SlideShare a Scribd company logo
1 of 9
Henry Chapman CV/Resume Page 1
Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a-
160726215849.docx 12/07/2016
ADDRESS: 7 Old Beecroft Road,
CHELTENHAM NSW 2119
PHONE/FAX : +61 438 594 140
EMAIL : bronte88@optusnet.com.au
NATIONALITY: UK and Australian
HEALTH: Good.
QUALIFICATIONS: Master of Science (M.Sc)
from Surrey University, England
Computer & Control Systems
I.E.E. (Institute of Electrical Engineers, UK)
REFEREES: Dr. Bob Brownell Consultant +61 413 582 667 Mobile
Ralph Pickering ex Alstom, 0404 003 138
Terry Chapman ex Alstom +61 419 283 958 Mobil
Robert Mahood UGL +61 457 528 961 Mobile
Leo Cooper ex Origin Energy +61 467 727 817
----------------------------------------------------------------------------------------------------------------------------
Quick Summary
95% Success rate. On time and Cost better than budget. Projects up to $250M
1. Safety:
Record Lows for Lost Time Injury Frequency Rate (LTIFR) better than 3 per 1.047,431
Million Hrs worked.
Total recordable cases Frequency (TRCFR) better than 7 per 1 Million Hrs worked.
2. Companies:
Origin Energy. Alstom (Projects, Signalling and Switchyards), Leightons. UGL. Defence (UK
and Aus.) SECWA. NSW Rail. Ford. Telstra. GEC. VicRail. Marconi
3. Infrastructure:
Process improvement of Procurement and Engineering and QA for Origin Energy.
M&E for Tunnels. Switchyards. 50Tonne Cranes for Port of Pennang. Paint Systems for Ford
Motor Co. SSE for NSW Rail. Comms. for Telstra.
4. Engineering:
Design of Comms Network Equipment for Telstra. Direct involvement in design and process
innovation in all projects.
5. Defence:
Transmitters. Submarines (Collins class) and Mine Hunter switchboards.
6. Contractual:
Never incurred LDs. Pro Active resolution with Clients and Subbies.
7. Management, and Computer integration:
Henry Chapman CV/Resume Page 2
Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a-
160726215849.docx 12/07/2016
Design, Production, Cost and Reporting/Reviews, Construction, Commissioning, OHS,
Integration of SAP and Primavera 6 with Engineering, Procurement and Planning. Also Oracle
MRP software for Procurement by Origin Energy.
Personal Details and Experience commentary follow:
Jul 2012 to
Dec 2013 Origin Energy, Coal Seam Gas Project approx. $5 Billion
Process Improvement Manager
 Prepare and execute Project Improvement Processes for Planning,
Engineering, Procurement and Construction
 Investigate and resolve detailed site Construction processes with Poly
Pipe and logistics in outback Queensland
 Research and Implement the introduction and implementation of an
Oracle based MRP procurement and material management system to
replace a vast array of spreadsheets.
 Minimise waste in the material budget of$600 Million from an estimated
15% to a target of 5%
 Change the ISO 9000 QA implementation by making it more meaningful
and actively useful and better integrated with the day to day Project
requirements. Eliminated unnecessary forms, multiple signatures and
approvals.
 Rework over 200 engineering drawings to improve their usefulness and
integration of Engineering and Oracle based Procurement and site
material Management.
 Motivated QA, engineers, Supervisors and other staff to enthusiastically
undertake continuous improvement. A most satisfactory and lasting
legacy.
Jan 2012 to
May 2012 WDS Brisbane, Coal Seam Gas
 Tenderpreparation for CSG Gathering Pipe Line works for Origin energy
in central Queensland
Aug 2010 to
Jan 2011 Doha, Qatar, Al Habtoor/Leighton
Commissioning of Al Shaqab Equestrian Centre for the Emir of Doha
 Prepare and execute Commissioning Plans
 Recruit 8 person commissioning team
 Interface with Civil, Electrical, Mechanical and Control engineers
 Returned to Australia. Commissioning held up due to incomplete Civil
and Mechanical/Electrical Works.
Nov 2007- United Group Ltd, Infrastructure, N. Sydney, NSW, Australia.
Mar 2010 Project Manager, M&E Systems, M7(Clem 7 Tunnel, Brisbane,
Queensland
 Project Management of a 4.8 km dual bore road Tunnel under the
Brisbane River from April 2006 to April 2010. I joined the Project in Nov
2007.
 Contract value $206 Million
 Profit almost doubled from $22M to $40M. Completed 3 months ahead
of schedule. Material waste was near zero.
Henry Chapman CV/Resume Page 3
Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a-
160726215849.docx 12/07/2016
 Tasks included directing the Planning, Engineering Design, Material
procurement, Construction and Commissioning and handover activities
associated with the Mechanical, Electrical, Control, Ventilation and
Drainage design.
 Introduced a factory MRP approach to material management and Job
Control with SAP and Primavera managed from a central Project Control
Centre which is unique to M&E Project Work sites.
 Management of the commercial and Financial interfaces with the Client
and Subcontractors, and the forecasting activities within UGL.
 Major departments organized, and new systems developed and
introduced.Active Departments for the project, with 60 professionalstaff
and 300 trades persons, were:
o Safety
o Engineering Design
o Material Management
o Quality
o Planning and Programming
o Production Control
o Construction
o Human Resources
o Finance
o Commercial
o Project completed in March/April 2010.
Sep 2005 to
Oct 2007- Voluntary work performed at zero cost in Cambodia for a New York
based charity.
Contract and Project direction:
 Completion of building a 100 children orphanage including reclamation
and riverbank protection along the Mekong River in Phnom Penh.
 Sort out a disastrous Contractual and Subcontractor situation.
 Provide assistance annually for ongoing Riverbank protection
Dec 2004- Alstom Transport, 373 Horsley Rd. , Milperra, Sydney
Sep 2005 MIS Information Systems Management
Manage the IT department during the sale of this business to united Group by Alstom in
France.
May 2004- Transfield Services, Kent St, Sydney
Nov 2004 Manage construction of Cobalt Plant
Project Manage the building of a Cobalt Refinery in Townsville, North Queensland for
BHP/QNI
June 2003- Visit UK and Europe on holiday/retirement.
Jan 2004
March 2003- ALSTOM Australia, Sydney
June 2003 Review Operation of Switchyard Design Group
Analyse and recommend a course of engineering actions and strategies for the High
Voltage Projects group.Involved investigating the repeatability of the tendering and design
Henry Chapman CV/Resume Page 4
Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a-
160726215849.docx 12/07/2016
process and the resourcing or Project teams to maximise the efficient use of engineers and
resources.
May 2002- Period of Retirement. Travel around Asia and UK
March 2003
March 2001- Marconi Australia, North Sydney, Sydney
April 2002 Project Manager for Fibre Optic Link between Melbourne and
Perth.
Contract was with Amcom-IP1 in Perth, W.A.to be executed in 2 phases.Responsibilities
include the planning and implementation for the installation and commissioning of the
DWDM equipment into the 9 nominated remote sites. Completion of phase one expected
by end May 2002. Extensive period spent in the U.K. to project manage the transfer of info
for factory and site testing. Phase 2 is now under way, equipment is in final test and
completion is expected in November 2002. Now completed and the network was sold to
Telstra Australia.
May 2000- Fairlight ESP, French’s Forest, Sydney
Jan 2001 Project Manager
This company produces high quality sound recording and synthesiser systems for the
recording, film, television and video industry worldwide. Introduction of a new product
resulted in an untidy and painful overlap with the previous equipment I was made
responsible for providing the interface between the R and D team of 20 engineers and a
variety of subcontractors that manufactured the designed components that comprised the
new M4 system. The major task was to introduce certain disciplines that resulted in a
smoother and more predictable output that allowed substantial back orders to be met, at
the same time ensuring the R and D effort continued in a sensible manner. At the end of
my term Fairlight was awarded a Hollywood Oscar for the performance and innovation of
their dubbing systems.
May 1999- ALSTOM Australia Limited, 373 Horsley Rd. Milperra, Sydney
May 2000 Project Manager
Alstom Wide Area Network. Responsibility for the specification, and tender evaluation
for this network. Over 26 sites in all of the Australian states were connected togetherover
a wide area network that was ultimately let to Telecom Australia. Approximately 1000
users are connected to this network through major hubs is each capital city. A combination
of Frame Relay and ATM systems were used and the appropriate firewall and security
systems were chosen in conjunction with the Alstom CHQ personnel in France. The
network is now complete to the satisfaction of users and management.
Investigation, direction and reorganisation of the IT systems in place at Milperra and to
transition this to new management personnel. This is now complete.
More recently I am involved with the transition phase of the take over of the Ballarat
workshops from the PTC in Victoria that have been bought by the ALSTOM group. The
workshop repairs and refurbish train and tram assemblies and will be involved in the fit
out of new trains and rolling stock since the Alstom group purchased the franchise for
Hillside trains in Melbourne from the PTC of Victoria.
October 1997- Ilid Systems, Collingwood, Melbourne
May 1999 Project Manager
Principal responsibility was to set up and supervise the development of an Electronic Shelf
Label systemfor Supermarkets. This includes the initial financial and engineering analysis
of each of the main engineering elements from the design of the low power LCD display
Henry Chapman CV/Resume Page 5
Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a-
160726215849.docx 12/07/2016
units to the Power modulation systems.Management Cost structures were established,and
major engineering development, production and installation tasks were identified. Contact
and negotiations with suppliers and manufacturers in Singapore were established..
Engineering standards and design procedures were established and all engineering and
documentation activities were planned under my direction. The design and trial was
successfully completed and a 15000-label trial was instituted in a Kmart store for the Coles
Myer group at Chadstone in Melbourne. Since that time negotiations are now in progress
for in excess of 6 million labels to Coles Myer who are under pressure to introduce an
automated price update scheme to cope with the forthcoming introduction of the GST.
.
April 1995- ALSTOM Australia Limited, 373 Horsley Rd., Milperra, Sydney
October 97 Operations Manager
Principal responsibility is to set up and supervise Project Managers on all projects
undertaken by the Division. This included the initial financial and engineering analysis of
each project after contract award. Management Cost structures established, and major
engineering and development tasks identified. Thereafter, personnel requirements are
identified and the necessary staff hired under my direction. The smooth running and
profitability are important part of this activity. Contact and negotiations with clients are
undertaken regularly. Subcontractors are selected and approved to my satisfaction, this
includes price and Commercial Conditions. Engineering standards are established to ISO
9001 and all engineering and documentation activities were planned and carried out under
my direction. I was responsible for major projects, each of which has a dedicated Project
Manager.
The following Projects were established and completed.
Northbridge Tunnel, Perth, WA. Project value $35 Million. Client: Baulderstone
Clough.
Project Manager
Electrical and Mechanical fit out of a new road tunnel in Perth. Project was the
best project set up and successfully completed by the company.
New Paint Facility, Ford Motor Co., Victoria, Project value $55 Million
This was undertaken with a French counterpart and required time to be spent in
France to establish the appropriate contractual, engineering and documentation
outcomes from this technology source. Project works included Civil Buildings,
Paint robots, Hazardous areas, and all Building Services and facilities. Industrial
relations and site agreements were a significant achievement. Completed in January
1998.
Minehunter Switchboards, ADI Newcastle, Project value $9 Million
Apart from the similar activities described above,the use ofnon welded Aluminium
structures was developed as a world first in meeting the Defence standards for
vibration and shock. Computer modelling facilities were established to simulate
the requirements that proved satisfactory when physical tests were done.
Production of switchboards, distribution boards, and starters have been
satisfactorily made to ADI strictly to schedule. The financial prospect for the
remainder of this project is more than promising.
Aug 1993- ALSTOM Australia Limited, 373 Horsley Rd. , Milperra, Sydney
May 1995 Project Manager, Penang Cranes Project, PPSB, and Penang, Malaysia
Value $27 Million
Henry Chapman CV/Resume Page 6
Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a-
160726215849.docx 12/07/2016
Three off, 750 Tonne Cranes were ordered by the Port of Penang. I was responsible for
the Design, Manufacture, Installation and Commissioning. Challenges on all aspects were
unique for our company. The logistics of manufacture and installation were particularly
difficult in view of the practices and customs in a foreign country. In spite of the many
problems encountered, this project was successful and profit exceeded budget.
Nov 1992-ALSTOM Australia Limited, 373 Horsley Rd. , Milperra, Sydney
Jul 1993 Project Manager, Solid State Manufacture for SRA
Completed the tender negotiations for the manufacture and bulk supply of Electronic
Signalling systems. This required the UK based SSI system components to be
manufactured in Australia. Factory was fitted out and all processes and MRP systems
established.Environmental systems were set up and manufacturing processes scrutinised.
Units produced were 30 % cheaper than UK produced units and reliability improvements
were at least double that of UK units.
May 1992- ALSTOM Australia Limited, 373 Horsley Rd. , Milperra, Sydney
Nov 1992 Project Manager, Liverpool Resignalling for State Rail Authority
This project had deteriorated and was out of control. I was appointed to rectify this
situation. Engineering and site activities were reviewed and software development halted
until proper procedures and staff were reassigned. Client confidence was re established
and the project was successfully completed on time and cost.
Mar 1991- ALSTOM Australia Limited, 373 Horsley Rd. , Milperra, Sydney
May 1992 Project Manager, Submarine Switchboards For ASC, Adelaide.
The Client was GEC Marconi Defence. Project was behind schedule and out of control. I
was asked to get this project back on track and under control. Until then it had been
running for more than a year. Engineering and production processes were introduced that
established the predictability of all the necessary outcomes. Schedules were successfully
re-established and all switchboards for all shipsets manufactured. Profits exceeded the
budgeted expectations.
May 1989- GEC Marconi Defence, 373 Horsley Rd. , Milperra, Sydney
May 1991 Project Manager, FATS Contract.
Contract with the Department of Defence for the supply of Frequency Agile Transmitters
at Harts Range, Alice Springs. Value approximately $14 Million.
Production and Installation of Marconi UK designed High Frequency 20kW power
amplifiers.
July 1988- GEC Projects Division - 373 Horsley Rd. , Milperra, Sydney
Dec.1989 Project Manager, Goldfields Project for SECWA, Perth, WA
Contract with the State Electricity Commission of Western Australia (SECWA) for
Augmentation of two 220KV Switchyards (at Kalgoorlie and Merriden). Value
approximately $14 Million. Design and Procurement and Installation was undertaken,
Project of fourteen months was completed on time and better than budget.
Nov 1984- GEC Plessey Telecommunications, 4 Slough Avenue, Silverwater, Sydney
July 1988 Project Manager, TDCC and DDN Projects.
Similar but considerably more complex than the previous DDN project. The TDCC project
exceeded $70 million in Telecom Australia contracts up to 1990. The requirement was for
advanced digital switching equipment, which will enhance Telecom's Digital Data Service
Henry Chapman CV/Resume Page 7
Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a-
160726215849.docx 12/07/2016
by use of this Time Division Cross Connect (TDCC) equipment. Design and production
in the UK and GEC in Australia.
Establishment and control of development costing systems.The totalbudget undercontrol
exceeds $7 million.
July 1983 GEC Plessey Telecommunications, 4 Slough Avenue, Silverwater, Sydney
Nov 1984 Project Manager, DDN Project.
The DDN involved the design and development of advanced data communications
equipment for national use for Telecom Australia. The production contract for GEC is
expected to be approximately $50 million over 5 years. Design and production was carried
out jointly between Marconi in the UK and GEC in Australia.
March 1982- GEC Defence Division –Giffnock Avenue, Noth Ryde, Sydney
July 1983 System Designer
Preparation of tenders for large communications Projects for evaluation by the Defence
Department. Included close co-ordination with UK companies. Tender presentation to
Defence personnel in Canberra.
Marketing of advanced Automatic Test Equipment to local electronic industry,and setting
up a sales and service group for product and customer support.
July 1979- GEC Digital – 323 Reserve Rd, Artamon, Sydney
March 1983 Project Manager
PLC Software System Design for Vales Point Power Station
Software development for programmed logic controller (PLC) for controlling ash and dust
plant using a specialised March 4 PLC. Technical specification, programming, testing and
installation.
$500,000 Display System for Central Station, Sydney
Responsibility for a project that was similar to MURLA but on a smaller scale. Completed
in June, 1982 on schedule. Profitability was in excess of 25%.
$5 Million MURLA Display System contract in Melbourne
Control of several engineers and programmers in the implementation of an extensive
microprocessor based passengerdisplay systemand the MIDEF temporary train controller
system. Over 30 Intel SBC microprocessors are used and were delivered to schedule.
Aug 1975- AWA Pty Ltd –Talavera Rd, Sydney
July 1979 Systems Engineer/Project Manager, Traffic Control Systems
Design and manufacture of Delta traffic Controllers.
Project Manager, Newcastle Jockey Club Totalisator Project
Planning and implementation of a totalisator systemusing AWA produced betting
machines (QTIMS) and Perkin Elmer computers. Extensive experience gained in
determining customer requirements and achieving satisfactory solutions to
problems involved in:
Project Manager, Sydney Racing Clubs Totalisator Project
Henry Chapman CV/Resume Page 8
Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a-
160726215849.docx 12/07/2016
On-site field evaluation and commissioning of microprocessor based betting and
totalisator system. A wide-ranging brief was given to improve the reliability of
betting machines and to implement these recommendations on site and in factory
production, this involved investigation into the microprocessors used and many
aspects of on line computer use. Further problems investigated concerned special
large systemFerranti-Packard displays, which were eventually jointly investigated
with the University of NSW, the Electricity Commission and myself to successfully
determine solutions to large-scale power switching problems.
System Engineer/Project Manager TAA Airports Information Display System
Negotiation with TAA on implementation of a computerised airport management
and display system for Sydney, Melbourne and Brisbane airports., Contract
negotiation. site planning and installation of PDP 11 computer systems.Design of
special interfaces to many existing airport systems including Autophon flap board
displays.
Design Engineer/ Project Manger NSW Ambulance Board, Scheduling
System
Design, installation and testing of special hardware interfaces for a PDP 11/35
computer systemthat enables ambulance locations to be maintained on a detailed
may systemfor the Eastern suburbs of Sydney.
August 1971- Australian Telecom, Kent St, Sydney
August 1975 Engineer, Network Systems
Supervision of Network Performance Analysis Centre for Metropolitan Sydney. collection
and analysis of network performance information from approx. 150 telephone exchanges,
also the publication of monthly reports highlighting network problems and exchange
performance.
Feb1971- British Aircraft Corporation, Stevenage, UK
June 1971 Design Engineer, Missile System
Design and development of a line driving circuit (used in a test sub-systemfor the Rapier
missile) for line lengths up to 100 feet at a frequency of 5 MHz for data transfer.
Dec1970- Phillips Electrologica Gmbh, Bremen, West Germany
Feb1971 Project Engineer, Character Display Unit
Assessing design and performance of inplant modems for long distance data transmission
at 9600 baud. Evaluation of signal to noise ratio against bit error rate. Measurement and
evaluation of multi-terminal configurations concerning eye-pattern distortion and
attenuation.
This contract was suddenly terminated by the parent company in Holland.
Jun 1970 to Pye TMC Co. Ltd., Orpington, Kent, UK
Dec 1970 Design Engineer
Design and development of automatic test equipment for PCM telephone production
equipment.
Henry Chapman CV/Resume Page 9
Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a-
160726215849.docx 12/07/2016
Dec 69- Specto Avionics, Feltham, Middlesex, England
Jun 1970 Design Engineer
Design and development of digital to analog converters foruse in a cockpit head up display
systemfor the Royal Aircraft Establishment Blind landing Unit in Farnborough
Feb1969- Honeywell Controls, Canada Ltd., Don Mills, Toronto, Canada
Dec1969 Design Engineer
Design and development ofkeyboard units for Air Canada Raytheon terminals. Evaluation
of customer requirements, cost estimating, complete logic, circuit and test geardesign and
development. Extensive technical visits to the US parent company in Freeport, Illinois.
May 65- Development Engineer, Electronics.
Jan 69 Oct 67 to Jan 69 HF Transmission, STC, UK
Oct 66 to Oct 67 M.Sc Course Battersea
College of Technology (Surrey University)
Apr 66 to Oct 66 Computers, English
Electric, Willesden, London, UK
May 65 to Nov 65 Telephone Exchanges, STC Telecoms,
Basildon and New Southgate, London, UK

More Related Content

What's hot

Resume_BLM Update
Resume_BLM UpdateResume_BLM Update
Resume_BLM UpdateBarth Maher
 
Jamal_Ashraf -1 oil@gas
Jamal_Ashraf -1 oil@gasJamal_Ashraf -1 oil@gas
Jamal_Ashraf -1 oil@gasJAMAL ASHRAF
 
Electromechanical Contractors in Egypt
Electromechanical Contractors in EgyptElectromechanical Contractors in Egypt
Electromechanical Contractors in EgyptDailyBlog1
 

What's hot (8)

CV - Chris Gibbins
CV - Chris GibbinsCV - Chris Gibbins
CV - Chris Gibbins
 
Personal Presentation
Personal PresentationPersonal Presentation
Personal Presentation
 
Keith Kent CV
Keith Kent CVKeith Kent CV
Keith Kent CV
 
Resume_BLM Update
Resume_BLM UpdateResume_BLM Update
Resume_BLM Update
 
Ukeje cv updated
Ukeje cv updatedUkeje cv updated
Ukeje cv updated
 
Jamal_Ashraf -1 oil@gas
Jamal_Ashraf -1 oil@gasJamal_Ashraf -1 oil@gas
Jamal_Ashraf -1 oil@gas
 
k4_Engg_profile_New
k4_Engg_profile_Newk4_Engg_profile_New
k4_Engg_profile_New
 
Electromechanical Contractors in Egypt
Electromechanical Contractors in EgyptElectromechanical Contractors in Egypt
Electromechanical Contractors in Egypt
 

Viewers also liked

Unidad12
Unidad12 Unidad12
Unidad12 jayerxD
 
24apr28newtonslawslinearangularmomentumpresented 090428161102-phpapp01
24apr28newtonslawslinearangularmomentumpresented 090428161102-phpapp0124apr28newtonslawslinearangularmomentumpresented 090428161102-phpapp01
24apr28newtonslawslinearangularmomentumpresented 090428161102-phpapp01waqasrashidchaudhary
 
100 years of Indian Cinema Quiz
100 years of Indian Cinema Quiz100 years of Indian Cinema Quiz
100 years of Indian Cinema QuizAswin Shenoy
 
Finals chithramela (malayalam movie quiz)
Finals  chithramela (malayalam movie quiz)Finals  chithramela (malayalam movie quiz)
Finals chithramela (malayalam movie quiz)rajesh1868
 

Viewers also liked (12)

Resumé CMB
Resumé CMBResumé CMB
Resumé CMB
 
POWER POINT
POWER POINTPOWER POINT
POWER POINT
 
Kesiapan Desa menghadapi MEA
Kesiapan Desa menghadapi MEAKesiapan Desa menghadapi MEA
Kesiapan Desa menghadapi MEA
 
seema resume email
seema resume emailseema resume email
seema resume email
 
Unidad12
Unidad12 Unidad12
Unidad12
 
24apr28newtonslawslinearangularmomentumpresented 090428161102-phpapp01
24apr28newtonslawslinearangularmomentumpresented 090428161102-phpapp0124apr28newtonslawslinearangularmomentumpresented 090428161102-phpapp01
24apr28newtonslawslinearangularmomentumpresented 090428161102-phpapp01
 
Seputar Media Center
Seputar Media CenterSeputar Media Center
Seputar Media Center
 
100 years of Indian Cinema Quiz
100 years of Indian Cinema Quiz100 years of Indian Cinema Quiz
100 years of Indian Cinema Quiz
 
Mvcv v10
Mvcv v10Mvcv v10
Mvcv v10
 
Finals chithramela (malayalam movie quiz)
Finals  chithramela (malayalam movie quiz)Finals  chithramela (malayalam movie quiz)
Finals chithramela (malayalam movie quiz)
 
Macular Degeneration
Macular DegenerationMacular Degeneration
Macular Degeneration
 
Complications of cataract surgery
Complications of cataract surgeryComplications of cataract surgery
Complications of cataract surgery
 

Similar to CV, Henry Chapman, 12 Jul 16

RashidFaruqi_Resume_Current
RashidFaruqi_Resume_CurrentRashidFaruqi_Resume_Current
RashidFaruqi_Resume_CurrentRashid Faruqi
 
Ons Corporate Presentation 2009
Ons Corporate Presentation 2009Ons Corporate Presentation 2009
Ons Corporate Presentation 2009Taralee
 
PEckardt Resume 2014
PEckardt Resume 2014PEckardt Resume 2014
PEckardt Resume 2014Paul Eckardt
 
Stewart Spence Elect_Comm CV 2015
Stewart Spence Elect_Comm CV 2015Stewart Spence Elect_Comm CV 2015
Stewart Spence Elect_Comm CV 2015Stewart Spence
 
Garry Nicholas Bunce CV
Garry Nicholas Bunce CVGarry Nicholas Bunce CV
Garry Nicholas Bunce CVGarry Bunce
 
Gary Hall CV 2015
Gary Hall  CV 2015Gary Hall  CV 2015
Gary Hall CV 2015Gary Hall
 
CV_PhilMorris_2015
CV_PhilMorris_2015CV_PhilMorris_2015
CV_PhilMorris_2015Phil Morris
 
Lakhdeep Singh CV
Lakhdeep Singh CVLakhdeep Singh CV
Lakhdeep Singh CVlucky singh
 
Pcts Proj Service
Pcts Proj ServicePcts Proj Service
Pcts Proj ServiceClacher
 
CURRICULUM_VITAE_BC_Botes dated 8 October 2014 for Maintenance Specialist E I
CURRICULUM_VITAE_BC_Botes dated 8 October 2014 for Maintenance Specialist E  ICURRICULUM_VITAE_BC_Botes dated 8 October 2014 for Maintenance Specialist E  I
CURRICULUM_VITAE_BC_Botes dated 8 October 2014 for Maintenance Specialist E IBernardus Cornelius Botes
 
Mohd.RiyazKhan_Resume.docx
Mohd.RiyazKhan_Resume.docxMohd.RiyazKhan_Resume.docx
Mohd.RiyazKhan_Resume.docxRIYAZ Khan
 
Resume John I Coffman AL 8-29-16
Resume John I Coffman AL 8-29-16Resume John I Coffman AL 8-29-16
Resume John I Coffman AL 8-29-16John Coffman PMP
 

Similar to CV, Henry Chapman, 12 Jul 16 (20)

RashidFaruqi_Resume_Current
RashidFaruqi_Resume_CurrentRashidFaruqi_Resume_Current
RashidFaruqi_Resume_Current
 
CV~PW~02-02-16 Opus
CV~PW~02-02-16 OpusCV~PW~02-02-16 Opus
CV~PW~02-02-16 Opus
 
Ons Corporate Presentation 2009
Ons Corporate Presentation 2009Ons Corporate Presentation 2009
Ons Corporate Presentation 2009
 
CL
CLCL
CL
 
PEckardt Resume 2014
PEckardt Resume 2014PEckardt Resume 2014
PEckardt Resume 2014
 
Stewart Spence Elect_Comm CV 2015
Stewart Spence Elect_Comm CV 2015Stewart Spence Elect_Comm CV 2015
Stewart Spence Elect_Comm CV 2015
 
Garry Nicholas Bunce CV
Garry Nicholas Bunce CVGarry Nicholas Bunce CV
Garry Nicholas Bunce CV
 
Gary Hall CV 2015
Gary Hall  CV 2015Gary Hall  CV 2015
Gary Hall CV 2015
 
CV_PhilMorris_2015
CV_PhilMorris_2015CV_PhilMorris_2015
CV_PhilMorris_2015
 
Lakhdeep Singh CV
Lakhdeep Singh CVLakhdeep Singh CV
Lakhdeep Singh CV
 
Pcts Proj Service
Pcts Proj ServicePcts Proj Service
Pcts Proj Service
 
Graeme Hannah CV
Graeme Hannah CVGraeme Hannah CV
Graeme Hannah CV
 
CURRICULUM_VITAE_BC_Botes dated 8 October 2014 for Maintenance Specialist E I
CURRICULUM_VITAE_BC_Botes dated 8 October 2014 for Maintenance Specialist E  ICURRICULUM_VITAE_BC_Botes dated 8 October 2014 for Maintenance Specialist E  I
CURRICULUM_VITAE_BC_Botes dated 8 October 2014 for Maintenance Specialist E I
 
Mohd.RiyazKhan_Resume.docx
Mohd.RiyazKhan_Resume.docxMohd.RiyazKhan_Resume.docx
Mohd.RiyazKhan_Resume.docx
 
Resume John I Coffman AL 8-29-16
Resume John I Coffman AL 8-29-16Resume John I Coffman AL 8-29-16
Resume John I Coffman AL 8-29-16
 
Gopa 16 Aug 2016
Gopa 16 Aug 2016Gopa 16 Aug 2016
Gopa 16 Aug 2016
 
Gary's cv 2016
Gary's  cv 2016Gary's  cv 2016
Gary's cv 2016
 
Gary's _CV_2016
Gary's _CV_2016Gary's _CV_2016
Gary's _CV_2016
 
Gerrard Michaels CV 2016
Gerrard Michaels CV 2016Gerrard Michaels CV 2016
Gerrard Michaels CV 2016
 
Ahmed abd elazim c.v
Ahmed abd elazim c.vAhmed abd elazim c.v
Ahmed abd elazim c.v
 

CV, Henry Chapman, 12 Jul 16

  • 1. Henry Chapman CV/Resume Page 1 Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a- 160726215849.docx 12/07/2016 ADDRESS: 7 Old Beecroft Road, CHELTENHAM NSW 2119 PHONE/FAX : +61 438 594 140 EMAIL : bronte88@optusnet.com.au NATIONALITY: UK and Australian HEALTH: Good. QUALIFICATIONS: Master of Science (M.Sc) from Surrey University, England Computer & Control Systems I.E.E. (Institute of Electrical Engineers, UK) REFEREES: Dr. Bob Brownell Consultant +61 413 582 667 Mobile Ralph Pickering ex Alstom, 0404 003 138 Terry Chapman ex Alstom +61 419 283 958 Mobil Robert Mahood UGL +61 457 528 961 Mobile Leo Cooper ex Origin Energy +61 467 727 817 ---------------------------------------------------------------------------------------------------------------------------- Quick Summary 95% Success rate. On time and Cost better than budget. Projects up to $250M 1. Safety: Record Lows for Lost Time Injury Frequency Rate (LTIFR) better than 3 per 1.047,431 Million Hrs worked. Total recordable cases Frequency (TRCFR) better than 7 per 1 Million Hrs worked. 2. Companies: Origin Energy. Alstom (Projects, Signalling and Switchyards), Leightons. UGL. Defence (UK and Aus.) SECWA. NSW Rail. Ford. Telstra. GEC. VicRail. Marconi 3. Infrastructure: Process improvement of Procurement and Engineering and QA for Origin Energy. M&E for Tunnels. Switchyards. 50Tonne Cranes for Port of Pennang. Paint Systems for Ford Motor Co. SSE for NSW Rail. Comms. for Telstra. 4. Engineering: Design of Comms Network Equipment for Telstra. Direct involvement in design and process innovation in all projects. 5. Defence: Transmitters. Submarines (Collins class) and Mine Hunter switchboards. 6. Contractual: Never incurred LDs. Pro Active resolution with Clients and Subbies. 7. Management, and Computer integration:
  • 2. Henry Chapman CV/Resume Page 2 Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a- 160726215849.docx 12/07/2016 Design, Production, Cost and Reporting/Reviews, Construction, Commissioning, OHS, Integration of SAP and Primavera 6 with Engineering, Procurement and Planning. Also Oracle MRP software for Procurement by Origin Energy. Personal Details and Experience commentary follow: Jul 2012 to Dec 2013 Origin Energy, Coal Seam Gas Project approx. $5 Billion Process Improvement Manager  Prepare and execute Project Improvement Processes for Planning, Engineering, Procurement and Construction  Investigate and resolve detailed site Construction processes with Poly Pipe and logistics in outback Queensland  Research and Implement the introduction and implementation of an Oracle based MRP procurement and material management system to replace a vast array of spreadsheets.  Minimise waste in the material budget of$600 Million from an estimated 15% to a target of 5%  Change the ISO 9000 QA implementation by making it more meaningful and actively useful and better integrated with the day to day Project requirements. Eliminated unnecessary forms, multiple signatures and approvals.  Rework over 200 engineering drawings to improve their usefulness and integration of Engineering and Oracle based Procurement and site material Management.  Motivated QA, engineers, Supervisors and other staff to enthusiastically undertake continuous improvement. A most satisfactory and lasting legacy. Jan 2012 to May 2012 WDS Brisbane, Coal Seam Gas  Tenderpreparation for CSG Gathering Pipe Line works for Origin energy in central Queensland Aug 2010 to Jan 2011 Doha, Qatar, Al Habtoor/Leighton Commissioning of Al Shaqab Equestrian Centre for the Emir of Doha  Prepare and execute Commissioning Plans  Recruit 8 person commissioning team  Interface with Civil, Electrical, Mechanical and Control engineers  Returned to Australia. Commissioning held up due to incomplete Civil and Mechanical/Electrical Works. Nov 2007- United Group Ltd, Infrastructure, N. Sydney, NSW, Australia. Mar 2010 Project Manager, M&E Systems, M7(Clem 7 Tunnel, Brisbane, Queensland  Project Management of a 4.8 km dual bore road Tunnel under the Brisbane River from April 2006 to April 2010. I joined the Project in Nov 2007.  Contract value $206 Million  Profit almost doubled from $22M to $40M. Completed 3 months ahead of schedule. Material waste was near zero.
  • 3. Henry Chapman CV/Resume Page 3 Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a- 160726215849.docx 12/07/2016  Tasks included directing the Planning, Engineering Design, Material procurement, Construction and Commissioning and handover activities associated with the Mechanical, Electrical, Control, Ventilation and Drainage design.  Introduced a factory MRP approach to material management and Job Control with SAP and Primavera managed from a central Project Control Centre which is unique to M&E Project Work sites.  Management of the commercial and Financial interfaces with the Client and Subcontractors, and the forecasting activities within UGL.  Major departments organized, and new systems developed and introduced.Active Departments for the project, with 60 professionalstaff and 300 trades persons, were: o Safety o Engineering Design o Material Management o Quality o Planning and Programming o Production Control o Construction o Human Resources o Finance o Commercial o Project completed in March/April 2010. Sep 2005 to Oct 2007- Voluntary work performed at zero cost in Cambodia for a New York based charity. Contract and Project direction:  Completion of building a 100 children orphanage including reclamation and riverbank protection along the Mekong River in Phnom Penh.  Sort out a disastrous Contractual and Subcontractor situation.  Provide assistance annually for ongoing Riverbank protection Dec 2004- Alstom Transport, 373 Horsley Rd. , Milperra, Sydney Sep 2005 MIS Information Systems Management Manage the IT department during the sale of this business to united Group by Alstom in France. May 2004- Transfield Services, Kent St, Sydney Nov 2004 Manage construction of Cobalt Plant Project Manage the building of a Cobalt Refinery in Townsville, North Queensland for BHP/QNI June 2003- Visit UK and Europe on holiday/retirement. Jan 2004 March 2003- ALSTOM Australia, Sydney June 2003 Review Operation of Switchyard Design Group Analyse and recommend a course of engineering actions and strategies for the High Voltage Projects group.Involved investigating the repeatability of the tendering and design
  • 4. Henry Chapman CV/Resume Page 4 Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a- 160726215849.docx 12/07/2016 process and the resourcing or Project teams to maximise the efficient use of engineers and resources. May 2002- Period of Retirement. Travel around Asia and UK March 2003 March 2001- Marconi Australia, North Sydney, Sydney April 2002 Project Manager for Fibre Optic Link between Melbourne and Perth. Contract was with Amcom-IP1 in Perth, W.A.to be executed in 2 phases.Responsibilities include the planning and implementation for the installation and commissioning of the DWDM equipment into the 9 nominated remote sites. Completion of phase one expected by end May 2002. Extensive period spent in the U.K. to project manage the transfer of info for factory and site testing. Phase 2 is now under way, equipment is in final test and completion is expected in November 2002. Now completed and the network was sold to Telstra Australia. May 2000- Fairlight ESP, French’s Forest, Sydney Jan 2001 Project Manager This company produces high quality sound recording and synthesiser systems for the recording, film, television and video industry worldwide. Introduction of a new product resulted in an untidy and painful overlap with the previous equipment I was made responsible for providing the interface between the R and D team of 20 engineers and a variety of subcontractors that manufactured the designed components that comprised the new M4 system. The major task was to introduce certain disciplines that resulted in a smoother and more predictable output that allowed substantial back orders to be met, at the same time ensuring the R and D effort continued in a sensible manner. At the end of my term Fairlight was awarded a Hollywood Oscar for the performance and innovation of their dubbing systems. May 1999- ALSTOM Australia Limited, 373 Horsley Rd. Milperra, Sydney May 2000 Project Manager Alstom Wide Area Network. Responsibility for the specification, and tender evaluation for this network. Over 26 sites in all of the Australian states were connected togetherover a wide area network that was ultimately let to Telecom Australia. Approximately 1000 users are connected to this network through major hubs is each capital city. A combination of Frame Relay and ATM systems were used and the appropriate firewall and security systems were chosen in conjunction with the Alstom CHQ personnel in France. The network is now complete to the satisfaction of users and management. Investigation, direction and reorganisation of the IT systems in place at Milperra and to transition this to new management personnel. This is now complete. More recently I am involved with the transition phase of the take over of the Ballarat workshops from the PTC in Victoria that have been bought by the ALSTOM group. The workshop repairs and refurbish train and tram assemblies and will be involved in the fit out of new trains and rolling stock since the Alstom group purchased the franchise for Hillside trains in Melbourne from the PTC of Victoria. October 1997- Ilid Systems, Collingwood, Melbourne May 1999 Project Manager Principal responsibility was to set up and supervise the development of an Electronic Shelf Label systemfor Supermarkets. This includes the initial financial and engineering analysis of each of the main engineering elements from the design of the low power LCD display
  • 5. Henry Chapman CV/Resume Page 5 Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a- 160726215849.docx 12/07/2016 units to the Power modulation systems.Management Cost structures were established,and major engineering development, production and installation tasks were identified. Contact and negotiations with suppliers and manufacturers in Singapore were established.. Engineering standards and design procedures were established and all engineering and documentation activities were planned under my direction. The design and trial was successfully completed and a 15000-label trial was instituted in a Kmart store for the Coles Myer group at Chadstone in Melbourne. Since that time negotiations are now in progress for in excess of 6 million labels to Coles Myer who are under pressure to introduce an automated price update scheme to cope with the forthcoming introduction of the GST. . April 1995- ALSTOM Australia Limited, 373 Horsley Rd., Milperra, Sydney October 97 Operations Manager Principal responsibility is to set up and supervise Project Managers on all projects undertaken by the Division. This included the initial financial and engineering analysis of each project after contract award. Management Cost structures established, and major engineering and development tasks identified. Thereafter, personnel requirements are identified and the necessary staff hired under my direction. The smooth running and profitability are important part of this activity. Contact and negotiations with clients are undertaken regularly. Subcontractors are selected and approved to my satisfaction, this includes price and Commercial Conditions. Engineering standards are established to ISO 9001 and all engineering and documentation activities were planned and carried out under my direction. I was responsible for major projects, each of which has a dedicated Project Manager. The following Projects were established and completed. Northbridge Tunnel, Perth, WA. Project value $35 Million. Client: Baulderstone Clough. Project Manager Electrical and Mechanical fit out of a new road tunnel in Perth. Project was the best project set up and successfully completed by the company. New Paint Facility, Ford Motor Co., Victoria, Project value $55 Million This was undertaken with a French counterpart and required time to be spent in France to establish the appropriate contractual, engineering and documentation outcomes from this technology source. Project works included Civil Buildings, Paint robots, Hazardous areas, and all Building Services and facilities. Industrial relations and site agreements were a significant achievement. Completed in January 1998. Minehunter Switchboards, ADI Newcastle, Project value $9 Million Apart from the similar activities described above,the use ofnon welded Aluminium structures was developed as a world first in meeting the Defence standards for vibration and shock. Computer modelling facilities were established to simulate the requirements that proved satisfactory when physical tests were done. Production of switchboards, distribution boards, and starters have been satisfactorily made to ADI strictly to schedule. The financial prospect for the remainder of this project is more than promising. Aug 1993- ALSTOM Australia Limited, 373 Horsley Rd. , Milperra, Sydney May 1995 Project Manager, Penang Cranes Project, PPSB, and Penang, Malaysia Value $27 Million
  • 6. Henry Chapman CV/Resume Page 6 Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a- 160726215849.docx 12/07/2016 Three off, 750 Tonne Cranes were ordered by the Port of Penang. I was responsible for the Design, Manufacture, Installation and Commissioning. Challenges on all aspects were unique for our company. The logistics of manufacture and installation were particularly difficult in view of the practices and customs in a foreign country. In spite of the many problems encountered, this project was successful and profit exceeded budget. Nov 1992-ALSTOM Australia Limited, 373 Horsley Rd. , Milperra, Sydney Jul 1993 Project Manager, Solid State Manufacture for SRA Completed the tender negotiations for the manufacture and bulk supply of Electronic Signalling systems. This required the UK based SSI system components to be manufactured in Australia. Factory was fitted out and all processes and MRP systems established.Environmental systems were set up and manufacturing processes scrutinised. Units produced were 30 % cheaper than UK produced units and reliability improvements were at least double that of UK units. May 1992- ALSTOM Australia Limited, 373 Horsley Rd. , Milperra, Sydney Nov 1992 Project Manager, Liverpool Resignalling for State Rail Authority This project had deteriorated and was out of control. I was appointed to rectify this situation. Engineering and site activities were reviewed and software development halted until proper procedures and staff were reassigned. Client confidence was re established and the project was successfully completed on time and cost. Mar 1991- ALSTOM Australia Limited, 373 Horsley Rd. , Milperra, Sydney May 1992 Project Manager, Submarine Switchboards For ASC, Adelaide. The Client was GEC Marconi Defence. Project was behind schedule and out of control. I was asked to get this project back on track and under control. Until then it had been running for more than a year. Engineering and production processes were introduced that established the predictability of all the necessary outcomes. Schedules were successfully re-established and all switchboards for all shipsets manufactured. Profits exceeded the budgeted expectations. May 1989- GEC Marconi Defence, 373 Horsley Rd. , Milperra, Sydney May 1991 Project Manager, FATS Contract. Contract with the Department of Defence for the supply of Frequency Agile Transmitters at Harts Range, Alice Springs. Value approximately $14 Million. Production and Installation of Marconi UK designed High Frequency 20kW power amplifiers. July 1988- GEC Projects Division - 373 Horsley Rd. , Milperra, Sydney Dec.1989 Project Manager, Goldfields Project for SECWA, Perth, WA Contract with the State Electricity Commission of Western Australia (SECWA) for Augmentation of two 220KV Switchyards (at Kalgoorlie and Merriden). Value approximately $14 Million. Design and Procurement and Installation was undertaken, Project of fourteen months was completed on time and better than budget. Nov 1984- GEC Plessey Telecommunications, 4 Slough Avenue, Silverwater, Sydney July 1988 Project Manager, TDCC and DDN Projects. Similar but considerably more complex than the previous DDN project. The TDCC project exceeded $70 million in Telecom Australia contracts up to 1990. The requirement was for advanced digital switching equipment, which will enhance Telecom's Digital Data Service
  • 7. Henry Chapman CV/Resume Page 7 Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a- 160726215849.docx 12/07/2016 by use of this Time Division Cross Connect (TDCC) equipment. Design and production in the UK and GEC in Australia. Establishment and control of development costing systems.The totalbudget undercontrol exceeds $7 million. July 1983 GEC Plessey Telecommunications, 4 Slough Avenue, Silverwater, Sydney Nov 1984 Project Manager, DDN Project. The DDN involved the design and development of advanced data communications equipment for national use for Telecom Australia. The production contract for GEC is expected to be approximately $50 million over 5 years. Design and production was carried out jointly between Marconi in the UK and GEC in Australia. March 1982- GEC Defence Division –Giffnock Avenue, Noth Ryde, Sydney July 1983 System Designer Preparation of tenders for large communications Projects for evaluation by the Defence Department. Included close co-ordination with UK companies. Tender presentation to Defence personnel in Canberra. Marketing of advanced Automatic Test Equipment to local electronic industry,and setting up a sales and service group for product and customer support. July 1979- GEC Digital – 323 Reserve Rd, Artamon, Sydney March 1983 Project Manager PLC Software System Design for Vales Point Power Station Software development for programmed logic controller (PLC) for controlling ash and dust plant using a specialised March 4 PLC. Technical specification, programming, testing and installation. $500,000 Display System for Central Station, Sydney Responsibility for a project that was similar to MURLA but on a smaller scale. Completed in June, 1982 on schedule. Profitability was in excess of 25%. $5 Million MURLA Display System contract in Melbourne Control of several engineers and programmers in the implementation of an extensive microprocessor based passengerdisplay systemand the MIDEF temporary train controller system. Over 30 Intel SBC microprocessors are used and were delivered to schedule. Aug 1975- AWA Pty Ltd –Talavera Rd, Sydney July 1979 Systems Engineer/Project Manager, Traffic Control Systems Design and manufacture of Delta traffic Controllers. Project Manager, Newcastle Jockey Club Totalisator Project Planning and implementation of a totalisator systemusing AWA produced betting machines (QTIMS) and Perkin Elmer computers. Extensive experience gained in determining customer requirements and achieving satisfactory solutions to problems involved in: Project Manager, Sydney Racing Clubs Totalisator Project
  • 8. Henry Chapman CV/Resume Page 8 Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a- 160726215849.docx 12/07/2016 On-site field evaluation and commissioning of microprocessor based betting and totalisator system. A wide-ranging brief was given to improve the reliability of betting machines and to implement these recommendations on site and in factory production, this involved investigation into the microprocessors used and many aspects of on line computer use. Further problems investigated concerned special large systemFerranti-Packard displays, which were eventually jointly investigated with the University of NSW, the Electricity Commission and myself to successfully determine solutions to large-scale power switching problems. System Engineer/Project Manager TAA Airports Information Display System Negotiation with TAA on implementation of a computerised airport management and display system for Sydney, Melbourne and Brisbane airports., Contract negotiation. site planning and installation of PDP 11 computer systems.Design of special interfaces to many existing airport systems including Autophon flap board displays. Design Engineer/ Project Manger NSW Ambulance Board, Scheduling System Design, installation and testing of special hardware interfaces for a PDP 11/35 computer systemthat enables ambulance locations to be maintained on a detailed may systemfor the Eastern suburbs of Sydney. August 1971- Australian Telecom, Kent St, Sydney August 1975 Engineer, Network Systems Supervision of Network Performance Analysis Centre for Metropolitan Sydney. collection and analysis of network performance information from approx. 150 telephone exchanges, also the publication of monthly reports highlighting network problems and exchange performance. Feb1971- British Aircraft Corporation, Stevenage, UK June 1971 Design Engineer, Missile System Design and development of a line driving circuit (used in a test sub-systemfor the Rapier missile) for line lengths up to 100 feet at a frequency of 5 MHz for data transfer. Dec1970- Phillips Electrologica Gmbh, Bremen, West Germany Feb1971 Project Engineer, Character Display Unit Assessing design and performance of inplant modems for long distance data transmission at 9600 baud. Evaluation of signal to noise ratio against bit error rate. Measurement and evaluation of multi-terminal configurations concerning eye-pattern distortion and attenuation. This contract was suddenly terminated by the parent company in Holland. Jun 1970 to Pye TMC Co. Ltd., Orpington, Kent, UK Dec 1970 Design Engineer Design and development of automatic test equipment for PCM telephone production equipment.
  • 9. Henry Chapman CV/Resume Page 9 Z:tempwindows20160726215917_7b14bc530ece3d5f2a04f0dd8c5f5d4a900d5aadb84aef9f-4bf3-48ac-b824-0fd54791be8a- 160726215849.docx 12/07/2016 Dec 69- Specto Avionics, Feltham, Middlesex, England Jun 1970 Design Engineer Design and development of digital to analog converters foruse in a cockpit head up display systemfor the Royal Aircraft Establishment Blind landing Unit in Farnborough Feb1969- Honeywell Controls, Canada Ltd., Don Mills, Toronto, Canada Dec1969 Design Engineer Design and development ofkeyboard units for Air Canada Raytheon terminals. Evaluation of customer requirements, cost estimating, complete logic, circuit and test geardesign and development. Extensive technical visits to the US parent company in Freeport, Illinois. May 65- Development Engineer, Electronics. Jan 69 Oct 67 to Jan 69 HF Transmission, STC, UK Oct 66 to Oct 67 M.Sc Course Battersea College of Technology (Surrey University) Apr 66 to Oct 66 Computers, English Electric, Willesden, London, UK May 65 to Nov 65 Telephone Exchanges, STC Telecoms, Basildon and New Southgate, London, UK