Focus 2018 Power Point
- 1. Copyright © 2018 JDA Software Group, Inc. Confidential
Up, Up and Away!
Darius Marshall
GE Lighting -Staff Technical Project Lead
Session Code: XXXXXX
- 2. Copyright © 2018 JDA Software Group, Inc. Confidential 2
Global Business with Two Channels
• Current, Powered by GE – LED Professional Sales and Projects
(40%)
• GE Lighting – Consumer Lighting Sales (60%)
GE Lighting Landscape
Overview
Focusing on New Growth Areas
• LED Technology
• Internet of Things (Predix)
Our market has changed rapidly; GE Lighting
continues to strive to stay ahead
- 3. Copyright © 2018 JDA Software Group, Inc. Confidential
Project Overview
Results
3
In 2018, GE completed a system-wide Cloud migration and WMS
Upgrade with help from Ascension Logistics.
GE Lighting now manages all 4 of their warehouses on the same
platform; reduced support staff from 4 to 1.5 while increasing
overall productivity by approximately 15 % network-wide.
- 4. Copyright © 2018 JDA Software Group, Inc. Confidential 4
>2010 – Partial network upgrade
- Started upgrade process in 2010 with GE Lighting’s planned move to SAP ERP.
- Selected 2009.2 as WMS platform and went from 50 to about 20 modification.
- Upgraded 2 paper based Distribution Centers ( Mira Loma and Ravenna )
- Not comfortable upgrading largest site given available functionality
- Upgrade project went on hold.
>2016 – Begin Full Upgrade and Cloud Migration
- Selected JDA WMS version 8.2
- Selected JDA Cloud as Hosting Solution
- Developed Upgrade Roadmap and began first site
Project Overview
A Brief History
- 5. Copyright © 2018 JDA Software Group, Inc. Confidential 5
1. Corporate mandated the elimination Window XP, Old Oracle versions,
and HP-UX (TMS, WMS).
2. Required transition to cloud based infrastructure due to business
divestiture.
3. Standardize WMS and interface to SAP
4. SAP conversion
> GE’s highest volume Distribution Center using oldest WMS technology.
> Eliminate another 20 WMS modifications.
> Fast transition to cloud based infrastructure due to business divestiture.
Project Overview
The BIG Y’s and Challenges
- 6. Copyright © 2018 JDA Software Group, Inc. Confidential
How to build a
Successful Template?
6
Why Templatize?
Reduce total cost
of ownership
(TCO)
Unify processes to
improve
supportability
Ability to share
business and IT
staff between sites
Create stable
foundation for SAP
Implementation
Move fast and
maintain
momentum!
But how?!
- 7. Copyright © 2018 JDA Software Group, Inc. Confidential
The Living Template Model
The Living Template
7
Start Small
Go Big and
Templatize
Rollouts Synchronize
Site 1 Site 2 Site 3+ Site 1
• Hard to identify relative importance of gaps without a live system
• Disparate process between existing DC’s; need to convince DC’s to use same process
• Desire to begin delivering value quickly: A 6 month template design followed by full
implementation -> more than a year before realizing value.
Overcoming Template Challenges:
- 8. Copyright © 2018 JDA Software Group, Inc. Confidential
The Living Template
8
Start
Small
Go Big and
Templatize
Rollouts Synch-Up
Site 1
• Select a lower complexity, low risk site for a first
deployment : Oakville Canada
• Run a standard project with an ‘eye’ to global requirements
• Bring Site 1 Live and Learn
Site 1 Site 2 Site 3+ Site 1
Start
Small
- 9. Copyright © 2018 JDA Software Group, Inc. Confidential
The Living Template
9
Start
Small
Go Big and
Templatize
Rollouts Synch-Up
Site 1 Site 2 Site 3+ Site 1
Go Big and
Templatize
Site 2
• Select a high complexity site which utilizes most or all
processes: Charleston DC
• Key users and business partners review initial site;
collectively identify areas of improvement
• Build template design and implement in large site
- 10. Copyright © 2018 JDA Software Group, Inc. Confidential
Charleston DC Image HERE
10
The Journey
Charleston Deployment
> Upgraded Charleston Distribution Center in 2017
> 60% of network volume
> Move from DLx 2005.2 to WMS 8.2
> JDA Cloud hosted environment
> Standardized and templatized GE Lighting
> Moved from Paper based picking to full directed work
> Parcel using pack-station model and automatic ship confirmation
> Systematized over 120 sets of customer documents and requirements
> Designed with no core modification to WMS 8.2
- 11. Copyright © 2018 JDA Software Group, Inc. Confidential
The Living Template
11
Start
Small
Go Big and
Templatize
Rollouts Synch-Up
Site 1 Site 2 Site 3+ Site 1
Rollouts
Site 3+
• Implement template at remaining sites: Ravenna and Mira
Loma
• Maximize re-use of collateral
• Business involvement mostly limited to validate and deploy
phases
• Control changes: “If it works in Charleston..”
- 12. Copyright © 2018 JDA Software Group, Inc. Confidential
The Living Template
12
Start
Small
Go Big and
Templatize
Rollouts Synch-Up
Site 1 Site 2 Site 3+ Site 1
Sync-Up
Site 1 Sync-Up
• Synchronize site 1 with global template
• 1 month mini project
• All sites now operate on single, unified template!
- 13. Copyright © 2018 JDA Software Group, Inc. Confidential
Less than 90 days.
Predictable, fixed cost. 13
The Results
Template Pay-Off
Site 1: Oakville
“Start Small”
• Build base Interfaces
• Build subset of
customer requirements
• Implement initial
design
Site 2: Charleston
“Go Big!”
• Build all Customer
Requirements
• Identify design
improvements;
formalize template
• Implement Template
Design
8 Months
Site 2+
“Rollout”
• Localize template
design
3 Months
Synchronize Site 1
• Update elements of
config to match
template design
<1 Months7 Months
- 14. Copyright © 2018 JDA Software Group, Inc. Confidential
#BoringGoLive
-NO issues
-Plenty of Ping Pong
14
The Results
Template Pay-Off
- 15. Copyright © 2018 JDA Software Group, Inc. Confidential
The Plan
Moving to the Cloud
15
GE partnered with JDA to provide a Cloud Platform for all sites
- 16. Copyright © 2018 JDA Software Group, Inc. Confidential 16
The Results
Implementation Results
For the first time in over 25 years, we have all our distribution
centers operating on the same WMS platform and version.
- 17. Copyright © 2018 JDA Software Group, Inc. Confidential 17
Our Partners
Better Together
• Implementation and thought partners
• Apply ‘Living Template’ process
• Accelerated Issue Resolution
• Deep knowledge of GE Business Process
• Provide fix fee or TM engagements
• Provide full Cloud Environment
• Database and OS system administration
• Able to guarantee performance
• 24/7 Infra and Network Support
Example: During post Go-Live Hyper care for the largest site, performance began to degrade. Ascension investigated,
worked with JDA Cloud, and JDA Cloud was able to double system specs to ensure performance. Overnight.
- 18. Copyright © 2018 JDA Software Group, Inc. Confidential 18