The document discusses forecasting the total cost and duration to complete a product backlog using Scrum methodology. It is given that the team velocity is 30 points per sprint and each sprint is 2 weeks. It is calculated that it will take 5 sprints, or 10 weeks, to complete the backlog. With each sprint costing $30,000 in resources, the total cost to complete the backlog is estimated at $300,000. However, due to the uncertainty inherent in forecasts, the summary increases the estimates to 14 weeks duration and $360,000 cost.