SlideShare a Scribd company logo
1 of 31
Diversion head works
Definition
• It is a structure constructed across the river so as to raise water
level on u/s side so that it can be diverted towards canal
• Ideal site for diversion head works-
1. Good foundation should be available
2. The site should be such that weir can be aligned at right angle to
the diversion of water in the river
3. The site should be such that there should be sufficient space for
regulation of head regulator and other component of the
diversion head works
4. The overall cost should be less
5. Proper approach way should be near by site
6. On the u/s side where water is retained, should not include costly
land
7. While construction of weir or barrages river should be available
near the site.
• The materials and labours should be available near by site.
• The river should be perennial
• The river should have non erodible as well as non submersible
banks
• The site should be narrow and well defined
Layout of diversion head works
• Weir
• Under sluice
• Fish ladder
• Divide wall
• Canal head regulator
• Silt excluder
• Guide bank
• Marginal bund
Weir
• A structure constructed across river to raise water
so as to divert this raise water into canal and this
raising of water is mostly done by the crest wall
constructed across river and very small part or nil
part is by shutter sometimes if provided on its top
is called as weir and
• when storing of water is done by gates or shutters
and small part of water is by raised crest then
such structure constructed is known as barrage.
Types of weir
• Gravity weir
the wt. of weir balances the uplift pressure
caused by seepage water
1. Vertical drop weir
2. Rock fill weir
3. Concrete weir
• Non gravity weir
uplift pressure is largely resisted by wt. of
concrete slab with the wt. of divide piers
Vertical drop weir
• It consist of
horizontal floor
and a masonry
crest with
vertical or
nearly vertical
d/s face and the
shutters are
provided at the
crest
• Most storage is
done by weir
crest and some
storages by
shutters
Rock fill weir
• Called as dry stone slope weir
• Suitable for sandy foundation
• Requires large quantity of stones
Concrete weir
• Suitable for permeable foundation
• Sheet piles are provided for both u/s & d/s
floors to destroy the energy of the water
Classification of weir
• According to use & function-
1. Storage weir
2. Pick up weir
3. Diversion weir
4. Waste weir
Storage weir
• High weir for storing water called as diversion weir
• Shutters may or may not provided
Pick up weir-
• Constructed when command area is far away from reservoir
due to rolling topography or no culturable land
• Water from main storage is released and carried through
same river up to pick up weir from which it is diverted into
canal
Diversion weir-
• A weir is constructed to divert the river water into the canal is
called as diversion weir
• Constructed at 90⁰ to the flow of river.
Waste weir-
• Constructed in continuation of dam
• Known as escape channel or spillway
Diversion weir
Pick up weir
Under sluice
• Opening provided in
the body of weir at low
level
• Located at same side
from which canal is
taking off
• Functions-
1. Control entry of silt
into canal
2. Lower the HFL
3. Helps in passing the
low river floods
without lifting
shutters
4. Helps to pass silt on
d/s side of weir
Divide wall
• Wall constructed between
under sluices & the weir at
right angle to the axis of weir
to divide the river channel.
• Functions-
1. Separate the under sluices
from weir
2. Also helps in reducing
velocity of flow near head
regulator due to which silt
is deposited and clear
water passes into canal
3. Prevents vortices means
flow in circular motion.
Fish ladder
• It is passage
provided
adjacent to
divide wall for
movement of
fish from u/s
to d/s and vice
versa called as
fish ladder
• Normally fish
moves from
colder water
to warm water
Silt exclusion devices
• Device which are constructed at the main head of canal
which prevent entry of silt called as silt exclusion devices
Silt ejectors
• The structure which is constructed across the canal to eject the silt
accumulated in canal section are called as silt ejectors
• It consist of tunnel with sufficient slope so that silt not to be deposited
Silt excluder
• It is structure in under sluices to pass water
containing silt on d/s through under sluices so
that only clear water enters into the head
regulator
• These are parallel to the axis of head regulator
silt excluder prevent entry of silt into the canal
• Consist of no. of small tunnels with their roof
slab at same level.
Guide bank
• Provided on either side of diversion head works
• Function-
1. Prevent oblique approach to the head regulator
2. Protect regulator from river attack
3. Increases max. discharge at all points
4. Prevent out flanking of structure
5. Create reasonable water way for a weir
Component parts of weir
• Body of weir
• u/s apron
• u/s curtain wall
• d/s apron
• d/s curtain wall
• Crest
• shutter
Barrage
• Component of barrage
1. Crest wall 2. Gate
Advantages-
1. As small afflux is caused above hfl, the area under
flooding is less
2. Low cost flood bank
3. More safe due to less afflux
4. Economical as preventive and energy dissipations work is
less
5. Control of flood with gates
6. Preferred in flat longitudinal area and low silt
Disadvantages-
1. Storage capacity is less
2. Maintenance and initial cost is more
Sr. no. Weir Barrage
1 Initial cost low More
2 More area of submergence Less
3 Silting problem No
4 Rising and lowering of shutters are
not convenient as it is operated by
manually
By mechanically and easy
5 No control over flood Possible
6 Difficult to inspect and repair Easy
7 Roadway is not possible Possible
8 Storage is by crest By gates/shutters
Diversion head works

More Related Content

What's hot (20)

Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic Structures
 
Dams and spillways
Dams and spillwaysDams and spillways
Dams and spillways
 
Canal falls and its classification
Canal falls and its classificationCanal falls and its classification
Canal falls and its classification
 
Design of stilling basin and roughness devices
Design of stilling basin and roughness devices Design of stilling basin and roughness devices
Design of stilling basin and roughness devices
 
Gravity Dam
Gravity DamGravity Dam
Gravity Dam
 
Spillways
SpillwaysSpillways
Spillways
 
4 spillways
4 spillways4 spillways
4 spillways
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 
Spillways & energy dissipator
Spillways & energy dissipatorSpillways & energy dissipator
Spillways & energy dissipator
 
5 Reservoir Planning
5 Reservoir Planning5 Reservoir Planning
5 Reservoir Planning
 
Types of spillways
Types of spillwaysTypes of spillways
Types of spillways
 
Canal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage WorksCanal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage Works
 
ogee design
ogee designogee design
ogee design
 
Canal outlets
Canal outletsCanal outlets
Canal outlets
 
Weir and barrage lecture
Weir and barrage lectureWeir and barrage lecture
Weir and barrage lecture
 
Regulation Works
Regulation WorksRegulation Works
Regulation Works
 
Spillways
SpillwaysSpillways
Spillways
 
Failure of weir and barrage
Failure of weir and barrageFailure of weir and barrage
Failure of weir and barrage
 
Weirs
WeirsWeirs
Weirs
 
Canal design
Canal designCanal design
Canal design
 

Similar to Diversion head works

Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01saibabu48
 
diversionheadworks-150327075328-conversion-gate01.pdf
diversionheadworks-150327075328-conversion-gate01.pdfdiversionheadworks-150327075328-conversion-gate01.pdf
diversionheadworks-150327075328-conversion-gate01.pdfShrutiLotliker
 
Presentation1 hydro;ogy-SKK.pdf
Presentation1 hydro;ogy-SKK.pdfPresentation1 hydro;ogy-SKK.pdf
Presentation1 hydro;ogy-SKK.pdfShrutiLotliker
 
Diversion of headwork
Diversion of headwork Diversion of headwork
Diversion of headwork Jay Khoradiya
 
Ce 413 hydraulic structures 8th
Ce 413 hydraulic structures 8thCe 413 hydraulic structures 8th
Ce 413 hydraulic structures 8thEngrHayatHussain
 
Presenation on Diversion Headworks irrigation.pptx
Presenation on Diversion Headworks irrigation.pptxPresenation on Diversion Headworks irrigation.pptx
Presenation on Diversion Headworks irrigation.pptxqureshixahoor
 
weir & barrage
weir & barrageweir & barrage
weir & barrageRaj Daxini
 
DIVERSION HEAD WORKS
DIVERSION HEAD WORKSDIVERSION HEAD WORKS
DIVERSION HEAD WORKSMood Naik
 
Wreii unitv-170917082636
Wreii unitv-170917082636Wreii unitv-170917082636
Wreii unitv-170917082636saibabu48
 
chapter-3.pptx: CHANNEL HEADWORKS AND CANALS
chapter-3.pptx: CHANNEL HEADWORKS AND CANALSchapter-3.pptx: CHANNEL HEADWORKS AND CANALS
chapter-3.pptx: CHANNEL HEADWORKS AND CANALSmulugeta48
 
Diversion head work
Diversion head workDiversion head work
Diversion head workdhruvalsu
 
Canal MASONRY WORK
Canal MASONRY WORKCanal MASONRY WORK
Canal MASONRY WORKSAGAR RAUT
 

Similar to Diversion head works (20)

Diversion head work
Diversion head workDiversion head work
Diversion head work
 
Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01
 
diversionheadworks-150327075328-conversion-gate01.pdf
diversionheadworks-150327075328-conversion-gate01.pdfdiversionheadworks-150327075328-conversion-gate01.pdf
diversionheadworks-150327075328-conversion-gate01.pdf
 
Presentation1 hydro;ogy-SKK.pdf
Presentation1 hydro;ogy-SKK.pdfPresentation1 hydro;ogy-SKK.pdf
Presentation1 hydro;ogy-SKK.pdf
 
Diversion of headwork
Diversion of headwork Diversion of headwork
Diversion of headwork
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Ch-3.pptx
Ch-3.pptxCh-3.pptx
Ch-3.pptx
 
Ce 413 hydraulic structures 8th
Ce 413 hydraulic structures 8thCe 413 hydraulic structures 8th
Ce 413 hydraulic structures 8th
 
DIVERSION HEAD WORK
DIVERSION HEAD WORKDIVERSION HEAD WORK
DIVERSION HEAD WORK
 
Presenation on Diversion Headworks irrigation.pptx
Presenation on Diversion Headworks irrigation.pptxPresenation on Diversion Headworks irrigation.pptx
Presenation on Diversion Headworks irrigation.pptx
 
weir & barrage
weir & barrageweir & barrage
weir & barrage
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Dams
DamsDams
Dams
 
DIVERSION HEAD WORKS
DIVERSION HEAD WORKSDIVERSION HEAD WORKS
DIVERSION HEAD WORKS
 
Lecture 8
Lecture 8Lecture 8
Lecture 8
 
Wreii unitv-170917082636
Wreii unitv-170917082636Wreii unitv-170917082636
Wreii unitv-170917082636
 
chapter-3.pptx: CHANNEL HEADWORKS AND CANALS
chapter-3.pptx: CHANNEL HEADWORKS AND CANALSchapter-3.pptx: CHANNEL HEADWORKS AND CANALS
chapter-3.pptx: CHANNEL HEADWORKS AND CANALS
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Diversion head work
Diversion head workDiversion head work
Diversion head work
 
Canal MASONRY WORK
Canal MASONRY WORKCanal MASONRY WORK
Canal MASONRY WORK
 

Recently uploaded

(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 

Recently uploaded (20)

(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 

Diversion head works

  • 2.
  • 3. Definition • It is a structure constructed across the river so as to raise water level on u/s side so that it can be diverted towards canal • Ideal site for diversion head works- 1. Good foundation should be available 2. The site should be such that weir can be aligned at right angle to the diversion of water in the river 3. The site should be such that there should be sufficient space for regulation of head regulator and other component of the diversion head works 4. The overall cost should be less 5. Proper approach way should be near by site 6. On the u/s side where water is retained, should not include costly land 7. While construction of weir or barrages river should be available near the site.
  • 4. • The materials and labours should be available near by site. • The river should be perennial • The river should have non erodible as well as non submersible banks • The site should be narrow and well defined
  • 5. Layout of diversion head works • Weir • Under sluice • Fish ladder • Divide wall • Canal head regulator • Silt excluder • Guide bank • Marginal bund
  • 6.
  • 7. Weir • A structure constructed across river to raise water so as to divert this raise water into canal and this raising of water is mostly done by the crest wall constructed across river and very small part or nil part is by shutter sometimes if provided on its top is called as weir and • when storing of water is done by gates or shutters and small part of water is by raised crest then such structure constructed is known as barrage.
  • 8.
  • 9.
  • 10. Types of weir • Gravity weir the wt. of weir balances the uplift pressure caused by seepage water 1. Vertical drop weir 2. Rock fill weir 3. Concrete weir • Non gravity weir uplift pressure is largely resisted by wt. of concrete slab with the wt. of divide piers
  • 11. Vertical drop weir • It consist of horizontal floor and a masonry crest with vertical or nearly vertical d/s face and the shutters are provided at the crest • Most storage is done by weir crest and some storages by shutters
  • 12.
  • 13. Rock fill weir • Called as dry stone slope weir • Suitable for sandy foundation • Requires large quantity of stones
  • 14. Concrete weir • Suitable for permeable foundation • Sheet piles are provided for both u/s & d/s floors to destroy the energy of the water
  • 15.
  • 16. Classification of weir • According to use & function- 1. Storage weir 2. Pick up weir 3. Diversion weir 4. Waste weir
  • 17. Storage weir • High weir for storing water called as diversion weir • Shutters may or may not provided Pick up weir- • Constructed when command area is far away from reservoir due to rolling topography or no culturable land • Water from main storage is released and carried through same river up to pick up weir from which it is diverted into canal Diversion weir- • A weir is constructed to divert the river water into the canal is called as diversion weir • Constructed at 90⁰ to the flow of river. Waste weir- • Constructed in continuation of dam • Known as escape channel or spillway
  • 19. Under sluice • Opening provided in the body of weir at low level • Located at same side from which canal is taking off • Functions- 1. Control entry of silt into canal 2. Lower the HFL 3. Helps in passing the low river floods without lifting shutters 4. Helps to pass silt on d/s side of weir
  • 20. Divide wall • Wall constructed between under sluices & the weir at right angle to the axis of weir to divide the river channel. • Functions- 1. Separate the under sluices from weir 2. Also helps in reducing velocity of flow near head regulator due to which silt is deposited and clear water passes into canal 3. Prevents vortices means flow in circular motion.
  • 21. Fish ladder • It is passage provided adjacent to divide wall for movement of fish from u/s to d/s and vice versa called as fish ladder • Normally fish moves from colder water to warm water
  • 22. Silt exclusion devices • Device which are constructed at the main head of canal which prevent entry of silt called as silt exclusion devices
  • 23. Silt ejectors • The structure which is constructed across the canal to eject the silt accumulated in canal section are called as silt ejectors • It consist of tunnel with sufficient slope so that silt not to be deposited
  • 24. Silt excluder • It is structure in under sluices to pass water containing silt on d/s through under sluices so that only clear water enters into the head regulator • These are parallel to the axis of head regulator silt excluder prevent entry of silt into the canal • Consist of no. of small tunnels with their roof slab at same level.
  • 25.
  • 26. Guide bank • Provided on either side of diversion head works • Function- 1. Prevent oblique approach to the head regulator 2. Protect regulator from river attack 3. Increases max. discharge at all points 4. Prevent out flanking of structure 5. Create reasonable water way for a weir
  • 27.
  • 28. Component parts of weir • Body of weir • u/s apron • u/s curtain wall • d/s apron • d/s curtain wall • Crest • shutter
  • 29. Barrage • Component of barrage 1. Crest wall 2. Gate Advantages- 1. As small afflux is caused above hfl, the area under flooding is less 2. Low cost flood bank 3. More safe due to less afflux 4. Economical as preventive and energy dissipations work is less 5. Control of flood with gates 6. Preferred in flat longitudinal area and low silt Disadvantages- 1. Storage capacity is less 2. Maintenance and initial cost is more
  • 30. Sr. no. Weir Barrage 1 Initial cost low More 2 More area of submergence Less 3 Silting problem No 4 Rising and lowering of shutters are not convenient as it is operated by manually By mechanically and easy 5 No control over flood Possible 6 Difficult to inspect and repair Easy 7 Roadway is not possible Possible 8 Storage is by crest By gates/shutters