Curriculum Vitae
Kitjuk Harijanto
Date of Birth : May 13th ,1967
Nationality : Indonesia
Education : D3 Electrical Polytechnic of University Brawijaya, Malang
Address : Perumahan Widodo Kencana A/11, Madiun city
East Java - Indonesia
Mobile : +6282129940123 / +601133977151
Email : kitjuk_harijanto@yahoo.co.id or kharijanto67@gmail.com
Education :
- 1986–1989 Politechnic of University Brawijaya Malang
D3, Electrical
- 1983–1986 SMAN 2 Madiun
- 1980–1983 SMPN 1 Ponorogo
- 1974–1980 SDN Mangkujayan I Ponorogo
Summary of Experience :
- Background encompasses 23 years experience in the General Contractor, a joint
venture company between Indonesia and Japan as Permanent Employee of
Mechanical, Electrical, Instrument and Piping Work
Additional Capabilities :
- Microsoft Office (Excel, Word )
- Internet
Languages :
- Native language Bahasa Indonesia. : Excellent
- English : Fair
Kitjuk Harijanto +6282129940123 / +601133977151 /kitjuk_harijanto@yahoo.co.id
Curriculum Vitae
Work Experience :
1. PT. REKIND MALAYSIA (Period : December 2014 - Present)
Project : Sabah Urea Ammonia Feletaizer Project
Location : Sipitang, Sabah, Malaysia
Position Held : Superintendent of Logistic and Procurement
Responsible for :
• Prepare all of Tool, Consumable & Material
• Prepare all Mobilization & Demobilitation
• Finally all Stock Balance Material & Consumable
2. PT. PROMITS (Period : October 2014 – December 2014)
Project : LTCA Maintanance & Service Conoco Philip
Location : Conoco Philip, Palembang
Position Held : Material Control & Procurement Coordinator
Responsible for :
• Prepare all of Tool, Consumable & Material
• Prepare all Mobilization & Demobilitation
• Finally all Stock Balance Material & Consumable
3. PT. PROMITS (Period : until September 2014)
Project : Mechanical & Piping Work
Location : CNG Plant for Peaking Generation (80MW), Jambi
Position Held : Piping Fabrication & Material/Logistic Coordinator
Responsible for :
• Prepare & Execution of Piping Fabrication
• Prepare all of Tool, Consumable & Material
• Prepare all Mobilization & Demobilitation
• Finally all Stock Balance Material & Consumable
4. PT. PROMITS (Period : 2010 – 2012)
Project : Mechanical, Piping & Structure Work
Location : Fertilazer Plant Urea & Granulation 1/2, Algeria, North Africa
Position Held : Material Control & Logistic Manager
Responsible for :
• Prepare all of Tool, Consumable & Material.
• Finally all Stock Balance Material & Consumable
Kitjuk Harijanto +6282129940123 / +601133977151 /kitjuk_harijanto@yahoo.co.id
Curriculum Vitae
5. PT. PROMITS (Period : 2009 – 2010)
Project : Piping Work
Location : Ammonium Nitrate Prill Plant, Bontang, East Kalimantan
Position Held : Fabrication & Material / Logistic Coordinator
Responsible for :
• Prepare & Execution of Piping Fabrication .
• Prepare all of Tool, Consumable & Material
• Prepare all Mobilization & Demobilitation
• Finally all Stock Balance Material & Consumable.
6. PT. PROMITS (Period : 2009 )
Project : Development of Gas Pipe Distribution
Location : Dirjen MIGAS, Surabaya, East Java
Position Held : Document Control
Responsible for :
• Control all of Execution Work
• Prepare all of Document
7. PT. PROMITS (Period : 2007 – 2009)
Project : Piping Work
Location : LNG Tangguh, West Papua
Position Held : Material Control & Logistic Coordinator
Responsible for :
• Prepare all of Tool, Consumable & Material.
• Prepare all Mobilization & Demobilitation.
• Finally all Stock Balance Material & Consumable
8. PT. PROMITS (Period : 2006)
Project : Mechanical, Electrical & Piping Work
Location : Bukit Sentul Reservoir & Pump Station, Sentul, West Java
Position Held : Material Control & Electrical / Instrument Supervisor
Responsible for :
• Prepare all of Tool, Consumable & Material.
• Prepare all Mobilization & Demobilitation.
• Engineering & Installation Electrical System.
• Finally all Stock Balance Material & Consumable
Kitjuk Harijanto +6282129940123 / +601133977151 /kitjuk_harijanto@yahoo.co.id
Curriculum Vitae
9. PT. PROMITS (Period : 2004 - 2005)
Project : Piping Work
Location : Fertilizer Plant PT. Pupuk Kujang, Cikampek, West Java
Position Held : Material Control & Logistic Coordinator
Responsible for :
• Prepare all of Tool, Consumable & Material.
• Prepare all Mobilization & Demobilitation.
• Finally all Stock Balance Material & Consumable
10. PT. PROMITS (Period : 2003 - 2004)
Project : Piping Work
Location : Balongan Blue Sky Project, Balongan, West Java
Position Held : Fabrication Manager
Responsible for :
• Manage all of Fabrication Work
11. PT. PROMITS (Period : 2002 - 2003)
Project : Mechanical & Piping Work
Location : Gas & Oil Plant Peciko 3 Project, Sanipah, East Kalimantan
Position Held : Fabrication Manager
Responsible for :
• Manage all of Fabrication Work.
12. PT. PROMITS (Period : 2001 – 2002)
Project : Piping Work
Location : Fertelizer Plant PT.Pupuk Kaltim, Bontang, East Kalimantan
Position Held : Material Control & Logistic Coordinator
Responsible for :
• Prepare all of Tool, Consumable & Material.
• Prepare all Mobilization & Demobilitation.
• Finally all Stock Balance Material & Consumable
13. PT. PROMITS (Period : 2000 – 2001)
Project : Mechanical & Piping Work
Location : PA & MA Chemical Plant, Petrowidada, Gresik, East Java
Position Held : Material Control & Logistic Coordinator
Responsible for :
• Prepare all of Tool, Consumable & Material.
• Prepare all Mobilization & Demobilitation.
• Finally all Stock Balance Material & Consumable
Kitjuk Harijanto +6282129940123 / +601133977151 /kitjuk_harijanto@yahoo.co.id
Curriculum Vitae
14. PT. PROMITS (Period : 1998 – 1999)
Project : Annual Shutdown Mechanical,Piping & Electrical Work
Location : PT. Satomo Indovil Monomer,PT. Statomer, Merak,West Java
Position Held : Ass Manager
Responsible for :
• Prepare Schedule & Progress of work
• Site control of work
• Finally Project execution plann
15. PT. PROMITS (Period : 1997 – 1999)
Project : Mechanical, Piping, Electrical & Instrument Work
Location : Paiton Private Power Plant 7 & 8 (2x600MW), East Java
Position Held : Electrical / Instrument Supervisor
Responsible for :
• Site Control of Electrical / Instrument Work
• Prepare progress of work
16. PT. PROMITS (Period : 1996 – 1997)
Project : Tank Work
Location : PVC Resin Plant PT. Asahimas Subentra, Anyer, West Java
Position Held : Site Supervisor
Responsible for :
• Site Control of Fabrication & Erection 12Unit Cone roof, 1Unit Ethylene Tank
• Prepare progress of work
17. PT. PROMITS (Period : 1995 – 1996)
Project : Mechanical, Piping, Electrical & Instrument Work
Location : CMC Plant Sembawang SS, Cikarang, West Java
Position Held : Electrical / Instrument Supervisor
Responsible for :
• Site Control of Electrical / Instrument Work
• Prepare progress of work
18. PT. PROMITS (Period : 1994 – 1995)
Project : Mechanical, Piping, Electrical & Instrument Work
Location : Muara Karang Natural Gas 4 & 5, Jakarta
Position Held : Electrical / Instrument Supervisor
Responsible for :
• Site Control of Electrical / Instrument Work
• Prepare progress of work
Kitjuk Harijanto +6282129940123 / +601133977151 /kitjuk_harijanto@yahoo.co.id
Curriculum Vitae
19. PT. PROMITS (Period : 1992 – 1993)
Project : Mechanical & Piping Work
Location : PKM II 60.000 MT/Y Poly Alkyl Benzene Plant,Palembang
Position Held : Material Control & Logistic Coordinator
Responsible for :
• Prepare all of Tool, Consumable & Material.
• Prepare all Mobilization & Demobilitation.
• Finally all Stock Balance Material & Consumable
20. PT. PROMITS (Period : 1991 – 1992)
Project : Mechanical & Piping Work
Location : Edible Oil Refinery Plant PT.SMII, Pulogadung, Jakarta
Position Held : Material Control & Logistic Coordinator
Responsible for :
• Control all of Execution Work
• Prepare all of Document
• Prepare Progress of Work
21. PT. PROMITS (Period : 1990 – 1991)
Project : Mechanical, Piping, Electrical & Instrument Work
Location : 2000MTPa PolyAlumuniumChloride Plant Samsung, Cirebon
Position Held : Electrical / Instrument Supervisor
Responsible for :
• Site Control of Electrical / Instrument Work
• Prepare progress of work
22. PT. DUTA RENDRA MULYA PLYWOOD (Period : 1989)
Location : Ds. Sukalanting, Pontianak, West Kalimantan
Position Held : Maintanance Supervisor
Responsible for :
• Resposibility for all Factory Equipment
• Maintance any trouble for equipment
Kitjuk Harijanto +6282129940123 / +601133977151 /kitjuk_harijanto@yahoo.co.id
Curriculum Vitae
19. PT. PROMITS (Period : 1992 – 1993)
Project : Mechanical & Piping Work
Location : PKM II 60.000 MT/Y Poly Alkyl Benzene Plant,Palembang
Position Held : Material Control & Logistic Coordinator
Responsible for :
• Prepare all of Tool, Consumable & Material.
• Prepare all Mobilization & Demobilitation.
• Finally all Stock Balance Material & Consumable
20. PT. PROMITS (Period : 1991 – 1992)
Project : Mechanical & Piping Work
Location : Edible Oil Refinery Plant PT.SMII, Pulogadung, Jakarta
Position Held : Material Control & Logistic Coordinator
Responsible for :
• Control all of Execution Work
• Prepare all of Document
• Prepare Progress of Work
21. PT. PROMITS (Period : 1990 – 1991)
Project : Mechanical, Piping, Electrical & Instrument Work
Location : 2000MTPa PolyAlumuniumChloride Plant Samsung, Cirebon
Position Held : Electrical / Instrument Supervisor
Responsible for :
• Site Control of Electrical / Instrument Work
• Prepare progress of work
22. PT. DUTA RENDRA MULYA PLYWOOD (Period : 1989)
Location : Ds. Sukalanting, Pontianak, West Kalimantan
Position Held : Maintanance Supervisor
Responsible for :
• Resposibility for all Factory Equipment
• Maintance any trouble for equipment
Kitjuk Harijanto +6282129940123 / +601133977151 /kitjuk_harijanto@yahoo.co.id

More Related Content

What's hot (19)

CV
CVCV
CV
 
CV - LAMPIRAN KETERANGAN KERJA - SERTIFIKAT
CV - LAMPIRAN KETERANGAN KERJA - SERTIFIKATCV - LAMPIRAN KETERANGAN KERJA - SERTIFIKAT
CV - LAMPIRAN KETERANGAN KERJA - SERTIFIKAT
 
Rozlan Ramli 2015
Rozlan Ramli 2015Rozlan Ramli 2015
Rozlan Ramli 2015
 
Copy of BhaskarSarkar_AECOM
Copy of BhaskarSarkar_AECOMCopy of BhaskarSarkar_AECOM
Copy of BhaskarSarkar_AECOM
 
CV_Anup
CV_AnupCV_Anup
CV_Anup
 
New CV of VRB
New CV of VRBNew CV of VRB
New CV of VRB
 
Erry Sudewo's CV
Erry Sudewo's CVErry Sudewo's CV
Erry Sudewo's CV
 
Ko Ko Naing Thein (update 2015)
Ko Ko Naing Thein (update 2015)Ko Ko Naing Thein (update 2015)
Ko Ko Naing Thein (update 2015)
 
Wp 241016
Wp 241016Wp 241016
Wp 241016
 
Corporate presentation of P & R Infraprojects Ltd
Corporate presentation of P & R Infraprojects LtdCorporate presentation of P & R Infraprojects Ltd
Corporate presentation of P & R Infraprojects Ltd
 
CV Victorianus Cahya Prakasa-Dec 2016
CV Victorianus Cahya Prakasa-Dec 2016CV Victorianus Cahya Prakasa-Dec 2016
CV Victorianus Cahya Prakasa-Dec 2016
 
MIDEL C resume013[1] (1)
MIDEL C resume013[1] (1)MIDEL C resume013[1] (1)
MIDEL C resume013[1] (1)
 
CURRICULUM VITAE
CURRICULUM VITAECURRICULUM VITAE
CURRICULUM VITAE
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
 
Marasigan Norvel Resume 2016
Marasigan Norvel Resume 2016Marasigan Norvel Resume 2016
Marasigan Norvel Resume 2016
 
Makhate CV - Jun 2015
Makhate CV - Jun 2015Makhate CV - Jun 2015
Makhate CV - Jun 2015
 
CV_JAKKARIN PAETPITAK_(ENG)_141015
CV_JAKKARIN PAETPITAK_(ENG)_141015CV_JAKKARIN PAETPITAK_(ENG)_141015
CV_JAKKARIN PAETPITAK_(ENG)_141015
 
My Resume.1
My Resume.1My Resume.1
My Resume.1
 
New (Civ) Ehsan
New (Civ) EhsanNew (Civ) Ehsan
New (Civ) Ehsan
 

Viewers also liked

Misting Systems By MistCooling
Misting Systems By MistCoolingMisting Systems By MistCooling
Misting Systems By MistCoolingmistcooling
 
Sample collection, Preservation and its Estimation
Sample collection, Preservation and its EstimationSample collection, Preservation and its Estimation
Sample collection, Preservation and its EstimationMD Abdul Haleem
 
PARTNERSHIP & INVESTMENTS
PARTNERSHIP & INVESTMENTSPARTNERSHIP & INVESTMENTS
PARTNERSHIP & INVESTMENTSAzalnarziev
 

Viewers also liked (6)

Misting Systems By MistCooling
Misting Systems By MistCoolingMisting Systems By MistCooling
Misting Systems By MistCooling
 
Stored Machinery Preservation
Stored Machinery PreservationStored Machinery Preservation
Stored Machinery Preservation
 
Sample collection, Preservation and its Estimation
Sample collection, Preservation and its EstimationSample collection, Preservation and its Estimation
Sample collection, Preservation and its Estimation
 
SAP – Non Stock Materials (NLAG)
SAP – Non Stock Materials (NLAG)SAP – Non Stock Materials (NLAG)
SAP – Non Stock Materials (NLAG)
 
Consumable Materials
Consumable MaterialsConsumable Materials
Consumable Materials
 
PARTNERSHIP & INVESTMENTS
PARTNERSHIP & INVESTMENTSPARTNERSHIP & INVESTMENTS
PARTNERSHIP & INVESTMENTS
 

Similar to CV Kitjuk Harijanto (20)

CV Achmad Zaelani
CV Achmad ZaelaniCV Achmad Zaelani
CV Achmad Zaelani
 
CV_Arijanto EP_2016
CV_Arijanto EP_2016CV_Arijanto EP_2016
CV_Arijanto EP_2016
 
CV
CVCV
CV
 
AMT CV (3)
AMT CV (3)AMT CV (3)
AMT CV (3)
 
CURICULUM VITAE (CV)
CURICULUM VITAE (CV)CURICULUM VITAE (CV)
CURICULUM VITAE (CV)
 
cv Syukur Anton Nugroho
cv  Syukur Anton Nugrohocv  Syukur Anton Nugroho
cv Syukur Anton Nugroho
 
CV-Gusryan Zari Khamsya
CV-Gusryan Zari KhamsyaCV-Gusryan Zari Khamsya
CV-Gusryan Zari Khamsya
 
Curriculum Vitae Muhammad Taufiq
Curriculum Vitae Muhammad TaufiqCurriculum Vitae Muhammad Taufiq
Curriculum Vitae Muhammad Taufiq
 
CV
CVCV
CV
 
Update CV-Junaidi_Juni 2016
Update CV-Junaidi_Juni 2016Update CV-Junaidi_Juni 2016
Update CV-Junaidi_Juni 2016
 
CV Ibnu Sodik.xlsx
CV  Ibnu Sodik.xlsxCV  Ibnu Sodik.xlsx
CV Ibnu Sodik.xlsx
 
Nuzlul Ihsan
Nuzlul IhsanNuzlul Ihsan
Nuzlul Ihsan
 
CV Bambang Eko Hermawan
CV Bambang Eko HermawanCV Bambang Eko Hermawan
CV Bambang Eko Hermawan
 
Curicculum Vitae Mardianto
Curicculum Vitae MardiantoCuricculum Vitae Mardianto
Curicculum Vitae Mardianto
 
CV souvanna.2.2
CV souvanna.2.2CV souvanna.2.2
CV souvanna.2.2
 
CV Farouk Alfisahar 2015
CV Farouk Alfisahar 2015CV Farouk Alfisahar 2015
CV Farouk Alfisahar 2015
 
Thomas vincent cv
Thomas vincent cvThomas vincent cv
Thomas vincent cv
 
CV Wahyu Wahono
CV Wahyu WahonoCV Wahyu Wahono
CV Wahyu Wahono
 
CV Eko Agus Tavala
CV Eko Agus TavalaCV Eko Agus Tavala
CV Eko Agus Tavala
 
CV_Rachmad Arif
CV_Rachmad ArifCV_Rachmad Arif
CV_Rachmad Arif
 

CV Kitjuk Harijanto

  • 1. Curriculum Vitae Kitjuk Harijanto Date of Birth : May 13th ,1967 Nationality : Indonesia Education : D3 Electrical Polytechnic of University Brawijaya, Malang Address : Perumahan Widodo Kencana A/11, Madiun city East Java - Indonesia Mobile : +6282129940123 / +601133977151 Email : kitjuk_harijanto@yahoo.co.id or kharijanto67@gmail.com Education : - 1986–1989 Politechnic of University Brawijaya Malang D3, Electrical - 1983–1986 SMAN 2 Madiun - 1980–1983 SMPN 1 Ponorogo - 1974–1980 SDN Mangkujayan I Ponorogo Summary of Experience : - Background encompasses 23 years experience in the General Contractor, a joint venture company between Indonesia and Japan as Permanent Employee of Mechanical, Electrical, Instrument and Piping Work Additional Capabilities : - Microsoft Office (Excel, Word ) - Internet Languages : - Native language Bahasa Indonesia. : Excellent - English : Fair Kitjuk Harijanto +6282129940123 / +601133977151 /kitjuk_harijanto@yahoo.co.id
  • 2. Curriculum Vitae Work Experience : 1. PT. REKIND MALAYSIA (Period : December 2014 - Present) Project : Sabah Urea Ammonia Feletaizer Project Location : Sipitang, Sabah, Malaysia Position Held : Superintendent of Logistic and Procurement Responsible for : • Prepare all of Tool, Consumable & Material • Prepare all Mobilization & Demobilitation • Finally all Stock Balance Material & Consumable 2. PT. PROMITS (Period : October 2014 – December 2014) Project : LTCA Maintanance & Service Conoco Philip Location : Conoco Philip, Palembang Position Held : Material Control & Procurement Coordinator Responsible for : • Prepare all of Tool, Consumable & Material • Prepare all Mobilization & Demobilitation • Finally all Stock Balance Material & Consumable 3. PT. PROMITS (Period : until September 2014) Project : Mechanical & Piping Work Location : CNG Plant for Peaking Generation (80MW), Jambi Position Held : Piping Fabrication & Material/Logistic Coordinator Responsible for : • Prepare & Execution of Piping Fabrication • Prepare all of Tool, Consumable & Material • Prepare all Mobilization & Demobilitation • Finally all Stock Balance Material & Consumable 4. PT. PROMITS (Period : 2010 – 2012) Project : Mechanical, Piping & Structure Work Location : Fertilazer Plant Urea & Granulation 1/2, Algeria, North Africa Position Held : Material Control & Logistic Manager Responsible for : • Prepare all of Tool, Consumable & Material. • Finally all Stock Balance Material & Consumable Kitjuk Harijanto +6282129940123 / +601133977151 /kitjuk_harijanto@yahoo.co.id
  • 3. Curriculum Vitae 5. PT. PROMITS (Period : 2009 – 2010) Project : Piping Work Location : Ammonium Nitrate Prill Plant, Bontang, East Kalimantan Position Held : Fabrication & Material / Logistic Coordinator Responsible for : • Prepare & Execution of Piping Fabrication . • Prepare all of Tool, Consumable & Material • Prepare all Mobilization & Demobilitation • Finally all Stock Balance Material & Consumable. 6. PT. PROMITS (Period : 2009 ) Project : Development of Gas Pipe Distribution Location : Dirjen MIGAS, Surabaya, East Java Position Held : Document Control Responsible for : • Control all of Execution Work • Prepare all of Document 7. PT. PROMITS (Period : 2007 – 2009) Project : Piping Work Location : LNG Tangguh, West Papua Position Held : Material Control & Logistic Coordinator Responsible for : • Prepare all of Tool, Consumable & Material. • Prepare all Mobilization & Demobilitation. • Finally all Stock Balance Material & Consumable 8. PT. PROMITS (Period : 2006) Project : Mechanical, Electrical & Piping Work Location : Bukit Sentul Reservoir & Pump Station, Sentul, West Java Position Held : Material Control & Electrical / Instrument Supervisor Responsible for : • Prepare all of Tool, Consumable & Material. • Prepare all Mobilization & Demobilitation. • Engineering & Installation Electrical System. • Finally all Stock Balance Material & Consumable Kitjuk Harijanto +6282129940123 / +601133977151 /kitjuk_harijanto@yahoo.co.id
  • 4. Curriculum Vitae 9. PT. PROMITS (Period : 2004 - 2005) Project : Piping Work Location : Fertilizer Plant PT. Pupuk Kujang, Cikampek, West Java Position Held : Material Control & Logistic Coordinator Responsible for : • Prepare all of Tool, Consumable & Material. • Prepare all Mobilization & Demobilitation. • Finally all Stock Balance Material & Consumable 10. PT. PROMITS (Period : 2003 - 2004) Project : Piping Work Location : Balongan Blue Sky Project, Balongan, West Java Position Held : Fabrication Manager Responsible for : • Manage all of Fabrication Work 11. PT. PROMITS (Period : 2002 - 2003) Project : Mechanical & Piping Work Location : Gas & Oil Plant Peciko 3 Project, Sanipah, East Kalimantan Position Held : Fabrication Manager Responsible for : • Manage all of Fabrication Work. 12. PT. PROMITS (Period : 2001 – 2002) Project : Piping Work Location : Fertelizer Plant PT.Pupuk Kaltim, Bontang, East Kalimantan Position Held : Material Control & Logistic Coordinator Responsible for : • Prepare all of Tool, Consumable & Material. • Prepare all Mobilization & Demobilitation. • Finally all Stock Balance Material & Consumable 13. PT. PROMITS (Period : 2000 – 2001) Project : Mechanical & Piping Work Location : PA & MA Chemical Plant, Petrowidada, Gresik, East Java Position Held : Material Control & Logistic Coordinator Responsible for : • Prepare all of Tool, Consumable & Material. • Prepare all Mobilization & Demobilitation. • Finally all Stock Balance Material & Consumable Kitjuk Harijanto +6282129940123 / +601133977151 /kitjuk_harijanto@yahoo.co.id
  • 5. Curriculum Vitae 14. PT. PROMITS (Period : 1998 – 1999) Project : Annual Shutdown Mechanical,Piping & Electrical Work Location : PT. Satomo Indovil Monomer,PT. Statomer, Merak,West Java Position Held : Ass Manager Responsible for : • Prepare Schedule & Progress of work • Site control of work • Finally Project execution plann 15. PT. PROMITS (Period : 1997 – 1999) Project : Mechanical, Piping, Electrical & Instrument Work Location : Paiton Private Power Plant 7 & 8 (2x600MW), East Java Position Held : Electrical / Instrument Supervisor Responsible for : • Site Control of Electrical / Instrument Work • Prepare progress of work 16. PT. PROMITS (Period : 1996 – 1997) Project : Tank Work Location : PVC Resin Plant PT. Asahimas Subentra, Anyer, West Java Position Held : Site Supervisor Responsible for : • Site Control of Fabrication & Erection 12Unit Cone roof, 1Unit Ethylene Tank • Prepare progress of work 17. PT. PROMITS (Period : 1995 – 1996) Project : Mechanical, Piping, Electrical & Instrument Work Location : CMC Plant Sembawang SS, Cikarang, West Java Position Held : Electrical / Instrument Supervisor Responsible for : • Site Control of Electrical / Instrument Work • Prepare progress of work 18. PT. PROMITS (Period : 1994 – 1995) Project : Mechanical, Piping, Electrical & Instrument Work Location : Muara Karang Natural Gas 4 & 5, Jakarta Position Held : Electrical / Instrument Supervisor Responsible for : • Site Control of Electrical / Instrument Work • Prepare progress of work Kitjuk Harijanto +6282129940123 / +601133977151 /kitjuk_harijanto@yahoo.co.id
  • 6. Curriculum Vitae 19. PT. PROMITS (Period : 1992 – 1993) Project : Mechanical & Piping Work Location : PKM II 60.000 MT/Y Poly Alkyl Benzene Plant,Palembang Position Held : Material Control & Logistic Coordinator Responsible for : • Prepare all of Tool, Consumable & Material. • Prepare all Mobilization & Demobilitation. • Finally all Stock Balance Material & Consumable 20. PT. PROMITS (Period : 1991 – 1992) Project : Mechanical & Piping Work Location : Edible Oil Refinery Plant PT.SMII, Pulogadung, Jakarta Position Held : Material Control & Logistic Coordinator Responsible for : • Control all of Execution Work • Prepare all of Document • Prepare Progress of Work 21. PT. PROMITS (Period : 1990 – 1991) Project : Mechanical, Piping, Electrical & Instrument Work Location : 2000MTPa PolyAlumuniumChloride Plant Samsung, Cirebon Position Held : Electrical / Instrument Supervisor Responsible for : • Site Control of Electrical / Instrument Work • Prepare progress of work 22. PT. DUTA RENDRA MULYA PLYWOOD (Period : 1989) Location : Ds. Sukalanting, Pontianak, West Kalimantan Position Held : Maintanance Supervisor Responsible for : • Resposibility for all Factory Equipment • Maintance any trouble for equipment Kitjuk Harijanto +6282129940123 / +601133977151 /kitjuk_harijanto@yahoo.co.id
  • 7. Curriculum Vitae 19. PT. PROMITS (Period : 1992 – 1993) Project : Mechanical & Piping Work Location : PKM II 60.000 MT/Y Poly Alkyl Benzene Plant,Palembang Position Held : Material Control & Logistic Coordinator Responsible for : • Prepare all of Tool, Consumable & Material. • Prepare all Mobilization & Demobilitation. • Finally all Stock Balance Material & Consumable 20. PT. PROMITS (Period : 1991 – 1992) Project : Mechanical & Piping Work Location : Edible Oil Refinery Plant PT.SMII, Pulogadung, Jakarta Position Held : Material Control & Logistic Coordinator Responsible for : • Control all of Execution Work • Prepare all of Document • Prepare Progress of Work 21. PT. PROMITS (Period : 1990 – 1991) Project : Mechanical, Piping, Electrical & Instrument Work Location : 2000MTPa PolyAlumuniumChloride Plant Samsung, Cirebon Position Held : Electrical / Instrument Supervisor Responsible for : • Site Control of Electrical / Instrument Work • Prepare progress of work 22. PT. DUTA RENDRA MULYA PLYWOOD (Period : 1989) Location : Ds. Sukalanting, Pontianak, West Kalimantan Position Held : Maintanance Supervisor Responsible for : • Resposibility for all Factory Equipment • Maintance any trouble for equipment Kitjuk Harijanto +6282129940123 / +601133977151 /kitjuk_harijanto@yahoo.co.id