SlideShare a Scribd company logo
Leonam dos Santos Guimarães
FLEET AGING
61 NPPS being built in 15 countries
2007 - 2016: 46 new connections to the grid
(by August 2016)
ANGRA 3
FANGCHENGGANG-2
15 Jul, 2016
GENERATION CHANGE: II -> III -> III+ -> IV
PERMANENT SHUTDOWN REACTORS
Source: IAEA PRIS (August 2016)
To date, about 157 commercial power reactors, experimental or prototype
reactors, over 250 research reactors and a number of fuel cycle facilities
have been retired from operation. Some of these have been fully dismantled.
Nuclear power reactors worldwide
Source: NEA/OECD (September 2016)
Growing Importance of Decommissioning
• Need to manage this end of life cycle in a safe and cost-effective
manner:
– a condition to support new nuclear
• Strengthen work on integrated waste management:
– including characterization, processing and storage
• Most parts of a nuclear power plant do not become radioactive, or are
contaminated at only very low levels. Most of the metal can be recycled.
• Proven techniques and equipment are available to dismantle nuclear
facilities safely and these have now been well demonstrated in several parts
of the world.
• Decommissioning costs for nuclear power plants, including disposal of
associated wastes, are reducing and contribute only a small fraction of the
total cost of electricity generation.
NUCLEAR IN BRAZIL: TODAY
ANGRA 2 PWR
Power: 1.350 MW
Technology: Siemens/KWU
Operation start: JAN/2001
ANGRA 1 PWR
Power: 657 MW
Technology: Westinghouse
Operation start: JAN/1985
NUCLEAR IN BRAZIL: TOMORROW
ANGRA 2 PWR
Power: 1.405 MW
Technology: AREVA
Operation start: JAN/2022
NUCLEAR POTENCIAL ATLAS
2) Southeast
2.000 MW
1) Northeast
2.000 MW
EPRI SITTING CRITERIA
Geographic Information Systems
National Energy Plan 2030
NUCLEAR IN BRAZIL: FUTURE
NUCLEAR POTENCIAL ATLAS
Roadmap
Site Data
Levantamento de campo
Outros dados
PPE
Plant Parameter Envelope
2016
ESP
Early Site Permit
Environmental and Nuclear site
licensing independent of vendor
Vendor Qualification
Brazilian Utility Requirement
BUR
2017
PPA
Power Purchase Agreement
Definition and Decison to Build
.
2018 - 2019
Site Selection
Which Sites will be studied in
detail
2014 - 2015
RFI
Request for Information
Request as per IAEA
and NEI guides
Additional data with
technical details
SitingTechnology
AUCTION
Licensing
Start
BUSINESS
MODEL
NUCLEAR
POTENCIAL
ATLAS
Feasibility
Soc-Eco Impacts
CURRENT ACTIVITIES
• Plant Parameter Envelope
– RFIs to suppliers
– Early Site Permit Report
• Brazilian Utility
Requirements
– URD/EUR Model
• Business Model
– Public-Private Partnership
• Economic and Financial
Feasibility
• Social and Economic
Impacts
NUCLEAR IN BRAZIL: FUTURE
Decommissioning Policy
• defined as the framework implemented by governments, including
laws, regulations, standards and mandatory requirements, that
imposes the background rules to be followed by the nuclear industry
for decommissioning projects.
• National decommissioning policies were found to differ on many
aspects that may have an impact on costs.
Key points in this regard - Brazilian Policy:




BROWNFIELD
REGULATED
REGULATED
 REGULATED
Decommissioning Strategies
(acepted by Brazilian Safety Authority)
ALVARO ALBERTO NUCLEAR POWER STATION
Preliminary Decommissioning Plan (PDP)
Considers planned Angra 1, Angra 2 and
Angra 3 end of operations:
2024 / 2040 / 2050
Life extensions not considered (yet)
Whole site should be decommissioned.
3 approaches:
• Pure SAFSTOR
• Alternative SAFSTOR
• Mixed DECON-SAFSTOR
1st approach: Pure SAFSTOR
Angra 1
Proposal of pure SAFSTOR CNAAA site decommissioning strategy: main approach
Start
Planning
Costing estimation
Final state definition
2022
2024 - 2054
Shutdown procedures
Reactor defuelling
Spent fuel pool operation
Previous decontamination and dismantling
Safe state
Final decontamination and dismantling
Waste storage, disposal and final state
Angra 2
2040 - 2070
Angra 3
2050 - 2080
Site cleaning
Site remediation
Amends and fees payment
Licence termination
2080 - 2085
Final site survey and
monitoring
EndBegin
• Plants decommissioning schedule coincidence:
• Cost reduction possibility
• experience gain by the decommissioning team (same to whole site);
• Safe Storage Period:
• reduce waste volumes and associated potential problems to deal with.
2nd approach: Alternative SAFSTOR
Angra 1
Proposal of SAFSTOR CNAAA site decommissioning strategy: alternative approach
Start
Planning
Costing estimation
Final state definition
2022
2024 - 2080
Shutdown procedures
Reactor defuelling
Spent fuel pool operation
Previous decontamination and dismantling
Safe state
Final decontamination and dismantling
Waste storage, disposal and final state
Angra 2
2040 - 2080
Angra 3
2050 - 2080
Site cleaning
Site remediation
Amends and fees
payment
Licence termination
Final site survey and
monitoring
Final decontamination and
dismantling
Waste storage, disposal and final state
2080 - 2085
EndBegin
• Plants decommissioning schedule coincidence: Same benefits of 1st approach;
• Angra 1 and Angra 2 decommissioning postponed to coincide with Angra 3
• Extended Safe Storage Period (Angra 1 and Angra 2):
• lower radioactivity and waste volumes to be stored/disposed;
• Costs of Angra 1 and Angra 2 could be increased:
• extended period of survey, maintenance and security of deactivated plants.
3rd approach: Mixed DECON-SAFSTOR strategy
Angra 1
Proposal of mixed DECON and SAFSTOR CNAAA site decommissioning strategy
Start
Planning
Costing estimation
Final state
definition
2022
2024 - 2040
Shutdown procedures
Reactor defuelling
Spent fuel pool operation
Previous decontamination and dismantling
Safe state
Final decontamination and dismantling
Waste storage, disposal and final state
Angra 2
2040 - 2050
Angra 3
2050 - 2060
Site cleaning
Site remediation
Amends and fees
payment
Licence termination
Final site survey
and monitoring
Final decontamination
and dismantling
Waste storage, disposal and final state
2060 - 2065
EndBegin
• Angra 1 and Angra 2 decommissioned with SAFSTOR strategy while Angra 3 will be with
DECON strategy: Time reduced about 20 years;
• Angra 3: experience in Angra 1 and Angra 2 decommissioning (lessons learned)
• Even with DECON, could reduce dose exposure and costs;
• Higher volumes of wastes to deal with: experience gain aid during
decontamination/dismantling techniques selection and waste treatment tasks.
Estimated production of wastes:
• Operational wastes will have to be managed during decommissioning:
– Only disposal facility in Brazil: dispose Goiania town accident wastes;
– Operational wastes stored on-site: cost considered separately from
Decommissioning wastes;
– Values based on estimated waste volumes of Trojan and Ringhals NPPs.
• Operational:
– Packages volume: 2.805,14 m³ (7.403 units);
– LLW/ILW: 5.800m³;
– ECIs (management and storage): 3.420 units.
• Decommissioning:
– LLW (metals, concrete and others): 28.443,3m³;
– ILW: 496,2 m³;
– HLW: 212,4m³.
ALVARO ALBERTO NUCLEAR POWER STATION
Preliminary Decommissioning Plan (PDP)
Estimated production of wastes:
• Volume reduction techniques:
– Choice of suitable decontamination and dismantling
technique
• Reduce waste production (primary and
secondary wastes);
– Compress, Supercompression, Incineration, Immobilization
(cement, glass and ceramic matrix):
– Aid to handling, transport, storage/disposal tasks.
ALVARO ALBERTO NUCLEAR POWER STATION
Preliminary Decommissioning Plan (PDP)
Main Cost Drivers:
• project management;
• dismantling of the reactor vessel and
internals;
• decontamination of the major primary
components;
• demolition of the buildings; and
• waste management.
ALVARO ALBERTO NUCLEAR POWER STATION
Preliminary Decommissioning Plan (PDP)
Direct Decommissioning Cost Breakdown
SOURCE:
COST ESTIMATING STRUCTURE
SOURCE:
Estimated costs:
• “Minimum Decommissioning Fund Formula,”
NRC 10 CFR 50.75(c) (1988)
• site (3 NPPs) decommissioning costs:
US$ 1,5 billion to the whole site
ALVARO ALBERTO NUCLEAR POWER STATION
Preliminary Decommissioning Plan (PDP)
EC Year X = 1986 $ Cost × [A LX + B EX + C BX]
International Structure for decommissioning
Costing (ISDC) of Nuclear Installations
IN PROGRESS
Funding:
• Decommissioning Financial Fund managed
by Eletronuclear holding company Eletrobras
– Financial resources from electricity sales
– Annual amounts defined by Brazilian Electric
Energy Regulatory Agency
ALVARO ALBERTO NUCLEAR POWER STATION
Preliminary Decommissioning Plan (PDP)
FINANCIAL POSITION ON AUG/2016 (in Brazilian Reais)
IAEA International Conference on Advancing the
Global Implementation of Decommissioning and
Environmental Remediation Programmes
May 23-27 2016, Madrid, Spain
• THE ROLE OF GOVERNMENT
– Confirmed the importance of national policies and strategies and of responsibility resting with the current generation.
– Emphasis on cost-effectiveness, to conserve resources, on early planning and on prompt action.
– Strong linkage between decommissioning or environmental remediation, and associated management of waste (“cradle to grave”
management)
• THE LEGAL AND REGULATORY FRAMEWORK FOR DECOMMISSIONING AND ENVIRONMENTAL
REMEDIATION
– International standards and associated guidance should be developed for conditional clearance of materials from decommissioning.
– The conference recommended that the international community needs to do more to identify what levels of radioactive contamination
could generally be regarded as being sufficiently low that they do not pose a threat to the safety of people and the environment.
– The Conference further recommended that additional consideration be given to establishing international guidelines for post-accident
recovery
• THE DECISION PROCESS AND INVOLVEMENT OF STAKEHOLDERS
– Value of transparency and stakeholder engagement in decision making.
• TECHNOLOGY AND INNOVATION
– Coordination of research and development activities related to decommissioning.
– Importance of continued exchange of experiences through accessible forums and the value of looking to other technical fields for
solutions
• SUPPLY CHAIN
– Develop guidance on the management of project risks in decommissioning and remediation programmes, including opportunities for
sharing information on good practice on this issue.
– Develop training opportunities for young professionals.
Leonam Guimarães

More Related Content

What's hot

09 reynolds 7th salt workshop (trr)
09 reynolds 7th salt workshop (trr)09 reynolds 7th salt workshop (trr)
09 reynolds 7th salt workshop (trr)
leann_mays
 
修勤绪 国际林业碳汇市场研究
修勤绪 国际林业碳汇市场研究修勤绪 国际林业碳汇市场研究
修勤绪 国际林业碳汇市场研究xiu1982
 
Environmental lean six_sigma_case_studies
Environmental lean six_sigma_case_studiesEnvironmental lean six_sigma_case_studies
Environmental lean six_sigma_case_studies
billclintonvn
 
Waste Confidence Rule Project Presentation for UM NERS 531
Waste Confidence Rule Project Presentation for UM NERS 531Waste Confidence Rule Project Presentation for UM NERS 531
Waste Confidence Rule Project Presentation for UM NERS 531Doug Kripke
 
SMART Plant Project - EUBCE2019
SMART Plant Project - EUBCE2019SMART Plant Project - EUBCE2019
SMART Plant Project - EUBCE2019
SALTGAEProject
 
Circular Economy Solutions in the Water Sector
Circular Economy Solutions in the Water SectorCircular Economy Solutions in the Water Sector
Circular Economy Solutions in the Water Sector
NextGen Water Solutions
 
Looming Challenges of Aviation GHG (2009)
Looming Challenges of Aviation GHG (2009)Looming Challenges of Aviation GHG (2009)
Looming Challenges of Aviation GHG (2009)
Jawad Rachami
 
Management of Disused Sealed Radioactive Sources
Management of Disused Sealed Radioactive SourcesManagement of Disused Sealed Radioactive Sources
Management of Disused Sealed Radioactive SourcesAlan Carolissen
 
Sgcp14beckmanncp
Sgcp14beckmanncpSgcp14beckmanncp
Sgcp14beckmanncp
Justin Hayward
 
07 vicente guna fa 0073-feasibility of pvp_ps in spain-20110913_ed01
07 vicente guna fa 0073-feasibility of pvp_ps in spain-20110913_ed0107 vicente guna fa 0073-feasibility of pvp_ps in spain-20110913_ed01
07 vicente guna fa 0073-feasibility of pvp_ps in spain-20110913_ed01pvsinbloom
 
Techno-economic assessment and global sensitivity analysis for biomass-based ...
Techno-economic assessment and global sensitivity analysis for biomass-based ...Techno-economic assessment and global sensitivity analysis for biomass-based ...
Techno-economic assessment and global sensitivity analysis for biomass-based ...
UK Carbon Capture and Storage Research Centre
 
C0 2 ricardo_environmental
C0 2 ricardo_environmentalC0 2 ricardo_environmental
C0 2 ricardo_environmental
Ricardo Energy & Environment
 
CCAFS and GRA Resources for CLIFF-GRADS 2021
CCAFS and GRA Resources for CLIFF-GRADS 2021CCAFS and GRA Resources for CLIFF-GRADS 2021
Biomass Gasification Overview - Ilkka Hannula
Biomass Gasification Overview - Ilkka HannulaBiomass Gasification Overview - Ilkka Hannula
Biomass Gasification Overview - Ilkka Hannula
EBAconference
 
Mitigation Pathways to well below 2C in ETSAP-TIAM
Mitigation Pathways to well below 2C in ETSAP-TIAMMitigation Pathways to well below 2C in ETSAP-TIAM
Mitigation Pathways to well below 2C in ETSAP-TIAM
IEA-ETSAP
 
Review of the reference documents on best available technique (BREF) for wast...
Review of the reference documents on best available technique (BREF) for wast...Review of the reference documents on best available technique (BREF) for wast...
Review of the reference documents on best available technique (BREF) for wast...
EBAconference
 
Experimental Study of Some Agro-Industrial Residues Targeted As Partial Subst...
Experimental Study of Some Agro-Industrial Residues Targeted As Partial Subst...Experimental Study of Some Agro-Industrial Residues Targeted As Partial Subst...
Experimental Study of Some Agro-Industrial Residues Targeted As Partial Subst...
ijceronline
 
Biomethane in the Netherlands - current state and future outlook - Michael Sa...
Biomethane in the Netherlands - current state and future outlook - Michael Sa...Biomethane in the Netherlands - current state and future outlook - Michael Sa...
Biomethane in the Netherlands - current state and future outlook - Michael Sa...
EBAconference
 
Emirates Steel Industry Carbon Capture Usage & Storage Project and ADNOC Ruma...
Emirates Steel Industry Carbon Capture Usage & Storage Project and ADNOC Ruma...Emirates Steel Industry Carbon Capture Usage & Storage Project and ADNOC Ruma...
Emirates Steel Industry Carbon Capture Usage & Storage Project and ADNOC Ruma...
Global CCS Institute
 

What's hot (19)

09 reynolds 7th salt workshop (trr)
09 reynolds 7th salt workshop (trr)09 reynolds 7th salt workshop (trr)
09 reynolds 7th salt workshop (trr)
 
修勤绪 国际林业碳汇市场研究
修勤绪 国际林业碳汇市场研究修勤绪 国际林业碳汇市场研究
修勤绪 国际林业碳汇市场研究
 
Environmental lean six_sigma_case_studies
Environmental lean six_sigma_case_studiesEnvironmental lean six_sigma_case_studies
Environmental lean six_sigma_case_studies
 
Waste Confidence Rule Project Presentation for UM NERS 531
Waste Confidence Rule Project Presentation for UM NERS 531Waste Confidence Rule Project Presentation for UM NERS 531
Waste Confidence Rule Project Presentation for UM NERS 531
 
SMART Plant Project - EUBCE2019
SMART Plant Project - EUBCE2019SMART Plant Project - EUBCE2019
SMART Plant Project - EUBCE2019
 
Circular Economy Solutions in the Water Sector
Circular Economy Solutions in the Water SectorCircular Economy Solutions in the Water Sector
Circular Economy Solutions in the Water Sector
 
Looming Challenges of Aviation GHG (2009)
Looming Challenges of Aviation GHG (2009)Looming Challenges of Aviation GHG (2009)
Looming Challenges of Aviation GHG (2009)
 
Management of Disused Sealed Radioactive Sources
Management of Disused Sealed Radioactive SourcesManagement of Disused Sealed Radioactive Sources
Management of Disused Sealed Radioactive Sources
 
Sgcp14beckmanncp
Sgcp14beckmanncpSgcp14beckmanncp
Sgcp14beckmanncp
 
07 vicente guna fa 0073-feasibility of pvp_ps in spain-20110913_ed01
07 vicente guna fa 0073-feasibility of pvp_ps in spain-20110913_ed0107 vicente guna fa 0073-feasibility of pvp_ps in spain-20110913_ed01
07 vicente guna fa 0073-feasibility of pvp_ps in spain-20110913_ed01
 
Techno-economic assessment and global sensitivity analysis for biomass-based ...
Techno-economic assessment and global sensitivity analysis for biomass-based ...Techno-economic assessment and global sensitivity analysis for biomass-based ...
Techno-economic assessment and global sensitivity analysis for biomass-based ...
 
C0 2 ricardo_environmental
C0 2 ricardo_environmentalC0 2 ricardo_environmental
C0 2 ricardo_environmental
 
CCAFS and GRA Resources for CLIFF-GRADS 2021
CCAFS and GRA Resources for CLIFF-GRADS 2021CCAFS and GRA Resources for CLIFF-GRADS 2021
CCAFS and GRA Resources for CLIFF-GRADS 2021
 
Biomass Gasification Overview - Ilkka Hannula
Biomass Gasification Overview - Ilkka HannulaBiomass Gasification Overview - Ilkka Hannula
Biomass Gasification Overview - Ilkka Hannula
 
Mitigation Pathways to well below 2C in ETSAP-TIAM
Mitigation Pathways to well below 2C in ETSAP-TIAMMitigation Pathways to well below 2C in ETSAP-TIAM
Mitigation Pathways to well below 2C in ETSAP-TIAM
 
Review of the reference documents on best available technique (BREF) for wast...
Review of the reference documents on best available technique (BREF) for wast...Review of the reference documents on best available technique (BREF) for wast...
Review of the reference documents on best available technique (BREF) for wast...
 
Experimental Study of Some Agro-Industrial Residues Targeted As Partial Subst...
Experimental Study of Some Agro-Industrial Residues Targeted As Partial Subst...Experimental Study of Some Agro-Industrial Residues Targeted As Partial Subst...
Experimental Study of Some Agro-Industrial Residues Targeted As Partial Subst...
 
Biomethane in the Netherlands - current state and future outlook - Michael Sa...
Biomethane in the Netherlands - current state and future outlook - Michael Sa...Biomethane in the Netherlands - current state and future outlook - Michael Sa...
Biomethane in the Netherlands - current state and future outlook - Michael Sa...
 
Emirates Steel Industry Carbon Capture Usage & Storage Project and ADNOC Ruma...
Emirates Steel Industry Carbon Capture Usage & Storage Project and ADNOC Ruma...Emirates Steel Industry Carbon Capture Usage & Storage Project and ADNOC Ruma...
Emirates Steel Industry Carbon Capture Usage & Storage Project and ADNOC Ruma...
 

Viewers also liked

A Limited Analysis of Some Nonacoustic Antisubmarine Warfare Systems
A Limited Analysis of Some Nonacoustic Antisubmarine Warfare SystemsA Limited Analysis of Some Nonacoustic Antisubmarine Warfare Systems
A Limited Analysis of Some Nonacoustic Antisubmarine Warfare Systems
Leonam Guimarães
 
THE CHALLENGE OF HYDROTHERMAL TRANSITION IN BRAZIL
THE CHALLENGE OF HYDROTHERMAL TRANSITION IN BRAZILTHE CHALLENGE OF HYDROTHERMAL TRANSITION IN BRAZIL
THE CHALLENGE OF HYDROTHERMAL TRANSITION IN BRAZIL
Leonam Guimarães
 
Nuclear Power in Brazil and Latin America
Nuclear Power in Brazil and Latin AmericaNuclear Power in Brazil and Latin America
Nuclear Power in Brazil and Latin America
Leonam Guimarães
 
O Desafio da Segurança de Tecnologias
O Desafio da Segurança de TecnologiasO Desafio da Segurança de Tecnologias
O Desafio da Segurança de Tecnologias
Leonam Guimarães
 
Naval Nuclear Propulsion: Assessing Benefits and Risks
Naval Nuclear Propulsion: Assessing Benefits and RisksNaval Nuclear Propulsion: Assessing Benefits and Risks
Naval Nuclear Propulsion: Assessing Benefits and Risks
Leonam Guimarães
 
NUCLEAR POWER: THE FOUR TRANSITIONS
NUCLEAR POWER: THE FOUR TRANSITIONSNUCLEAR POWER: THE FOUR TRANSITIONS
NUCLEAR POWER: THE FOUR TRANSITIONS
Leonam Guimarães
 
Soviet and Russian Nuclear Submarines
Soviet and Russian Nuclear SubmarinesSoviet and Russian Nuclear Submarines
Soviet and Russian Nuclear SubmarinesLeonam Guimarães
 
World nuclear-performance-report-2016
World nuclear-performance-report-2016World nuclear-performance-report-2016
World nuclear-performance-report-2016
Leonam Guimarães
 
Àtomos para a Paz e Desenvolvimento
Àtomos para a Paz e DesenvolvimentoÀtomos para a Paz e Desenvolvimento
Àtomos para a Paz e Desenvolvimento
Leonam Guimarães
 
NAVAL NUCLEAR PROPULSION AND THE INTERNATIONAL NONPROLIFERATION REGIME
NAVAL NUCLEAR PROPULSION AND THE INTERNATIONAL NONPROLIFERATION REGIMENAVAL NUCLEAR PROPULSION AND THE INTERNATIONAL NONPROLIFERATION REGIME
NAVAL NUCLEAR PROPULSION AND THE INTERNATIONAL NONPROLIFERATION REGIMELeonam Guimarães
 
The Global Risks report 2015
The Global Risks report 2015The Global Risks report 2015
The Global Risks report 2015
Leonam Guimarães
 
Nuclear power and sustainable development
Nuclear power and sustainable developmentNuclear power and sustainable development
Nuclear power and sustainable development
Leonam Guimarães
 
Rickover’s Legacy: Secrets of the Nuclear Navy’s Success
Rickover’s Legacy: Secrets of the Nuclear Navy’s SuccessRickover’s Legacy: Secrets of the Nuclear Navy’s Success
Rickover’s Legacy: Secrets of the Nuclear Navy’s SuccessLeonam Guimarães
 
Learning from experience Lessons from the Submarine Programs of the United St...
Learning from experience Lessons from the Submarine Programs of the United St...Learning from experience Lessons from the Submarine Programs of the United St...
Learning from experience Lessons from the Submarine Programs of the United St...Leonam Guimarães
 
Why does Brazil need nuclear submarines?
Why does Brazil need nuclear submarines?Why does Brazil need nuclear submarines?
Why does Brazil need nuclear submarines?Leonam Guimarães
 
US nuclear submarines: the fast attack
US nuclear submarines: the fast attackUS nuclear submarines: the fast attack
US nuclear submarines: the fast attackLeonam Guimarães
 

Viewers also liked (17)

A Limited Analysis of Some Nonacoustic Antisubmarine Warfare Systems
A Limited Analysis of Some Nonacoustic Antisubmarine Warfare SystemsA Limited Analysis of Some Nonacoustic Antisubmarine Warfare Systems
A Limited Analysis of Some Nonacoustic Antisubmarine Warfare Systems
 
THE CHALLENGE OF HYDROTHERMAL TRANSITION IN BRAZIL
THE CHALLENGE OF HYDROTHERMAL TRANSITION IN BRAZILTHE CHALLENGE OF HYDROTHERMAL TRANSITION IN BRAZIL
THE CHALLENGE OF HYDROTHERMAL TRANSITION IN BRAZIL
 
Nuclear Power in Brazil and Latin America
Nuclear Power in Brazil and Latin AmericaNuclear Power in Brazil and Latin America
Nuclear Power in Brazil and Latin America
 
Nuclear marine propulsion
Nuclear marine propulsionNuclear marine propulsion
Nuclear marine propulsion
 
O Desafio da Segurança de Tecnologias
O Desafio da Segurança de TecnologiasO Desafio da Segurança de Tecnologias
O Desafio da Segurança de Tecnologias
 
Naval Nuclear Propulsion: Assessing Benefits and Risks
Naval Nuclear Propulsion: Assessing Benefits and RisksNaval Nuclear Propulsion: Assessing Benefits and Risks
Naval Nuclear Propulsion: Assessing Benefits and Risks
 
NUCLEAR POWER: THE FOUR TRANSITIONS
NUCLEAR POWER: THE FOUR TRANSITIONSNUCLEAR POWER: THE FOUR TRANSITIONS
NUCLEAR POWER: THE FOUR TRANSITIONS
 
Soviet and Russian Nuclear Submarines
Soviet and Russian Nuclear SubmarinesSoviet and Russian Nuclear Submarines
Soviet and Russian Nuclear Submarines
 
World nuclear-performance-report-2016
World nuclear-performance-report-2016World nuclear-performance-report-2016
World nuclear-performance-report-2016
 
Àtomos para a Paz e Desenvolvimento
Àtomos para a Paz e DesenvolvimentoÀtomos para a Paz e Desenvolvimento
Àtomos para a Paz e Desenvolvimento
 
NAVAL NUCLEAR PROPULSION AND THE INTERNATIONAL NONPROLIFERATION REGIME
NAVAL NUCLEAR PROPULSION AND THE INTERNATIONAL NONPROLIFERATION REGIMENAVAL NUCLEAR PROPULSION AND THE INTERNATIONAL NONPROLIFERATION REGIME
NAVAL NUCLEAR PROPULSION AND THE INTERNATIONAL NONPROLIFERATION REGIME
 
The Global Risks report 2015
The Global Risks report 2015The Global Risks report 2015
The Global Risks report 2015
 
Nuclear power and sustainable development
Nuclear power and sustainable developmentNuclear power and sustainable development
Nuclear power and sustainable development
 
Rickover’s Legacy: Secrets of the Nuclear Navy’s Success
Rickover’s Legacy: Secrets of the Nuclear Navy’s SuccessRickover’s Legacy: Secrets of the Nuclear Navy’s Success
Rickover’s Legacy: Secrets of the Nuclear Navy’s Success
 
Learning from experience Lessons from the Submarine Programs of the United St...
Learning from experience Lessons from the Submarine Programs of the United St...Learning from experience Lessons from the Submarine Programs of the United St...
Learning from experience Lessons from the Submarine Programs of the United St...
 
Why does Brazil need nuclear submarines?
Why does Brazil need nuclear submarines?Why does Brazil need nuclear submarines?
Why does Brazil need nuclear submarines?
 
US nuclear submarines: the fast attack
US nuclear submarines: the fast attackUS nuclear submarines: the fast attack
US nuclear submarines: the fast attack
 

Similar to DECOMMISSIONING BRAZILIAN NPPs: POLICY, STRATEGY AND PLANNING

The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016Alan Carolissen
 
LLW challenges and developments FINAL pptx
LLW challenges and developments FINAL pptxLLW challenges and developments FINAL pptx
LLW challenges and developments FINAL pptxPeter ORMAI
 
OPTIMIZING BATTERY END-OF-LIFE BY STATIONARY APPLICATIONS AND RECYCLING
OPTIMIZING BATTERY END-OF-LIFE BY STATIONARY APPLICATIONS AND RECYCLINGOPTIMIZING BATTERY END-OF-LIFE BY STATIONARY APPLICATIONS AND RECYCLING
OPTIMIZING BATTERY END-OF-LIFE BY STATIONARY APPLICATIONS AND RECYCLING
iQHub
 
Savigliano UNIDO’s concept on resource mobilization for non-eligible activi...
Savigliano   UNIDO’s concept on resource mobilization for non-eligible activi...Savigliano   UNIDO’s concept on resource mobilization for non-eligible activi...
Savigliano UNIDO’s concept on resource mobilization for non-eligible activi...
Centro Studi Galileo
 
Le Trench Introductory PO extended
Le Trench Introductory PO extended Le Trench Introductory PO extended
Le Trench Introductory PO extended Peter ORMAI
 
EXIT SPEECH FOR BANGLADESH
EXIT SPEECH FOR BANGLADESHEXIT SPEECH FOR BANGLADESH
EXIT SPEECH FOR BANGLADESHPeter ORMAI
 
Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17
Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17
Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17
Michael Habig
 
4 sarah nightingale decc offshore wind seminar 18 19 march 2014
4 sarah nightingale decc offshore wind seminar 18 19  march 20144 sarah nightingale decc offshore wind seminar 18 19  march 2014
4 sarah nightingale decc offshore wind seminar 18 19 march 2014
NaturalEngland
 
Business case of CCUS, Sasha Mackler, SUMMIT Carbon Capture
Business case of CCUS, Sasha Mackler, SUMMIT Carbon CaptureBusiness case of CCUS, Sasha Mackler, SUMMIT Carbon Capture
Business case of CCUS, Sasha Mackler, SUMMIT Carbon Capture
Global CCS Institute
 
techUK Environment and Compliance Programme
techUK Environment and Compliance ProgrammetechUK Environment and Compliance Programme
techUK Environment and Compliance Programme
techUK
 
Containment Filtered Venting - A new approach
Containment Filtered Venting - A new approachContainment Filtered Venting - A new approach
Containment Filtered Venting - A new approach
Alexander Wolski
 
Cambridge July 2016 _Enkom
Cambridge July 2016 _EnkomCambridge July 2016 _Enkom
Cambridge July 2016 _EnkomMartyn Jenkins
 
ADBA Spring Regulatory Forum - May 2016
ADBA Spring Regulatory Forum - May 2016ADBA Spring Regulatory Forum - May 2016
ADBA Spring Regulatory Forum - May 2016
Anaerobic Digestion & Biogas Association
 
Solar energy ongoing project by Magda Cayón
Solar energy ongoing project by Magda CayónSolar energy ongoing project by Magda Cayón
Solar energy ongoing project by Magda Cayón
ASCAME
 
Demonstration project design, Ed Steadman, EERC
Demonstration project design, Ed Steadman, EERCDemonstration project design, Ed Steadman, EERC
Demonstration project design, Ed Steadman, EERC
Global CCS Institute
 
Waste to energy projects with reference to MSW, Sourabh Manuja, TERI, India
Waste to energy projects with reference to MSW, Sourabh Manuja, TERI, IndiaWaste to energy projects with reference to MSW, Sourabh Manuja, TERI, India
Waste to energy projects with reference to MSW, Sourabh Manuja, TERI, India
ESD UNU-IAS
 
TEEP and lessons learned from UK approach to EU compliance
TEEP and lessons learned from UK approach to EU complianceTEEP and lessons learned from UK approach to EU compliance
TEEP and lessons learned from UK approach to EU compliance
Ricardo Energy & Environment
 
Analyzing the Hazardous Waste Generator Improvements Rule
Analyzing the Hazardous Waste Generator Improvements RuleAnalyzing the Hazardous Waste Generator Improvements Rule
Analyzing the Hazardous Waste Generator Improvements Rule
Triumvirate Environmental
 
GB Energy storage market update and supply chain opportunities Johnny Gowdy
GB Energy storage market update and supply chain opportunities Johnny GowdyGB Energy storage market update and supply chain opportunities Johnny Gowdy
GB Energy storage market update and supply chain opportunities Johnny Gowdy
Invest Northern Ireland
 

Similar to DECOMMISSIONING BRAZILIAN NPPs: POLICY, STRATEGY AND PLANNING (20)

The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
 
LLW challenges and developments FINAL pptx
LLW challenges and developments FINAL pptxLLW challenges and developments FINAL pptx
LLW challenges and developments FINAL pptx
 
OPTIMIZING BATTERY END-OF-LIFE BY STATIONARY APPLICATIONS AND RECYCLING
OPTIMIZING BATTERY END-OF-LIFE BY STATIONARY APPLICATIONS AND RECYCLINGOPTIMIZING BATTERY END-OF-LIFE BY STATIONARY APPLICATIONS AND RECYCLING
OPTIMIZING BATTERY END-OF-LIFE BY STATIONARY APPLICATIONS AND RECYCLING
 
Savigliano UNIDO’s concept on resource mobilization for non-eligible activi...
Savigliano   UNIDO’s concept on resource mobilization for non-eligible activi...Savigliano   UNIDO’s concept on resource mobilization for non-eligible activi...
Savigliano UNIDO’s concept on resource mobilization for non-eligible activi...
 
Used fuel andrew sowder - epri
Used fuel   andrew sowder - epriUsed fuel   andrew sowder - epri
Used fuel andrew sowder - epri
 
Le Trench Introductory PO extended
Le Trench Introductory PO extended Le Trench Introductory PO extended
Le Trench Introductory PO extended
 
EXIT SPEECH FOR BANGLADESH
EXIT SPEECH FOR BANGLADESHEXIT SPEECH FOR BANGLADESH
EXIT SPEECH FOR BANGLADESH
 
Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17
Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17
Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17
 
4 sarah nightingale decc offshore wind seminar 18 19 march 2014
4 sarah nightingale decc offshore wind seminar 18 19  march 20144 sarah nightingale decc offshore wind seminar 18 19  march 2014
4 sarah nightingale decc offshore wind seminar 18 19 march 2014
 
Business case of CCUS, Sasha Mackler, SUMMIT Carbon Capture
Business case of CCUS, Sasha Mackler, SUMMIT Carbon CaptureBusiness case of CCUS, Sasha Mackler, SUMMIT Carbon Capture
Business case of CCUS, Sasha Mackler, SUMMIT Carbon Capture
 
techUK Environment and Compliance Programme
techUK Environment and Compliance ProgrammetechUK Environment and Compliance Programme
techUK Environment and Compliance Programme
 
Containment Filtered Venting - A new approach
Containment Filtered Venting - A new approachContainment Filtered Venting - A new approach
Containment Filtered Venting - A new approach
 
Cambridge July 2016 _Enkom
Cambridge July 2016 _EnkomCambridge July 2016 _Enkom
Cambridge July 2016 _Enkom
 
ADBA Spring Regulatory Forum - May 2016
ADBA Spring Regulatory Forum - May 2016ADBA Spring Regulatory Forum - May 2016
ADBA Spring Regulatory Forum - May 2016
 
Solar energy ongoing project by Magda Cayón
Solar energy ongoing project by Magda CayónSolar energy ongoing project by Magda Cayón
Solar energy ongoing project by Magda Cayón
 
Demonstration project design, Ed Steadman, EERC
Demonstration project design, Ed Steadman, EERCDemonstration project design, Ed Steadman, EERC
Demonstration project design, Ed Steadman, EERC
 
Waste to energy projects with reference to MSW, Sourabh Manuja, TERI, India
Waste to energy projects with reference to MSW, Sourabh Manuja, TERI, IndiaWaste to energy projects with reference to MSW, Sourabh Manuja, TERI, India
Waste to energy projects with reference to MSW, Sourabh Manuja, TERI, India
 
TEEP and lessons learned from UK approach to EU compliance
TEEP and lessons learned from UK approach to EU complianceTEEP and lessons learned from UK approach to EU compliance
TEEP and lessons learned from UK approach to EU compliance
 
Analyzing the Hazardous Waste Generator Improvements Rule
Analyzing the Hazardous Waste Generator Improvements RuleAnalyzing the Hazardous Waste Generator Improvements Rule
Analyzing the Hazardous Waste Generator Improvements Rule
 
GB Energy storage market update and supply chain opportunities Johnny Gowdy
GB Energy storage market update and supply chain opportunities Johnny GowdyGB Energy storage market update and supply chain opportunities Johnny Gowdy
GB Energy storage market update and supply chain opportunities Johnny Gowdy
 

Recently uploaded

NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 

Recently uploaded (20)

NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 

DECOMMISSIONING BRAZILIAN NPPs: POLICY, STRATEGY AND PLANNING

  • 1. Leonam dos Santos Guimarães
  • 3. 61 NPPS being built in 15 countries 2007 - 2016: 46 new connections to the grid (by August 2016) ANGRA 3 FANGCHENGGANG-2 15 Jul, 2016
  • 4. GENERATION CHANGE: II -> III -> III+ -> IV
  • 5. PERMANENT SHUTDOWN REACTORS Source: IAEA PRIS (August 2016) To date, about 157 commercial power reactors, experimental or prototype reactors, over 250 research reactors and a number of fuel cycle facilities have been retired from operation. Some of these have been fully dismantled.
  • 6. Nuclear power reactors worldwide Source: NEA/OECD (September 2016)
  • 7. Growing Importance of Decommissioning • Need to manage this end of life cycle in a safe and cost-effective manner: – a condition to support new nuclear • Strengthen work on integrated waste management: – including characterization, processing and storage • Most parts of a nuclear power plant do not become radioactive, or are contaminated at only very low levels. Most of the metal can be recycled. • Proven techniques and equipment are available to dismantle nuclear facilities safely and these have now been well demonstrated in several parts of the world. • Decommissioning costs for nuclear power plants, including disposal of associated wastes, are reducing and contribute only a small fraction of the total cost of electricity generation.
  • 8. NUCLEAR IN BRAZIL: TODAY ANGRA 2 PWR Power: 1.350 MW Technology: Siemens/KWU Operation start: JAN/2001 ANGRA 1 PWR Power: 657 MW Technology: Westinghouse Operation start: JAN/1985
  • 9. NUCLEAR IN BRAZIL: TOMORROW ANGRA 2 PWR Power: 1.405 MW Technology: AREVA Operation start: JAN/2022
  • 10. NUCLEAR POTENCIAL ATLAS 2) Southeast 2.000 MW 1) Northeast 2.000 MW EPRI SITTING CRITERIA Geographic Information Systems National Energy Plan 2030 NUCLEAR IN BRAZIL: FUTURE
  • 12. Roadmap Site Data Levantamento de campo Outros dados PPE Plant Parameter Envelope 2016 ESP Early Site Permit Environmental and Nuclear site licensing independent of vendor Vendor Qualification Brazilian Utility Requirement BUR 2017 PPA Power Purchase Agreement Definition and Decison to Build . 2018 - 2019 Site Selection Which Sites will be studied in detail 2014 - 2015 RFI Request for Information Request as per IAEA and NEI guides Additional data with technical details SitingTechnology AUCTION Licensing Start BUSINESS MODEL NUCLEAR POTENCIAL ATLAS Feasibility Soc-Eco Impacts
  • 13. CURRENT ACTIVITIES • Plant Parameter Envelope – RFIs to suppliers – Early Site Permit Report • Brazilian Utility Requirements – URD/EUR Model • Business Model – Public-Private Partnership • Economic and Financial Feasibility • Social and Economic Impacts NUCLEAR IN BRAZIL: FUTURE
  • 14. Decommissioning Policy • defined as the framework implemented by governments, including laws, regulations, standards and mandatory requirements, that imposes the background rules to be followed by the nuclear industry for decommissioning projects. • National decommissioning policies were found to differ on many aspects that may have an impact on costs. Key points in this regard - Brazilian Policy:     BROWNFIELD REGULATED REGULATED  REGULATED
  • 15. Decommissioning Strategies (acepted by Brazilian Safety Authority)
  • 16. ALVARO ALBERTO NUCLEAR POWER STATION Preliminary Decommissioning Plan (PDP) Considers planned Angra 1, Angra 2 and Angra 3 end of operations: 2024 / 2040 / 2050 Life extensions not considered (yet) Whole site should be decommissioned. 3 approaches: • Pure SAFSTOR • Alternative SAFSTOR • Mixed DECON-SAFSTOR
  • 17. 1st approach: Pure SAFSTOR Angra 1 Proposal of pure SAFSTOR CNAAA site decommissioning strategy: main approach Start Planning Costing estimation Final state definition 2022 2024 - 2054 Shutdown procedures Reactor defuelling Spent fuel pool operation Previous decontamination and dismantling Safe state Final decontamination and dismantling Waste storage, disposal and final state Angra 2 2040 - 2070 Angra 3 2050 - 2080 Site cleaning Site remediation Amends and fees payment Licence termination 2080 - 2085 Final site survey and monitoring EndBegin • Plants decommissioning schedule coincidence: • Cost reduction possibility • experience gain by the decommissioning team (same to whole site); • Safe Storage Period: • reduce waste volumes and associated potential problems to deal with.
  • 18. 2nd approach: Alternative SAFSTOR Angra 1 Proposal of SAFSTOR CNAAA site decommissioning strategy: alternative approach Start Planning Costing estimation Final state definition 2022 2024 - 2080 Shutdown procedures Reactor defuelling Spent fuel pool operation Previous decontamination and dismantling Safe state Final decontamination and dismantling Waste storage, disposal and final state Angra 2 2040 - 2080 Angra 3 2050 - 2080 Site cleaning Site remediation Amends and fees payment Licence termination Final site survey and monitoring Final decontamination and dismantling Waste storage, disposal and final state 2080 - 2085 EndBegin • Plants decommissioning schedule coincidence: Same benefits of 1st approach; • Angra 1 and Angra 2 decommissioning postponed to coincide with Angra 3 • Extended Safe Storage Period (Angra 1 and Angra 2): • lower radioactivity and waste volumes to be stored/disposed; • Costs of Angra 1 and Angra 2 could be increased: • extended period of survey, maintenance and security of deactivated plants.
  • 19. 3rd approach: Mixed DECON-SAFSTOR strategy Angra 1 Proposal of mixed DECON and SAFSTOR CNAAA site decommissioning strategy Start Planning Costing estimation Final state definition 2022 2024 - 2040 Shutdown procedures Reactor defuelling Spent fuel pool operation Previous decontamination and dismantling Safe state Final decontamination and dismantling Waste storage, disposal and final state Angra 2 2040 - 2050 Angra 3 2050 - 2060 Site cleaning Site remediation Amends and fees payment Licence termination Final site survey and monitoring Final decontamination and dismantling Waste storage, disposal and final state 2060 - 2065 EndBegin • Angra 1 and Angra 2 decommissioned with SAFSTOR strategy while Angra 3 will be with DECON strategy: Time reduced about 20 years; • Angra 3: experience in Angra 1 and Angra 2 decommissioning (lessons learned) • Even with DECON, could reduce dose exposure and costs; • Higher volumes of wastes to deal with: experience gain aid during decontamination/dismantling techniques selection and waste treatment tasks.
  • 20. Estimated production of wastes: • Operational wastes will have to be managed during decommissioning: – Only disposal facility in Brazil: dispose Goiania town accident wastes; – Operational wastes stored on-site: cost considered separately from Decommissioning wastes; – Values based on estimated waste volumes of Trojan and Ringhals NPPs. • Operational: – Packages volume: 2.805,14 m³ (7.403 units); – LLW/ILW: 5.800m³; – ECIs (management and storage): 3.420 units. • Decommissioning: – LLW (metals, concrete and others): 28.443,3m³; – ILW: 496,2 m³; – HLW: 212,4m³. ALVARO ALBERTO NUCLEAR POWER STATION Preliminary Decommissioning Plan (PDP)
  • 21. Estimated production of wastes: • Volume reduction techniques: – Choice of suitable decontamination and dismantling technique • Reduce waste production (primary and secondary wastes); – Compress, Supercompression, Incineration, Immobilization (cement, glass and ceramic matrix): – Aid to handling, transport, storage/disposal tasks. ALVARO ALBERTO NUCLEAR POWER STATION Preliminary Decommissioning Plan (PDP)
  • 22. Main Cost Drivers: • project management; • dismantling of the reactor vessel and internals; • decontamination of the major primary components; • demolition of the buildings; and • waste management. ALVARO ALBERTO NUCLEAR POWER STATION Preliminary Decommissioning Plan (PDP)
  • 23. Direct Decommissioning Cost Breakdown SOURCE:
  • 25. Estimated costs: • “Minimum Decommissioning Fund Formula,” NRC 10 CFR 50.75(c) (1988) • site (3 NPPs) decommissioning costs: US$ 1,5 billion to the whole site ALVARO ALBERTO NUCLEAR POWER STATION Preliminary Decommissioning Plan (PDP) EC Year X = 1986 $ Cost × [A LX + B EX + C BX]
  • 26. International Structure for decommissioning Costing (ISDC) of Nuclear Installations IN PROGRESS
  • 27. Funding: • Decommissioning Financial Fund managed by Eletronuclear holding company Eletrobras – Financial resources from electricity sales – Annual amounts defined by Brazilian Electric Energy Regulatory Agency ALVARO ALBERTO NUCLEAR POWER STATION Preliminary Decommissioning Plan (PDP) FINANCIAL POSITION ON AUG/2016 (in Brazilian Reais)
  • 28. IAEA International Conference on Advancing the Global Implementation of Decommissioning and Environmental Remediation Programmes May 23-27 2016, Madrid, Spain • THE ROLE OF GOVERNMENT – Confirmed the importance of national policies and strategies and of responsibility resting with the current generation. – Emphasis on cost-effectiveness, to conserve resources, on early planning and on prompt action. – Strong linkage between decommissioning or environmental remediation, and associated management of waste (“cradle to grave” management) • THE LEGAL AND REGULATORY FRAMEWORK FOR DECOMMISSIONING AND ENVIRONMENTAL REMEDIATION – International standards and associated guidance should be developed for conditional clearance of materials from decommissioning. – The conference recommended that the international community needs to do more to identify what levels of radioactive contamination could generally be regarded as being sufficiently low that they do not pose a threat to the safety of people and the environment. – The Conference further recommended that additional consideration be given to establishing international guidelines for post-accident recovery • THE DECISION PROCESS AND INVOLVEMENT OF STAKEHOLDERS – Value of transparency and stakeholder engagement in decision making. • TECHNOLOGY AND INNOVATION – Coordination of research and development activities related to decommissioning. – Importance of continued exchange of experiences through accessible forums and the value of looking to other technical fields for solutions • SUPPLY CHAIN – Develop guidance on the management of project risks in decommissioning and remediation programmes, including opportunities for sharing information on good practice on this issue. – Develop training opportunities for young professionals.