Agenda
1) Introduction
2) Enkom’s nuclear experience & capability
3) Nuclear Decommissioning costs & financing
 Types of decommissioning
 Analysing the challenges of long-term provision of funding
 Evaluating the importance of estimating costs
 Identifying the future of finance for decommissioning projects
Page 2 of 25July 2016
July 2016
Who we are, what we do & who we work with
 Enkom is an Independent consultancy offering
professional services to the Nuclear and Energy
sectors
 Lifecycle Baselines & Whole Life Costing
 Establish Programme Management Offices and
Project Controls teams with clients
 Develop Contract Strategies and Project
Execution Plans which are aligned with business
objectives
 Independently verify scope, schedule & costs at
Project, Programme & Enterprise level
 Provide Subject Matter Expertise and Assurance
for all phases of nuclear projects
Page 4 of 25July 2016
Timeline of projects our team has supported
July 2016 Page 5 of 25
Major Clients / Projects 02/03 03/04 04/05 05/06 06/07 07/08 08/09 09/10 10/11 11/12 12/13 13/ 14 14/ 15 15/ 16 16/ 17
Environmental Services (BNG)
Baseline Decommissioning Plans
(BDP)
British Nuclear Group Ltd
Preparation of LCBL /
NTWP
British Energy
Verification of
DWMP
Magnox North Limited
Consultancy support to central Project
Controls
Magnox South Limited
Consultancy support
Optimised Plan
Magnox Limited Strategic
Programmes
Cost Capture & Benchmarking
Magnox Limited (Business)
Consultancy support - Central Cost
Function
Nuclear Decom Authority
(NDA), Magnox & MWH
Benchmarking
Report
Cost
Reviews
Sellafield Limited and Tier 2
Contractors
Commercial
Assistance
Nuclear Decommissioning
Authority (NDA) – Special
Nuclear Services – Lot 6
SNS - GDF Estimate Review
NDA - IR & BCP - Deloitte
Review &
Benchmarking
NuGeneration Limited –
Assurance of DWMP
Cost &
Technical
Our story is one of evolution & strong relationships
The Enkom team has evolved from our work on;
 the development of early Baseline Decommissioning Plans,
 drafting procedures and processes to allow best practice to be applied,
 establishing SLC internal Integrated Assurance processes to allow challenge,
 developing Benchmarking methodologies to support value for money,
 providing Subject Matter Expertise on national decommissioning portfolios, and
 Advisors on Decommissioning Waste Management Plans for nuclear New Build
Page 6 of 25July 2016
July 2016
Decommissioning Costs and Financing
 Types of decommissioning
 Analysing the challenges of long-term provision of funding
 Evaluating the importance of estimating costs
 Identifying the future of finance for decommissioning projects
Page 8 of 25July 2016
Types of Decommissioning
July 2016
Types of decommissioning -
Immediate vs Deferred
 Immediate and deferred dismantling may be considered to present specific benefits
and disadvantages.
 National policies determine which approach is adopted and, for any selected
approach, adequate funding is required as well as;
 trained personnel
 regulatory oversight
 adequate waste storage and disposal facilities
 Regardless of the option selected it is vital that early and clear decisions are taken
about the timing of the closure of facilities and intended future use of the site.
Page 10 of 25July 2016
Immediate Decommissioning
Advantages Disadvantages
 availability of highly qualified workforce
and experience and knowledge on the
operational history of the specific facility
 easier radiological characterisation and
reduced effects of deterioration and ageing
 less risk of loss of knowledge and
corruption of records
 dilution of economic effects for the region
 earlier reuse of site
 responsibility for the decommissioning is
not transferred to future generations
 the motivation of personnel might be a
problem when demolishing a plant where
the workers will lose their jobs
 higher radiation exposure during
dismantling
 greater precautions needed during
dismantling
 larger volumes of decommissioning waste
classified as radioactive
July 2016 Page 11 of 25
Deferred Decommissioning
Advantages Disadvantages
 reduction of residual radioactivity due to
decay
 reduction of radiation hazard during
dismantling and reduction of volume of
radioactive waste
 possibility to wait for availability of disposal
routes for rad-waste or for expected
improvements in techniques (e.g. Robotics)
 possibility to co-ordinate the
decommissioning of different units in
multiple reactor sites
 time for decommissioning funds to grow or
to be additionally raised
 possibility to increase the size of the fund
though effective investments policies
 some materials or buildings, including
concrete and steel, may deteriorate
 costs for maintenance/disposition may
increase
 knowledge of operational history lost over
time
 new qualified staff required
 no foreseeable changes in boundary
conditions e.g. availability of waste disposal
routes or changes in the regulatory
framework
 leaves the burden to be borne by future
generations
 risk of losing fund value.
July 2016 Page 12 of 25
Challenges of long-term provision of funding
July 2016
Decommissioning funds - what they cover
 Preliminary decommissioning
planning
 Spent fuel management
 Site decommissioning and
restoration
 Waste management
 Long term storage / disposal of
waste materials
Page 14 of 25July 2016
Current vs future liabilities – who pays for what ?
State funding Operator funding
 UK existing legacy funded by
government
 UK New build funded by operators –
Funded Decommissioning Plan (FDP)
 Germany – ongoing dialogue
between Government & utilities
 Sweden – contributions to fund
 Finland – operators responsible
for all costs
Page 15 of 25July 2016
European position - revenue and investment
• Costs of decommissioning
generally paid for by
operators
• Influenced by factors such as;
• Electricity prices
• Subsides and taxes
• Political issues
• Final disposal costs
Page 16 of 25July 2016
Importance of Cost Estimating
July 2016
Key drivers for decommissioning cost estimates
• Decommissioning policy &
strategy.
• Regulatory involvement
• Dismantling techniques
• Waste management
• Oversight and management
costs (overheads)
• Management of Spent fuel
and operational waste
• Long term storage / disposal
of waste material
Page 18 of 25July 2016
• Uncertainty and contingency
Reactor shutdowns
Page 19 of 25July 2016
UK Nuclear Provision – previous 5 years
July 2016 Page 20 of 25
Estimating uncertainty application in Europe
Source - NEA (2016, p. 82). Costs of Decommissioning Nuclear Power Plants Paris: OECD
Page 21 of 25July 2016
Future of financing decommissioning
July 2016
UK Energy Act 2008 – Funded Decommissioning Plan
 Energy Act 2008 requires nuclear
operators have secure financing in place
to meet full Decom / waste costs
 The FDP must set out realistic, clearly
defined and achievable plans
 Decommissioning Waste Management
Plan (DWMP) the part of the FDP that
sets out and costs the steps involved in
decommissioning a Nuclear Power
Station.
Page 23 of25July 2016
European - Funding Policy and Strategy
• Considerable variations between
countries in the details of funding
requirements.
• Need for planning, updating cost
estimates, collecting and securing the
funding and financial risks
management...
• Funding arrangements are vulnerable
to earlier than expected permanent
plant closures (e.g., political decisions,
or permanent market price declines),
• Practices vary widely among countries
Extract from The Financial Times : Guy Chazan Berlin 15th March‘16
Page 24 of 25July 2016
Contact Details
 Martyn Jenkins - Managing Director
 Email - martyn.jenkins@enkom.co.uk
 Website - www.enkom.co.uk
 Phone - 00 44 (0) 7968 756 695
Page 25 of 25July 2016

More Related Content

What's hot

CCXG Workshop, May 2021, Key takeaways
CCXG Workshop, May 2021, Key takeawaysCCXG Workshop, May 2021, Key takeaways
CCXG Workshop, May 2021, Key takeaways
OECD Environment
 
Day 2 Workshop Recommendations
Day 2 Workshop RecommendationsDay 2 Workshop Recommendations
Day 2 Workshop Recommendations
RCREEE
 
OECD DAC Joint ENVIRONET-WP-STAT Task Team Work Programme: Update on status a...
OECD DAC Joint ENVIRONET-WP-STAT Task Team Work Programme: Update on status a...OECD DAC Joint ENVIRONET-WP-STAT Task Team Work Programme: Update on status a...
OECD DAC Joint ENVIRONET-WP-STAT Task Team Work Programme: Update on status a...
Development Co-operation Directorate (DCD-DAC)
 
Ccs ready minimum requirements ian havercroft
Ccs ready minimum requirements ian havercroftCcs ready minimum requirements ian havercroft
Ccs ready minimum requirements ian havercroft
Global CCS Institute
 
Session2 the mediterranean solar plan status and recent developments-authored...
Session2 the mediterranean solar plan status and recent developments-authored...Session2 the mediterranean solar plan status and recent developments-authored...
Session2 the mediterranean solar plan status and recent developments-authored...
RCREEE
 
GRT Gaz
GRT GazGRT Gaz
GRT Gaz
Mark Peterson
 
FGSZ
FGSZFGSZ
Monitoring CCS and CCUS projects for GHG regulatory compliance , Pamela Tomsk...
Monitoring CCS and CCUS projects for GHG regulatory compliance , Pamela Tomsk...Monitoring CCS and CCUS projects for GHG regulatory compliance , Pamela Tomsk...
Monitoring CCS and CCUS projects for GHG regulatory compliance , Pamela Tomsk...
Global CCS Institute
 
tech_roadmap_ukerc
tech_roadmap_ukerctech_roadmap_ukerc
tech_roadmap_ukerc
Henry Jeffrey
 
Coal Regions in Transition Initiative
Coal Regions in Transition InitiativeCoal Regions in Transition Initiative
Coal Regions in Transition Initiative
energydialog
 
Building international cooperation with key global partners – the example of ...
Building international cooperation with key global partners – the example of ...Building international cooperation with key global partners – the example of ...
Building international cooperation with key global partners – the example of ...
Francois Stepman
 
CCXG Forum, March 2020, Chiara Falduto
CCXG Forum, March 2020, Chiara FaldutoCCXG Forum, March 2020, Chiara Falduto
CCXG Forum, March 2020, Chiara Falduto
OECD Environment
 
Challenges and Proposals Related to the List of ODA-Eligible International Or...
Challenges and Proposals Related to the List of ODA-Eligible International Or...Challenges and Proposals Related to the List of ODA-Eligible International Or...
Challenges and Proposals Related to the List of ODA-Eligible International Or...
Development Co-operation Directorate (DCD-DAC)
 
marine_action_plan
marine_action_planmarine_action_plan
marine_action_plan
Henry Jeffrey
 
Edison stoccaggio
Edison stoccaggioEdison stoccaggio
Edison stoccaggio
Mark Peterson
 
Ivs 2013 stormwater vic conference iouri draft 3
Ivs   2013 stormwater vic conference iouri draft 3Ivs   2013 stormwater vic conference iouri draft 3
Ivs 2013 stormwater vic conference iouri draft 3
Iouri Vaisman
 
CCXG Forum, March 2020, Marcia Rocha
CCXG Forum, March 2020, Marcia RochaCCXG Forum, March 2020, Marcia Rocha
CCXG Forum, March 2020, Marcia Rocha
OECD Environment
 
Workshop recommendations
Workshop recommendationsWorkshop recommendations
Workshop recommendations
RCREEE
 
Overview of the revised proposal for fine-tuning the climate Rio markers and ...
Overview of the revised proposal for fine-tuning the climate Rio markers and ...Overview of the revised proposal for fine-tuning the climate Rio markers and ...
Overview of the revised proposal for fine-tuning the climate Rio markers and ...
Development Co-operation Directorate (DCD-DAC)
 
CCXG, Forum, March 2020, Key Takeaways
CCXG, Forum, March 2020, Key TakeawaysCCXG, Forum, March 2020, Key Takeaways
CCXG, Forum, March 2020, Key Takeaways
OECD Environment
 

What's hot (20)

CCXG Workshop, May 2021, Key takeaways
CCXG Workshop, May 2021, Key takeawaysCCXG Workshop, May 2021, Key takeaways
CCXG Workshop, May 2021, Key takeaways
 
Day 2 Workshop Recommendations
Day 2 Workshop RecommendationsDay 2 Workshop Recommendations
Day 2 Workshop Recommendations
 
OECD DAC Joint ENVIRONET-WP-STAT Task Team Work Programme: Update on status a...
OECD DAC Joint ENVIRONET-WP-STAT Task Team Work Programme: Update on status a...OECD DAC Joint ENVIRONET-WP-STAT Task Team Work Programme: Update on status a...
OECD DAC Joint ENVIRONET-WP-STAT Task Team Work Programme: Update on status a...
 
Ccs ready minimum requirements ian havercroft
Ccs ready minimum requirements ian havercroftCcs ready minimum requirements ian havercroft
Ccs ready minimum requirements ian havercroft
 
Session2 the mediterranean solar plan status and recent developments-authored...
Session2 the mediterranean solar plan status and recent developments-authored...Session2 the mediterranean solar plan status and recent developments-authored...
Session2 the mediterranean solar plan status and recent developments-authored...
 
GRT Gaz
GRT GazGRT Gaz
GRT Gaz
 
FGSZ
FGSZFGSZ
FGSZ
 
Monitoring CCS and CCUS projects for GHG regulatory compliance , Pamela Tomsk...
Monitoring CCS and CCUS projects for GHG regulatory compliance , Pamela Tomsk...Monitoring CCS and CCUS projects for GHG regulatory compliance , Pamela Tomsk...
Monitoring CCS and CCUS projects for GHG regulatory compliance , Pamela Tomsk...
 
tech_roadmap_ukerc
tech_roadmap_ukerctech_roadmap_ukerc
tech_roadmap_ukerc
 
Coal Regions in Transition Initiative
Coal Regions in Transition InitiativeCoal Regions in Transition Initiative
Coal Regions in Transition Initiative
 
Building international cooperation with key global partners – the example of ...
Building international cooperation with key global partners – the example of ...Building international cooperation with key global partners – the example of ...
Building international cooperation with key global partners – the example of ...
 
CCXG Forum, March 2020, Chiara Falduto
CCXG Forum, March 2020, Chiara FaldutoCCXG Forum, March 2020, Chiara Falduto
CCXG Forum, March 2020, Chiara Falduto
 
Challenges and Proposals Related to the List of ODA-Eligible International Or...
Challenges and Proposals Related to the List of ODA-Eligible International Or...Challenges and Proposals Related to the List of ODA-Eligible International Or...
Challenges and Proposals Related to the List of ODA-Eligible International Or...
 
marine_action_plan
marine_action_planmarine_action_plan
marine_action_plan
 
Edison stoccaggio
Edison stoccaggioEdison stoccaggio
Edison stoccaggio
 
Ivs 2013 stormwater vic conference iouri draft 3
Ivs   2013 stormwater vic conference iouri draft 3Ivs   2013 stormwater vic conference iouri draft 3
Ivs 2013 stormwater vic conference iouri draft 3
 
CCXG Forum, March 2020, Marcia Rocha
CCXG Forum, March 2020, Marcia RochaCCXG Forum, March 2020, Marcia Rocha
CCXG Forum, March 2020, Marcia Rocha
 
Workshop recommendations
Workshop recommendationsWorkshop recommendations
Workshop recommendations
 
Overview of the revised proposal for fine-tuning the climate Rio markers and ...
Overview of the revised proposal for fine-tuning the climate Rio markers and ...Overview of the revised proposal for fine-tuning the climate Rio markers and ...
Overview of the revised proposal for fine-tuning the climate Rio markers and ...
 
CCXG, Forum, March 2020, Key Takeaways
CCXG, Forum, March 2020, Key TakeawaysCCXG, Forum, March 2020, Key Takeaways
CCXG, Forum, March 2020, Key Takeaways
 

Viewers also liked

Diapostiva del tic
Diapostiva del ticDiapostiva del tic
Diapostiva del tic
Anita Capellán Romero
 
Encuesta para alumnos de nuevo ingreso
Encuesta para alumnos de nuevo ingresoEncuesta para alumnos de nuevo ingreso
Encuesta para alumnos de nuevo ingreso
ortizomarbernal
 
Game1
Game1Game1
Game1
Cáo Cáo
 
ENFERMERIA
ENFERMERIAENFERMERIA
ECONOMIA Y POLITICA ALIMENTARIA.
ECONOMIA Y POLITICA ALIMENTARIA.ECONOMIA Y POLITICA ALIMENTARIA.
ECONOMIA Y POLITICA ALIMENTARIA.
holaDANA
 
Genaro caldas 1-sistemas-A
Genaro caldas 1-sistemas-AGenaro caldas 1-sistemas-A
Genaro caldas 1-sistemas-A
Ismael Caldas
 
Teaching Project Survival Skills: Lessons from "The Martian."
Teaching Project Survival Skills:  Lessons from "The Martian."Teaching Project Survival Skills:  Lessons from "The Martian."
Teaching Project Survival Skills: Lessons from "The Martian."
Wayne Pferdehirt
 
Educatie deschisa ce, de ce, cum
Educatie deschisa ce, de ce, cumEducatie deschisa ce, de ce, cum
Educatie deschisa ce, de ce, cum
Centrul pentru Inovare Publică
 
Best Practices in Communicating with College Parents & Families
Best Practices in Communicating with College Parents & FamiliesBest Practices in Communicating with College Parents & Families
Best Practices in Communicating with College Parents & Families
Sarah Schupp
 
10 Derecho Económico
10 Derecho Económico10 Derecho Económico
10 Derecho Económico
ALBERTO VEGA HERNÁNDEZ
 

Viewers also liked (10)

Diapostiva del tic
Diapostiva del ticDiapostiva del tic
Diapostiva del tic
 
Encuesta para alumnos de nuevo ingreso
Encuesta para alumnos de nuevo ingresoEncuesta para alumnos de nuevo ingreso
Encuesta para alumnos de nuevo ingreso
 
Game1
Game1Game1
Game1
 
ENFERMERIA
ENFERMERIAENFERMERIA
ENFERMERIA
 
ECONOMIA Y POLITICA ALIMENTARIA.
ECONOMIA Y POLITICA ALIMENTARIA.ECONOMIA Y POLITICA ALIMENTARIA.
ECONOMIA Y POLITICA ALIMENTARIA.
 
Genaro caldas 1-sistemas-A
Genaro caldas 1-sistemas-AGenaro caldas 1-sistemas-A
Genaro caldas 1-sistemas-A
 
Teaching Project Survival Skills: Lessons from "The Martian."
Teaching Project Survival Skills:  Lessons from "The Martian."Teaching Project Survival Skills:  Lessons from "The Martian."
Teaching Project Survival Skills: Lessons from "The Martian."
 
Educatie deschisa ce, de ce, cum
Educatie deschisa ce, de ce, cumEducatie deschisa ce, de ce, cum
Educatie deschisa ce, de ce, cum
 
Best Practices in Communicating with College Parents & Families
Best Practices in Communicating with College Parents & FamiliesBest Practices in Communicating with College Parents & Families
Best Practices in Communicating with College Parents & Families
 
10 Derecho Económico
10 Derecho Económico10 Derecho Económico
10 Derecho Económico
 

Similar to Cambridge July 2016 _Enkom

Eurporean nuclear conference 2016 enkom
Eurporean nuclear conference 2016  enkomEurporean nuclear conference 2016  enkom
Eurporean nuclear conference 2016 enkom
Martyn Jenkins
 
Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...
Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...
Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...
ScottMadden, Inc.
 
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
Alan Carolissen
 
EXIT SPEECH FOR BANGLADESH
EXIT SPEECH FOR BANGLADESHEXIT SPEECH FOR BANGLADESH
EXIT SPEECH FOR BANGLADESH
Peter ORMAI
 
Framework launch_vf.pdf
Framework launch_vf.pdfFramework launch_vf.pdf
Framework launch_vf.pdf
OECD Environment
 
4 sarah nightingale decc offshore wind seminar 18 19 march 2014
4 sarah nightingale decc offshore wind seminar 18 19  march 20144 sarah nightingale decc offshore wind seminar 18 19  march 2014
4 sarah nightingale decc offshore wind seminar 18 19 march 2014
NaturalEngland
 
Key issues and barriers in developing countries
Key issues and barriers in developing countriesKey issues and barriers in developing countries
Key issues and barriers in developing countries
Global CCS Institute
 
DECOMMISSIONING BRAZILIAN NPPs: POLICY, STRATEGY AND PLANNING
DECOMMISSIONING BRAZILIAN NPPs: POLICY, STRATEGY AND PLANNINGDECOMMISSIONING BRAZILIAN NPPs: POLICY, STRATEGY AND PLANNING
DECOMMISSIONING BRAZILIAN NPPs: POLICY, STRATEGY AND PLANNING
Leonam Guimarães
 
techUK Environment and Compliance Programme
techUK Environment and Compliance ProgrammetechUK Environment and Compliance Programme
techUK Environment and Compliance Programme
techUK
 
DSD-INT 2023 Dynamic Adaptive Policy Pathways (DAPP) - Theory & Showcase - Wa...
DSD-INT 2023 Dynamic Adaptive Policy Pathways (DAPP) - Theory & Showcase - Wa...DSD-INT 2023 Dynamic Adaptive Policy Pathways (DAPP) - Theory & Showcase - Wa...
DSD-INT 2023 Dynamic Adaptive Policy Pathways (DAPP) - Theory & Showcase - Wa...
Deltares
 
Atlantic Council - Victor Der
Atlantic Council - Victor DerAtlantic Council - Victor Der
Atlantic Council - Victor Der
Global CCS Institute
 
Session 4.5 Updating the National Climate Change Action Plan: Towards an e...
Session 4.5 Updating the National Climate Change Action Plan: Towards an e...Session 4.5 Updating the National Climate Change Action Plan: Towards an e...
Session 4.5 Updating the National Climate Change Action Plan: Towards an e...
NAP Events
 
Offshore Wind Energy: Improving Project Development and Supply Chain Processe...
Offshore Wind Energy: Improving Project Development and Supply Chain Processe...Offshore Wind Energy: Improving Project Development and Supply Chain Processe...
Offshore Wind Energy: Improving Project Development and Supply Chain Processe...
Stavros Thomas
 
CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
UK Carbon Capture and Storage Research Centre
 
نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)
نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)
نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)
AMPA
 
Robin Campbell & Paul Davies - Planning for Sustainable Drainage
Robin Campbell & Paul Davies - Planning for Sustainable DrainageRobin Campbell & Paul Davies - Planning for Sustainable Drainage
Robin Campbell & Paul Davies - Planning for Sustainable Drainage
PAS_Team
 
Webinar: The Global Status of CCS: 2014 - Overcoming challenges in Europe
Webinar: The Global Status of CCS: 2014 - Overcoming challenges in EuropeWebinar: The Global Status of CCS: 2014 - Overcoming challenges in Europe
Webinar: The Global Status of CCS: 2014 - Overcoming challenges in Europe
Global CCS Institute
 
Thailand UNDP-GIZ workshop on CBA - Appraisal outcomes
Thailand UNDP-GIZ workshop on CBA - Appraisal outcomesThailand UNDP-GIZ workshop on CBA - Appraisal outcomes
Thailand UNDP-GIZ workshop on CBA - Appraisal outcomes
UNDP Climate
 
Advanced Fossil Energy Technologies: Presentation by Global CCS Institute
Advanced Fossil Energy Technologies: Presentation by Global CCS InstituteAdvanced Fossil Energy Technologies: Presentation by Global CCS Institute
Advanced Fossil Energy Technologies: Presentation by Global CCS Institute
atlanticcouncil
 
02 highlights from integrated waste management system analyses, storage and t...
02 highlights from integrated waste management system analyses, storage and t...02 highlights from integrated waste management system analyses, storage and t...
02 highlights from integrated waste management system analyses, storage and t...
leann_mays
 

Similar to Cambridge July 2016 _Enkom (20)

Eurporean nuclear conference 2016 enkom
Eurporean nuclear conference 2016  enkomEurporean nuclear conference 2016  enkom
Eurporean nuclear conference 2016 enkom
 
Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...
Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...
Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...
 
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
 
EXIT SPEECH FOR BANGLADESH
EXIT SPEECH FOR BANGLADESHEXIT SPEECH FOR BANGLADESH
EXIT SPEECH FOR BANGLADESH
 
Framework launch_vf.pdf
Framework launch_vf.pdfFramework launch_vf.pdf
Framework launch_vf.pdf
 
4 sarah nightingale decc offshore wind seminar 18 19 march 2014
4 sarah nightingale decc offshore wind seminar 18 19  march 20144 sarah nightingale decc offshore wind seminar 18 19  march 2014
4 sarah nightingale decc offshore wind seminar 18 19 march 2014
 
Key issues and barriers in developing countries
Key issues and barriers in developing countriesKey issues and barriers in developing countries
Key issues and barriers in developing countries
 
DECOMMISSIONING BRAZILIAN NPPs: POLICY, STRATEGY AND PLANNING
DECOMMISSIONING BRAZILIAN NPPs: POLICY, STRATEGY AND PLANNINGDECOMMISSIONING BRAZILIAN NPPs: POLICY, STRATEGY AND PLANNING
DECOMMISSIONING BRAZILIAN NPPs: POLICY, STRATEGY AND PLANNING
 
techUK Environment and Compliance Programme
techUK Environment and Compliance ProgrammetechUK Environment and Compliance Programme
techUK Environment and Compliance Programme
 
DSD-INT 2023 Dynamic Adaptive Policy Pathways (DAPP) - Theory & Showcase - Wa...
DSD-INT 2023 Dynamic Adaptive Policy Pathways (DAPP) - Theory & Showcase - Wa...DSD-INT 2023 Dynamic Adaptive Policy Pathways (DAPP) - Theory & Showcase - Wa...
DSD-INT 2023 Dynamic Adaptive Policy Pathways (DAPP) - Theory & Showcase - Wa...
 
Atlantic Council - Victor Der
Atlantic Council - Victor DerAtlantic Council - Victor Der
Atlantic Council - Victor Der
 
Session 4.5 Updating the National Climate Change Action Plan: Towards an e...
Session 4.5 Updating the National Climate Change Action Plan: Towards an e...Session 4.5 Updating the National Climate Change Action Plan: Towards an e...
Session 4.5 Updating the National Climate Change Action Plan: Towards an e...
 
Offshore Wind Energy: Improving Project Development and Supply Chain Processe...
Offshore Wind Energy: Improving Project Development and Supply Chain Processe...Offshore Wind Energy: Improving Project Development and Supply Chain Processe...
Offshore Wind Energy: Improving Project Development and Supply Chain Processe...
 
CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
 
نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)
نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)
نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)
 
Robin Campbell & Paul Davies - Planning for Sustainable Drainage
Robin Campbell & Paul Davies - Planning for Sustainable DrainageRobin Campbell & Paul Davies - Planning for Sustainable Drainage
Robin Campbell & Paul Davies - Planning for Sustainable Drainage
 
Webinar: The Global Status of CCS: 2014 - Overcoming challenges in Europe
Webinar: The Global Status of CCS: 2014 - Overcoming challenges in EuropeWebinar: The Global Status of CCS: 2014 - Overcoming challenges in Europe
Webinar: The Global Status of CCS: 2014 - Overcoming challenges in Europe
 
Thailand UNDP-GIZ workshop on CBA - Appraisal outcomes
Thailand UNDP-GIZ workshop on CBA - Appraisal outcomesThailand UNDP-GIZ workshop on CBA - Appraisal outcomes
Thailand UNDP-GIZ workshop on CBA - Appraisal outcomes
 
Advanced Fossil Energy Technologies: Presentation by Global CCS Institute
Advanced Fossil Energy Technologies: Presentation by Global CCS InstituteAdvanced Fossil Energy Technologies: Presentation by Global CCS Institute
Advanced Fossil Energy Technologies: Presentation by Global CCS Institute
 
02 highlights from integrated waste management system analyses, storage and t...
02 highlights from integrated waste management system analyses, storage and t...02 highlights from integrated waste management system analyses, storage and t...
02 highlights from integrated waste management system analyses, storage and t...
 

Cambridge July 2016 _Enkom

  • 1.
  • 2. Agenda 1) Introduction 2) Enkom’s nuclear experience & capability 3) Nuclear Decommissioning costs & financing  Types of decommissioning  Analysing the challenges of long-term provision of funding  Evaluating the importance of estimating costs  Identifying the future of finance for decommissioning projects Page 2 of 25July 2016
  • 4. Who we are, what we do & who we work with  Enkom is an Independent consultancy offering professional services to the Nuclear and Energy sectors  Lifecycle Baselines & Whole Life Costing  Establish Programme Management Offices and Project Controls teams with clients  Develop Contract Strategies and Project Execution Plans which are aligned with business objectives  Independently verify scope, schedule & costs at Project, Programme & Enterprise level  Provide Subject Matter Expertise and Assurance for all phases of nuclear projects Page 4 of 25July 2016
  • 5. Timeline of projects our team has supported July 2016 Page 5 of 25 Major Clients / Projects 02/03 03/04 04/05 05/06 06/07 07/08 08/09 09/10 10/11 11/12 12/13 13/ 14 14/ 15 15/ 16 16/ 17 Environmental Services (BNG) Baseline Decommissioning Plans (BDP) British Nuclear Group Ltd Preparation of LCBL / NTWP British Energy Verification of DWMP Magnox North Limited Consultancy support to central Project Controls Magnox South Limited Consultancy support Optimised Plan Magnox Limited Strategic Programmes Cost Capture & Benchmarking Magnox Limited (Business) Consultancy support - Central Cost Function Nuclear Decom Authority (NDA), Magnox & MWH Benchmarking Report Cost Reviews Sellafield Limited and Tier 2 Contractors Commercial Assistance Nuclear Decommissioning Authority (NDA) – Special Nuclear Services – Lot 6 SNS - GDF Estimate Review NDA - IR & BCP - Deloitte Review & Benchmarking NuGeneration Limited – Assurance of DWMP Cost & Technical
  • 6. Our story is one of evolution & strong relationships The Enkom team has evolved from our work on;  the development of early Baseline Decommissioning Plans,  drafting procedures and processes to allow best practice to be applied,  establishing SLC internal Integrated Assurance processes to allow challenge,  developing Benchmarking methodologies to support value for money,  providing Subject Matter Expertise on national decommissioning portfolios, and  Advisors on Decommissioning Waste Management Plans for nuclear New Build Page 6 of 25July 2016
  • 8. Decommissioning Costs and Financing  Types of decommissioning  Analysing the challenges of long-term provision of funding  Evaluating the importance of estimating costs  Identifying the future of finance for decommissioning projects Page 8 of 25July 2016
  • 10. Types of decommissioning - Immediate vs Deferred  Immediate and deferred dismantling may be considered to present specific benefits and disadvantages.  National policies determine which approach is adopted and, for any selected approach, adequate funding is required as well as;  trained personnel  regulatory oversight  adequate waste storage and disposal facilities  Regardless of the option selected it is vital that early and clear decisions are taken about the timing of the closure of facilities and intended future use of the site. Page 10 of 25July 2016
  • 11. Immediate Decommissioning Advantages Disadvantages  availability of highly qualified workforce and experience and knowledge on the operational history of the specific facility  easier radiological characterisation and reduced effects of deterioration and ageing  less risk of loss of knowledge and corruption of records  dilution of economic effects for the region  earlier reuse of site  responsibility for the decommissioning is not transferred to future generations  the motivation of personnel might be a problem when demolishing a plant where the workers will lose their jobs  higher radiation exposure during dismantling  greater precautions needed during dismantling  larger volumes of decommissioning waste classified as radioactive July 2016 Page 11 of 25
  • 12. Deferred Decommissioning Advantages Disadvantages  reduction of residual radioactivity due to decay  reduction of radiation hazard during dismantling and reduction of volume of radioactive waste  possibility to wait for availability of disposal routes for rad-waste or for expected improvements in techniques (e.g. Robotics)  possibility to co-ordinate the decommissioning of different units in multiple reactor sites  time for decommissioning funds to grow or to be additionally raised  possibility to increase the size of the fund though effective investments policies  some materials or buildings, including concrete and steel, may deteriorate  costs for maintenance/disposition may increase  knowledge of operational history lost over time  new qualified staff required  no foreseeable changes in boundary conditions e.g. availability of waste disposal routes or changes in the regulatory framework  leaves the burden to be borne by future generations  risk of losing fund value. July 2016 Page 12 of 25
  • 13. Challenges of long-term provision of funding July 2016
  • 14. Decommissioning funds - what they cover  Preliminary decommissioning planning  Spent fuel management  Site decommissioning and restoration  Waste management  Long term storage / disposal of waste materials Page 14 of 25July 2016
  • 15. Current vs future liabilities – who pays for what ? State funding Operator funding  UK existing legacy funded by government  UK New build funded by operators – Funded Decommissioning Plan (FDP)  Germany – ongoing dialogue between Government & utilities  Sweden – contributions to fund  Finland – operators responsible for all costs Page 15 of 25July 2016
  • 16. European position - revenue and investment • Costs of decommissioning generally paid for by operators • Influenced by factors such as; • Electricity prices • Subsides and taxes • Political issues • Final disposal costs Page 16 of 25July 2016
  • 17. Importance of Cost Estimating July 2016
  • 18. Key drivers for decommissioning cost estimates • Decommissioning policy & strategy. • Regulatory involvement • Dismantling techniques • Waste management • Oversight and management costs (overheads) • Management of Spent fuel and operational waste • Long term storage / disposal of waste material Page 18 of 25July 2016 • Uncertainty and contingency
  • 19. Reactor shutdowns Page 19 of 25July 2016
  • 20. UK Nuclear Provision – previous 5 years July 2016 Page 20 of 25
  • 21. Estimating uncertainty application in Europe Source - NEA (2016, p. 82). Costs of Decommissioning Nuclear Power Plants Paris: OECD Page 21 of 25July 2016
  • 22. Future of financing decommissioning July 2016
  • 23. UK Energy Act 2008 – Funded Decommissioning Plan  Energy Act 2008 requires nuclear operators have secure financing in place to meet full Decom / waste costs  The FDP must set out realistic, clearly defined and achievable plans  Decommissioning Waste Management Plan (DWMP) the part of the FDP that sets out and costs the steps involved in decommissioning a Nuclear Power Station. Page 23 of25July 2016
  • 24. European - Funding Policy and Strategy • Considerable variations between countries in the details of funding requirements. • Need for planning, updating cost estimates, collecting and securing the funding and financial risks management... • Funding arrangements are vulnerable to earlier than expected permanent plant closures (e.g., political decisions, or permanent market price declines), • Practices vary widely among countries Extract from The Financial Times : Guy Chazan Berlin 15th March‘16 Page 24 of 25July 2016