Part 1: 
Team velocity is 30 points* 
Sprint length is two weeks** 
How many Sprints will it take to complete Product Backlog? 
Part 2: 
What is the duration to complete? 
Part 3: 
What is the cost if a two week Sprint has a total resource rate of $30,000? 
Product Backlog 
Story 
Size 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
12 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
Forecasting Total Cost and Duration of Product Backlog 
* If team velocity is not know you can extrapolate it by conducting a pseudo Sprint Planning session 
**Team predetermines Sprint length –for the sake of this example I have select to use a two week Sprint 
Copyright © 2014 Russell Pannone. All rights reserved.
Part 1: 
Team velocity is 30 points 
Sprint length is two weeks 
How many Sprints will it take to complete Product Backlog? Answer: 5 (based on Velocity of 30 points) 
Part 2: 
What is the timeline to complete? 
Part 3: 
What is the cost if a two week Sprint has a total resource rate of $30,000? 
Product Backlog 
Story 
Size 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
12 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
Forecasting Total Cost and Duration of Product Backlog 
1 
2 
3 
4 
5 
Copyright © 2014 Russell Pannone. All rights reserved.
Part 1: 
Team velocity is 30 points 
Sprint length is two weeks 
How many Sprints will it take to complete Product Backlog? Answer: 5 (based on Velocity of 30 points) 
Part 2: 
What is the duration to complete? Answer: 10 weeks (5 (Sprints) x 2 (weeks each Sprint) = 10) 
Part 3: 
What is the cost if a two week Sprint has a total resource rate of $30,000? 
Product Backlog 
Story 
Size 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
12 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
Forecasting Total Cost and Duration of Product Backlog 
Copyright © 2014 Russell Pannone. All rights reserved.
Part 1: 
Team velocity is 30 points 
Sprint length is two weeks 
How many Sprints will it take to complete Product Backlog? Answer: 5 (based on Velocity of 30 points) 
Part 2: 
What is the duration to complete? Answer: 10 weeks (5 (Sprints) x 2 (weeks each Sprint) = 10) 
Part 3: 
What is the total cost if a two week Sprint has a total resource rate of $30,000? Answer: $300,000 ( 10 Sprints x $30,000 = $300,000.00) 
Product Backlog 
Story 
Size 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
12 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
ForcastingTotal Cost and Duration of Product Backlog 
Copyright © 2014 Russell Pannone. All rights reserved.
Forecasting Total Cost and Duration of Product Backlog 
Copyright © 2014 Russell Pannone. All rights reserved. 
Forecast based on calculations from previous slides = 
•Duration to complete = 10 weeks 
•Cost to complete = $300,000.00 
Because of the relevance of the cone-of-uncertainty I would change forecast to: 
Duration to complete = 14 weeks 
Cost to complete = $360,000.00

Forecasting total cost and duration of Product Backlog

  • 1.
    Part 1: Teamvelocity is 30 points* Sprint length is two weeks** How many Sprints will it take to complete Product Backlog? Part 2: What is the duration to complete? Part 3: What is the cost if a two week Sprint has a total resource rate of $30,000? Product Backlog Story Size As a … I want to…So that….. 3 As a … I want to…So that….. 8 As a … I want to…So that….. 2 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 2 As a … I want to…So that….. 2 As a … I want to…So that….. 12 As a … I want to…So that….. 3 As a … I want to…So that….. 3 As a … I want to…So that….. 2 As a … I want to…So that….. 8 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 20 As a … I want to…So that….. 20 As a … I want to…So that….. 5 As a … I want to…So that….. 20 As a … I want to…So that….. 20 Forecasting Total Cost and Duration of Product Backlog * If team velocity is not know you can extrapolate it by conducting a pseudo Sprint Planning session **Team predetermines Sprint length –for the sake of this example I have select to use a two week Sprint Copyright © 2014 Russell Pannone. All rights reserved.
  • 2.
    Part 1: Teamvelocity is 30 points Sprint length is two weeks How many Sprints will it take to complete Product Backlog? Answer: 5 (based on Velocity of 30 points) Part 2: What is the timeline to complete? Part 3: What is the cost if a two week Sprint has a total resource rate of $30,000? Product Backlog Story Size As a … I want to…So that….. 3 As a … I want to…So that….. 8 As a … I want to…So that….. 2 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 2 As a … I want to…So that….. 2 As a … I want to…So that….. 12 As a … I want to…So that….. 3 As a … I want to…So that….. 3 As a … I want to…So that….. 2 As a … I want to…So that….. 8 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 20 As a … I want to…So that….. 20 As a … I want to…So that….. 5 As a … I want to…So that….. 20 As a … I want to…So that….. 20 Forecasting Total Cost and Duration of Product Backlog 1 2 3 4 5 Copyright © 2014 Russell Pannone. All rights reserved.
  • 3.
    Part 1: Teamvelocity is 30 points Sprint length is two weeks How many Sprints will it take to complete Product Backlog? Answer: 5 (based on Velocity of 30 points) Part 2: What is the duration to complete? Answer: 10 weeks (5 (Sprints) x 2 (weeks each Sprint) = 10) Part 3: What is the cost if a two week Sprint has a total resource rate of $30,000? Product Backlog Story Size As a … I want to…So that….. 3 As a … I want to…So that….. 8 As a … I want to…So that….. 2 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 2 As a … I want to…So that….. 2 As a … I want to…So that….. 12 As a … I want to…So that….. 3 As a … I want to…So that….. 3 As a … I want to…So that….. 2 As a … I want to…So that….. 8 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 20 As a … I want to…So that….. 20 As a … I want to…So that….. 5 As a … I want to…So that….. 20 As a … I want to…So that….. 20 Forecasting Total Cost and Duration of Product Backlog Copyright © 2014 Russell Pannone. All rights reserved.
  • 4.
    Part 1: Teamvelocity is 30 points Sprint length is two weeks How many Sprints will it take to complete Product Backlog? Answer: 5 (based on Velocity of 30 points) Part 2: What is the duration to complete? Answer: 10 weeks (5 (Sprints) x 2 (weeks each Sprint) = 10) Part 3: What is the total cost if a two week Sprint has a total resource rate of $30,000? Answer: $300,000 ( 10 Sprints x $30,000 = $300,000.00) Product Backlog Story Size As a … I want to…So that….. 3 As a … I want to…So that….. 8 As a … I want to…So that….. 2 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 2 As a … I want to…So that….. 2 As a … I want to…So that….. 12 As a … I want to…So that….. 3 As a … I want to…So that….. 3 As a … I want to…So that….. 2 As a … I want to…So that….. 8 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 20 As a … I want to…So that….. 20 As a … I want to…So that….. 5 As a … I want to…So that….. 20 As a … I want to…So that….. 20 ForcastingTotal Cost and Duration of Product Backlog Copyright © 2014 Russell Pannone. All rights reserved.
  • 5.
    Forecasting Total Costand Duration of Product Backlog Copyright © 2014 Russell Pannone. All rights reserved. Forecast based on calculations from previous slides = •Duration to complete = 10 weeks •Cost to complete = $300,000.00 Because of the relevance of the cone-of-uncertainty I would change forecast to: Duration to complete = 14 weeks Cost to complete = $360,000.00