This document summarizes a wax deposition study on the Ravn oil field production system. It found that:
1) Wax deposition could reduce pipeline flow area and cause blockages. The study modeled wax deposition risks in the Ravn infield and export lines.
2) For the infield line, up to 4mm of wax could deposit at the seabed and 13mm at topsides within 30 days without inhibitors. Inhibitors could reduce this by 40%. Pigging was recommended every month without inhibitors and every 45 days with.
3) For the export line, up to 4mm of wax could deposit at the seabed within 22-31 days depending on inhibitors. Higher flows increased deposition risks