Inventory Management
Independent Demand
A
B(4) C(2)
D(2) E(1) D(3) F(2)
Dependent Demand
Independent demand is uncertain.
Dependent demand is certain.
Inventory
Inventory
• Independent demand – finished goods, items
that are ready to be sold
– E.g. a computer
• Dependent demand – components of finished
products
– E.g. parts that make up the computer
Types of Inventories
• Raw materials & purchased parts
• Partially completed goods called
work in progress
• Finished-goods inventories
– (manufacturing firms)
or merchandise (retail stores)
Types of Inventories (Cont’d)
• Goods-in-transit to warehouses or
customers
Functions of Inventory
• To meet anticipated demand
• To smooth production
requirements
• To protect against stock-outs
Functions of Inventory (Cont’d)
• To help hedge against price
increases
• To permit operations
• To take advantage of quantity
discounts
Objective of Inventory Control
• To achieve satisfactory levels of customer
service while keeping inventory costs within
reasonable bounds
– Level of customer service
– Costs of ordering and carrying inventory
Effective Inventory Management
• A system to keep track of inventory
• A reliable forecast of demand
• Knowledge of lead times
• Reasonable estimates of
– Holding costs
– Ordering costs
– Shortage costs
• A classification system
Inventory Models
• Single period model
• Multiple period model
 Fixed order quantity model
 Fixed time period model
Key Inventory Terms
• Lead time: time interval between ordering and
receiving the order
• Holding (carrying) costs: cost to carry an item in
inventory for a length of time, usually a year
• Ordering costs: costs of ordering and receiving
inventory
• Shortage costs: costs when demand exceeds supply
Examples of holding costs
• Insurance costs
• Warehousing costs
• Spoilage/breakage losses
Example of Ordering Cost
• Cost to prepare a purchase requisition
• Cost to prepare a purchase order
• Cost of the labor required to inspect goods when they are
received
• Cost to put away goods once they have been received
• Cost to process the supplier invoice related to an order
• Cost to prepare and issue a payment to the supplier
Single period model
• A news paper boy has the following probabilities of
selling a magazine:
• No. of copies sold probabilities
10 .10
11 .15
12 .20
13 .25
14 .30
Cost of a copy is 30 paise and sale price is 50 paise. He
cannot return unsold copies. How many copies should
he order?
Conditional Loss Table
possible
demand probabilities possible stock action
(no. of
copies)
10
copies
11
copies
12
copies
13
copies
14
copies
10 0.1 0 30 60 90 120
11 0.15 20 0 30 60 90
12 0.2 40 20 0 30 60
13 0.25 60 40 20 0 30
14 0.3 80 60 40 20 0
Expected Loss Table
possible
demand probabilities possible stock action
(no. of
copies)
10
copies
11
copies
12
copies
13
copies
14
copies
10 0.1 0 3 6 9 12
11 0.15 3 0 4.5 9 13.5
12 0.2 8 4 0 6 12
13 0.25 15 10 5 0 7.5
14 0.3 24 18 12 6 0
EOL 50 35 27.5 30 45
Fixed-Order Quantity
Models
17
Fixed-Order Quantity Model:
Model Assumptions
• Demand for the product is constant and
uniform throughout the period.
• Lead time (time from ordering to receipt) is
constant.
• Price per unit of product is constant.
18
The Inventory Cycle
Profile of Inventory Level Over Time
Quantity
on hand
Q
Receive
order
Place
order
Receive
order
Place
order
Receive
order
Lead time
Reorder
point
Usage
rate
Time
Safety Stocks
Safety stock
buffer added to on hand inventory during lead time
Safety Stock
reduce risk of stockout during lead time
Operations Strategy
• Too much inventory
– Tends to hide problems
– Easier to live with problems than to eliminate
them
– Costly to maintain
• Wise strategy
– Reduce lot sizes
– Reduce safety stock
23
Basic Fixed-Order Quantity (EOQ) Model
Formula
H
2
Q
+S
Q
D
+DC=TC
Total Annual Cost =
Annual
Purchase
Cost
Annual
Ordering
Cost
Annual
Holding
Cost
+ +
TC = Total annual cost
D = annual Demand for the item,
over the year
C = Cost per unit
Q = Order quantity
S = Cost of placing an order
or setup cost
R = Reorder point
L = Lead time
H = Annual holding and storage
cost per unit of inventory
Cost Minimization Goal
Order Quantity (Q)
Ordering Costs
QO
AnnualCost
(optimal order quantity)
S
Q
D
H
Q
DCTC 
2
Minimum Total Cost
The total cost curve reaches its
minimum where the
Carrying Cost = Ordering Cost
Q
2
H
D
Q
S=
Reorder Point without
Safety Stock
Deriving the EOQ
Using calculus, we take the derivative of
the total cost function and set the
derivative (slope) equal to zero and solve
for Q.
Q =
2DS
H
=
2(Annual Demand )(Order or Setup Cost )
Annual Holding Cost
OPT
28
Deriving the EOQ
CostHoldingAnnual
Cost)SetuporderDemand)(Or2(Annual
=
H
2DS
=QOPT
Reorder point, R = d L
_
d = average daily demand (constant)
L = Lead time (constant)
_
29
EOQ Example Problem Data
Annual Demand = 1,000 units
Days per year considered in average daily demand = 365
Cost to place an order = $10
Holding cost per unit per year = $2.50
Lead time = 7 days
Cost per unit = $15
Given the information below, what are the EOQ and
reorder point?
30
EOQ Example Solution
Q =
2DS
H
=
2(1,000 )(10)
2.50
= 89.443 units orOPT 90 units
d =
1,000 units / year
365 days / year
= 2.74 units / day
units20or19.18=(7days)day2.74units/=Ld=Rpoint,Reorder
_
EOQ Example (2) Problem Data
Annual Demand = 10,000 units
Days per year considered in average daily demand = 365
Cost to place an order = $10
Holding cost per unit per year = 10% of cost per unit
Lead time = 10 days
Cost per unit = $15
Determine the economic order quantity and the reorder point.
EOQ Example (2) Solution
Q =
2DS
H
=
2(10,000 )(10)
1.50
= 365.148 units, orOPT 366 units
d =
10,000 units / year
365 days / year
= 27.397 units / day
units274or273.97=days)(10units/day27.397=Ld=R
_
Place an order for 366 units. When in the course of using
the inventory you are left with only 274 units, place the
next order of 366 units.
Reorder Point with Safety Stock
• S=Z × σLT
S= Safety Stock
Z= Number of standard deviations for a specified
service probability
σLT=Standard deviation of usage during the
lead time
Calculation of Safety Stock
• Standard deviation of demand is 10 units per
day, lead time is 5 days. Find safety stock at a
95 percentage probability of not stocking out?
σ5= SQRT OF [(10)2 + (10)2 +(10)2+(10)2+(10)2) = 22.36
S=Z × σLT =1.64+22.36 = 36.67 = Approx. 37.
Calculation of Reorder Point with
Safety Stock
• Consider an economic order quantity case
where annual demand D= 1000 units,
economic order quantity Q = 200 units, the
desired probability of not stocking out P=0.95,
the standard deviation of demand during lead
time= 25 units, and lead time L= 15 days.
Determine the reorder point. Assume that
demand is over a 250-workday year.
Calculation of Reorder Point with
Safety Stock
Fixed Time Period Model
with Safety Stock
Fixed Time Period Model with
Safety Stock
• Daily demand for the product is 10 units, with
a standard deviation of 3 units. The review
period is 30 days, and the lead time is 14 days.
Management has set a policy of satisfying 98
percentage of demand from items in stock. At
the beginning of this review period, there are
150 units in inventory. How many units should
be ordered?
Determinants of the Reorder Point
• The rate of demand
• The lead time
• Demand and/or lead time variability
• Stockout risk (safety stock)
ABC Classification System
 The Scheme
– Class B items
» Moderate in number--30-35%
» Moderate in rupee value--15-20%
» Exercise average control here
– Class C items
» Highest in number--about 50%
» Lowest in rupee value--5-10%
» Exercise the least control here
 Natural break or company policy scheme
ABC Classification
• Class A
– 5 – 15 % of units
– 70 – 80 % of value
• Class B
– 30 % of units
– 15 % of value
• Class C
– 50 – 60 % of units
– 5 – 10 % of value
ABC Classification: Example
1 $ 60 90
2 350 40
3 30 130
4 80 60
5 30 100
6 20 180
7 10 170
8 320 50
9 510 60
10 20 120
PART UNIT COST ANNUAL USAGE
ABC Classification:
Example (cont.)
Example 10.1
1 $ 60 90
2 350 40
3 30 130
4 80 60
5 30 100
6 20 180
7 10 170
8 320 50
9 510 60
10 20 120
PART UNIT COST ANNUAL USAGETOTAL % OF TOTAL % OF TOTAL
PART VALUE VALUE QUANTITY % CUMMULATIVE
9 $30,600 35.9 6.0 6.0
8 16,000 18.7 5.0 11.0
2 14,000 16.4 4.0 15.0
1 5,400 6.3 9.0 24.0
4 4,800 5.6 6.0 30.0
3 3,900 4.6 10.0 40.0
6 3,600 4.2 18.0 58.0
5 3,000 3.5 13.0 71.0
10 2,400 2.8 12.0 83.0
7 1,700 2.0 17.0 100.0
$85,400
A
B
C
% OF TOTAL % OF TOTAL
CLASS ITEMS VALUE QUANTITY
A 9, 8, 2 71.0 15.0
B 1, 4, 3 16.5 25.0
C 6, 5, 10, 7 12.5 60.0

More Related Content

What's hot

inventory management ppt
inventory management pptinventory management ppt
inventory management pptMayank Baheti
 
Make to order, stock, assembly
Make to order, stock, assemblyMake to order, stock, assembly
Make to order, stock, assemblyHammaduddin
 
Inventory management
Inventory managementInventory management
Inventory managementvimal raj
 
Inventory Management
Inventory ManagementInventory Management
Inventory Managementanoos
 
Inventory management
Inventory managementInventory management
Inventory managementsaurabhsabiba
 
Inventory management
Inventory managementInventory management
Inventory managementMayank Ghosh
 
Inventory Policy Decisions Deepa
Inventory Policy Decisions DeepaInventory Policy Decisions Deepa
Inventory Policy Decisions DeepaTICS
 
SAP MM PP Material requirement planning
SAP MM PP Material requirement planning SAP MM PP Material requirement planning
SAP MM PP Material requirement planning Lokesh Modem
 
C9 inventory management
C9 inventory managementC9 inventory management
C9 inventory managementhakimizaki
 
Lean Inventory
Lean Inventory Lean Inventory
Lean Inventory Tom Craig
 
Becdoms ppt on inventory management
Becdoms ppt on inventory management  Becdoms ppt on inventory management
Becdoms ppt on inventory management Babasab Patil
 
Reorder point
Reorder pointReorder point
Reorder pointDon Paul
 
Inventory Management - a ppt for PGDM/MBA
Inventory Management - a ppt for PGDM/MBAInventory Management - a ppt for PGDM/MBA
Inventory Management - a ppt for PGDM/MBAAJ Raina
 
Material requirements planning & erp ppt @ bec doms
Material requirements planning & erp  ppt @ bec domsMaterial requirements planning & erp  ppt @ bec doms
Material requirements planning & erp ppt @ bec domsBabasab Patil
 
Inventory Management Presentation
Inventory Management  Presentation Inventory Management  Presentation
Inventory Management Presentation KattareeyaPrompreing
 

What's hot (20)

Demand Planning
Demand PlanningDemand Planning
Demand Planning
 
inventory management ppt
inventory management pptinventory management ppt
inventory management ppt
 
Make to order, stock, assembly
Make to order, stock, assemblyMake to order, stock, assembly
Make to order, stock, assembly
 
Inventory management
Inventory managementInventory management
Inventory management
 
Inventory Management
Inventory ManagementInventory Management
Inventory Management
 
Inventory management
Inventory managementInventory management
Inventory management
 
Inventory Management
Inventory Management Inventory Management
Inventory Management
 
Inventory management
Inventory managementInventory management
Inventory management
 
Inventory Policy Decisions Deepa
Inventory Policy Decisions DeepaInventory Policy Decisions Deepa
Inventory Policy Decisions Deepa
 
SAP MM PP Material requirement planning
SAP MM PP Material requirement planning SAP MM PP Material requirement planning
SAP MM PP Material requirement planning
 
C9 inventory management
C9 inventory managementC9 inventory management
C9 inventory management
 
Lean Inventory
Lean Inventory Lean Inventory
Lean Inventory
 
Inventory 1.1
Inventory 1.1Inventory 1.1
Inventory 1.1
 
Supply chain management
Supply chain managementSupply chain management
Supply chain management
 
Becdoms ppt on inventory management
Becdoms ppt on inventory management  Becdoms ppt on inventory management
Becdoms ppt on inventory management
 
Reorder point
Reorder pointReorder point
Reorder point
 
BASICS OF STORES AND MATERIALS MGT, (1)
BASICS OF STORES AND MATERIALS MGT, (1)BASICS OF STORES AND MATERIALS MGT, (1)
BASICS OF STORES AND MATERIALS MGT, (1)
 
Inventory Management - a ppt for PGDM/MBA
Inventory Management - a ppt for PGDM/MBAInventory Management - a ppt for PGDM/MBA
Inventory Management - a ppt for PGDM/MBA
 
Material requirements planning & erp ppt @ bec doms
Material requirements planning & erp  ppt @ bec domsMaterial requirements planning & erp  ppt @ bec doms
Material requirements planning & erp ppt @ bec doms
 
Inventory Management Presentation
Inventory Management  Presentation Inventory Management  Presentation
Inventory Management Presentation
 

Similar to Inventory management

24867879 inventory-management-control-lecture-3
24867879 inventory-management-control-lecture-324867879 inventory-management-control-lecture-3
24867879 inventory-management-control-lecture-3Harshawardhan Thakare
 
Inventory management
Inventory managementInventory management
Inventory managementKuldeep Uttam
 
Lession - 1(Inventory Management).pptx
Lession - 1(Inventory Management).pptxLession - 1(Inventory Management).pptx
Lession - 1(Inventory Management).pptxRajeevRanjan743854
 
AGIFORS1995-EPIM-QUILLINAN
AGIFORS1995-EPIM-QUILLINANAGIFORS1995-EPIM-QUILLINAN
AGIFORS1995-EPIM-QUILLINANJohn Quillinan
 
Inventory Man2
Inventory Man2Inventory Man2
Inventory Man2ajithsrc
 
Admissions in india for b.tech
Admissions in india for b.techAdmissions in india for b.tech
Admissions in india for b.techCss Founder
 
Inventory management
Inventory managementInventory management
Inventory managementAngelaMaurya
 
kuldeep10119015pi-131028193336-phpapp01.pdf
kuldeep10119015pi-131028193336-phpapp01.pdfkuldeep10119015pi-131028193336-phpapp01.pdf
kuldeep10119015pi-131028193336-phpapp01.pdfAnmolAshraya1
 
kuldeep10119015pi-131028193336-phpapp01.pdf
kuldeep10119015pi-131028193336-phpapp01.pdfkuldeep10119015pi-131028193336-phpapp01.pdf
kuldeep10119015pi-131028193336-phpapp01.pdfAnmolAshraya1
 
Session 6
Session 6Session 6
Session 6thangv
 
OM_4.ppt
OM_4.pptOM_4.ppt
OM_4.pptsengar3
 
Productions & Operations Management Chapter 12
Productions & Operations Management Chapter 12Productions & Operations Management Chapter 12
Productions & Operations Management Chapter 12jncgw5t6xq
 
Managing Inventory In SC Lect#12 in.pptx
Managing Inventory In SC Lect#12 in.pptxManaging Inventory In SC Lect#12 in.pptx
Managing Inventory In SC Lect#12 in.pptxSahilAgrawal80
 

Similar to Inventory management (20)

24867879 inventory-management-control-lecture-3
24867879 inventory-management-control-lecture-324867879 inventory-management-control-lecture-3
24867879 inventory-management-control-lecture-3
 
Inventory management
Inventory managementInventory management
Inventory management
 
Lession - 1(Inventory Management).pptx
Lession - 1(Inventory Management).pptxLession - 1(Inventory Management).pptx
Lession - 1(Inventory Management).pptx
 
Goods16
Goods16Goods16
Goods16
 
AGIFORS1995-EPIM-QUILLINAN
AGIFORS1995-EPIM-QUILLINANAGIFORS1995-EPIM-QUILLINAN
AGIFORS1995-EPIM-QUILLINAN
 
Unit 3-inventory control
Unit 3-inventory controlUnit 3-inventory control
Unit 3-inventory control
 
Inventory notes
Inventory notesInventory notes
Inventory notes
 
Inventry..
Inventry..Inventry..
Inventry..
 
Inventory Man2
Inventory Man2Inventory Man2
Inventory Man2
 
Admissions in india for b.tech
Admissions in india for b.techAdmissions in india for b.tech
Admissions in india for b.tech
 
Inventory management
Inventory managementInventory management
Inventory management
 
Ops5
Ops5Ops5
Ops5
 
Inventory control
Inventory controlInventory control
Inventory control
 
kuldeep10119015pi-131028193336-phpapp01.pdf
kuldeep10119015pi-131028193336-phpapp01.pdfkuldeep10119015pi-131028193336-phpapp01.pdf
kuldeep10119015pi-131028193336-phpapp01.pdf
 
kuldeep10119015pi-131028193336-phpapp01.pdf
kuldeep10119015pi-131028193336-phpapp01.pdfkuldeep10119015pi-131028193336-phpapp01.pdf
kuldeep10119015pi-131028193336-phpapp01.pdf
 
Chapter 6_OM
Chapter 6_OMChapter 6_OM
Chapter 6_OM
 
Session 6
Session 6Session 6
Session 6
 
OM_4.ppt
OM_4.pptOM_4.ppt
OM_4.ppt
 
Productions & Operations Management Chapter 12
Productions & Operations Management Chapter 12Productions & Operations Management Chapter 12
Productions & Operations Management Chapter 12
 
Managing Inventory In SC Lect#12 in.pptx
Managing Inventory In SC Lect#12 in.pptxManaging Inventory In SC Lect#12 in.pptx
Managing Inventory In SC Lect#12 in.pptx
 

Recently uploaded

VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
Risk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptxRisk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptxSaujanya Jung Pandey
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
LPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System PresentationLPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System Presentationthomas851723
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
Training Methods and Training Objectives
Training Methods and Training ObjectivesTraining Methods and Training Objectives
Training Methods and Training Objectivesmintusiprd
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
LPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering PresentationLPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering Presentationthomas851723
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 

Recently uploaded (20)

VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
Risk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptxRisk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptx
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
LPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System PresentationLPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System Presentation
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
Training Methods and Training Objectives
Training Methods and Training ObjectivesTraining Methods and Training Objectives
Training Methods and Training Objectives
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
LPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering PresentationLPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering Presentation
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 

Inventory management

  • 2. Independent Demand A B(4) C(2) D(2) E(1) D(3) F(2) Dependent Demand Independent demand is uncertain. Dependent demand is certain. Inventory
  • 3. Inventory • Independent demand – finished goods, items that are ready to be sold – E.g. a computer • Dependent demand – components of finished products – E.g. parts that make up the computer
  • 4. Types of Inventories • Raw materials & purchased parts • Partially completed goods called work in progress • Finished-goods inventories – (manufacturing firms) or merchandise (retail stores)
  • 5. Types of Inventories (Cont’d) • Goods-in-transit to warehouses or customers
  • 6. Functions of Inventory • To meet anticipated demand • To smooth production requirements • To protect against stock-outs
  • 7. Functions of Inventory (Cont’d) • To help hedge against price increases • To permit operations • To take advantage of quantity discounts
  • 8. Objective of Inventory Control • To achieve satisfactory levels of customer service while keeping inventory costs within reasonable bounds – Level of customer service – Costs of ordering and carrying inventory
  • 9. Effective Inventory Management • A system to keep track of inventory • A reliable forecast of demand • Knowledge of lead times • Reasonable estimates of – Holding costs – Ordering costs – Shortage costs • A classification system
  • 10. Inventory Models • Single period model • Multiple period model  Fixed order quantity model  Fixed time period model
  • 11. Key Inventory Terms • Lead time: time interval between ordering and receiving the order • Holding (carrying) costs: cost to carry an item in inventory for a length of time, usually a year • Ordering costs: costs of ordering and receiving inventory • Shortage costs: costs when demand exceeds supply
  • 12. Examples of holding costs • Insurance costs • Warehousing costs • Spoilage/breakage losses
  • 13. Example of Ordering Cost • Cost to prepare a purchase requisition • Cost to prepare a purchase order • Cost of the labor required to inspect goods when they are received • Cost to put away goods once they have been received • Cost to process the supplier invoice related to an order • Cost to prepare and issue a payment to the supplier
  • 14. Single period model • A news paper boy has the following probabilities of selling a magazine: • No. of copies sold probabilities 10 .10 11 .15 12 .20 13 .25 14 .30 Cost of a copy is 30 paise and sale price is 50 paise. He cannot return unsold copies. How many copies should he order?
  • 15. Conditional Loss Table possible demand probabilities possible stock action (no. of copies) 10 copies 11 copies 12 copies 13 copies 14 copies 10 0.1 0 30 60 90 120 11 0.15 20 0 30 60 90 12 0.2 40 20 0 30 60 13 0.25 60 40 20 0 30 14 0.3 80 60 40 20 0
  • 16. Expected Loss Table possible demand probabilities possible stock action (no. of copies) 10 copies 11 copies 12 copies 13 copies 14 copies 10 0.1 0 3 6 9 12 11 0.15 3 0 4.5 9 13.5 12 0.2 8 4 0 6 12 13 0.25 15 10 5 0 7.5 14 0.3 24 18 12 6 0 EOL 50 35 27.5 30 45
  • 18. Fixed-Order Quantity Model: Model Assumptions • Demand for the product is constant and uniform throughout the period. • Lead time (time from ordering to receipt) is constant. • Price per unit of product is constant. 18
  • 19. The Inventory Cycle Profile of Inventory Level Over Time Quantity on hand Q Receive order Place order Receive order Place order Receive order Lead time Reorder point Usage rate Time
  • 20. Safety Stocks Safety stock buffer added to on hand inventory during lead time
  • 21. Safety Stock reduce risk of stockout during lead time
  • 22. Operations Strategy • Too much inventory – Tends to hide problems – Easier to live with problems than to eliminate them – Costly to maintain • Wise strategy – Reduce lot sizes – Reduce safety stock
  • 23. 23 Basic Fixed-Order Quantity (EOQ) Model Formula H 2 Q +S Q D +DC=TC Total Annual Cost = Annual Purchase Cost Annual Ordering Cost Annual Holding Cost + + TC = Total annual cost D = annual Demand for the item, over the year C = Cost per unit Q = Order quantity S = Cost of placing an order or setup cost R = Reorder point L = Lead time H = Annual holding and storage cost per unit of inventory
  • 24. Cost Minimization Goal Order Quantity (Q) Ordering Costs QO AnnualCost (optimal order quantity) S Q D H Q DCTC  2
  • 25. Minimum Total Cost The total cost curve reaches its minimum where the Carrying Cost = Ordering Cost Q 2 H D Q S=
  • 27. Deriving the EOQ Using calculus, we take the derivative of the total cost function and set the derivative (slope) equal to zero and solve for Q. Q = 2DS H = 2(Annual Demand )(Order or Setup Cost ) Annual Holding Cost OPT
  • 28. 28 Deriving the EOQ CostHoldingAnnual Cost)SetuporderDemand)(Or2(Annual = H 2DS =QOPT Reorder point, R = d L _ d = average daily demand (constant) L = Lead time (constant) _
  • 29. 29 EOQ Example Problem Data Annual Demand = 1,000 units Days per year considered in average daily demand = 365 Cost to place an order = $10 Holding cost per unit per year = $2.50 Lead time = 7 days Cost per unit = $15 Given the information below, what are the EOQ and reorder point?
  • 30. 30 EOQ Example Solution Q = 2DS H = 2(1,000 )(10) 2.50 = 89.443 units orOPT 90 units d = 1,000 units / year 365 days / year = 2.74 units / day units20or19.18=(7days)day2.74units/=Ld=Rpoint,Reorder _
  • 31. EOQ Example (2) Problem Data Annual Demand = 10,000 units Days per year considered in average daily demand = 365 Cost to place an order = $10 Holding cost per unit per year = 10% of cost per unit Lead time = 10 days Cost per unit = $15 Determine the economic order quantity and the reorder point.
  • 32. EOQ Example (2) Solution Q = 2DS H = 2(10,000 )(10) 1.50 = 365.148 units, orOPT 366 units d = 10,000 units / year 365 days / year = 27.397 units / day units274or273.97=days)(10units/day27.397=Ld=R _ Place an order for 366 units. When in the course of using the inventory you are left with only 274 units, place the next order of 366 units.
  • 33. Reorder Point with Safety Stock • S=Z × σLT S= Safety Stock Z= Number of standard deviations for a specified service probability σLT=Standard deviation of usage during the lead time
  • 34. Calculation of Safety Stock • Standard deviation of demand is 10 units per day, lead time is 5 days. Find safety stock at a 95 percentage probability of not stocking out? σ5= SQRT OF [(10)2 + (10)2 +(10)2+(10)2+(10)2) = 22.36 S=Z × σLT =1.64+22.36 = 36.67 = Approx. 37.
  • 35. Calculation of Reorder Point with Safety Stock • Consider an economic order quantity case where annual demand D= 1000 units, economic order quantity Q = 200 units, the desired probability of not stocking out P=0.95, the standard deviation of demand during lead time= 25 units, and lead time L= 15 days. Determine the reorder point. Assume that demand is over a 250-workday year.
  • 36. Calculation of Reorder Point with Safety Stock
  • 37. Fixed Time Period Model with Safety Stock
  • 38. Fixed Time Period Model with Safety Stock
  • 39. • Daily demand for the product is 10 units, with a standard deviation of 3 units. The review period is 30 days, and the lead time is 14 days. Management has set a policy of satisfying 98 percentage of demand from items in stock. At the beginning of this review period, there are 150 units in inventory. How many units should be ordered?
  • 40.
  • 41. Determinants of the Reorder Point • The rate of demand • The lead time • Demand and/or lead time variability • Stockout risk (safety stock)
  • 42. ABC Classification System  The Scheme – Class B items » Moderate in number--30-35% » Moderate in rupee value--15-20% » Exercise average control here – Class C items » Highest in number--about 50% » Lowest in rupee value--5-10% » Exercise the least control here  Natural break or company policy scheme
  • 43. ABC Classification • Class A – 5 – 15 % of units – 70 – 80 % of value • Class B – 30 % of units – 15 % of value • Class C – 50 – 60 % of units – 5 – 10 % of value
  • 44. ABC Classification: Example 1 $ 60 90 2 350 40 3 30 130 4 80 60 5 30 100 6 20 180 7 10 170 8 320 50 9 510 60 10 20 120 PART UNIT COST ANNUAL USAGE
  • 45. ABC Classification: Example (cont.) Example 10.1 1 $ 60 90 2 350 40 3 30 130 4 80 60 5 30 100 6 20 180 7 10 170 8 320 50 9 510 60 10 20 120 PART UNIT COST ANNUAL USAGETOTAL % OF TOTAL % OF TOTAL PART VALUE VALUE QUANTITY % CUMMULATIVE 9 $30,600 35.9 6.0 6.0 8 16,000 18.7 5.0 11.0 2 14,000 16.4 4.0 15.0 1 5,400 6.3 9.0 24.0 4 4,800 5.6 6.0 30.0 3 3,900 4.6 10.0 40.0 6 3,600 4.2 18.0 58.0 5 3,000 3.5 13.0 71.0 10 2,400 2.8 12.0 83.0 7 1,700 2.0 17.0 100.0 $85,400 A B C % OF TOTAL % OF TOTAL CLASS ITEMS VALUE QUANTITY A 9, 8, 2 71.0 15.0 B 1, 4, 3 16.5 25.0 C 6, 5, 10, 7 12.5 60.0