SlideShare a Scribd company logo
INNOVAT MINERAL PROCESS SOLUTIONS LIMITED
760 Brant St., Suite 405C, Burlington ON, L7R 4B8, Canada
Tel 905-333-7133
Fax 905-333-9336
www.vatleach.com
INN14-CS-001 Sept 30, 2014
Document: TECHNICAL MEMORANDUM
Project: INNOVAT Case Study – 10,000 t/d Heap Leach – Panama
This memorandum presents an economic comparison based on a 10,000 t/d heap leach operation
located in Latin America. All assumptions, equipment layouts, mining, and costing, for the
purposes of this comparison, have been accepted from the pre-feasibility base case and have not
been adjusted except as required to implement a Continuous Vat Leaching (CVL) based process.
INNOVAT was directly engaged in engineering activities related to the project from 2007
through 2013, including bulk pilot plant testing, and believes that the cost estimates associated
with the implementation of Continuous Vat Leaching have been conservatively estimated, and
that potentially significant savings in both processing, and material handling can be realized with
modification to the base case.
1.0 INTRODUCTION
Three economic analyses are presented in this memo, two of which have been prepared by
INNOVAT, and one of which was presented as a heap leach, prefeasibility study by the owner.
All costing where possible has been carried forward, or based on the base case. The models are
as follows:
• Base case: 10,000t/d Heap Leach Facility (unadjusted)
• Direct Comparison: 10,000t/d Continuous Vat Leaching
• Alternate: 5,000t/d Continuous Vat Leaching
The following considerations were used when evaluating the alternate methods:
• Maintain design criteria of the original project plan
• Use direct cost from original project plan where feasible
CASE STUDY – 10,000t/d HEAP LEACH COMPARISON – INN14CS 2
INNOVAT MINERAL PROCESS SOLUTIONS LIMITED
• Use unit cost from original project plan where direct cost is not feasible
2.0 BASIS OF COMPARISON
INNOVAT has not modified the flow sheets in any way beyond addition of components which
are required for Continuous Vat Leaching, and removal of components related specifically to
Heap Leaching.
The mining and material handling process has been unmodified for the 10,000t/d Continuous Vat
Leach case, and modified only as a result of the reduction in processing rate for the 5,000t/d
CVL case.
The crushing circuit has been modified as a result of the Continuous Vat Leaching process feed
size requirement of -6mm. In order to use the primary and secondary crusher from the base case,
an additional tertiary, and quaternary crushing stage have been added to both of the CVL
scenarios. The cost of this inclusion has been captured in both the CAPEX and OPEX within the
comparison. It is expected that a crushing circuit designed specifically to reduce the particle size
from ROM to -6mm would require three stages and have a small cost savings over the crushing
circuit utilized in this comparison.
The CVL facility has been placed near the base of the proposed heap leach facility, and receives
ore from the crushed ore stockpile. No modification has been made to the material handling /
conveyor system as presented in the base case. The CVL is expected to discharge the material to
a tailings pile which has been modelled to occupy the space currently designed for the heap leach
facility. The costing associated with this tailings pile has been developed based on a
combination of the costs reported for the heap leach facility, and the costs reported for the waste
rock dump.
3.0 COMPARISON OF COSTS
3.1 PRE-PRODUCTION CAPITAL EXPENDITURE - PROCESS
In the case of the 10,000t/d CVL system, cost reductions associated with the centralization of the
process were included and amounted primarily to a minor reduction in the cost of the reagent
CASE STUDY – 10,000t/d HEAP LEACH COMPARISON – INN14CS 3
INNOVAT MINERAL PROCESS SOLUTIONS LIMITED
system. The pre-production direct cost comparison between the base case and 10,000t/d CVL
case excluding Area 30 – Heap Leach & Solution Handling, and Area 60 – Detoxification,
produces a difference of 0.33% capital expense. If we look at only Area 30 and 60, the
preproduction cost of the CVL scenario represents a 50% cost premium over the base case. It is
important to note however, that this cost premium is almost completely offset in year one during
the heap leach expansion. The difference between the total process & infrastructure capital cost
(pre-production) between the base case and 10,000t/d CVL case is a 12.4% increase in capital
cost.
In the case of the 5,000t/d CVL system, direct cost of associated equipment was reduced as a
result of the 50% reduction in processing rate. The aggregate reduction in direct cost associated
with this throughput reduction is 20.8%, excluding Area 30 – Heap Leach & Solution Handling,
and Area 60 – Detoxification. The capital cost difference associated with Area 30 & 60 is 9.2%
in favour of the 5,000t/d CVL case. Further savings occur following year one, where leach pad
expansion must occur with the base case. The difference between the total process &
infrastructure capital cost (pre-production) between the base case and 5,000t/d CVL case is a
19.4% decrease in capital cost.
3.2 PRE-PRODUCTION CAPITAL EXPENDITURE – MINING
As the mining schedule and mining method were not modified, the mining costs have been
carried directly for the 10,000t/d case, and reduced only by decreasing the number of required
haul trucks in the 5,000t/d case. The 10,000t/d CVL case shares a common mining capital
expenditure throughout life of mine in comparison to the base case, whereas the 5,000t/d case
includes a capital savings of 19.6% as the equipment requirement for 5,000t/d has decreased with
respect to the base case.
3.3 OPERATING EXPENSE - MINING
Mining costs have not been modified for the 10,000t/d comparison as the mining and material
handling process has not been altered. Additional mining cost was included in the 5,000t/d case
owing to the reduced equipment efficiency. This increase over the mine life amounts to a mining
operating cost increase of 6.9%.
CASE STUDY – 10,000t/d HEAP LEACH COMPARISON – INN14CS 4
INNOVAT MINERAL PROCESS SOLUTIONS LIMITED
3.4 OPERATING EXPENSE – PROCESS LABOUR
Process labour has been adjusted based on the removal of all of the tasks specifically associated
with the heap leach, offset by the workers required for continuous vat leaching. The main
difference is the removal of the piping crew which accounts for 10% of the process staff. In
comparison to the base case, the 10,000t/d CVL case total life of mine (LOM) process labour
expenditure is reduced by 12%. In comparison to the 5,000t/d CVL case, the total LOM process
labour expenditure increases by 62% exclusively as a result of an additional 6 years of operation.
It is expected that optimization of the project for a 5,000t/d operation would reduce this process
labour expense to a more comparable level.
3.5 OPERATING EXPENSE - PROCESSING
Processing cost was modified primarily to account for the switch from heap leaching to CVL. A
minor cost savings in the case of 10,000t/d of 3.8% over LOM is expected. This savings is
attributed to a reduction in power consumption, use of hydrated lime, and removal of heap
specific expenses. A similar savings is expected in the 5,000t/d case, with a 1.6% reduction in
total processing cost.
3.6 OPERATING EXPENSE - LABORATORY
Laboratory costs were reduced in both cases primarily by a reduction in the number of samples
taken. Given the rapid leach characteristics of the ore within the vat, and the ability of the
system to tolerate feed variation, the number of samples has been reduced. In the case of 10,000
t/d, this equates to 75 solids assays, and 125 solution assays per day. This results in a savings
over the base case of 19.4% and 33.9% for the 10,000t/d and 5,000t/d comparison respectively.
3.7 OPERATING EXPENSE – SERVICES & SUPPORT
Services and Support costs have not been affected by the change in processing method and
therefore the 10,000t/d CVL case cost remains identical to the base case. In comparison to the
5,000t/d CVL case, the LOM cost has increased 15.7% as a result of yearly expenditures
occurring for an additional 6 years.
CASE STUDY – 10,000t/d HEAP LEACH COMPARISON – INN14CS 5
INNOVAT MINERAL PROCESS SOLUTIONS LIMITED
3.8 OPERATING EXPENSE – G & A
G&A costs have not been modified in the case of the 10,000t/d comparison. The G&A costs
have been carried directly. For the 5,000t/d case, the yearly expenditure has been reduced to
accommodate the changes required for a 50% reduction in processing, with the total G&A
expenditure increasing by 74%. This is one area where significant additional savings can be
realized in the 5,000t/d case, as yearly costs from the base case have been extended over 12
years, resulting in much higher total expense per category. It is expected that these costs can be
reduced by virtue of the smaller plant, or distributed over the project life resulting in a more
accurate G&A cost comparison.
3.9 MONITORING/RECLAMATION & CLOSURE
The total cost of monitoring/reclamation & closure has not been adjusted in any way. This
activity is expected to take place following leaching and as such has been moved where required
to begin at the end of leaching activity. It should be noted that reclamation on an ongoing basis
can take place with either CVL scenario.
3.10 OTHER TAXES
The calculation of other taxes is done using the same formula as applied to the base case. The
total tax expenditure does not vary significantly between cases.
3.11 TRANSPORT, INSURANCE, REFINING
The same formula for determining the total cost of this category has been used across all cases.
Since the CVL installation has a higher total recovery, the total cost over the life of the project
has increased, but remains the same on a per ounce basis.
3.12 ONGOING CAPITAL EXPENDITURE
Mining capital expenditure on an ongoing basis remains unchanged in the 10,000t/d CVL case in
comparison to the base case. Closure cost is expected to reduce significantly, as the tailings pile
does not require the same treatment as the heap leach facility at project completion. In addition,
CASE STUDY – 10,000t/d HEAP LEACH COMPARISON – INN14CS 6
INNOVAT MINERAL PROCESS SOLUTIONS LIMITED
costs related to heap leach pad expansions have been modified to reflect tailings dump
expansion. The tailings area as designed for the CVL will undergo identical pad expansions, but
these expansions will consist only of appropriate clearing, and placement of a geotextile, more
closely resembling the preparation of the existing WRD site. The combined savings from
adjustment of the leach pad expansions, and reduction in closure requirements results in a
savings of approximately $12,950,644 LOM.
A similar savings is realized in the 5,000t/d CVL comparison. At this scale, $12,669,875 is
saved LOM on ongoing expenditures as a result of the transition from heap leach to tailings pile.
4.0 SUMMARY OF COMPARISON
A summary of the key financial parameters is shown in Table 1. Here you can see that the
10,000t/d CVL case offers superior economics in comparison to the base case, and that while the
average cost per ounce of gold is 7% higher in the 5,000t/d case, the overall economics are better
thanks to the reduced capital expenditure both initially and ongoing. In all cases the NPV of the
CVL installation betters the base case, which is aided by the short leach duration, which leads to
a rapid realization of gold production. A complete cash flow analysis for each case is attached in
the Appendix.
Table 1 - Key Financial Parameters
Base Case Heap
Leach (10,000t/d)
CVL Case
(10,000t/d)
CVL Case
(5,000t/d)
Mine Life 5.3 year 5.3 year 11.1 year
CAPEX (Pre-Production) $ 117 093 032 $ 129 531 835 $ 94 342 955
After-tax IRR 33.7% 47.1% 36.5%
Operating Years to Payback (5%) 2.2 1.42 2.13
After Tax NPV of Project Cash Flow
At 0% Discount Rate $ 152 011 800 $ 195 372 180 $ 191 045 234
At 5% Discount Rate $ 109 789 300 $ 148 918 522 $ 128 788 489
At 10% Discount Rate $ 77 822 500 $ 113 266 205 $ 86 976 345
CASE STUDY – 10,000t/d HEAP LEACH COMPARISON – INN14CS 7
INNOVAT MINERAL PROCESS SOLUTIONS LIMITED
Base Case Heap
Leach (10,000t/d)
CVL Case
(10,000t/d)
CVL Case
(5,000t/d)
At 15% Discount Rate $ 53 275 200 $ 85 487 409 $ 57 993 134
Average cash cost per oz $ 402 $ 359 $ 430
Cost per oz (including Capital) $ 981 $ 905 $ 865
5.0 APPENDIX
APPENDIX – 10,000t/d HEAP LEACH COMPARISON – INN14CS A
INNOVAT MINERAL PROCESS SOLUTIONS LIMITED
10,000 t/d – Heap Leach (Base Case)
APPENDIX – 10,000t/d HEAP LEACH COMPARISON – INN14CS B
INNOVAT MINERAL PROCESS SOLUTIONS LIMITED
10,000t/d – Continuous Vat Leaching
APPENDIX – 10,000t/d HEAP LEACH COMPARISON – INN14CS C
INNOVAT MINERAL PROCESS SOLUTIONS LIMITED
5,000t/d – Continuous Vat Leaching

More Related Content

What's hot

Case study wet ice blast technology for nuclear decontamination of surfaces 2001
Case study wet ice blast technology for nuclear decontamination of surfaces 2001Case study wet ice blast technology for nuclear decontamination of surfaces 2001
Case study wet ice blast technology for nuclear decontamination of surfaces 2001
Dave Davidson
 
Design criteria, Exhaust air odour Destruction
Design criteria, Exhaust air odour DestructionDesign criteria, Exhaust air odour Destruction
Design criteria, Exhaust air odour Destruction
Chemtronics Technologies (India) Pvt. Ltd.
 
Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...
Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...
Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...Carlos R. Conde
 
Superpave - Low Volume
Superpave - Low VolumeSuperpave - Low Volume
P1 acid project
P1   acid projectP1   acid project
P1 acid project
Radha Krishna
 
Remedios An Overview
Remedios An OverviewRemedios An Overview
Remedios An Overview
graemepaton
 
BESTFinalReport
BESTFinalReportBESTFinalReport
BESTFinalReportEvan Crall
 
Applying Process Modeling with GPS-X™ for Understanding WASSTRIP Impact on Nu...
Applying Process Modeling with GPS-X™ for Understanding WASSTRIP Impact on Nu...Applying Process Modeling with GPS-X™ for Understanding WASSTRIP Impact on Nu...
Applying Process Modeling with GPS-X™ for Understanding WASSTRIP Impact on Nu...
Malcolm Fabiyi
 
Compare cryogenic process
Compare cryogenic processCompare cryogenic process
Compare cryogenic process
simachem
 
Working plan guidance_wwtp
Working plan guidance_wwtpWorking plan guidance_wwtp
Working plan guidance_wwtpmedongonu
 
02 highlights from integrated waste management system analyses, storage and t...
02 highlights from integrated waste management system analyses, storage and t...02 highlights from integrated waste management system analyses, storage and t...
02 highlights from integrated waste management system analyses, storage and t...
leann_mays
 
Konstandinos_Zamfes_PSI_OPAL-OnSurface_Petrophysical_Analytical_Logging
Konstandinos_Zamfes_PSI_OPAL-OnSurface_Petrophysical_Analytical_LoggingKonstandinos_Zamfes_PSI_OPAL-OnSurface_Petrophysical_Analytical_Logging
Konstandinos_Zamfes_PSI_OPAL-OnSurface_Petrophysical_Analytical_LoggingKonstandinos Zamfes
 
Bullas a study of measurement methods for diesel sorbent 2014-04-22 - comp...
Bullas   a study of measurement methods for diesel sorbent 2014-04-22  - comp...Bullas   a study of measurement methods for diesel sorbent 2014-04-22  - comp...
Bullas a study of measurement methods for diesel sorbent 2014-04-22 - comp...
Dr John C Bullas
 
IRJET- Role of Compaction Energy on Dry density and CBR
IRJET- Role of Compaction Energy on Dry density and CBRIRJET- Role of Compaction Energy on Dry density and CBR
IRJET- Role of Compaction Energy on Dry density and CBR
IRJET Journal
 
XRF Based Multi-Metals Continuous Water Analyzer
XRF Based Multi-Metals Continuous Water AnalyzerXRF Based Multi-Metals Continuous Water Analyzer
XRF Based Multi-Metals Continuous Water Analyzer
European Tech Serv
 
Qatar Carbonates and Carbon Storage Centre
Qatar Carbonates and Carbon Storage CentreQatar Carbonates and Carbon Storage Centre
Qatar Carbonates and Carbon Storage Centre
Global CCS Institute
 
2017 Stormwater Management Pond Sediment Reuse Case Studies
2017 Stormwater Management Pond Sediment Reuse Case Studies2017 Stormwater Management Pond Sediment Reuse Case Studies
2017 Stormwater Management Pond Sediment Reuse Case Studies
Francine Kelly-Hooper, PhD
 
Chemical process debottlenecking
Chemical process debottleneckingChemical process debottlenecking
Chemical process debottlenecking
Stephen (Steve) Galante
 

What's hot (19)

Case study wet ice blast technology for nuclear decontamination of surfaces 2001
Case study wet ice blast technology for nuclear decontamination of surfaces 2001Case study wet ice blast technology for nuclear decontamination of surfaces 2001
Case study wet ice blast technology for nuclear decontamination of surfaces 2001
 
Design criteria, Exhaust air odour Destruction
Design criteria, Exhaust air odour DestructionDesign criteria, Exhaust air odour Destruction
Design criteria, Exhaust air odour Destruction
 
Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...
Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...
Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...
 
Qatar petroleum presentation
Qatar petroleum presentationQatar petroleum presentation
Qatar petroleum presentation
 
Superpave - Low Volume
Superpave - Low VolumeSuperpave - Low Volume
Superpave - Low Volume
 
P1 acid project
P1   acid projectP1   acid project
P1 acid project
 
Remedios An Overview
Remedios An OverviewRemedios An Overview
Remedios An Overview
 
BESTFinalReport
BESTFinalReportBESTFinalReport
BESTFinalReport
 
Applying Process Modeling with GPS-X™ for Understanding WASSTRIP Impact on Nu...
Applying Process Modeling with GPS-X™ for Understanding WASSTRIP Impact on Nu...Applying Process Modeling with GPS-X™ for Understanding WASSTRIP Impact on Nu...
Applying Process Modeling with GPS-X™ for Understanding WASSTRIP Impact on Nu...
 
Compare cryogenic process
Compare cryogenic processCompare cryogenic process
Compare cryogenic process
 
Working plan guidance_wwtp
Working plan guidance_wwtpWorking plan guidance_wwtp
Working plan guidance_wwtp
 
02 highlights from integrated waste management system analyses, storage and t...
02 highlights from integrated waste management system analyses, storage and t...02 highlights from integrated waste management system analyses, storage and t...
02 highlights from integrated waste management system analyses, storage and t...
 
Konstandinos_Zamfes_PSI_OPAL-OnSurface_Petrophysical_Analytical_Logging
Konstandinos_Zamfes_PSI_OPAL-OnSurface_Petrophysical_Analytical_LoggingKonstandinos_Zamfes_PSI_OPAL-OnSurface_Petrophysical_Analytical_Logging
Konstandinos_Zamfes_PSI_OPAL-OnSurface_Petrophysical_Analytical_Logging
 
Bullas a study of measurement methods for diesel sorbent 2014-04-22 - comp...
Bullas   a study of measurement methods for diesel sorbent 2014-04-22  - comp...Bullas   a study of measurement methods for diesel sorbent 2014-04-22  - comp...
Bullas a study of measurement methods for diesel sorbent 2014-04-22 - comp...
 
IRJET- Role of Compaction Energy on Dry density and CBR
IRJET- Role of Compaction Energy on Dry density and CBRIRJET- Role of Compaction Energy on Dry density and CBR
IRJET- Role of Compaction Energy on Dry density and CBR
 
XRF Based Multi-Metals Continuous Water Analyzer
XRF Based Multi-Metals Continuous Water AnalyzerXRF Based Multi-Metals Continuous Water Analyzer
XRF Based Multi-Metals Continuous Water Analyzer
 
Qatar Carbonates and Carbon Storage Centre
Qatar Carbonates and Carbon Storage CentreQatar Carbonates and Carbon Storage Centre
Qatar Carbonates and Carbon Storage Centre
 
2017 Stormwater Management Pond Sediment Reuse Case Studies
2017 Stormwater Management Pond Sediment Reuse Case Studies2017 Stormwater Management Pond Sediment Reuse Case Studies
2017 Stormwater Management Pond Sediment Reuse Case Studies
 
Chemical process debottlenecking
Chemical process debottleneckingChemical process debottlenecking
Chemical process debottlenecking
 

Similar to Economic analysis for cvat panama

63980877-Facility-Flare-Reduction.pdf
63980877-Facility-Flare-Reduction.pdf63980877-Facility-Flare-Reduction.pdf
63980877-Facility-Flare-Reduction.pdf
xjaf01
 
How to unlock productivity savings in mining operations part 2. "Show me the ...
How to unlock productivity savings in mining operations part 2. "Show me the ...How to unlock productivity savings in mining operations part 2. "Show me the ...
How to unlock productivity savings in mining operations part 2. "Show me the ...
David Mallinson MAICD
 
Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...
Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...
Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...SIMON ROONEY
 
Desktop study for biomethane utilization from POME.pptx
Desktop study for biomethane utilization from POME.pptxDesktop study for biomethane utilization from POME.pptx
Desktop study for biomethane utilization from POME.pptx
Windri Aji Brata
 
Case Study - STP Power Saving - Bacterial Culture
Case Study - STP Power Saving - Bacterial CultureCase Study - STP Power Saving - Bacterial Culture
Case Study - STP Power Saving - Bacterial CultureFermenta Biotech Ltd
 
Circulating load
Circulating load Circulating load
Circulating load
hamidfara
 
rhe-use_haynesville_1
rhe-use_haynesville_1rhe-use_haynesville_1
rhe-use_haynesville_1Manu Tayal
 
Simplifying stormwater design is costing us money - a short case study
Simplifying stormwater design is costing us money - a short case studySimplifying stormwater design is costing us money - a short case study
Simplifying stormwater design is costing us money - a short case study
Adam Berry
 
NYPD3 Selective Reopener Nersa public hearings - 23 June 2015
NYPD3 Selective Reopener  Nersa public hearings  - 23 June 2015NYPD3 Selective Reopener  Nersa public hearings  - 23 June 2015
NYPD3 Selective Reopener Nersa public hearings - 23 June 2015
Matthew Le Cordeur
 
Continuous open width treatment english
Continuous open width treatment englishContinuous open width treatment english
Continuous open width treatment english
Universidad Complutense de Madrid
 
COMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANT
COMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANTCOMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANT
COMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANTWALEBUBLÉ
 
Road Paving As An Option For Pm10 Er Cs
Road Paving As An Option For Pm10 Er CsRoad Paving As An Option For Pm10 Er Cs
Road Paving As An Option For Pm10 Er CsJoel Reisman
 
PetroSkills: Best Tips of the Month
PetroSkills: Best Tips of the MonthPetroSkills: Best Tips of the Month
PetroSkills: Best Tips of the Month
Weston Shepherd
 
Sandia 2014 Wind Turbine Blade Workshop- Nolet
Sandia 2014 Wind Turbine Blade Workshop- NoletSandia 2014 Wind Turbine Blade Workshop- Nolet
Sandia 2014 Wind Turbine Blade Workshop- Nolet
Sandia National Laboratories: Energy & Climate: Renewables
 
Basics of Solar PV O&M - Solarig Gensol
Basics of Solar PV O&M - Solarig GensolBasics of Solar PV O&M - Solarig Gensol
Basics of Solar PV O&M - Solarig Gensol
Gensol Engineering Limited
 
ES&T - HDD as GSR Feature
ES&T - HDD as GSR FeatureES&T - HDD as GSR Feature
ES&T - HDD as GSR FeatureMike Lubrecht
 
BASP Service Quality Meeting EMK-45 Final.pptx
BASP Service Quality Meeting EMK-45 Final.pptxBASP Service Quality Meeting EMK-45 Final.pptx
BASP Service Quality Meeting EMK-45 Final.pptx
ssusera21b97
 
Nitrogen removal for chemicals production
Nitrogen removal for chemicals productionNitrogen removal for chemicals production
Nitrogen removal for chemicals productionJorge Arizmendi-Sanchez
 
Sector Summary - Subsea
Sector Summary - SubseaSector Summary - Subsea
Sector Summary - SubseaThomas Burke
 
Upgrading co2 removal systems
Upgrading co2 removal systemsUpgrading co2 removal systems
Upgrading co2 removal systems
VK Arora
 

Similar to Economic analysis for cvat panama (20)

63980877-Facility-Flare-Reduction.pdf
63980877-Facility-Flare-Reduction.pdf63980877-Facility-Flare-Reduction.pdf
63980877-Facility-Flare-Reduction.pdf
 
How to unlock productivity savings in mining operations part 2. "Show me the ...
How to unlock productivity savings in mining operations part 2. "Show me the ...How to unlock productivity savings in mining operations part 2. "Show me the ...
How to unlock productivity savings in mining operations part 2. "Show me the ...
 
Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...
Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...
Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...
 
Desktop study for biomethane utilization from POME.pptx
Desktop study for biomethane utilization from POME.pptxDesktop study for biomethane utilization from POME.pptx
Desktop study for biomethane utilization from POME.pptx
 
Case Study - STP Power Saving - Bacterial Culture
Case Study - STP Power Saving - Bacterial CultureCase Study - STP Power Saving - Bacterial Culture
Case Study - STP Power Saving - Bacterial Culture
 
Circulating load
Circulating load Circulating load
Circulating load
 
rhe-use_haynesville_1
rhe-use_haynesville_1rhe-use_haynesville_1
rhe-use_haynesville_1
 
Simplifying stormwater design is costing us money - a short case study
Simplifying stormwater design is costing us money - a short case studySimplifying stormwater design is costing us money - a short case study
Simplifying stormwater design is costing us money - a short case study
 
NYPD3 Selective Reopener Nersa public hearings - 23 June 2015
NYPD3 Selective Reopener  Nersa public hearings  - 23 June 2015NYPD3 Selective Reopener  Nersa public hearings  - 23 June 2015
NYPD3 Selective Reopener Nersa public hearings - 23 June 2015
 
Continuous open width treatment english
Continuous open width treatment englishContinuous open width treatment english
Continuous open width treatment english
 
COMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANT
COMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANTCOMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANT
COMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANT
 
Road Paving As An Option For Pm10 Er Cs
Road Paving As An Option For Pm10 Er CsRoad Paving As An Option For Pm10 Er Cs
Road Paving As An Option For Pm10 Er Cs
 
PetroSkills: Best Tips of the Month
PetroSkills: Best Tips of the MonthPetroSkills: Best Tips of the Month
PetroSkills: Best Tips of the Month
 
Sandia 2014 Wind Turbine Blade Workshop- Nolet
Sandia 2014 Wind Turbine Blade Workshop- NoletSandia 2014 Wind Turbine Blade Workshop- Nolet
Sandia 2014 Wind Turbine Blade Workshop- Nolet
 
Basics of Solar PV O&M - Solarig Gensol
Basics of Solar PV O&M - Solarig GensolBasics of Solar PV O&M - Solarig Gensol
Basics of Solar PV O&M - Solarig Gensol
 
ES&T - HDD as GSR Feature
ES&T - HDD as GSR FeatureES&T - HDD as GSR Feature
ES&T - HDD as GSR Feature
 
BASP Service Quality Meeting EMK-45 Final.pptx
BASP Service Quality Meeting EMK-45 Final.pptxBASP Service Quality Meeting EMK-45 Final.pptx
BASP Service Quality Meeting EMK-45 Final.pptx
 
Nitrogen removal for chemicals production
Nitrogen removal for chemicals productionNitrogen removal for chemicals production
Nitrogen removal for chemicals production
 
Sector Summary - Subsea
Sector Summary - SubseaSector Summary - Subsea
Sector Summary - Subsea
 
Upgrading co2 removal systems
Upgrading co2 removal systemsUpgrading co2 removal systems
Upgrading co2 removal systems
 

More from ofrias1

Stretagicmanagement 150811123555-lva1-app6892
Stretagicmanagement 150811123555-lva1-app6892Stretagicmanagement 150811123555-lva1-app6892
Stretagicmanagement 150811123555-lva1-app6892
ofrias1
 
Apoyo panorama politico economico 2018. inicio gob.vizcarra. 4 de abril
Apoyo   panorama politico economico 2018. inicio gob.vizcarra. 4 de abrilApoyo   panorama politico economico 2018. inicio gob.vizcarra. 4 de abril
Apoyo panorama politico economico 2018. inicio gob.vizcarra. 4 de abril
ofrias1
 
Hidrometalurgia 160711053652-180401041910
Hidrometalurgia 160711053652-180401041910Hidrometalurgia 160711053652-180401041910
Hidrometalurgia 160711053652-180401041910
ofrias1
 
Greenfields copperpresentation-2011-07-01-110809092504-phpapp01
Greenfields copperpresentation-2011-07-01-110809092504-phpapp01Greenfields copperpresentation-2011-07-01-110809092504-phpapp01
Greenfields copperpresentation-2011-07-01-110809092504-phpapp01
ofrias1
 
Hidrometalurgia 160711053652
Hidrometalurgia 160711053652Hidrometalurgia 160711053652
Hidrometalurgia 160711053652
ofrias1
 
Flowsheetoxidocu
FlowsheetoxidocuFlowsheetoxidocu
Flowsheetoxidocu
ofrias1
 
Cr 15-a in-situ_copper
Cr 15-a in-situ_copperCr 15-a in-situ_copper
Cr 15-a in-situ_copper
ofrias1
 

More from ofrias1 (7)

Stretagicmanagement 150811123555-lva1-app6892
Stretagicmanagement 150811123555-lva1-app6892Stretagicmanagement 150811123555-lva1-app6892
Stretagicmanagement 150811123555-lva1-app6892
 
Apoyo panorama politico economico 2018. inicio gob.vizcarra. 4 de abril
Apoyo   panorama politico economico 2018. inicio gob.vizcarra. 4 de abrilApoyo   panorama politico economico 2018. inicio gob.vizcarra. 4 de abril
Apoyo panorama politico economico 2018. inicio gob.vizcarra. 4 de abril
 
Hidrometalurgia 160711053652-180401041910
Hidrometalurgia 160711053652-180401041910Hidrometalurgia 160711053652-180401041910
Hidrometalurgia 160711053652-180401041910
 
Greenfields copperpresentation-2011-07-01-110809092504-phpapp01
Greenfields copperpresentation-2011-07-01-110809092504-phpapp01Greenfields copperpresentation-2011-07-01-110809092504-phpapp01
Greenfields copperpresentation-2011-07-01-110809092504-phpapp01
 
Hidrometalurgia 160711053652
Hidrometalurgia 160711053652Hidrometalurgia 160711053652
Hidrometalurgia 160711053652
 
Flowsheetoxidocu
FlowsheetoxidocuFlowsheetoxidocu
Flowsheetoxidocu
 
Cr 15-a in-situ_copper
Cr 15-a in-situ_copperCr 15-a in-situ_copper
Cr 15-a in-situ_copper
 

Recently uploaded

Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
bhadouriyakaku
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 
01-GPON Fundamental fttx ftth basic .pptx
01-GPON Fundamental fttx ftth basic .pptx01-GPON Fundamental fttx ftth basic .pptx
01-GPON Fundamental fttx ftth basic .pptx
benykoy2024
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
obonagu
 

Recently uploaded (20)

Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 
01-GPON Fundamental fttx ftth basic .pptx
01-GPON Fundamental fttx ftth basic .pptx01-GPON Fundamental fttx ftth basic .pptx
01-GPON Fundamental fttx ftth basic .pptx
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
 

Economic analysis for cvat panama

  • 1. INNOVAT MINERAL PROCESS SOLUTIONS LIMITED 760 Brant St., Suite 405C, Burlington ON, L7R 4B8, Canada Tel 905-333-7133 Fax 905-333-9336 www.vatleach.com INN14-CS-001 Sept 30, 2014 Document: TECHNICAL MEMORANDUM Project: INNOVAT Case Study – 10,000 t/d Heap Leach – Panama This memorandum presents an economic comparison based on a 10,000 t/d heap leach operation located in Latin America. All assumptions, equipment layouts, mining, and costing, for the purposes of this comparison, have been accepted from the pre-feasibility base case and have not been adjusted except as required to implement a Continuous Vat Leaching (CVL) based process. INNOVAT was directly engaged in engineering activities related to the project from 2007 through 2013, including bulk pilot plant testing, and believes that the cost estimates associated with the implementation of Continuous Vat Leaching have been conservatively estimated, and that potentially significant savings in both processing, and material handling can be realized with modification to the base case. 1.0 INTRODUCTION Three economic analyses are presented in this memo, two of which have been prepared by INNOVAT, and one of which was presented as a heap leach, prefeasibility study by the owner. All costing where possible has been carried forward, or based on the base case. The models are as follows: • Base case: 10,000t/d Heap Leach Facility (unadjusted) • Direct Comparison: 10,000t/d Continuous Vat Leaching • Alternate: 5,000t/d Continuous Vat Leaching The following considerations were used when evaluating the alternate methods: • Maintain design criteria of the original project plan • Use direct cost from original project plan where feasible
  • 2. CASE STUDY – 10,000t/d HEAP LEACH COMPARISON – INN14CS 2 INNOVAT MINERAL PROCESS SOLUTIONS LIMITED • Use unit cost from original project plan where direct cost is not feasible 2.0 BASIS OF COMPARISON INNOVAT has not modified the flow sheets in any way beyond addition of components which are required for Continuous Vat Leaching, and removal of components related specifically to Heap Leaching. The mining and material handling process has been unmodified for the 10,000t/d Continuous Vat Leach case, and modified only as a result of the reduction in processing rate for the 5,000t/d CVL case. The crushing circuit has been modified as a result of the Continuous Vat Leaching process feed size requirement of -6mm. In order to use the primary and secondary crusher from the base case, an additional tertiary, and quaternary crushing stage have been added to both of the CVL scenarios. The cost of this inclusion has been captured in both the CAPEX and OPEX within the comparison. It is expected that a crushing circuit designed specifically to reduce the particle size from ROM to -6mm would require three stages and have a small cost savings over the crushing circuit utilized in this comparison. The CVL facility has been placed near the base of the proposed heap leach facility, and receives ore from the crushed ore stockpile. No modification has been made to the material handling / conveyor system as presented in the base case. The CVL is expected to discharge the material to a tailings pile which has been modelled to occupy the space currently designed for the heap leach facility. The costing associated with this tailings pile has been developed based on a combination of the costs reported for the heap leach facility, and the costs reported for the waste rock dump. 3.0 COMPARISON OF COSTS 3.1 PRE-PRODUCTION CAPITAL EXPENDITURE - PROCESS In the case of the 10,000t/d CVL system, cost reductions associated with the centralization of the process were included and amounted primarily to a minor reduction in the cost of the reagent
  • 3. CASE STUDY – 10,000t/d HEAP LEACH COMPARISON – INN14CS 3 INNOVAT MINERAL PROCESS SOLUTIONS LIMITED system. The pre-production direct cost comparison between the base case and 10,000t/d CVL case excluding Area 30 – Heap Leach & Solution Handling, and Area 60 – Detoxification, produces a difference of 0.33% capital expense. If we look at only Area 30 and 60, the preproduction cost of the CVL scenario represents a 50% cost premium over the base case. It is important to note however, that this cost premium is almost completely offset in year one during the heap leach expansion. The difference between the total process & infrastructure capital cost (pre-production) between the base case and 10,000t/d CVL case is a 12.4% increase in capital cost. In the case of the 5,000t/d CVL system, direct cost of associated equipment was reduced as a result of the 50% reduction in processing rate. The aggregate reduction in direct cost associated with this throughput reduction is 20.8%, excluding Area 30 – Heap Leach & Solution Handling, and Area 60 – Detoxification. The capital cost difference associated with Area 30 & 60 is 9.2% in favour of the 5,000t/d CVL case. Further savings occur following year one, where leach pad expansion must occur with the base case. The difference between the total process & infrastructure capital cost (pre-production) between the base case and 5,000t/d CVL case is a 19.4% decrease in capital cost. 3.2 PRE-PRODUCTION CAPITAL EXPENDITURE – MINING As the mining schedule and mining method were not modified, the mining costs have been carried directly for the 10,000t/d case, and reduced only by decreasing the number of required haul trucks in the 5,000t/d case. The 10,000t/d CVL case shares a common mining capital expenditure throughout life of mine in comparison to the base case, whereas the 5,000t/d case includes a capital savings of 19.6% as the equipment requirement for 5,000t/d has decreased with respect to the base case. 3.3 OPERATING EXPENSE - MINING Mining costs have not been modified for the 10,000t/d comparison as the mining and material handling process has not been altered. Additional mining cost was included in the 5,000t/d case owing to the reduced equipment efficiency. This increase over the mine life amounts to a mining operating cost increase of 6.9%.
  • 4. CASE STUDY – 10,000t/d HEAP LEACH COMPARISON – INN14CS 4 INNOVAT MINERAL PROCESS SOLUTIONS LIMITED 3.4 OPERATING EXPENSE – PROCESS LABOUR Process labour has been adjusted based on the removal of all of the tasks specifically associated with the heap leach, offset by the workers required for continuous vat leaching. The main difference is the removal of the piping crew which accounts for 10% of the process staff. In comparison to the base case, the 10,000t/d CVL case total life of mine (LOM) process labour expenditure is reduced by 12%. In comparison to the 5,000t/d CVL case, the total LOM process labour expenditure increases by 62% exclusively as a result of an additional 6 years of operation. It is expected that optimization of the project for a 5,000t/d operation would reduce this process labour expense to a more comparable level. 3.5 OPERATING EXPENSE - PROCESSING Processing cost was modified primarily to account for the switch from heap leaching to CVL. A minor cost savings in the case of 10,000t/d of 3.8% over LOM is expected. This savings is attributed to a reduction in power consumption, use of hydrated lime, and removal of heap specific expenses. A similar savings is expected in the 5,000t/d case, with a 1.6% reduction in total processing cost. 3.6 OPERATING EXPENSE - LABORATORY Laboratory costs were reduced in both cases primarily by a reduction in the number of samples taken. Given the rapid leach characteristics of the ore within the vat, and the ability of the system to tolerate feed variation, the number of samples has been reduced. In the case of 10,000 t/d, this equates to 75 solids assays, and 125 solution assays per day. This results in a savings over the base case of 19.4% and 33.9% for the 10,000t/d and 5,000t/d comparison respectively. 3.7 OPERATING EXPENSE – SERVICES & SUPPORT Services and Support costs have not been affected by the change in processing method and therefore the 10,000t/d CVL case cost remains identical to the base case. In comparison to the 5,000t/d CVL case, the LOM cost has increased 15.7% as a result of yearly expenditures occurring for an additional 6 years.
  • 5. CASE STUDY – 10,000t/d HEAP LEACH COMPARISON – INN14CS 5 INNOVAT MINERAL PROCESS SOLUTIONS LIMITED 3.8 OPERATING EXPENSE – G & A G&A costs have not been modified in the case of the 10,000t/d comparison. The G&A costs have been carried directly. For the 5,000t/d case, the yearly expenditure has been reduced to accommodate the changes required for a 50% reduction in processing, with the total G&A expenditure increasing by 74%. This is one area where significant additional savings can be realized in the 5,000t/d case, as yearly costs from the base case have been extended over 12 years, resulting in much higher total expense per category. It is expected that these costs can be reduced by virtue of the smaller plant, or distributed over the project life resulting in a more accurate G&A cost comparison. 3.9 MONITORING/RECLAMATION & CLOSURE The total cost of monitoring/reclamation & closure has not been adjusted in any way. This activity is expected to take place following leaching and as such has been moved where required to begin at the end of leaching activity. It should be noted that reclamation on an ongoing basis can take place with either CVL scenario. 3.10 OTHER TAXES The calculation of other taxes is done using the same formula as applied to the base case. The total tax expenditure does not vary significantly between cases. 3.11 TRANSPORT, INSURANCE, REFINING The same formula for determining the total cost of this category has been used across all cases. Since the CVL installation has a higher total recovery, the total cost over the life of the project has increased, but remains the same on a per ounce basis. 3.12 ONGOING CAPITAL EXPENDITURE Mining capital expenditure on an ongoing basis remains unchanged in the 10,000t/d CVL case in comparison to the base case. Closure cost is expected to reduce significantly, as the tailings pile does not require the same treatment as the heap leach facility at project completion. In addition,
  • 6. CASE STUDY – 10,000t/d HEAP LEACH COMPARISON – INN14CS 6 INNOVAT MINERAL PROCESS SOLUTIONS LIMITED costs related to heap leach pad expansions have been modified to reflect tailings dump expansion. The tailings area as designed for the CVL will undergo identical pad expansions, but these expansions will consist only of appropriate clearing, and placement of a geotextile, more closely resembling the preparation of the existing WRD site. The combined savings from adjustment of the leach pad expansions, and reduction in closure requirements results in a savings of approximately $12,950,644 LOM. A similar savings is realized in the 5,000t/d CVL comparison. At this scale, $12,669,875 is saved LOM on ongoing expenditures as a result of the transition from heap leach to tailings pile. 4.0 SUMMARY OF COMPARISON A summary of the key financial parameters is shown in Table 1. Here you can see that the 10,000t/d CVL case offers superior economics in comparison to the base case, and that while the average cost per ounce of gold is 7% higher in the 5,000t/d case, the overall economics are better thanks to the reduced capital expenditure both initially and ongoing. In all cases the NPV of the CVL installation betters the base case, which is aided by the short leach duration, which leads to a rapid realization of gold production. A complete cash flow analysis for each case is attached in the Appendix. Table 1 - Key Financial Parameters Base Case Heap Leach (10,000t/d) CVL Case (10,000t/d) CVL Case (5,000t/d) Mine Life 5.3 year 5.3 year 11.1 year CAPEX (Pre-Production) $ 117 093 032 $ 129 531 835 $ 94 342 955 After-tax IRR 33.7% 47.1% 36.5% Operating Years to Payback (5%) 2.2 1.42 2.13 After Tax NPV of Project Cash Flow At 0% Discount Rate $ 152 011 800 $ 195 372 180 $ 191 045 234 At 5% Discount Rate $ 109 789 300 $ 148 918 522 $ 128 788 489 At 10% Discount Rate $ 77 822 500 $ 113 266 205 $ 86 976 345
  • 7. CASE STUDY – 10,000t/d HEAP LEACH COMPARISON – INN14CS 7 INNOVAT MINERAL PROCESS SOLUTIONS LIMITED Base Case Heap Leach (10,000t/d) CVL Case (10,000t/d) CVL Case (5,000t/d) At 15% Discount Rate $ 53 275 200 $ 85 487 409 $ 57 993 134 Average cash cost per oz $ 402 $ 359 $ 430 Cost per oz (including Capital) $ 981 $ 905 $ 865 5.0 APPENDIX
  • 8. APPENDIX – 10,000t/d HEAP LEACH COMPARISON – INN14CS A INNOVAT MINERAL PROCESS SOLUTIONS LIMITED 10,000 t/d – Heap Leach (Base Case)
  • 9. APPENDIX – 10,000t/d HEAP LEACH COMPARISON – INN14CS B INNOVAT MINERAL PROCESS SOLUTIONS LIMITED 10,000t/d – Continuous Vat Leaching
  • 10. APPENDIX – 10,000t/d HEAP LEACH COMPARISON – INN14CS C INNOVAT MINERAL PROCESS SOLUTIONS LIMITED 5,000t/d – Continuous Vat Leaching