SlideShare a Scribd company logo
1 of 25
Financial Appraisal, Sensitivity and Scenario Analysis R.Ganesh, Sr.faculty, SBSC, Hyd
Capital Investment Process ,[object Object],Identification Evaluation Implementation & Follow up Selection ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Payback Period Payback period is the  number of periods  for the sum of project’s expected Cash Flows to equal its initial cash outlay. Payback period is the  time it takes to recover  its initial investment. A project is  acceptable  if the  payback period is shorter than  or equal to CUT-OFF period.
Expected cashflow streams – alternative investment proposals –  Initial outlay of ONE million rupees End of Year Investment A Investment B Investment C Investment D Invesrtment E Investment F 1 600,000 100,000 250,000 250,000 325,000 325,000 2 300,000 300,000 250,000 250,000 325,000 325,000 3 100,000 600,000 250,000 250,000 325,000 325,000 4 200,000 200,000 250,000 250,000 325,000 325,000 5 300,000 300,000 250,000 250,000 325,000 925,000 Total Cashflows 1,500,000 1,500,000 1,250,000 1,250,000 1,625,000 2,275,000 Payback period 3.00 3.00 4.00 4.00 3.08 3.08
Drawbacks of Payback method ,[object Object],Adjustment for timing of Cash Flows ? Adjustment for Risk ? Maximisation of the Firm’s Equity Value ? Its simplicity & ease of application Contributes to overall liquidity It is easy to employ when future events are difficult to quantify
Discounted payback period Discounted payback is the number of periods required for the  sum of present values  of project’s expected cash flows to equal its initial cash outlay.
Discounted Payback –calculations-  Investment ‘A’ End of Year Expected cashflows Discount factor Present Value Cumulative Present value 1 600,000 0.9091 545,455 545,455 2 300,000 0.8264 247,934 793,389 3 100,000 0.7513 75,131 868,520 4 200,000 0.6830 136,603 1,005,123 5 300,000 0.6209 186,276 1,191,399
Expected cashflow streams and cost of capital – alternative investment proposals –  Initial outlay of ONE million rupees End of Year Investment A Investment B Investment C Investment D Invesrtment E Investment F 1 600,000 100,000 250,000 250,000 325,000 325,000 2 300,000 300,000 250,000 250,000 325,000 325,000 3 100,000 600,000 250,000 250,000 325,000 325,000 4 200,000 200,000 250,000 250,000 325,000 325,000 5 300,000 300,000 250,000 250,000 325,000 925,000 Total Cashflows 1,500,000 1,500,000 1,250,000 1,250,000 1,625,000 2,275,000 Cost of capital 10% 10% 5% 10% 10% 10% NPV 191,399 112,511 82,369 -52,303 232,006 635,605 Discounted Payback period 3.96 4.40 4.58 More than 5 3.86 3.86
Internal Rate of Return(IRR) IRR is the discount rate that makes the Net Present Value (NPV) of the Project EQUAL to ZERO. An investment to be accepted if its IRR is higher than its Cost of Capital and should be rejected, if lower. IRR can be interpreted as a measure of profitability of its expected cashflows. IRR takes into account Time Value of money and risk of investment
Expected cashflow streams and cost of capital – alternative investment proposals –  Initial outlay of ONE million rupees End of Year Investment A Investment B Investment C Investment D Invesrtment E Investment F 1 600,000 100,000 250,000 250,000 325,000 325,000 2 300,000 300,000 250,000 250,000 325,000 325,000 3 100,000 600,000 250,000 250,000 325,000 325,000 4 200,000 200,000 250,000 250,000 325,000 325,000 5 300,000 300,000 250,000 250,000 325,000 925,000 Total Cashflows 1,500,000 1,500,000 1,250,000 1,250,000 1,625,000 2,275,000 Cost of capital 10% 10% 5% 10% 10% 10% IRR 19.05% 13.92% 7.93% 7.93% 18.72% 28.52%
Net Present Value Discount factor is the inverse of compounding factor.   NPV(k,N) = -CF0 + CF1  X DF1 + CF2 X DF2 + ……………   …… .CFt  X  DFt + ………………………...CFN X DFN NPV = (-)Initial cash outlay + Present value of future cash flows at the cost of capital. Investment to be undertaken if its NPV is positive and should be rejected if NPV is negative
Why NPV rule is a good investment rule ? ,[object Object],[object Object],[object Object],[object Object]
NPV Profile  Expected Cash Flows – CF(0), CF(1), CF(2)…….CF(n) Risk of expected cashflow stream Cost of Capital (k) required rate of return NPV = --CF(o) + ∑CF(t)/(1+k) t t=1,n NPV>0 NPV<0 Accept Project Reject Project
Cost of capital  The Project is going to be financed entirely with Debt, so its relevant cost of capital is the INTEREST Rate of Debt – or – Project is going to be financed entirely with Equity, so its cost of capital is Cost of Equity Although project does not have same risk as the Co, its relevant  cost of capital should be equal to firm’s WACC because firm’s shareholders and debtors are paid with cash from firm’s cash flows, NOT from the Project’s cash flows When Project’s risk is different from the risk of the Firm, the Project’s cost of capital should be lowered to account for the risk reduction that diversification brings to the firm.
 
Summary Evaluation Method Inputs  Required Decision Rule Does  the Rule Adjust cash flows for For Calculation For Decision Accept Reject Time ? Risk ? Net present Value(NPV) ,[object Object],[object Object],NPV NPV > 0 NPV < 0 Yes yes Profitability Index (PI) ,[object Object],[object Object],PI PI > 1 PI < 1 Yes Yes Internal Rate of return(IRR) ,[object Object],[object Object],[object Object],IRR > k IRR < k Yes Yes Discounted Payback period(DPP) ,[object Object],[object Object],[object Object],DPP < cutoff period DPP > cutoff period Only within DPP Only within DPP Payback period(PP) ,[object Object],[object Object],[object Object],PP < cutoff period PP > cutoff period No No
Financing Operation in India Equity/Risk Capital  Public Equity Issue Debt/Borrowed Capital  Foreign direct Investment Project Finance Term loans & Working capital finance External Commercial Borrowings Corporate Loan Market Corporate Debt Market
Equity Capital ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Raising Domestic equity ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Private Equity ,[object Object],[object Object],[object Object],[object Object],[object Object]
Corporate debt market in India ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Corporate debt market in India ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Project finance ,[object Object],[object Object],[object Object],[object Object],[object Object]
Project Finance (contd.) ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Term loans and working capital finance Fund based working capital services ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Securitization ,[object Object],[object Object],[object Object],[object Object],Long term loans

More Related Content

What's hot

Presentation on project appraisal
Presentation on project appraisalPresentation on project appraisal
Presentation on project appraisaljeni kayastha
 
Payback timevalue of money and iir
Payback timevalue of money and iirPayback timevalue of money and iir
Payback timevalue of money and iirSubhash Rohit
 
Payback period by harikrishnanan
Payback period by harikrishnananPayback period by harikrishnanan
Payback period by harikrishnananHari krishna
 
Time value of money
Time value of moneyTime value of money
Time value of moneymishra21
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysisHarinadh Karimikonda
 
Financial and economic analysis
Financial and economic analysisFinancial and economic analysis
Financial and economic analysisSiladitya Bag
 
133761133 2-project-financing-in-india-ppt
133761133 2-project-financing-in-india-ppt133761133 2-project-financing-in-india-ppt
133761133 2-project-financing-in-india-pptAshima Thakur
 
Project financing methods
Project financing methodsProject financing methods
Project financing methodsDaniel Oskooei
 
The Cost of capital for MNC
The Cost of capital for MNCThe Cost of capital for MNC
The Cost of capital for MNCSundar B N
 
Project identification & classification
Project identification & classificationProject identification & classification
Project identification & classificationRevathy Rajasekaran
 
Discounted payback period
Discounted payback periodDiscounted payback period
Discounted payback periodRavi Verma
 
The Discounted Cash Flow Valuation.pptx
The Discounted Cash Flow Valuation.pptxThe Discounted Cash Flow Valuation.pptx
The Discounted Cash Flow Valuation.pptxasde13
 

What's hot (20)

Presentation on project appraisal
Presentation on project appraisalPresentation on project appraisal
Presentation on project appraisal
 
Payback timevalue of money and iir
Payback timevalue of money and iirPayback timevalue of money and iir
Payback timevalue of money and iir
 
Project financing
Project financingProject financing
Project financing
 
Payback period by harikrishnanan
Payback period by harikrishnananPayback period by harikrishnanan
Payback period by harikrishnanan
 
Internal Rate of Return
Internal Rate of ReturnInternal Rate of Return
Internal Rate of Return
 
Capital structure
Capital structureCapital structure
Capital structure
 
Time value of money
Time value of moneyTime value of money
Time value of money
 
Npv
NpvNpv
Npv
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
Financial and economic analysis
Financial and economic analysisFinancial and economic analysis
Financial and economic analysis
 
Investment Appraisal
Investment AppraisalInvestment Appraisal
Investment Appraisal
 
133761133 2-project-financing-in-india-ppt
133761133 2-project-financing-in-india-ppt133761133 2-project-financing-in-india-ppt
133761133 2-project-financing-in-india-ppt
 
Project financing methods
Project financing methodsProject financing methods
Project financing methods
 
The Cost of capital for MNC
The Cost of capital for MNCThe Cost of capital for MNC
The Cost of capital for MNC
 
Project identification & classification
Project identification & classificationProject identification & classification
Project identification & classification
 
Cost of capital
Cost of capitalCost of capital
Cost of capital
 
Discounted payback period
Discounted payback periodDiscounted payback period
Discounted payback period
 
The Discounted Cash Flow Valuation.pptx
The Discounted Cash Flow Valuation.pptxThe Discounted Cash Flow Valuation.pptx
The Discounted Cash Flow Valuation.pptx
 
Payback method
Payback methodPayback method
Payback method
 
Debt Financing
Debt FinancingDebt Financing
Debt Financing
 

Viewers also liked

Financial Appraisal
Financial AppraisalFinancial Appraisal
Financial AppraisalROXYMAX
 
Recognizing Opportunities
Recognizing OpportunitiesRecognizing Opportunities
Recognizing OpportunitiesGC
 
Advertisement effectiveness.
Advertisement effectiveness.Advertisement effectiveness.
Advertisement effectiveness.Jaswinder Singh
 
Brand Positioning
Brand PositioningBrand Positioning
Brand PositioningCiti bank
 
Branding & Brand Positioning
Branding & Brand PositioningBranding & Brand Positioning
Branding & Brand PositioningSamer Meqdad
 
Brand Positioning
Brand PositioningBrand Positioning
Brand PositioningSj -
 
Advertising effectiveness
Advertising effectivenessAdvertising effectiveness
Advertising effectivenessAshu Chopra
 
brand positioning with examples
brand positioning with examplesbrand positioning with examples
brand positioning with examplesLinel Dias
 

Viewers also liked (15)

Financial Appraisal
Financial AppraisalFinancial Appraisal
Financial Appraisal
 
Recognizing Opportunities
Recognizing OpportunitiesRecognizing Opportunities
Recognizing Opportunities
 
Brand audit
Brand auditBrand audit
Brand audit
 
Spm unit 4
Spm unit 4Spm unit 4
Spm unit 4
 
Advertisement effectiveness.
Advertisement effectiveness.Advertisement effectiveness.
Advertisement effectiveness.
 
Spm unit2
Spm unit2Spm unit2
Spm unit2
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 
Brand Positioning
Brand PositioningBrand Positioning
Brand Positioning
 
Branding & Brand Positioning
Branding & Brand PositioningBranding & Brand Positioning
Branding & Brand Positioning
 
Advertising ppt
Advertising pptAdvertising ppt
Advertising ppt
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Media planning & strategy
Media planning & strategy Media planning & strategy
Media planning & strategy
 
Brand Positioning
Brand PositioningBrand Positioning
Brand Positioning
 
Advertising effectiveness
Advertising effectivenessAdvertising effectiveness
Advertising effectiveness
 
brand positioning with examples
brand positioning with examplesbrand positioning with examples
brand positioning with examples
 

Similar to Financial appraisal techniques

Capital Budgeting (TITTO SUNNY)
Capital Budgeting   (TITTO SUNNY)Capital Budgeting   (TITTO SUNNY)
Capital Budgeting (TITTO SUNNY)Traum Academy
 
Capital budjeting & appraisal methods
Capital budjeting  & appraisal methodsCapital budjeting  & appraisal methods
Capital budjeting & appraisal methodsDhruv Dave
 
Capital Budgeting Decision
Capital Budgeting DecisionCapital Budgeting Decision
Capital Budgeting DecisionAshish Khera
 
Capital Investment And Budgeting
Capital Investment And BudgetingCapital Investment And Budgeting
Capital Investment And BudgetingShubham Goyal
 
Financial management
Financial managementFinancial management
Financial managementAnil Rana
 
UNIT-4 Capital Budgeting.pdf
UNIT-4 Capital Budgeting.pdfUNIT-4 Capital Budgeting.pdf
UNIT-4 Capital Budgeting.pdfPralayMondal3
 
Capital budgeting methods lecture notes
Capital budgeting methods lecture notesCapital budgeting methods lecture notes
Capital budgeting methods lecture notesWarui Maina
 
Making Investment Decisions (introduction)
Making Investment Decisions (introduction)Making Investment Decisions (introduction)
Making Investment Decisions (introduction)tutor2u
 
Capital budgeting decisions:
Capital budgeting decisions:Capital budgeting decisions:
Capital budgeting decisions:Dr Naim R Kidwai
 

Similar to Financial appraisal techniques (20)

FM2.pptx
FM2.pptxFM2.pptx
FM2.pptx
 
Cfd ppt
Cfd pptCfd ppt
Cfd ppt
 
Investment decision
Investment decisionInvestment decision
Investment decision
 
capital_budgeting.ppt
capital_budgeting.pptcapital_budgeting.ppt
capital_budgeting.ppt
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
TEORI INVESTASI
TEORI INVESTASITEORI INVESTASI
TEORI INVESTASI
 
Chapter iii capital budget
Chapter iii capital budgetChapter iii capital budget
Chapter iii capital budget
 
Capital Budgeting (TITTO SUNNY)
Capital Budgeting   (TITTO SUNNY)Capital Budgeting   (TITTO SUNNY)
Capital Budgeting (TITTO SUNNY)
 
Capital budjeting & appraisal methods
Capital budjeting  & appraisal methodsCapital budjeting  & appraisal methods
Capital budjeting & appraisal methods
 
Ch 08
Ch 08Ch 08
Ch 08
 
Capital Budgeting Decision
Capital Budgeting DecisionCapital Budgeting Decision
Capital Budgeting Decision
 
Capital Investment And Budgeting
Capital Investment And BudgetingCapital Investment And Budgeting
Capital Investment And Budgeting
 
Financial management
Financial managementFinancial management
Financial management
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
UNIT-4 Capital Budgeting.pdf
UNIT-4 Capital Budgeting.pdfUNIT-4 Capital Budgeting.pdf
UNIT-4 Capital Budgeting.pdf
 
Capital budgeting methods lecture notes
Capital budgeting methods lecture notesCapital budgeting methods lecture notes
Capital budgeting methods lecture notes
 
August Investor Presentation
August Investor PresentationAugust Investor Presentation
August Investor Presentation
 
Dvn aug-2018-investor-presentation
Dvn aug-2018-investor-presentationDvn aug-2018-investor-presentation
Dvn aug-2018-investor-presentation
 
Making Investment Decisions (introduction)
Making Investment Decisions (introduction)Making Investment Decisions (introduction)
Making Investment Decisions (introduction)
 
Capital budgeting decisions:
Capital budgeting decisions:Capital budgeting decisions:
Capital budgeting decisions:
 

Financial appraisal techniques

  • 1. Financial Appraisal, Sensitivity and Scenario Analysis R.Ganesh, Sr.faculty, SBSC, Hyd
  • 2.
  • 3. Payback Period Payback period is the number of periods for the sum of project’s expected Cash Flows to equal its initial cash outlay. Payback period is the time it takes to recover its initial investment. A project is acceptable if the payback period is shorter than or equal to CUT-OFF period.
  • 4. Expected cashflow streams – alternative investment proposals – Initial outlay of ONE million rupees End of Year Investment A Investment B Investment C Investment D Invesrtment E Investment F 1 600,000 100,000 250,000 250,000 325,000 325,000 2 300,000 300,000 250,000 250,000 325,000 325,000 3 100,000 600,000 250,000 250,000 325,000 325,000 4 200,000 200,000 250,000 250,000 325,000 325,000 5 300,000 300,000 250,000 250,000 325,000 925,000 Total Cashflows 1,500,000 1,500,000 1,250,000 1,250,000 1,625,000 2,275,000 Payback period 3.00 3.00 4.00 4.00 3.08 3.08
  • 5.
  • 6. Discounted payback period Discounted payback is the number of periods required for the sum of present values of project’s expected cash flows to equal its initial cash outlay.
  • 7. Discounted Payback –calculations- Investment ‘A’ End of Year Expected cashflows Discount factor Present Value Cumulative Present value 1 600,000 0.9091 545,455 545,455 2 300,000 0.8264 247,934 793,389 3 100,000 0.7513 75,131 868,520 4 200,000 0.6830 136,603 1,005,123 5 300,000 0.6209 186,276 1,191,399
  • 8. Expected cashflow streams and cost of capital – alternative investment proposals – Initial outlay of ONE million rupees End of Year Investment A Investment B Investment C Investment D Invesrtment E Investment F 1 600,000 100,000 250,000 250,000 325,000 325,000 2 300,000 300,000 250,000 250,000 325,000 325,000 3 100,000 600,000 250,000 250,000 325,000 325,000 4 200,000 200,000 250,000 250,000 325,000 325,000 5 300,000 300,000 250,000 250,000 325,000 925,000 Total Cashflows 1,500,000 1,500,000 1,250,000 1,250,000 1,625,000 2,275,000 Cost of capital 10% 10% 5% 10% 10% 10% NPV 191,399 112,511 82,369 -52,303 232,006 635,605 Discounted Payback period 3.96 4.40 4.58 More than 5 3.86 3.86
  • 9. Internal Rate of Return(IRR) IRR is the discount rate that makes the Net Present Value (NPV) of the Project EQUAL to ZERO. An investment to be accepted if its IRR is higher than its Cost of Capital and should be rejected, if lower. IRR can be interpreted as a measure of profitability of its expected cashflows. IRR takes into account Time Value of money and risk of investment
  • 10. Expected cashflow streams and cost of capital – alternative investment proposals – Initial outlay of ONE million rupees End of Year Investment A Investment B Investment C Investment D Invesrtment E Investment F 1 600,000 100,000 250,000 250,000 325,000 325,000 2 300,000 300,000 250,000 250,000 325,000 325,000 3 100,000 600,000 250,000 250,000 325,000 325,000 4 200,000 200,000 250,000 250,000 325,000 325,000 5 300,000 300,000 250,000 250,000 325,000 925,000 Total Cashflows 1,500,000 1,500,000 1,250,000 1,250,000 1,625,000 2,275,000 Cost of capital 10% 10% 5% 10% 10% 10% IRR 19.05% 13.92% 7.93% 7.93% 18.72% 28.52%
  • 11. Net Present Value Discount factor is the inverse of compounding factor. NPV(k,N) = -CF0 + CF1 X DF1 + CF2 X DF2 + …………… …… .CFt X DFt + ………………………...CFN X DFN NPV = (-)Initial cash outlay + Present value of future cash flows at the cost of capital. Investment to be undertaken if its NPV is positive and should be rejected if NPV is negative
  • 12.
  • 13. NPV Profile Expected Cash Flows – CF(0), CF(1), CF(2)…….CF(n) Risk of expected cashflow stream Cost of Capital (k) required rate of return NPV = --CF(o) + ∑CF(t)/(1+k) t t=1,n NPV>0 NPV<0 Accept Project Reject Project
  • 14. Cost of capital The Project is going to be financed entirely with Debt, so its relevant cost of capital is the INTEREST Rate of Debt – or – Project is going to be financed entirely with Equity, so its cost of capital is Cost of Equity Although project does not have same risk as the Co, its relevant cost of capital should be equal to firm’s WACC because firm’s shareholders and debtors are paid with cash from firm’s cash flows, NOT from the Project’s cash flows When Project’s risk is different from the risk of the Firm, the Project’s cost of capital should be lowered to account for the risk reduction that diversification brings to the firm.
  • 15.  
  • 16.
  • 17. Financing Operation in India Equity/Risk Capital Public Equity Issue Debt/Borrowed Capital Foreign direct Investment Project Finance Term loans & Working capital finance External Commercial Borrowings Corporate Loan Market Corporate Debt Market
  • 18.
  • 19.
  • 20.
  • 21.
  • 22.
  • 23.
  • 24.
  • 25.