
High Expansion Foam System
 
Hazardous Area Classification
Hazardous Area ClassificationHazardous Area Classification
Hazardous Area Classification
 
Human Factors in Barrier Thinking
Human Factors in Barrier ThinkingHuman Factors in Barrier Thinking
Human Factors in Barrier Thinking
 

Similar to Hazard Assessment Methodology of Liquid Hydrocarbon Tank | Risk Assessment of Tank | Gaurav Singh Rajput

Planning to Avoid Failure Storage Tanks
Planning to Avoid Failure Storage TanksPlanning to Avoid Failure Storage Tanks
Planning to Avoid Failure Storage Tanks
Orlando Costa
 
Military Training Summary Long Hand
Military Training Summary Long HandMilitary Training Summary Long Hand
Military Training Summary Long HandPierce Love
 
Powerpoint presentation Process Safety 22
Powerpoint presentation Process Safety 22Powerpoint presentation Process Safety 22
Powerpoint presentation Process Safety 22
cloudno9112
 
MIQA, An Ultimate Element of PSM Implementation
MIQA, An Ultimate Element of PSM ImplementationMIQA, An Ultimate Element of PSM Implementation
MIQA, An Ultimate Element of PSM Implementation
MAHENDRA KUMAR RASTOGI
 
TOC.pptx
TOC.pptxTOC.pptx
TOC.pptx
AmrElfekky1
 
TOC.pptx
TOC.pptxTOC.pptx
TOC.pptx
AmrElfekky1
 
EMERGENCY ISOLATION OF CHEMICAL PLANTS
EMERGENCY ISOLATION OF CHEMICAL PLANTS EMERGENCY ISOLATION OF CHEMICAL PLANTS
EMERGENCY ISOLATION OF CHEMICAL PLANTS
Gerard B. Hawkins
 
CRITICAL LNG HAZARD SOLUTION
CRITICAL LNG HAZARD SOLUTIONCRITICAL LNG HAZARD SOLUTION
CRITICAL LNG HAZARD SOLUTION
IRJET Journal
 
Military Training Recieved
Military Training RecievedMilitary Training Recieved
Military Training RecievedJoseph Slape
 
G0366046050
G0366046050G0366046050
G0366046050
theijes
 
PPT-on-false-air.ppt
PPT-on-false-air.pptPPT-on-false-air.ppt
PPT-on-false-air.ppt
vikramparuthi1
 
4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates
Dwarika Bhushan Sharma
 
Smart Transcript
Smart TranscriptSmart Transcript
Smart TranscriptJuan Flagg
 
STM_Autumn2015 Article Publication
STM_Autumn2015 Article PublicationSTM_Autumn2015 Article Publication
STM_Autumn2015 Article PublicationEwart Cox
 
Unit-III Safety in process.pptx
Unit-III Safety in process.pptxUnit-III Safety in process.pptx
Unit-III Safety in process.pptx
TYPPEOnlineLecture
 

Similar to Hazard Assessment Methodology of Liquid Hydrocarbon Tank | Risk Assessment of Tank | Gaurav Singh Rajput (20)

COMPL OF WORKS1
COMPL OF WORKS1COMPL OF WORKS1
COMPL OF WORKS1
 
Planning to Avoid Failure Storage Tanks
Planning to Avoid Failure Storage TanksPlanning to Avoid Failure Storage Tanks
Planning to Avoid Failure Storage Tanks
 
Military Training Summary Long Hand
Military Training Summary Long HandMilitary Training Summary Long Hand
Military Training Summary Long Hand
 
Powerpoint presentation Process Safety 22
Powerpoint presentation Process Safety 22Powerpoint presentation Process Safety 22
Powerpoint presentation Process Safety 22
 
MIQA, An Ultimate Element of PSM Implementation
MIQA, An Ultimate Element of PSM ImplementationMIQA, An Ultimate Element of PSM Implementation
MIQA, An Ultimate Element of PSM Implementation
 
TOC.pptx
TOC.pptxTOC.pptx
TOC.pptx
 
TOC.pptx
TOC.pptxTOC.pptx
TOC.pptx
 
Mithun Banjan CV
Mithun Banjan CVMithun Banjan CV
Mithun Banjan CV
 
SHUTDOWN
SHUTDOWNSHUTDOWN
SHUTDOWN
 
Standard practices r9
Standard practices r9Standard practices r9
Standard practices r9
 
EMERGENCY ISOLATION OF CHEMICAL PLANTS
EMERGENCY ISOLATION OF CHEMICAL PLANTS EMERGENCY ISOLATION OF CHEMICAL PLANTS
EMERGENCY ISOLATION OF CHEMICAL PLANTS
 
CRITICAL LNG HAZARD SOLUTION
CRITICAL LNG HAZARD SOLUTIONCRITICAL LNG HAZARD SOLUTION
CRITICAL LNG HAZARD SOLUTION
 
Military Training Recieved
Military Training RecievedMilitary Training Recieved
Military Training Recieved
 
G0366046050
G0366046050G0366046050
G0366046050
 
PPT-on-false-air.ppt
PPT-on-false-air.pptPPT-on-false-air.ppt
PPT-on-false-air.ppt
 
4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates
 
Smart Transcript
Smart TranscriptSmart Transcript
Smart Transcript
 
STM_Autumn2015 Article Publication
STM_Autumn2015 Article PublicationSTM_Autumn2015 Article Publication
STM_Autumn2015 Article Publication
 
Muhammad Resume
Muhammad ResumeMuhammad Resume
Muhammad Resume
 
Unit-III Safety in process.pptx
Unit-III Safety in process.pptxUnit-III Safety in process.pptx
Unit-III Safety in process.pptx
 

More from Gaurav Singh Rajput

Site Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputSite Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputQuantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Basic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputBasic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Gaurav Singh Rajput
 
Fire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputFire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputBasic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Hzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputHzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputBasic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput
Gaurav Singh Rajput
 
BBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputBBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh Rajput
Gaurav Singh Rajput
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh Rajput
Gaurav Singh Rajput
 
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
Gaurav Singh Rajput
 
Accident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputAccident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Calculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputCalculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Gaurav Singh Rajput
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh Rajput
Gaurav Singh Rajput
 

More from Gaurav Singh Rajput (20)

Site Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputSite Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh Rajput
 
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputQuantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
 
Basic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputBasic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh Rajput
 
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
 
Fire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputFire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh Rajput
 
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputBasic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
 
Hzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputHzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh Rajput
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
 
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputBasic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput
 
BBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputBBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh Rajput
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh Rajput
 
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
 
Accident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputAccident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh Rajput
 
Calculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputCalculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh Rajput
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh Rajput
 

Recently uploaded

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 

Recently uploaded (20)

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 

Hazard Assessment Methodology of Liquid Hydrocarbon Tank | Risk Assessment of Tank | Gaurav Singh Rajput

  • 1. Gaurav Kumar Singh Rajput Roll no- 15 Gaurav Kumar Singh Rajput Roll No- 15 HAZARD ASSESSMENT METHODOLOGY FOR LIQUID HYDROCARBON TANK Gaurav Kumar Singh Rajput Roll No- 15 S8 School Of Engineering
  • 2. PRESENTATION OUTLINE- 1. Tank fire accident scenario 2. Failure cause of tank accident 3. Jaipur fire 4. Barton solvent chemical plant 5. Preventive and protective measure 6. potential process and non-process hazard 7. Risk assessment flow diagram 8. Risk calculation 9. Discussion of methodology 10. References
  • 3. Tank fire accident scenarios-  Rim seal fire  Spill on roof fire  Full surface fire  Bund or dyke wall  Pontoon explosion  Boilover
  • 4. Failure cause of tank accident- 1. Operational error  Tank overfilling  Valves left open accidently  Vent closed during loading unloading 2. Equipment/instrument failure  Floating roof sunk  Level indicator  Discharge valve rupture  Rusted vent valve 3. Lightning  Poor grounding
  • 5. 4. Static electricity  Damage seal  Poor grounding  Poor bonding  Fluid transfer 5. Maintenance error  Welding/cutting  Circuit shortcut  Non explosive-proof equipment used 6. Tank crack/rupture  Poor soldering  Corrosion  Distortion/buckling
  • 6. 7. Piping rupture/leak  Valve leaking  Pump leak  Cut accidentally 8. Safety supporting system  Insufficient tank cooling  electric power loss  Firefighter water loss 9. Miscellaneous  Earthquake  Arson  Extreme weather
  • 7. Jaipur Fire Jaipur IOC Terminal (oct 2009) 11 people lost their life Fire in 11 tank, fire continue for 11 days Cause-  Basic operation procedure was not followed  No control room  Delay in emergency response team  ESD from control room was not available Recommendations-  Engineering related  Operation related  Training related  Procurement related  Management related By M.B Lal committee
  • 8. Standard operating sequence Likely sequence 1. Ensure MOV and HOV are closed 2. Reverse the position of hammer blind valve 3. Open the HOV 4. Open MOV 1. MOV opened first 2. Hammer blind valve opened 3. Leakage started
  • 9.
  • 10. Barton Solvents Chemical Plant Accident Barton solvent chemical plant Kansas (July 2007) Evacuation of 6000 residents, destroyed the tank farm Cause-  Faulty design of level gauge.  The tank contained an ignitable vapour-air mixture in its head space.  Stop-start filling, air in transfer pipe, sediment and water. Recommendations-  Add inert gas to the head space  Avoid loose linkage  Anti static additives  Reduce fluid pumping velocity  Require additional manufacture guidance  By pass conductor
  • 11.
  • 12.
  • 13. Preventive and protection measure- 1. Design  Follow engineering standard and regulations  Modification in design  Dyke, Bund 2. Maintenance  Routine inspection  Periodic proof testing  Use proper equipment  Use explosion-proof tools 3. Equipment  Follow engineering standard  Lightning protection system  ROSOV  Temperature monitoring device
  • 14. 4. Safety supporting system  Fire detection and alarm system  Fire fighting system  Tank cooling system  Emergency response plan  CCTV equipment 5. Miscellaneous  Safeguarding  Good house keeping/No smoking  Protection from DOMINO effect, areal electrical power lines, extreme weather, mechanical stress and vehicle bumping.
  • 15. POTENTIAL PROCESS AND NON-PROCESS HAZARD-
  • 17. RISK CALCULATION-  Risk due to hazard at storage tank terminal and its surrounding is composed of summation of all risk given no escalation of event of undesired event and all risk given an escalation. Risk= Risk/ No Escalation + Risk/ Escalation The result of the quantitative risk analysis are commonly represented by the following parameter- 1. Individual risk 2. Societal risk
  • 18. -Individual risk is the risk that an individual remaining at a particular spot would face from the plant facility. The individual risk value is a frequency of fatality usually chance per million per year and represent on ALARP triangle. -Societal risk is the risk on number of people who might be affected by hazardous incident and represent on F-N (Frequency-Number curve) curve . Risk Analysis Qualitative Risk Analysis Quantitative Risk Analysis
  • 20. DISCUSSION OF METHODOLOGY-  All expert practitioner place great importance to an integrated automatic system for overfilling protection.  The protection against lightning is considered vital.  A rim seal fire is considered as the most frequent fire for floating roof tank.  Venting devices placed on the top of the fixed roof tank should be regularly checked.  The sinking of the floating roof must be avoided.  Reduce the all possibility of Boilover.  Regular maintenance and inspection should be done and their report should be maintain.
  • 21.  Good drainage facility to avoid flooding in tank farm area.  High inlet temperature of the fuel is not considered a probable accident cause.  The non existence of specific safety measure, like an obligatory cooling system, in the that the tank farm have been built prior to the actually existing regulation.  Qualitative and quantitative risk assessment should be conducted time to time.  Layer of protection analysis should be done before QRA.
  • 22. References-  A hazard assessment methodology for large liquid hydrocarbon fuel tanks, C.D. Argyropoulos, M.N. Christolis, Z. Nivolianitou, N.C. Markatos.  Barton Solvents Flammable Liquid Explosion and Fire, CSB report. http://www.csb.gov/barton-solvents-flammable-liquid-explosion-and-fire/  Jaipur Terminal Fire of 29.10.2009. http://www.hrdp- idrm.in/live/hrdpmp/hrdpmaster/idrm/content/e6547/e6546/e32086/e3208 7/eventReport32415/MbLalreportonJaipurFire.Mr.Roy.ppt  U.S. Chemical Safety Board. (2009). Cited at December, 5, 2011, available at http://www.csb.gov/investigation/detail.aspx?SID=87  A novel approach for Risk Assessment of Large Oil Storage Tanks Ali Sari, Ph.D,. P.E. GenesisOilandGas.com  A Holistic Risk Assessment Method For Storage Tank Terminals Considering Domino Effects Triggered by Natural Hazards. ALI SARI, PH.D,. P.E.