1. The document provides cost breakdowns for four projects including labor, materials, subcontractors, purchases, and overhead costs.
2. Project costs include take-off hours, materials, subcontractors, purchases, productivity factors, taxes, payroll, group costs, overhead, profit, and insurance.
3. The total bid prices for the four projects are $1,223,947.09, $1,006,333.57, $1,223,947.09, and $262,867.12 respectively.