EASTERN MARKET
ANC Meeting
October 15, 2019
Project Goals + Objectives
Agenda
01/
03/
02/ Master Plan Overview
Community Input Process
Urban Forestry Coordination05/
Transportation Impact
Study Update
06/
Maintenance Planning07/
04/ Pavilion + Shade Structures
 Update park to 21st century standards and best practices in
programming, materials, safety and sustainability
 Create a Town Square for Capitol Hill, a destination park
 Improve pedestrian access, safety, circulation and wayfinding
 Introduce playground amenity
 Improve physical relationship with library
Project Goals + Objectives
Project is driven by the 2015 community-led master plan
Eastern Market Metro Park Advisory Team
Community Meetings
 Concept Design- December 13, 2018; February 6, 2019; April 3, 2019
 Schematic Design- July 31, 2019
 2 Community Surveys conducted online:
 732 respondents in December/January
 429 respondents in July
Community Input Process
 March 18, 2019
 May 14, 2019
 June 19, 2019
 October 22, 2018
 December 10, 2018
 January 29, 2019
 July 23, 2019
 August 27, 2019
 September 25, 2019
 Playground location shifted
 Improved tree canopy (existing and proposed)
 Added traffic calming measures and improved pedestrian
connectivity and safety, including D Street closure
 Addition of a pavilion
 Addition of splash pad
 Addition of a table-top in front of Library with safety bollards
 Bioretention treatment approach
 Incorporation of park style and playground theme
Key Community Impacts
PLAN
OVERVIEW
D STREET
D STREET
D STREET
D STREET
SC AVE.
SC AVE.
9THSTREET
8THSTREET
7THSTREET
8THSTREET
PERSPECTIVE VIEW PARCEL 5, LOOKING WEST Renderings shown for illustrative purpose only, final layout and materials may vary.
PERSPECTIVE VIEW PARCEL 5, LOOKING WEST Renderings shown for illustrative purpose only, final layout and materials may vary.
PERSPECTIVE VIEW PARCEL 5, LOOKING WEST Renderings shown for illustrative purpose only, final layout and materials may vary.
PERSPECTIVE VIEW OVERALL Renderings shown for illustrative purpose only, final layout and materials may vary.
PAVILLION
LOCATION
 Approximate
location and size
(20-25’ diameter)
 Maintain views to
library
 Maintain plaza area
for audience and
flexible event space
Urban Forestry Requests
 Protect critical root zone (CRZ)
 Locate bioretention away from existing trees
 Minimize construction/post construction activities in CRZ
Design Refinements
 Shift playground away from existing trees
 Utilize low impact surfacing
 Relocating bioretention facilities
 Arborist to be engaged to support design + construction activities
Urban Forestry Coordination
TRANSPORTATION IMPACT STUDY
NETWORK CHANGES
LEGEND
TRAFFIC REVERSAL
ROAD CLOSURE
STREETSCAPE IMPROVEMENTS
TRANSPORTATION IMPACT STUDY
CONCEPT PLAN – INTERSECTION IMPROVEMENTS
TRANSPORTATION IMPACT STUDY
CONCEPT PLAN – PARKING IMPACTS
LEGEND
PARKING PROHIBITIED
METRO BUS STOP
LOADING/METERED PARKING
30-MINUTE PARKING
ZONE 6 PERMIT/OTHER 2-HOUR
ZIPCAR
LOSSES(-)/GAINS(+)
-5
-3
-5
-2
-4
+2
+1
-3
-3
TRANSPORTATION IMPACT STUDY
ANALYSIS STUDY AREA
Detailed Study Area
Greater Study Area
TRANSPORTATION IMPACT STUDY
DETAILED STUDY AREA ANALYSIS - MANUAL REDISTRIBUTION METHODOLOGY
TRANSPORTATION IMPACT STUDY
DETAILED STUDY AREA- SATURDAY PEAK HR VEHICLE + PEDESTRIAN VOLUMES
TRANSPORTATION IMPACT STUDY
DETAILED STUDY AREA- EXISTING WEEKDAY PEAK HR VEHICLE + PED VOLUMES
TRANSPORTATION IMPACT STUDY
DETAILED STUDY AREA- FUTURE WEEKDAY PEAK HR VEHICLE + PED VOLUMES
TRANSPORTATION IMPACT STUDY
GREATER STUDY AREA ANALYSIS – MORNING RUSH HOUR VOLUME CHANGES
Veh/hr (-) Dec. (+) Inc.
change
0-50
50-100
100-200+
TRANSPORTATION IMPACT STUDY
GREATER STUDY AREA ANALYSIS – AFTERNOON RUSH HOUR VOLUME CHANGES
Veh/hr (-) Dec. (+) Inc.
change
0-50
50-100
100-200+
TRANSPORTATION IMPACT STUDY
DETAILED STUDY AREA– WEEKDAY AM + PM PEAK HOUR LEVEL-OF-SERVICE
TRANSPORTATION IMPACT STUDY
SUMMARY AND MITIGATION
STRATEGIES
Existing Future
C
D
All overall Intersection LOS “D” or Better Satisfied
D Street Reversals
Improvement at D St (south) at 8th St - PM, from LOS E to A
Slight deterioration at both intersections of Penn (EB and WB) at 8th St (both LOS B to
C
D Street Slip-Lane Closures
No overall intersection deterioration associated with the elimination of the D St (north
and south) slip lanes
One intersection approach, 8th St NB at Penn EB - PM experienced deterioration
(LOS C to D)
Mitigation Strategies
9th St SB at Penn Ave WB - AM (LOS F), suffers disproportionately (112 sec of delay
versus others <50 sec)
Signal optimization did not provide significant improvement
Dedicated right turn lane on 9th St SB at Penn Ave - AM will provide favorable LOS
(overall intersection LOS = C; approach LOS = D - 49 seconds delay)
9thStreetS.E.
DGS to provide day to day and seasonal maintenance:
 Mowing
 Pruning
 Bioretention facility upkeep
 Repairs
 Winterization
DGS to provide capital upgrades
Draft Life Cycle Budget to be released soon
Maintenance Planning
QUESTIONS??
SCHEMATIC PLAN
EASTERN MARKET METRO
PARK
December 10, 2018
EASTERN MARKET METRO PARK
October 15, 2019

Emmp community presentations_anc oct 15 presentation final rev1

  • 1.
  • 2.
    Project Goals +Objectives Agenda 01/ 03/ 02/ Master Plan Overview Community Input Process Urban Forestry Coordination05/ Transportation Impact Study Update 06/ Maintenance Planning07/ 04/ Pavilion + Shade Structures
  • 3.
     Update parkto 21st century standards and best practices in programming, materials, safety and sustainability  Create a Town Square for Capitol Hill, a destination park  Improve pedestrian access, safety, circulation and wayfinding  Introduce playground amenity  Improve physical relationship with library Project Goals + Objectives
  • 4.
    Project is drivenby the 2015 community-led master plan Eastern Market Metro Park Advisory Team Community Meetings  Concept Design- December 13, 2018; February 6, 2019; April 3, 2019  Schematic Design- July 31, 2019  2 Community Surveys conducted online:  732 respondents in December/January  429 respondents in July Community Input Process  March 18, 2019  May 14, 2019  June 19, 2019  October 22, 2018  December 10, 2018  January 29, 2019  July 23, 2019  August 27, 2019  September 25, 2019
  • 5.
     Playground locationshifted  Improved tree canopy (existing and proposed)  Added traffic calming measures and improved pedestrian connectivity and safety, including D Street closure  Addition of a pavilion  Addition of splash pad  Addition of a table-top in front of Library with safety bollards  Bioretention treatment approach  Incorporation of park style and playground theme Key Community Impacts
  • 6.
    PLAN OVERVIEW D STREET D STREET DSTREET D STREET SC AVE. SC AVE. 9THSTREET 8THSTREET 7THSTREET 8THSTREET
  • 7.
    PERSPECTIVE VIEW PARCEL5, LOOKING WEST Renderings shown for illustrative purpose only, final layout and materials may vary.
  • 8.
    PERSPECTIVE VIEW PARCEL5, LOOKING WEST Renderings shown for illustrative purpose only, final layout and materials may vary.
  • 9.
    PERSPECTIVE VIEW PARCEL5, LOOKING WEST Renderings shown for illustrative purpose only, final layout and materials may vary.
  • 10.
    PERSPECTIVE VIEW OVERALLRenderings shown for illustrative purpose only, final layout and materials may vary.
  • 11.
    PAVILLION LOCATION  Approximate location andsize (20-25’ diameter)  Maintain views to library  Maintain plaza area for audience and flexible event space
  • 12.
    Urban Forestry Requests Protect critical root zone (CRZ)  Locate bioretention away from existing trees  Minimize construction/post construction activities in CRZ Design Refinements  Shift playground away from existing trees  Utilize low impact surfacing  Relocating bioretention facilities  Arborist to be engaged to support design + construction activities Urban Forestry Coordination
  • 13.
    TRANSPORTATION IMPACT STUDY NETWORKCHANGES LEGEND TRAFFIC REVERSAL ROAD CLOSURE STREETSCAPE IMPROVEMENTS
  • 14.
    TRANSPORTATION IMPACT STUDY CONCEPTPLAN – INTERSECTION IMPROVEMENTS
  • 15.
    TRANSPORTATION IMPACT STUDY CONCEPTPLAN – PARKING IMPACTS LEGEND PARKING PROHIBITIED METRO BUS STOP LOADING/METERED PARKING 30-MINUTE PARKING ZONE 6 PERMIT/OTHER 2-HOUR ZIPCAR LOSSES(-)/GAINS(+) -5 -3 -5 -2 -4 +2 +1 -3 -3
  • 16.
    TRANSPORTATION IMPACT STUDY ANALYSISSTUDY AREA Detailed Study Area Greater Study Area
  • 17.
    TRANSPORTATION IMPACT STUDY DETAILEDSTUDY AREA ANALYSIS - MANUAL REDISTRIBUTION METHODOLOGY
  • 18.
    TRANSPORTATION IMPACT STUDY DETAILEDSTUDY AREA- SATURDAY PEAK HR VEHICLE + PEDESTRIAN VOLUMES
  • 19.
    TRANSPORTATION IMPACT STUDY DETAILEDSTUDY AREA- EXISTING WEEKDAY PEAK HR VEHICLE + PED VOLUMES
  • 20.
    TRANSPORTATION IMPACT STUDY DETAILEDSTUDY AREA- FUTURE WEEKDAY PEAK HR VEHICLE + PED VOLUMES
  • 21.
    TRANSPORTATION IMPACT STUDY GREATERSTUDY AREA ANALYSIS – MORNING RUSH HOUR VOLUME CHANGES Veh/hr (-) Dec. (+) Inc. change 0-50 50-100 100-200+
  • 22.
    TRANSPORTATION IMPACT STUDY GREATERSTUDY AREA ANALYSIS – AFTERNOON RUSH HOUR VOLUME CHANGES Veh/hr (-) Dec. (+) Inc. change 0-50 50-100 100-200+
  • 23.
    TRANSPORTATION IMPACT STUDY DETAILEDSTUDY AREA– WEEKDAY AM + PM PEAK HOUR LEVEL-OF-SERVICE
  • 24.
    TRANSPORTATION IMPACT STUDY SUMMARYAND MITIGATION STRATEGIES Existing Future C D All overall Intersection LOS “D” or Better Satisfied D Street Reversals Improvement at D St (south) at 8th St - PM, from LOS E to A Slight deterioration at both intersections of Penn (EB and WB) at 8th St (both LOS B to C D Street Slip-Lane Closures No overall intersection deterioration associated with the elimination of the D St (north and south) slip lanes One intersection approach, 8th St NB at Penn EB - PM experienced deterioration (LOS C to D) Mitigation Strategies 9th St SB at Penn Ave WB - AM (LOS F), suffers disproportionately (112 sec of delay versus others <50 sec) Signal optimization did not provide significant improvement Dedicated right turn lane on 9th St SB at Penn Ave - AM will provide favorable LOS (overall intersection LOS = C; approach LOS = D - 49 seconds delay) 9thStreetS.E.
  • 25.
    DGS to provideday to day and seasonal maintenance:  Mowing  Pruning  Bioretention facility upkeep  Repairs  Winterization DGS to provide capital upgrades Draft Life Cycle Budget to be released soon Maintenance Planning
  • 26.
  • 27.
    EASTERN MARKET METRO PARK December10, 2018 EASTERN MARKET METRO PARK October 15, 2019