SlideShare a Scribd company logo
1 of 19
Metal-Clad SwitchgearMetal-Clad Switchgear
Installation & Precommissioning InspectionInstallation & Precommissioning Inspection
April 15, 2007
Abdullah M Al-Dushaishi
2
OUTLINEOUTLINE
EQUIPMENT INSTALLATION INSPECTION
BUSBAR INSTALLATION INSPECTION
CABLE CONNECTION INSPECTION
GROUNDING CONNECTION INSPECTION
SOME DESIGN CONCERNS
PRE-COMMISSIONING
REFERENCES
3
EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION
INSPECTIONINSPECTION
Ensure that adequate protection is provided when installing
switchgear
Switchgear shall only be installed in an indoor, air-conditioned
environment
Switchgear shall have an unobstructed horizontal space of:
a) Not less than 2 meters in front
b) Not less than 1 meter in back and sides
Spacing requirement between equipment shall be based upon
the largest dimension for either
4
EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION
INSPECTIONINSPECTION
Lifting/handling devices shall be provided within a room
containing switchgear to mechanically assist in removing to
floor level, any withdrawable component (e.g., circuit breaker,
contactor, potential transformer, etc.) weighing over 20 kg
Switchgear shall be free of any physical damage after
installation
Switchgear should be properly anchored to its foundation
5
EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION
INSPECTIONINSPECTION
Switches, circuit breakers, and other operating mechanisms
shall be manually exercised to make sure that they are
properly aligned and operate freely
Grounding connections shall be made properly
Debris, scrap wires and surplus shall be removed from the
switchgear interior before closing the enclosure
6
EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION
INSPECTIONINSPECTION
Covers, doors & enclosure parts shall
be properly tightened
The switchgear shall be vertically &
horizontally aligned before anchoring
Check components for proper
identification as per IFC drawings and
specifications
Nameplate on equipment shall conform
to single line diagrams and schematics
7
EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION
INSPECTIONINSPECTION
Concrete floor in front of switchgear shall be flush with the
roller level of lower breaker carriage rack and have a smooth
surface to facilitate removal and rolling of breaker
The bay spacing of transformers and the location of the
incoming circuit breakers on switchgear lineups shall be
positioned to minimize metal enclosed bus or cable bus length
and/or eliminate bends
Preferably, incomer circuit breakers shall be located at ends
of switchgear lineup
Unavoidable bends in cable bus or metal enclosed bus shall
be inside the substation building
8
BUSBAR INSTALLATIONBUSBAR INSTALLATION
INSPECTIONINSPECTION
Neutral buses shall not be used within
switchgear
Cable shall not be used to extend the
main bus of switchgear
9
BUSBAR INSTALLATIONBUSBAR INSTALLATION
INSPECTIONINSPECTION
Contact surfaces for the main bus
connections shall be clean
Tightness of bolted bus joints are correct
as per manufacturer's instruction for the
proper torque (foot-pound) levels
10
CABLECONNECTION INSPECTIONCABLECONNECTION INSPECTION
Cable phasing shall be in accordance
with connection diagram
Proper cable tags shall be provided
Cables termination shall be in accordance
with cable manufacturer's instruction
Cable connections are clean and securely
bolted.
Bolt torque values shall be as per
manufacturer's specifications
11
GROUNDING CONNECTIONGROUNDING CONNECTION
INSPECTIONINSPECTION
Sections of ground bus previously disconnected at shipping
sections shall be reconnected when units are installed
Secondary wirings are connected to switchgear ground bus as
indicated on IFC drawings
Ground bus shall be connected direct to grounding grid and
shall not run in metal conduit unless conduit is adequately
bonded to the circuit
12
SOMEDESIGN CONCERNSSOMEDESIGN CONCERNS
Switchgear shall not be used to control:
low voltage motors and
high voltage motors rated less than 5kV
In industrial facilities, 480V switchgear shall not be fed from
4160V systems
A separate 120 VAC branch circuit shall be provided for the
space heater
13
PRE-COMMISSIONINGPRE-COMMISSIONING
Check electrical relays, meters, or
instruments to determine connections
are made properly and devices function
properly
Check settings of the adjustable
current and voltage trip mechanisms to
confirm that they are at proper values.
Check control, power transformer and
PT fuses for size, type, and circuit
location
Check PT and CT ratios
14
PRE-COMMISSIONINGPRE-COMMISSIONING
Check wiring connections for
tightness at instrument transformers
and terminal blocks
Protective devices’ setting for
current, voltage, or other relays shall
be done on-site in accordance with
manufacturer’s recommendation
Ground-fault protection system shall
be tested in accordance with
manufacturer's instruction
15
PRE-COMMISSIONINGPRE-COMMISSIONING
Protective relays, overcurrent trip devices, and breakers shall
be tested for correct connections and operation at factory
Factory test results shall be referenced during
Precommissioning
16
PRE-COMMISSIONINGPRE-COMMISSIONING
Insulation resistance test shall be performed to make sure
switchgear is free from short circuits and grounds. This test shall
be done both phase to ground and phase to phase and with the
switches and breakers both opened and closed
Switchgear busbar shall be tested for insulation resistance with
a 1-minute test (phase to phase and phase to ground) with 1kV
megohmmeter
Instrument transformers shall be tested for insulation resistance
with a 1-minute test with 1 kV megohmmeter
17
PRE-COMMISSIONINGPRE-COMMISSIONING
Each circuit breaker protective relay device shall be calibrated
and tested with final settings in accordance with relay setting
summary or coordination study
With CT disconnected, CT secondary circuit shall be tested for
continuity and operation of applicable relays and meters by
applying current to the CT secondary winding
PT secondary circuit shall be tested by applying voltage to the
PT secondary, with PT disconnected, verifying operation of all
applicable relays and meters
18
PRE-COMMISSIONINGPRE-COMMISSIONING
Space heaters, switching and indicating devices shall be tested
for operation
Auxiliary devices interlocks shall be tested for operation
Local and remote control devices/circuits shall be tested
according to engineering specification
19
REFERENCESREFERENCES
NFPA 70 --National Electrical Code, 2005
NETA ATS -- Acceptance Testing Specification for Electrical
Power Distribution Equipment and Systems, 1999
SAES-P-116 -- Switchgear and Control Equipment, 28
February 2005
SAES-P-119 -- Onshore Substations, 30 march 2005

More Related Content

What's hot

TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...Jobin Abraham
 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-StationTowfiqur Rahman
 
Lv switchgear & lv cable sizing
Lv switchgear & lv cable sizingLv switchgear & lv cable sizing
Lv switchgear & lv cable sizingAsif Eqbal
 
Electrical installation for commercial & public building
Electrical installation for commercial & public buildingElectrical installation for commercial & public building
Electrical installation for commercial & public buildingddsshukla
 
ESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRING
ESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRINGESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRING
ESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRINGRanjitKumar Parmar
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1anuphowlader1
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersLiving Online
 
Electric substation
Electric substation Electric substation
Electric substation ANNU KUMAR
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentationNadir Baloch
 
Electrical system design of garden project at belhaven (10 Storey High Rise B...
Electrical system design of garden project at belhaven (10 Storey High Rise B...Electrical system design of garden project at belhaven (10 Storey High Rise B...
Electrical system design of garden project at belhaven (10 Storey High Rise B...Nithya Susan Varghese
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design) SayanSarkar55
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxLiewChiaPing
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systemsBiswajit Pratihari
 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationraiamitesh8
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guideSlides Hub
 

What's hot (20)

TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-Station
 
Lv switchgear & lv cable sizing
Lv switchgear & lv cable sizingLv switchgear & lv cable sizing
Lv switchgear & lv cable sizing
 
Electrical installation for commercial & public building
Electrical installation for commercial & public buildingElectrical installation for commercial & public building
Electrical installation for commercial & public building
 
ESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRING
ESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRINGESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRING
ESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRING
 
1.substation layouts
1.substation  layouts1.substation  layouts
1.substation layouts
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of Transformers
 
132 kv
132 kv132 kv
132 kv
 
Electric substation
Electric substation Electric substation
Electric substation
 
Cable and laying
Cable and layingCable and laying
Cable and laying
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
Electrical system design of garden project at belhaven (10 Storey High Rise B...
Electrical system design of garden project at belhaven (10 Storey High Rise B...Electrical system design of garden project at belhaven (10 Storey High Rise B...
Electrical system design of garden project at belhaven (10 Storey High Rise B...
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design)
 
Load list calculation
Load list calculationLoad list calculation
Load list calculation
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systems
 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substation
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guide
 
Cable Sizing Calculations
Cable Sizing CalculationsCable Sizing Calculations
Cable Sizing Calculations
 

Similar to Switchgear Installation Precomissioning Inspection.PPT

Access control basics-7
Access control basics-7Access control basics-7
Access control basics-7grantlerc
 
2011 12-33kv tech.spec for v c b type- m2-c1-revised
2011 12-33kv tech.spec for v c b type- m2-c1-revised2011 12-33kv tech.spec for v c b type- m2-c1-revised
2011 12-33kv tech.spec for v c b type- m2-c1-revisedBasudev patra
 
Artessa 2202 - QCAT electrical.ppt
Artessa 2202 - QCAT electrical.pptArtessa 2202 - QCAT electrical.ppt
Artessa 2202 - QCAT electrical.pptALshafiqShuai
 
Access control basics-9
Access control basics-9Access control basics-9
Access control basics-9grantlerc
 
'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.ppt'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.pptThien Phan Bản
 
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.pptSVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.pptssuser4b097a
 
2311 s5500 checkout & comm. of elec. equip, rev. a 8
2311 s5500 checkout & comm. of elec. equip, rev. a 82311 s5500 checkout & comm. of elec. equip, rev. a 8
2311 s5500 checkout & comm. of elec. equip, rev. a 8Olusegun Abode
 
2311 s5500 checkout & comm. of elec. equip, rev. a 8
2311 s5500 checkout & comm. of elec. equip, rev. a 82311 s5500 checkout & comm. of elec. equip, rev. a 8
2311 s5500 checkout & comm. of elec. equip, rev. a 8Olusegun Abode
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100Ali Sepehri
 
Specification for electrical automation and instrumentation 02
Specification for electrical automation and instrumentation  02Specification for electrical automation and instrumentation  02
Specification for electrical automation and instrumentation 02Sajeewa Lakmal
 

Similar to Switchgear Installation Precomissioning Inspection.PPT (20)

Access control basics-7
Access control basics-7Access control basics-7
Access control basics-7
 
2011 12-33kv tech.spec for v c b type- m2-c1-revised
2011 12-33kv tech.spec for v c b type- m2-c1-revised2011 12-33kv tech.spec for v c b type- m2-c1-revised
2011 12-33kv tech.spec for v c b type- m2-c1-revised
 
Test Switch Operation, Specifications & Accesories
Test Switch Operation, Specifications & Accesories Test Switch Operation, Specifications & Accesories
Test Switch Operation, Specifications & Accesories
 
Artessa 2202 - QCAT electrical.ppt
Artessa 2202 - QCAT electrical.pptArtessa 2202 - QCAT electrical.ppt
Artessa 2202 - QCAT electrical.ppt
 
SEMA 2016 - Introduction to Transformer Rated Metering
SEMA 2016 -  Introduction to Transformer Rated MeteringSEMA 2016 -  Introduction to Transformer Rated Metering
SEMA 2016 - Introduction to Transformer Rated Metering
 
Test Switch Operation and Accessories
Test Switch Operation and AccessoriesTest Switch Operation and Accessories
Test Switch Operation and Accessories
 
16950
1695016950
16950
 
Access control basics-9
Access control basics-9Access control basics-9
Access control basics-9
 
'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.ppt'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.ppt
 
Test Switch Operation, Specification & Accessories
Test Switch Operation, Specification & AccessoriesTest Switch Operation, Specification & Accessories
Test Switch Operation, Specification & Accessories
 
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.pptSVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
 
MIL-STD-461G - CS
MIL-STD-461G - CSMIL-STD-461G - CS
MIL-STD-461G - CS
 
TESCO Tuesday: Test Switch Operation & Accessories
TESCO Tuesday: Test Switch Operation & AccessoriesTESCO Tuesday: Test Switch Operation & Accessories
TESCO Tuesday: Test Switch Operation & Accessories
 
2311 s5500 checkout & comm. of elec. equip, rev. a 8
2311 s5500 checkout & comm. of elec. equip, rev. a 82311 s5500 checkout & comm. of elec. equip, rev. a 8
2311 s5500 checkout & comm. of elec. equip, rev. a 8
 
2311 s5500 checkout & comm. of elec. equip, rev. a 8
2311 s5500 checkout & comm. of elec. equip, rev. a 82311 s5500 checkout & comm. of elec. equip, rev. a 8
2311 s5500 checkout & comm. of elec. equip, rev. a 8
 
Test Switch Operation, Specifications & Accesories
Test Switch Operation, Specifications & Accesories Test Switch Operation, Specifications & Accesories
Test Switch Operation, Specifications & Accesories
 
Standing type outdoor full sf6 gas insualted ring main unit
Standing type outdoor full sf6 gas insualted ring main unitStanding type outdoor full sf6 gas insualted ring main unit
Standing type outdoor full sf6 gas insualted ring main unit
 
Standing type GIS RMU
Standing type GIS RMUStanding type GIS RMU
Standing type GIS RMU
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100
 
Specification for electrical automation and instrumentation 02
Specification for electrical automation and instrumentation  02Specification for electrical automation and instrumentation  02
Specification for electrical automation and instrumentation 02
 

More from Abdullah Al Dushaishi

More from Abdullah Al Dushaishi (12)

Nuclear Safety and Technologies
Nuclear Safety and TechnologiesNuclear Safety and Technologies
Nuclear Safety and Technologies
 
PE SCE
PE SCEPE SCE
PE SCE
 
Nuclear Workshop China
Nuclear Workshop ChinaNuclear Workshop China
Nuclear Workshop China
 
CABLE PENETRATION IN KGP SUBSTATIONS
CABLE PENETRATION IN KGP SUBSTATIONSCABLE PENETRATION IN KGP SUBSTATIONS
CABLE PENETRATION IN KGP SUBSTATIONS
 
Construction Supervision Certificate
Construction Supervision CertificateConstruction Supervision Certificate
Construction Supervision Certificate
 
18.4 Safety Recognition_SGS
18.4 Safety Recognition_SGS18.4 Safety Recognition_SGS
18.4 Safety Recognition_SGS
 
18.3 Safety Recognition_ARAMCO
18.3 Safety Recognition_ARAMCO18.3 Safety Recognition_ARAMCO
18.3 Safety Recognition_ARAMCO
 
18.2 Snam Qatif GOSP1 Safety Recognition Certificate
18.2 Snam Qatif GOSP1 Safety Recognition Certificate18.2 Snam Qatif GOSP1 Safety Recognition Certificate
18.2 Snam Qatif GOSP1 Safety Recognition Certificate
 
17.2 QMS Lead Auditor Training
17.2 QMS Lead Auditor Training17.2 QMS Lead Auditor Training
17.2 QMS Lead Auditor Training
 
17.1 Internal Auditor Course Certificate
17.1 Internal Auditor Course Certificate17.1 Internal Auditor Course Certificate
17.1 Internal Auditor Course Certificate
 
15 Ecoman Course Certificate.PDF
15 Ecoman Course Certificate.PDF15 Ecoman Course Certificate.PDF
15 Ecoman Course Certificate.PDF
 
14 Aramco PEDD EEX 103 Course Certificate
14 Aramco PEDD EEX 103 Course Certificate14 Aramco PEDD EEX 103 Course Certificate
14 Aramco PEDD EEX 103 Course Certificate
 

Switchgear Installation Precomissioning Inspection.PPT

  • 1. Metal-Clad SwitchgearMetal-Clad Switchgear Installation & Precommissioning InspectionInstallation & Precommissioning Inspection April 15, 2007 Abdullah M Al-Dushaishi
  • 2. 2 OUTLINEOUTLINE EQUIPMENT INSTALLATION INSPECTION BUSBAR INSTALLATION INSPECTION CABLE CONNECTION INSPECTION GROUNDING CONNECTION INSPECTION SOME DESIGN CONCERNS PRE-COMMISSIONING REFERENCES
  • 3. 3 EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION INSPECTIONINSPECTION Ensure that adequate protection is provided when installing switchgear Switchgear shall only be installed in an indoor, air-conditioned environment Switchgear shall have an unobstructed horizontal space of: a) Not less than 2 meters in front b) Not less than 1 meter in back and sides Spacing requirement between equipment shall be based upon the largest dimension for either
  • 4. 4 EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION INSPECTIONINSPECTION Lifting/handling devices shall be provided within a room containing switchgear to mechanically assist in removing to floor level, any withdrawable component (e.g., circuit breaker, contactor, potential transformer, etc.) weighing over 20 kg Switchgear shall be free of any physical damage after installation Switchgear should be properly anchored to its foundation
  • 5. 5 EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION INSPECTIONINSPECTION Switches, circuit breakers, and other operating mechanisms shall be manually exercised to make sure that they are properly aligned and operate freely Grounding connections shall be made properly Debris, scrap wires and surplus shall be removed from the switchgear interior before closing the enclosure
  • 6. 6 EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION INSPECTIONINSPECTION Covers, doors & enclosure parts shall be properly tightened The switchgear shall be vertically & horizontally aligned before anchoring Check components for proper identification as per IFC drawings and specifications Nameplate on equipment shall conform to single line diagrams and schematics
  • 7. 7 EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION INSPECTIONINSPECTION Concrete floor in front of switchgear shall be flush with the roller level of lower breaker carriage rack and have a smooth surface to facilitate removal and rolling of breaker The bay spacing of transformers and the location of the incoming circuit breakers on switchgear lineups shall be positioned to minimize metal enclosed bus or cable bus length and/or eliminate bends Preferably, incomer circuit breakers shall be located at ends of switchgear lineup Unavoidable bends in cable bus or metal enclosed bus shall be inside the substation building
  • 8. 8 BUSBAR INSTALLATIONBUSBAR INSTALLATION INSPECTIONINSPECTION Neutral buses shall not be used within switchgear Cable shall not be used to extend the main bus of switchgear
  • 9. 9 BUSBAR INSTALLATIONBUSBAR INSTALLATION INSPECTIONINSPECTION Contact surfaces for the main bus connections shall be clean Tightness of bolted bus joints are correct as per manufacturer's instruction for the proper torque (foot-pound) levels
  • 10. 10 CABLECONNECTION INSPECTIONCABLECONNECTION INSPECTION Cable phasing shall be in accordance with connection diagram Proper cable tags shall be provided Cables termination shall be in accordance with cable manufacturer's instruction Cable connections are clean and securely bolted. Bolt torque values shall be as per manufacturer's specifications
  • 11. 11 GROUNDING CONNECTIONGROUNDING CONNECTION INSPECTIONINSPECTION Sections of ground bus previously disconnected at shipping sections shall be reconnected when units are installed Secondary wirings are connected to switchgear ground bus as indicated on IFC drawings Ground bus shall be connected direct to grounding grid and shall not run in metal conduit unless conduit is adequately bonded to the circuit
  • 12. 12 SOMEDESIGN CONCERNSSOMEDESIGN CONCERNS Switchgear shall not be used to control: low voltage motors and high voltage motors rated less than 5kV In industrial facilities, 480V switchgear shall not be fed from 4160V systems A separate 120 VAC branch circuit shall be provided for the space heater
  • 13. 13 PRE-COMMISSIONINGPRE-COMMISSIONING Check electrical relays, meters, or instruments to determine connections are made properly and devices function properly Check settings of the adjustable current and voltage trip mechanisms to confirm that they are at proper values. Check control, power transformer and PT fuses for size, type, and circuit location Check PT and CT ratios
  • 14. 14 PRE-COMMISSIONINGPRE-COMMISSIONING Check wiring connections for tightness at instrument transformers and terminal blocks Protective devices’ setting for current, voltage, or other relays shall be done on-site in accordance with manufacturer’s recommendation Ground-fault protection system shall be tested in accordance with manufacturer's instruction
  • 15. 15 PRE-COMMISSIONINGPRE-COMMISSIONING Protective relays, overcurrent trip devices, and breakers shall be tested for correct connections and operation at factory Factory test results shall be referenced during Precommissioning
  • 16. 16 PRE-COMMISSIONINGPRE-COMMISSIONING Insulation resistance test shall be performed to make sure switchgear is free from short circuits and grounds. This test shall be done both phase to ground and phase to phase and with the switches and breakers both opened and closed Switchgear busbar shall be tested for insulation resistance with a 1-minute test (phase to phase and phase to ground) with 1kV megohmmeter Instrument transformers shall be tested for insulation resistance with a 1-minute test with 1 kV megohmmeter
  • 17. 17 PRE-COMMISSIONINGPRE-COMMISSIONING Each circuit breaker protective relay device shall be calibrated and tested with final settings in accordance with relay setting summary or coordination study With CT disconnected, CT secondary circuit shall be tested for continuity and operation of applicable relays and meters by applying current to the CT secondary winding PT secondary circuit shall be tested by applying voltage to the PT secondary, with PT disconnected, verifying operation of all applicable relays and meters
  • 18. 18 PRE-COMMISSIONINGPRE-COMMISSIONING Space heaters, switching and indicating devices shall be tested for operation Auxiliary devices interlocks shall be tested for operation Local and remote control devices/circuits shall be tested according to engineering specification
  • 19. 19 REFERENCESREFERENCES NFPA 70 --National Electrical Code, 2005 NETA ATS -- Acceptance Testing Specification for Electrical Power Distribution Equipment and Systems, 1999 SAES-P-116 -- Switchgear and Control Equipment, 28 February 2005 SAES-P-119 -- Onshore Substations, 30 march 2005