SlideShare a Scribd company logo
2441

    COUNTERMEASURES AGAINST LIQUEFACTION INDUCED SETTLEMENT
                FOR POWER TRANSMISSION TOWERS


             Hidenori ABO1, Kenichi HORIKOSHI2, Susumu YASUDA3 And Masayuki SATOH4


                                                          SUMMARY

        After the 1995 Hyogoken Nambu earthquake, it has been recognized that restoring service facility
        from the damage is critical for urgent recovery of city function.        Among lifelines, power
        transmission towers are highly important electrical components, some of which are required to
        survive with only minor damage even after a strong earthquake. In the past earthquakes such as
        1964 Niigata earthquake, transmission towers were inclined due to the effects of soil liquefaction.

        It is therefore important to develop a method for estimating seismic performance of transmission
        towers during and after earthquakes. A series of dynamic centrifuge tests were conducted by
        modeling an isolated footing of a tower on sand. In these tests, four isolated footings were
        modeled together on a liquefiable sand layer and the effectiveness of three types of
        countermeasures against settlement due to liquefaction was examined. These countermeasures
        were designed to connect the four footings to each other, and the types of connections modeled
        were: 1) a plate at the base of the footing, 2) a plate at soil surface level, and 3) a surface plate with
        surrounding sheet piles. The seismic performances of these countermeasures were compared with
        that of a tower without any countermeasures. The results show that the base plate can prevent the
        settlement by as much as 70 %, and that even the surface plate can prevent the settlement by 30 %.
        The test results also show that, in the modeled conditions, the effectiveness of the surrounding
        sheet pile walls was relatively small. This result was considered to be a consequence of an
        inadequate length of the sheet piles compared with the width of the foundation.



                                                      INTRODUCTION

It has been recognized that power transmission towers are very important facilities which affect the post-
earthquake recovery of city services. The damages of towers due to soil liquefaction were reported after Niigata
earthquake in 1964, as shown in Figure 1. The inclination and the settlement of the towers were the main
damages according to the report. The 1995 Hyogoken Nambu Earthquake revealed that much wider types of
soil might liquefy due to strong earthquake motions. Power transmission towers sometimes use ‘isolated
footing’ type foundations, with each of the four legs of the tower supported on an independent footing. Given
the importance of these towers it is important to develop a method for evaluating the settlement of such isolated
footings on liquefiable soils during and after earthquakes.




1
    Power System Engineering Department, Tokyo Electric Power Co., Tokyo, Japan Email: T0632711@pmail.tepco.co.jp
2
    Taisei Research Institute, Taisei Corporation, Yokohama, Japan Email: kenichi.horikoshi@sakura.taisei.co.jp
3
    Department of Civil Engineering, Tokyo Denki University, Saitama, Japan Email: yasuda@g.dendai.ac.jp
4
    Advanced Engineering Operation Center, Tokyo Electric Power Service Co., Ltd., Tokyo, Japan Email:sato@aed.tepsco.co.jp
The authors conducted a series of dynamic
centrifuge tests to examine the settlement of
power transmission towers during and after
liquefaction, as already reported by Kawasaki et
al [1][2].     In the first phase of this study,
attention was placed on finding factors which
govern the settlement of isolated footings. The
four main variables in the tests were relative
density of soil, magnitude of input motion,
number of cycles of motion, and width of the
footing. A typical isolated footing designed to
support one of the legs of a power transmission
tower was extensively tested. Finally, based on
the results of the centrifuge tests, a simple Figure 1: Inclined power transmission towers seen after
method to estimate the settlement was presented.             Niigata earthquake, 1964
The predicted settlement was expressed in a
conventional form by using a number of
deviating factors which relate to the above four factors. From the results of more than 30 tests, the following
empirical equation was proposed for estimating the settlement of the transmission towers:

S = S o ⋅ C1 ⋅ C 2                             Cm ⋅ D1 ⋅ D 2                Dn                                                                  (1)

where, S is the settlement of transmission tower, So is the settlement of tower under particular standard
conditions defined below, C1-Cm are deviating factors from So relevant to the actual ground condition and input
motion, and D1-Dn are deviating factors from So relevant to the specific structure under consideration. In the
proposed method, the factors taken into account were: thickness of liquefiable layer (C1), thickness of
unliquefiable layer (C2), relative density (C3), grain size (C4), factor related to degree of liquefaction (C5),
width of footing (D1) and load intensity (D2).

Each deviating factor is shown graphically in Figure 2. In the tests, the conditions set as the standard conditions
were:
        C1 : 13.2 m, C2 : 0 m, C3 : 40 %, C4 : D50 = 0.161 mm (Toyoura sand), C5 : FL = 1,
        D1 : 3.2 m and D2 : 28.4 kPa.


            2
                                             C1                                     C2                            C3                       C4
           1.5
  Factor




            1
           0.5
            0
                 0     2    4        6   8 10 12             0    1 2       3   4        5   6   0 10 20 30 40 50 60          0 0.1 0.2 0.3 0.4 0.5
                     Liquifiable layer thickness                  Unliquefiable layer
                       -1/2Footing width (m)                                                      Relative density (%)              D (mm)
                                                                     thickness(m)                                                     50


                                     2
                                                             C5                                  D1                             D2
                                 1.5
                            Factor




                                     1
                                 0.5
                                     0                                          0     1 2 3 4 5             -20    0     20    40    60
                                         0        0.5    1       1.5    2
                                                        FL                           Footing width (m)      Additional pressure (kPa)
                                             Figure 2: Deviating factors obtained a series of centrifuge tests

It should be noted that, a more accurate estimation of the settlement requires an additional, extensive review of
the field observations and an effort is currently being made for refining the proposed method, which will be
presented in the near future.

After examining the factors which govern the footing settlement, the authors conducted another series of
dynamic centrifuge tests to examine the effectiveness of three methods for reducing the settlement of the



                                                                                             2                                                        2441
Plate connected to each footing        Vertical load
          Isolated footing                                                               Circular laminar box

                                                                                           A10
                                                                                  A6




                                                                                                 86
                                                                            P14




                                     55
                                                                           P7          A9 P13




                                                             350
                                                                           A4




                                           210
                                     100
                                                                                  P3


                                     55                                           P1

                  Toyoura sand                                                      Toyoura sand


        Pore fluid pressure transducers                                       400
        Accelerometers                                   P14 Installed only for model D (with sheet piles)
        Displacement transducers            Unit : mm

                 (a) PLAN                                          (b) SECTION
                               Figure 3: Schematic figure of centrifuge model

footings. The results obtained from the second series of tests are presented in this paper. It should be noted
that countermeasures for reducing the settlement considered in this paper are for already existing isolated tower
footings, rather than for newly constructed footings.

                              MODEL DESIGNS AND TEST PROCEDURES


The details of the centrifuge machine used in this study were described by Nagura et al. [3]. The machine has
an effective radius of 2.65 m and has an electrohydraulic servo-controlled shaking table designed for conducting
dynamic tests. A centrifugal acceleration of 50 g was applied to a 1/50 model (here, ‘g’ denotes gravity).

Figure 3 shows a schematic figure of the centrifuge setup designed for the study. Four independent footings,
which support a transmission tower, were modeled. The model shown in the figure corresponds to ‘Model C’ in
this paper (see Figure 4 in the next section). A circular laminar box with an inside diameter of 400 mm was
used as the soil box. The material of the model footing was made by mixing cement, sand and iron powder.
The width of the model footing was 50 mm (2.5 m at prototype scale) and a weight of 18.3 tons per footing at
prototype scale was applied vertically. The distance between two footings in the model was set at 100 mm (5.0
m). Toyoura sand with a height of 350 mm (17.5 m) was used as a soil sample. The properties of Toyoura
sand are summarized in Table 1.

                                     Table 1: Properties of Toyoura sand

Density of soil particle (g/cm3) Maximum density (g/cm3) Minimum density (g/cm3)          Mean grain size (mm)
            2.661                       1.654                   1.349                            0.162

Dry Toyoura sand was first poured into the soil box. After placing four model footings on the sand and placing
the surface sand at the prescribed level, the sand was saturated with silicon oil with a viscosity 50 times higher
than that of water. The relative density of the soil was set at about 40-45 % prior to the shaking. Before
starting the main shaking test, the model was spun to observe the initial settlement due to a centrifugal
acceleration of 50 g. The test models with and without countermeasures for reducing the settlement are shown
in Figure 4. The models tested were:
    Model A: Without any countermeasures.
    Model B: Connecting the base of all footings by a concrete plate.
    Model C: Connecting the four footings by a concrete plate at ground surface level.



                                                        3                                                       2441
10.5 m
                                            Concrete Plate                      Concrete Plate         Concrete Plate



              Isolated footing                 10.5 m                                                                   Sheet piles
                                                                                                                        (Type III)




                                    4.3 m
                                                                                Concrete plate
                                                                                (t = 150 mm)
                 Model A                     Model B                               Model C                 Model D
            (no countermeasure)             (Base plate)                        (Surface plate)   (Surface plate + Sheet piles)

                                 Figure 4: Countermeasures modeled in the study

    Model D: In addition to connecting the four footings by a concrete plate at ground surface level, as in Model
              C, the footings were surrounded by sheet pile walls.
The models A and B were tested and reported by Sakemi et al [4]. The base and surface plates in the models
were made by plastic plate with a thickness of 5 mm, which corresponds to a concrete plate of about 150 mm at
prototype scale. Sandpaper was attached on the surface of the plastic plate to create a rough surface. The
model B was thought to be the most effective as the four footings behave as one single foundation with respect
to the soil above the base plate. However, constructing such a base plate of footings of already existing towers
during the tower operation is not only difficult but may also be unrealistic.

Other two models C and D were proposed as feasible alternatives to the model B. A photograph of model C is
shown in Figure 5. In both models C and D, the plate connecting the four isolated footings was attached at the
ground surface level, which is not only much easier but is, also, more economic. It was considered that the use
of a surface plate would reduce the stress transferred to the isolated footings as the plate itself would provide
additional resistance against settlement of the tower. Model D is similar to model C but in addition to the
surface plate, sheet pile walls were placed around the four footings. The bending rigidity of the sheet piles was
set equivalent to Type III sheet piles in Japan.

The above models were excited by a sinusoidal horizontal wave with 20 cycles at 50 Hz which is equivalent to
20 cycles at 1 Hz for the prototype model. The motion shown in Figure 6 was applied to the base of the model.
The peak acceleration corresponding to the motion was set at 4.5 g at model scale (90 gal at prototype scale).
During the tests, pore fluid pressure, acceleration and the settlement of the soil surface were measured as well as
the settlement of the model footing. The locations of the transducers are shown in Figure 3.

                                                    TEST RESULTS

Acceleration Response:
The observed acceleration responses for the models A and C are compared in Figures 7 to 9. Figure 7 shows the
response of the accelerometer A10 (at the soil surface, see Figure 3), Figure 8 shows the response of A9 (on soil
below near the center of the model), and Figure 9 shows the response of A6 (in the model footing). In all three
figures, the acceleration response did not fade away right up to the end of the shaking even though the soil
liquefied significantly.
                                                                                100
                                                             Input Acc. (gal)




                                                                                 50

                                                                                  0

                                                                                -50

                                                                         -100
                                                                                      0      10       20         30       40
                                                                                                   Time (sec.)

                 Figure 5: Photograph of Model C                                            Figure 6: Input acceleration


                                                             4                                                                        2441
200




                                                                                                          Acceleration (gal)
                                                        200




                            Acceleration (gal)
                                                                Model A                                                                                                Model C
                                                  100                                                                                 100
                                                    0                                                                                   0
                                                 -100                                                                                -100
                                                 -200                                                                                -200
                                                            0         10        20      30      40                                                             0           10       20      30            40
                                                                             Time (sec)                                                                                          Time (sec)
           Figure 7: Acceleration response observed at soil surface (Models A & C, A10)
                                                                                                                                                         200




                                                                                                               Acceleration (gal)
                                                        200
                                   Acceleration (gal)




                                                                Model A                                                                                                Model C
                                                         100                                                                                    100
                                                           0                                                                                      0
                                                        -100                                                                                   -100
                                                        -200                                                                                   -200
                                                            0          10        20      30      40                                                                0       10       20      30            40
                                                                              Time (sec)                                                                                         Time (sec)
           Figure 8: Acceleration response observed below the center of footing (Models A & C, A9)

                                                                                                          Acceleration (gal)
                                                                                                                                      200
                       Acceleration (gal)




                                                  200           Model A                                                                                                Model C
                                             100                                                                                      100
                                               0                                                                                        0
                                            -100                                                                                     -100
                                            -200                                                                                     -200
                                                 0                    10        20      30      40                                                             0           10       20      30            40
                                                                             Time (sec)                                                                                          Time (sec)
           Figure 9: Acceleration response in the model footing (Models A & C, A6)


Figures 7 and 8 show clearly the difference between the acceleration responses of models A and C. The
response of the model D was close to that of the model C. The magnitude of the acceleration of model A was
higher than those observed in the other three models, and the response of model A was also more complex. Since
each footing was set independently in model A, the acceleration response of the four footings was considered not
to be completely the same, and this might influence the acceleration response of the soil around the model. It
was also considered that, models B, C, and D, in which the four footings were connected together, behaved as a
single unit, which could lead to a much higher effective mass in these models than in model A.
                                -50                                                                                                                           0
                                                                                                                               Settlement ratio to Model A




                                  0                                                                                                                                                             Model B
             Settlement (mm)




                                                                                     Model B                                                                 0.2
                                 50
                                100                                                                                                                          0.4
                                                                                     Model D                                                                                                    Model D
                                150                                                                                                                          0.6
                                200                                                  Model C                                                                 0.8                                Model C
                                250                         Model A
                                300                                                                                                                           1
                                                        0       200        400 600       800   1000                                                                0      200     400     600      800     1000
                                                                           Time (sec.)                                                                                            Time (sec.)
                 (a) Observed settlement at prototype scale                                                                                                            (b) Settlement ratio to Model A

                                                                                Figure 10: Settlement of model footings

Settlement
Figure 10 and Table 2 summarize the settlement of the models during and after the shaking at prototype scale.
The settlement shown in the figures and the table is the average of the four footings settlements. In the figure,
only the initial 20 seconds corresponds to the shaking period, i.e. the settlement continued after the shaking.
The following observations can be made from Figure 10:
      As expected, model B, in which the connecting plate was attached at the base of the footings, was the most
      effective way of reducing the settlement. The final settlement measured in model B was as low as 80 mm,
      compared with that of 250 mm in model A (without countermeasure), i.e. the settlement reduced by about
      70 %. The settlement during the shaking period itself was significantly smaller in model B than those


                                                                                                      5                                                                                                           2441
observed in the other models. An explanation of this behavior is the much smaller pore fluid pressure ratio
     beneath the model, as shown later in this paper.
     Although the measured settlements of models C and D were larger than that of model B, their settlements
     were about 2/3 of that of model A, i.e. the settlement was reduced by about 30 % by connecting the four
     independent footings at the ground surface level.
     The results of the tests in this study showed the effect of the surrounding sheet piles on the settlement to be
     small. The final settlement in model D was about 61% of model A. It was considered that the relatively
     short length of the sheet piles used in model D could be the reason for the small difference in the final
     settlements of models C and D.

Table 2: Settlement of model footings
 Model                              Relative                               Maximum             Settlement          Final settlement
                                    Density                                   input              during         Footing Soil surface
                                      (%)                                 acceleration          shaking          (mm)          (mm)
                                                                              (gal)               (mm)
 A: Without any countermeasures                                39.6             91                 200            250     Not measured
 B: Base plate                                                 43.7            93                  75             75            80
 C: Surface plate                                              45.5             88                  70            174           81
 D: Surface plate + Sheet piles                                45.1             86                  64            154           55
                                                                       Input acceleration and settlement are shown at prototype scale

Pore Fluid Pressure
The pore fluid pressure responses of the four models at various locations are shown in Figure 11. The figures
show that the rate of increase in the pore fluid pressure to be relatively slower in models A and B compared to
models C and D. This difference in behavior was considered to be the result of the slight difference in the shape
of the created input motions. The following observations can be made from the figures:
   ・ As shown later, the excess pore fluid ratio outside the influenced area seemed to increase close to unity,
      indicating that the soil in this area liquefied significantly.
   ・ Although the instrumented depths for transducers P7 and P13 were the same, the increase in the excess
      pore fluid pressure was smaller for P7 in the models C and D. In the case of model B, the rate of increase
      in the pore fluid pressure was slightly slower compared with the other models. This might be related to
      the very small settlement of the footing during and after the shaking, which was caused by higher confining
      pressure.
   ・ The increase in the pore fluid pressure for P14 in model D was considerably small. This may be as a result
      of the sheet pile walls around the model footing which prevented an increase.

Figure 12 shows the pore fluid pressure ratio at a depth just beneath the model footing for models A, B and D.
The effective overburden pressure was estimated by using Boussinesq solution. Note that, for model D, the

                                  150        Shaking period         Model A                                        Shaking period        Model B
                                                                                                        150
                                  120                                 P1                                120                                P1
                Ex. PFP (kPa)




                                                                                        Ex. PFP (kPa)




                                   90                                 P3                                 90
                                                                                                                                           P3
                                   60                                                                    60
                                   30                                 P7                                                                  P7 & P13
                                                                                                         30
                                    0                                                                     0
                                        0       20     40      60     80      100                             0      20     40      60     80      100
                                                      Time(Sec.)                                                            Time (sec)
                                            (a) Model A                                                                      (b) Model B
                                  150         Shaking period                                                      Shaking Period         Model D
                                                                    Model C                             150
                                  120                                  P1                               120                                P1
                  Ex. PFP (kPa)




                                                                                        Ex. PFP (kPa)




                                   90                                  P3                                90                                P3
                                   60                                 P13                                60                                     P14
                                   30                                                                                                     P13
                                                                       P7                                30                               P7
                                    0                                                                     0
                                        0       20     40      60     80      100                          0        20      40      60    80       100
                                                      Time (sec.)                                                          Time (sec.)
                                      (c) Model C                                       (d) Model D
                                    Figure 11: Pore fluid pressure response observed for Models A - D

                                                                                    6                                                                    2441
effects of the load transferred directly from the surface plate
were ignored for simplicity in calculating the initial                           1                    Model A
overburden pressure. The peak pressure ratio for model A                                              Model B
                                                                                0.8                   Model D




                                                                    PFP ratio
(without any countermeasures) was close to unity and model B
                                                                                0.6
shows the lowest value of about 0.5. Figure 12 clearly shows
that the lower the pore fluid pressure ratio below the model                    0.4
footings was, the smaller the footing settlement became.                        0.2
                                                                                 0
It is also very important to relate the pore fluid pressure               0          500         1000        1500
response with the observed settlement behavior.              The                        Time(sec.)
distribution of pore fluid pressure around the model footing Figure 12: Pore fluid pressure ratio observed
just after the shaking is drawn for each model in Figure 13.                  beneath the model footings
The corresponding pressure ratio is also drawn in Figure 14.
A point of caution regarding these figures, the contours were
created from a limited number of pressure transducer readings so that the profiles far from the location of the
transducers might not be correct. The small circles shown in the figures indicate the location of the pore
pressure transducers. Figure 12 indicates that in all four models the soil near the bottom of the box liquefied
significantly. The magnitude of the pore fluid pressure ratio of model B in Figure 14 can be seen to be very
small due to the effects of the load transferred through the base plate of the model. The pore pressure ratios for
models C and D showed a more centered area with a low ratio as there was significant load transfer through the
connecting plate at the surface.

The distribution of pore fluid pressure ratio when the settlement increase rate decreased is shown in Figure 15.
During these tests, it was found that, after the pore fluid pressure ratio decreased to about 0.6 - 0.7, there was a




                                                                                      x100 kPa
          (a) Model A             (b) Model B               (c) Model C               (d) Model D
                  Figure 13: Contour of pore fluid pressure just after the end of shaking




          (a) Model A             (b) Model B               (c) Model C                 (d) Model D
                Figure 14: Contour of pore fluid pressure ratio just after the end of shaking

                                                         7                                                      2441
(a) Model A              (b) Model B               (c) Model D
      Figure 15: Contour of pore fluid pressure ratio when the degree of settlement increase dropped
decrease in the rate at which settlement increased. This trend was consistently observed throughout all the tests
including the first series in this study.

                                                       CONCLUSIONS

A series of dynamic centrifuge tests were conducted on isolated foundations of power transmission towers to
examine the effectiveness of countermeasures against the settlement due to liquefaction. Three types of
countermeasures were tested: in the first the four footings were connected at base level, in the second the
connection was made at ground surface level and in the third the footings were connected at ground surface level
and in addition sheet piles were installed around the footings. The following conclusions were drawn:
1.       The most effective method of reducing the settlement of the footing was to connect the four footings at
         base level. The settlement was reduced by as much as 70 % compared to the case without any
         countermeasures. In this method, the soil inside the four footings possibly behaved as one unit together
         as like one large footing, and the pressure transferred to the soil beneath the plates worked effectively to
         reduce the pore fluid ratios in the soil.
2.       Even using a method to connect four footings at ground surface level can reduce the settlement by about
         30 %. This was because the surface plate could be a resistant structure against the settlement, and thus
         the load transferred to the soil through the footings reduced. The pore fluid pressure ratios inside the
         four footings might also be smaller, which led to the model behavior more likely as a unit together with
         sand.
3.       Under the testing conditions in this paper, the effects of the sheet piles on the settlement reduction were
         small. It may be necessary to examine the effects of the length of the sheet piles on the settlement.
4.       Considering actual site conditions which are generally seen in Japan, the existence of an unliquefiable
         layer at the soil surface may influence the settlement behavior, especially when a surface plate is used
         as a countermeasure as used in models C and D. These effects will also be examined in the next stage.

                                                 ACKNOWLEDGEMENTS

The authors would like to express sincere appreciation to Mr. T. Fujiwara of Taisei Corporation for his great
assistance during the tests. This study was organized by the Association for Development of Earthquake
Prediction. The authors also would like to express sincere appreciation to the members in the committee for the
fruitful discussions and suggestions.
                                               REFERENCES

1.       Kawasaki, K. Sakai, T., Yasuda, S. and Satoh, M. (1998), “Earthquake-induced settlement of an isolated footing for power
         transmission tower”, Proc. Centrifuge 98, Tokyo, Balkema, pp271-276.
2.       Kawasaki, K. et al. (1996), “Dynamic centrifuge modeling of an isolated footing for transmission line tower”, Proc. 6th Japan –
         US Workshop on Earthquake Resistant Design of Lifeline Facilities and Countermeasures against Soil Liquefaction, pp243-258.
3.       Nagura, K., Tanaka, M., Kawasaki, K. and Higuchi, Y. (1994), “Development of an earthquake simulator for the TAISEI
         centrifuge, Proc. Centrifuge 94, Singapore, Balkema, pp151-156.
4.       Sakemi, T., Sakai, T., Satoh, M. and Yasuda, S. (1998), ‘Centrifuge modeling of power transmission tower Part 4 (Four footings
         model)’, Proc. Annual Convention, JSCE, III-A181, pp360-361 (in Japanese).




                                                                  8                                                                2441

More Related Content

Viewers also liked

Design of transmission lines in india a review of multiple swing angle
Design of transmission lines in india  a review of multiple swing angleDesign of transmission lines in india  a review of multiple swing angle
Design of transmission lines in india a review of multiple swing angleLahmeyer International, UAE
 
Techniquescontrolledblasting 091217003405-phpapp01
Techniquescontrolledblasting 091217003405-phpapp01Techniquescontrolledblasting 091217003405-phpapp01
Techniquescontrolledblasting 091217003405-phpapp01Lahmeyer International, UAE
 
Case study on non destructive testing on concrete structures
Case study on non destructive testing on concrete structuresCase study on non destructive testing on concrete structures
Case study on non destructive testing on concrete structuresLahmeyer International, UAE
 

Viewers also liked (18)

monopole
monopolemonopole
monopole
 
Copy of stub setting
Copy of stub settingCopy of stub setting
Copy of stub setting
 
Gap Conductor
Gap ConductorGap Conductor
Gap Conductor
 
Copy of prop setting calculations final
Copy of prop setting calculations finalCopy of prop setting calculations final
Copy of prop setting calculations final
 
Guide to sampling concrete
Guide to sampling concreteGuide to sampling concrete
Guide to sampling concrete
 
Copy of stub setting
Copy of stub settingCopy of stub setting
Copy of stub setting
 
Copy of prop setting calculations final
Copy of prop setting calculations finalCopy of prop setting calculations final
Copy of prop setting calculations final
 
Overhead lines electrical_hazards
Overhead lines electrical_hazardsOverhead lines electrical_hazards
Overhead lines electrical_hazards
 
Design of transmission lines in india a review of multiple swing angle
Design of transmission lines in india  a review of multiple swing angleDesign of transmission lines in india  a review of multiple swing angle
Design of transmission lines in india a review of multiple swing angle
 
Copy of prop setting calculations final
Copy of prop setting calculations finalCopy of prop setting calculations final
Copy of prop setting calculations final
 
Guide to sampling concrete
Guide to sampling concreteGuide to sampling concrete
Guide to sampling concrete
 
Swing angle
Swing angleSwing angle
Swing angle
 
Sample collection (Soil Investigation)
Sample collection (Soil Investigation)Sample collection (Soil Investigation)
Sample collection (Soil Investigation)
 
Techniquescontrolledblasting 091217003405-phpapp01
Techniquescontrolledblasting 091217003405-phpapp01Techniquescontrolledblasting 091217003405-phpapp01
Techniquescontrolledblasting 091217003405-phpapp01
 
Use of bentonite
Use of bentoniteUse of bentonite
Use of bentonite
 
Copy of prop setting calculations final
Copy of prop setting calculations finalCopy of prop setting calculations final
Copy of prop setting calculations final
 
Recommended limits for aggegates
Recommended limits for aggegatesRecommended limits for aggegates
Recommended limits for aggegates
 
Case study on non destructive testing on concrete structures
Case study on non destructive testing on concrete structuresCase study on non destructive testing on concrete structures
Case study on non destructive testing on concrete structures
 

Similar to Counter mesaures aginst liquefaction induced settlemnt for ohl

Mathematical modeling and Experimental Determination of Grade intermixing tim...
Mathematical modeling and Experimental Determination of Grade intermixing tim...Mathematical modeling and Experimental Determination of Grade intermixing tim...
Mathematical modeling and Experimental Determination of Grade intermixing tim...Ankit Karwa
 
2010 12 14 Byrd Decommissioning In The Usa
2010 12 14 Byrd  Decommissioning In The Usa2010 12 14 Byrd  Decommissioning In The Usa
2010 12 14 Byrd Decommissioning In The Usa
Robert Byrd
 
An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...
An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...
An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...
Altair
 
TALAT Lecture 2711: Design of a Helicopter Deck
TALAT Lecture 2711: Design of a Helicopter DeckTALAT Lecture 2711: Design of a Helicopter Deck
TALAT Lecture 2711: Design of a Helicopter Deck
CORE-Materials
 
Formability study of layered material based on numerical analysis
Formability study of layered material based on numerical analysisFormability study of layered material based on numerical analysis
Formability study of layered material based on numerical analysis
vikrammistry
 
The static loading test bengt h. fellenius
The  static loading test   bengt h. felleniusThe  static loading test   bengt h. fellenius
The static loading test bengt h. fellenius
cfpbolivia
 
Bearing capacity of piles
Bearing capacity of pilesBearing capacity of piles
Bearing capacity of piles
Amin El Gendy, Ph.D., P.Eng, PMP
 
Matrix Structural Analysis, Steel Frame Analysis in SAP2000
Matrix Structural Analysis, Steel Frame Analysis in SAP2000Matrix Structural Analysis, Steel Frame Analysis in SAP2000
Matrix Structural Analysis, Steel Frame Analysis in SAP2000Sajjad Ahmad
 
Dry Stack Tailings Facility
Dry Stack Tailings FacilityDry Stack Tailings Facility
Dry Stack Tailings Facility
Hudbay Minerals Inc.
 
Giatech Airframe Wire Development
Giatech Airframe Wire DevelopmentGiatech Airframe Wire Development
Giatech Airframe Wire Development
John Jocham
 
S10 tr-tank rupturetutorial
S10 tr-tank rupturetutorialS10 tr-tank rupturetutorial
S10 tr-tank rupturetutorial
azerty82
 
Swmm Example 4 - Water Quality
Swmm Example 4 - Water QualitySwmm Example 4 - Water Quality
Swmm Example 4 - Water Quality
은성 정
 
Concreat filing information about K007en.pdf
Concreat filing information about K007en.pdfConcreat filing information about K007en.pdf
Concreat filing information about K007en.pdf
thinagara
 
Distributed modelling simplified hydrological process models for humid areas
Distributed modelling simplified hydrological process models for humid areas Distributed modelling simplified hydrological process models for humid areas
Distributed modelling simplified hydrological process models for humid areas
International Water Management Institute (IWMI)
 
Chapter 9 Of Rock Engineering
Chapter 9 Of  Rock  EngineeringChapter 9 Of  Rock  Engineering
Chapter 9 Of Rock Engineering
Ngo Hung Long
 
Le.h insulation coordination - Digsilent
Le.h insulation coordination - DigsilentLe.h insulation coordination - Digsilent
Le.h insulation coordination - Digsilent
Gilberto Mejía
 
Clt mtb seminar_presentation_five
Clt mtb seminar_presentation_fiveClt mtb seminar_presentation_five
Clt mtb seminar_presentation_fiveFWPA
 
Mutooroo Magnetite Project Update October 2012
Mutooroo Magnetite Project Update October 2012Mutooroo Magnetite Project Update October 2012
Mutooroo Magnetite Project Update October 2012Minotaur Exploration
 

Similar to Counter mesaures aginst liquefaction induced settlemnt for ohl (20)

Mathematical modeling and Experimental Determination of Grade intermixing tim...
Mathematical modeling and Experimental Determination of Grade intermixing tim...Mathematical modeling and Experimental Determination of Grade intermixing tim...
Mathematical modeling and Experimental Determination of Grade intermixing tim...
 
021[1]
021[1]021[1]
021[1]
 
2010 12 14 Byrd Decommissioning In The Usa
2010 12 14 Byrd  Decommissioning In The Usa2010 12 14 Byrd  Decommissioning In The Usa
2010 12 14 Byrd Decommissioning In The Usa
 
An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...
An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...
An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...
 
TALAT Lecture 2711: Design of a Helicopter Deck
TALAT Lecture 2711: Design of a Helicopter DeckTALAT Lecture 2711: Design of a Helicopter Deck
TALAT Lecture 2711: Design of a Helicopter Deck
 
Formability study of layered material based on numerical analysis
Formability study of layered material based on numerical analysisFormability study of layered material based on numerical analysis
Formability study of layered material based on numerical analysis
 
The static loading test bengt h. fellenius
The  static loading test   bengt h. felleniusThe  static loading test   bengt h. fellenius
The static loading test bengt h. fellenius
 
Bearing capacity of piles
Bearing capacity of pilesBearing capacity of piles
Bearing capacity of piles
 
Matrix Structural Analysis, Steel Frame Analysis in SAP2000
Matrix Structural Analysis, Steel Frame Analysis in SAP2000Matrix Structural Analysis, Steel Frame Analysis in SAP2000
Matrix Structural Analysis, Steel Frame Analysis in SAP2000
 
Dry Stack Tailings Facility
Dry Stack Tailings FacilityDry Stack Tailings Facility
Dry Stack Tailings Facility
 
Giatech Airframe Wire Development
Giatech Airframe Wire DevelopmentGiatech Airframe Wire Development
Giatech Airframe Wire Development
 
S10 tr-tank rupturetutorial
S10 tr-tank rupturetutorialS10 tr-tank rupturetutorial
S10 tr-tank rupturetutorial
 
Swmm Example 4 - Water Quality
Swmm Example 4 - Water QualitySwmm Example 4 - Water Quality
Swmm Example 4 - Water Quality
 
Concreat filing information about K007en.pdf
Concreat filing information about K007en.pdfConcreat filing information about K007en.pdf
Concreat filing information about K007en.pdf
 
Distributed modelling simplified hydrological process models for humid areas
Distributed modelling simplified hydrological process models for humid areas Distributed modelling simplified hydrological process models for humid areas
Distributed modelling simplified hydrological process models for humid areas
 
Chapter 9 Of Rock Engineering
Chapter 9 Of  Rock  EngineeringChapter 9 Of  Rock  Engineering
Chapter 9 Of Rock Engineering
 
Le.h insulation coordination - Digsilent
Le.h insulation coordination - DigsilentLe.h insulation coordination - Digsilent
Le.h insulation coordination - Digsilent
 
Clt mtb seminar_presentation_five
Clt mtb seminar_presentation_fiveClt mtb seminar_presentation_five
Clt mtb seminar_presentation_five
 
Mutooroo Magnetite Project Update October 2012
Mutooroo Magnetite Project Update October 2012Mutooroo Magnetite Project Update October 2012
Mutooroo Magnetite Project Update October 2012
 
gantry crane report
gantry crane reportgantry crane report
gantry crane report
 

More from Lahmeyer International, UAE (19)

AP88 & AP91 shifting proposal
AP88 & AP91 shifting proposalAP88 & AP91 shifting proposal
AP88 & AP91 shifting proposal
 
Gb137
Gb137Gb137
Gb137
 
Ohl project risk register
Ohl project risk registerOhl project risk register
Ohl project risk register
 
Ohl project risk register
Ohl project risk registerOhl project risk register
Ohl project risk register
 
Copy of stub setting
Copy of stub settingCopy of stub setting
Copy of stub setting
 
Copy of prop setting calculations final
Copy of prop setting calculations finalCopy of prop setting calculations final
Copy of prop setting calculations final
 
Copy of stub setting 2
Copy of stub setting 2Copy of stub setting 2
Copy of stub setting 2
 
Copy of stub setting
Copy of stub settingCopy of stub setting
Copy of stub setting
 
Copy of stub setting 3
Copy of stub setting 3Copy of stub setting 3
Copy of stub setting 3
 
Copy of stub setting 1
Copy of stub setting 1Copy of stub setting 1
Copy of stub setting 1
 
Copy of stub setting 1
Copy of stub setting 1Copy of stub setting 1
Copy of stub setting 1
 
Copy of stub setting 3
Copy of stub setting 3Copy of stub setting 3
Copy of stub setting 3
 
Copy of stub setting 2
Copy of stub setting 2Copy of stub setting 2
Copy of stub setting 2
 
Copy of stub setting 2
Copy of stub setting 2Copy of stub setting 2
Copy of stub setting 2
 
Copy of stub setting
Copy of stub settingCopy of stub setting
Copy of stub setting
 
Copy of stub setting 3
Copy of stub setting 3Copy of stub setting 3
Copy of stub setting 3
 
Copy of stub setting 1
Copy of stub setting 1Copy of stub setting 1
Copy of stub setting 1
 
Airbirne observation plate
Airbirne observation plateAirbirne observation plate
Airbirne observation plate
 
3
33
3
 

Recently uploaded

Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Product School
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Inflectra
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Albert Hoitingh
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
DanBrown980551
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Thierry Lestable
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
BookNet Canada
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
Alison B. Lowndes
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
Guy Korland
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
Elena Simperl
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
RTTS
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
DianaGray10
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
DianaGray10
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
ControlCase
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
Safe Software
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
Cheryl Hung
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
KatiaHIMEUR1
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
Paul Groth
 

Recently uploaded (20)

Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
 

Counter mesaures aginst liquefaction induced settlemnt for ohl

  • 1. 2441 COUNTERMEASURES AGAINST LIQUEFACTION INDUCED SETTLEMENT FOR POWER TRANSMISSION TOWERS Hidenori ABO1, Kenichi HORIKOSHI2, Susumu YASUDA3 And Masayuki SATOH4 SUMMARY After the 1995 Hyogoken Nambu earthquake, it has been recognized that restoring service facility from the damage is critical for urgent recovery of city function. Among lifelines, power transmission towers are highly important electrical components, some of which are required to survive with only minor damage even after a strong earthquake. In the past earthquakes such as 1964 Niigata earthquake, transmission towers were inclined due to the effects of soil liquefaction. It is therefore important to develop a method for estimating seismic performance of transmission towers during and after earthquakes. A series of dynamic centrifuge tests were conducted by modeling an isolated footing of a tower on sand. In these tests, four isolated footings were modeled together on a liquefiable sand layer and the effectiveness of three types of countermeasures against settlement due to liquefaction was examined. These countermeasures were designed to connect the four footings to each other, and the types of connections modeled were: 1) a plate at the base of the footing, 2) a plate at soil surface level, and 3) a surface plate with surrounding sheet piles. The seismic performances of these countermeasures were compared with that of a tower without any countermeasures. The results show that the base plate can prevent the settlement by as much as 70 %, and that even the surface plate can prevent the settlement by 30 %. The test results also show that, in the modeled conditions, the effectiveness of the surrounding sheet pile walls was relatively small. This result was considered to be a consequence of an inadequate length of the sheet piles compared with the width of the foundation. INTRODUCTION It has been recognized that power transmission towers are very important facilities which affect the post- earthquake recovery of city services. The damages of towers due to soil liquefaction were reported after Niigata earthquake in 1964, as shown in Figure 1. The inclination and the settlement of the towers were the main damages according to the report. The 1995 Hyogoken Nambu Earthquake revealed that much wider types of soil might liquefy due to strong earthquake motions. Power transmission towers sometimes use ‘isolated footing’ type foundations, with each of the four legs of the tower supported on an independent footing. Given the importance of these towers it is important to develop a method for evaluating the settlement of such isolated footings on liquefiable soils during and after earthquakes. 1 Power System Engineering Department, Tokyo Electric Power Co., Tokyo, Japan Email: T0632711@pmail.tepco.co.jp 2 Taisei Research Institute, Taisei Corporation, Yokohama, Japan Email: kenichi.horikoshi@sakura.taisei.co.jp 3 Department of Civil Engineering, Tokyo Denki University, Saitama, Japan Email: yasuda@g.dendai.ac.jp 4 Advanced Engineering Operation Center, Tokyo Electric Power Service Co., Ltd., Tokyo, Japan Email:sato@aed.tepsco.co.jp
  • 2. The authors conducted a series of dynamic centrifuge tests to examine the settlement of power transmission towers during and after liquefaction, as already reported by Kawasaki et al [1][2]. In the first phase of this study, attention was placed on finding factors which govern the settlement of isolated footings. The four main variables in the tests were relative density of soil, magnitude of input motion, number of cycles of motion, and width of the footing. A typical isolated footing designed to support one of the legs of a power transmission tower was extensively tested. Finally, based on the results of the centrifuge tests, a simple Figure 1: Inclined power transmission towers seen after method to estimate the settlement was presented. Niigata earthquake, 1964 The predicted settlement was expressed in a conventional form by using a number of deviating factors which relate to the above four factors. From the results of more than 30 tests, the following empirical equation was proposed for estimating the settlement of the transmission towers: S = S o ⋅ C1 ⋅ C 2 Cm ⋅ D1 ⋅ D 2 Dn (1) where, S is the settlement of transmission tower, So is the settlement of tower under particular standard conditions defined below, C1-Cm are deviating factors from So relevant to the actual ground condition and input motion, and D1-Dn are deviating factors from So relevant to the specific structure under consideration. In the proposed method, the factors taken into account were: thickness of liquefiable layer (C1), thickness of unliquefiable layer (C2), relative density (C3), grain size (C4), factor related to degree of liquefaction (C5), width of footing (D1) and load intensity (D2). Each deviating factor is shown graphically in Figure 2. In the tests, the conditions set as the standard conditions were: C1 : 13.2 m, C2 : 0 m, C3 : 40 %, C4 : D50 = 0.161 mm (Toyoura sand), C5 : FL = 1, D1 : 3.2 m and D2 : 28.4 kPa. 2 C1 C2 C3 C4 1.5 Factor 1 0.5 0 0 2 4 6 8 10 12 0 1 2 3 4 5 6 0 10 20 30 40 50 60 0 0.1 0.2 0.3 0.4 0.5 Liquifiable layer thickness Unliquefiable layer -1/2Footing width (m) Relative density (%) D (mm) thickness(m) 50 2 C5 D1 D2 1.5 Factor 1 0.5 0 0 1 2 3 4 5 -20 0 20 40 60 0 0.5 1 1.5 2 FL Footing width (m) Additional pressure (kPa) Figure 2: Deviating factors obtained a series of centrifuge tests It should be noted that, a more accurate estimation of the settlement requires an additional, extensive review of the field observations and an effort is currently being made for refining the proposed method, which will be presented in the near future. After examining the factors which govern the footing settlement, the authors conducted another series of dynamic centrifuge tests to examine the effectiveness of three methods for reducing the settlement of the 2 2441
  • 3. Plate connected to each footing Vertical load Isolated footing Circular laminar box A10 A6 86 P14 55 P7 A9 P13 350 A4 210 100 P3 55 P1 Toyoura sand Toyoura sand Pore fluid pressure transducers 400 Accelerometers P14 Installed only for model D (with sheet piles) Displacement transducers Unit : mm (a) PLAN (b) SECTION Figure 3: Schematic figure of centrifuge model footings. The results obtained from the second series of tests are presented in this paper. It should be noted that countermeasures for reducing the settlement considered in this paper are for already existing isolated tower footings, rather than for newly constructed footings. MODEL DESIGNS AND TEST PROCEDURES The details of the centrifuge machine used in this study were described by Nagura et al. [3]. The machine has an effective radius of 2.65 m and has an electrohydraulic servo-controlled shaking table designed for conducting dynamic tests. A centrifugal acceleration of 50 g was applied to a 1/50 model (here, ‘g’ denotes gravity). Figure 3 shows a schematic figure of the centrifuge setup designed for the study. Four independent footings, which support a transmission tower, were modeled. The model shown in the figure corresponds to ‘Model C’ in this paper (see Figure 4 in the next section). A circular laminar box with an inside diameter of 400 mm was used as the soil box. The material of the model footing was made by mixing cement, sand and iron powder. The width of the model footing was 50 mm (2.5 m at prototype scale) and a weight of 18.3 tons per footing at prototype scale was applied vertically. The distance between two footings in the model was set at 100 mm (5.0 m). Toyoura sand with a height of 350 mm (17.5 m) was used as a soil sample. The properties of Toyoura sand are summarized in Table 1. Table 1: Properties of Toyoura sand Density of soil particle (g/cm3) Maximum density (g/cm3) Minimum density (g/cm3) Mean grain size (mm) 2.661 1.654 1.349 0.162 Dry Toyoura sand was first poured into the soil box. After placing four model footings on the sand and placing the surface sand at the prescribed level, the sand was saturated with silicon oil with a viscosity 50 times higher than that of water. The relative density of the soil was set at about 40-45 % prior to the shaking. Before starting the main shaking test, the model was spun to observe the initial settlement due to a centrifugal acceleration of 50 g. The test models with and without countermeasures for reducing the settlement are shown in Figure 4. The models tested were: Model A: Without any countermeasures. Model B: Connecting the base of all footings by a concrete plate. Model C: Connecting the four footings by a concrete plate at ground surface level. 3 2441
  • 4. 10.5 m Concrete Plate Concrete Plate Concrete Plate Isolated footing 10.5 m Sheet piles (Type III) 4.3 m Concrete plate (t = 150 mm) Model A Model B Model C Model D (no countermeasure) (Base plate) (Surface plate) (Surface plate + Sheet piles) Figure 4: Countermeasures modeled in the study Model D: In addition to connecting the four footings by a concrete plate at ground surface level, as in Model C, the footings were surrounded by sheet pile walls. The models A and B were tested and reported by Sakemi et al [4]. The base and surface plates in the models were made by plastic plate with a thickness of 5 mm, which corresponds to a concrete plate of about 150 mm at prototype scale. Sandpaper was attached on the surface of the plastic plate to create a rough surface. The model B was thought to be the most effective as the four footings behave as one single foundation with respect to the soil above the base plate. However, constructing such a base plate of footings of already existing towers during the tower operation is not only difficult but may also be unrealistic. Other two models C and D were proposed as feasible alternatives to the model B. A photograph of model C is shown in Figure 5. In both models C and D, the plate connecting the four isolated footings was attached at the ground surface level, which is not only much easier but is, also, more economic. It was considered that the use of a surface plate would reduce the stress transferred to the isolated footings as the plate itself would provide additional resistance against settlement of the tower. Model D is similar to model C but in addition to the surface plate, sheet pile walls were placed around the four footings. The bending rigidity of the sheet piles was set equivalent to Type III sheet piles in Japan. The above models were excited by a sinusoidal horizontal wave with 20 cycles at 50 Hz which is equivalent to 20 cycles at 1 Hz for the prototype model. The motion shown in Figure 6 was applied to the base of the model. The peak acceleration corresponding to the motion was set at 4.5 g at model scale (90 gal at prototype scale). During the tests, pore fluid pressure, acceleration and the settlement of the soil surface were measured as well as the settlement of the model footing. The locations of the transducers are shown in Figure 3. TEST RESULTS Acceleration Response: The observed acceleration responses for the models A and C are compared in Figures 7 to 9. Figure 7 shows the response of the accelerometer A10 (at the soil surface, see Figure 3), Figure 8 shows the response of A9 (on soil below near the center of the model), and Figure 9 shows the response of A6 (in the model footing). In all three figures, the acceleration response did not fade away right up to the end of the shaking even though the soil liquefied significantly. 100 Input Acc. (gal) 50 0 -50 -100 0 10 20 30 40 Time (sec.) Figure 5: Photograph of Model C Figure 6: Input acceleration 4 2441
  • 5. 200 Acceleration (gal) 200 Acceleration (gal) Model A Model C 100 100 0 0 -100 -100 -200 -200 0 10 20 30 40 0 10 20 30 40 Time (sec) Time (sec) Figure 7: Acceleration response observed at soil surface (Models A & C, A10) 200 Acceleration (gal) 200 Acceleration (gal) Model A Model C 100 100 0 0 -100 -100 -200 -200 0 10 20 30 40 0 10 20 30 40 Time (sec) Time (sec) Figure 8: Acceleration response observed below the center of footing (Models A & C, A9) Acceleration (gal) 200 Acceleration (gal) 200 Model A Model C 100 100 0 0 -100 -100 -200 -200 0 10 20 30 40 0 10 20 30 40 Time (sec) Time (sec) Figure 9: Acceleration response in the model footing (Models A & C, A6) Figures 7 and 8 show clearly the difference between the acceleration responses of models A and C. The response of the model D was close to that of the model C. The magnitude of the acceleration of model A was higher than those observed in the other three models, and the response of model A was also more complex. Since each footing was set independently in model A, the acceleration response of the four footings was considered not to be completely the same, and this might influence the acceleration response of the soil around the model. It was also considered that, models B, C, and D, in which the four footings were connected together, behaved as a single unit, which could lead to a much higher effective mass in these models than in model A. -50 0 Settlement ratio to Model A 0 Model B Settlement (mm) Model B 0.2 50 100 0.4 Model D Model D 150 0.6 200 Model C 0.8 Model C 250 Model A 300 1 0 200 400 600 800 1000 0 200 400 600 800 1000 Time (sec.) Time (sec.) (a) Observed settlement at prototype scale (b) Settlement ratio to Model A Figure 10: Settlement of model footings Settlement Figure 10 and Table 2 summarize the settlement of the models during and after the shaking at prototype scale. The settlement shown in the figures and the table is the average of the four footings settlements. In the figure, only the initial 20 seconds corresponds to the shaking period, i.e. the settlement continued after the shaking. The following observations can be made from Figure 10: As expected, model B, in which the connecting plate was attached at the base of the footings, was the most effective way of reducing the settlement. The final settlement measured in model B was as low as 80 mm, compared with that of 250 mm in model A (without countermeasure), i.e. the settlement reduced by about 70 %. The settlement during the shaking period itself was significantly smaller in model B than those 5 2441
  • 6. observed in the other models. An explanation of this behavior is the much smaller pore fluid pressure ratio beneath the model, as shown later in this paper. Although the measured settlements of models C and D were larger than that of model B, their settlements were about 2/3 of that of model A, i.e. the settlement was reduced by about 30 % by connecting the four independent footings at the ground surface level. The results of the tests in this study showed the effect of the surrounding sheet piles on the settlement to be small. The final settlement in model D was about 61% of model A. It was considered that the relatively short length of the sheet piles used in model D could be the reason for the small difference in the final settlements of models C and D. Table 2: Settlement of model footings Model Relative Maximum Settlement Final settlement Density input during Footing Soil surface (%) acceleration shaking (mm) (mm) (gal) (mm) A: Without any countermeasures 39.6 91 200 250 Not measured B: Base plate 43.7 93 75 75 80 C: Surface plate 45.5 88 70 174 81 D: Surface plate + Sheet piles 45.1 86 64 154 55 Input acceleration and settlement are shown at prototype scale Pore Fluid Pressure The pore fluid pressure responses of the four models at various locations are shown in Figure 11. The figures show that the rate of increase in the pore fluid pressure to be relatively slower in models A and B compared to models C and D. This difference in behavior was considered to be the result of the slight difference in the shape of the created input motions. The following observations can be made from the figures: ・ As shown later, the excess pore fluid ratio outside the influenced area seemed to increase close to unity, indicating that the soil in this area liquefied significantly. ・ Although the instrumented depths for transducers P7 and P13 were the same, the increase in the excess pore fluid pressure was smaller for P7 in the models C and D. In the case of model B, the rate of increase in the pore fluid pressure was slightly slower compared with the other models. This might be related to the very small settlement of the footing during and after the shaking, which was caused by higher confining pressure. ・ The increase in the pore fluid pressure for P14 in model D was considerably small. This may be as a result of the sheet pile walls around the model footing which prevented an increase. Figure 12 shows the pore fluid pressure ratio at a depth just beneath the model footing for models A, B and D. The effective overburden pressure was estimated by using Boussinesq solution. Note that, for model D, the 150 Shaking period Model A Shaking period Model B 150 120 P1 120 P1 Ex. PFP (kPa) Ex. PFP (kPa) 90 P3 90 P3 60 60 30 P7 P7 & P13 30 0 0 0 20 40 60 80 100 0 20 40 60 80 100 Time(Sec.) Time (sec) (a) Model A (b) Model B 150 Shaking period Shaking Period Model D Model C 150 120 P1 120 P1 Ex. PFP (kPa) Ex. PFP (kPa) 90 P3 90 P3 60 P13 60 P14 30 P13 P7 30 P7 0 0 0 20 40 60 80 100 0 20 40 60 80 100 Time (sec.) Time (sec.) (c) Model C (d) Model D Figure 11: Pore fluid pressure response observed for Models A - D 6 2441
  • 7. effects of the load transferred directly from the surface plate were ignored for simplicity in calculating the initial 1 Model A overburden pressure. The peak pressure ratio for model A Model B 0.8 Model D PFP ratio (without any countermeasures) was close to unity and model B 0.6 shows the lowest value of about 0.5. Figure 12 clearly shows that the lower the pore fluid pressure ratio below the model 0.4 footings was, the smaller the footing settlement became. 0.2 0 It is also very important to relate the pore fluid pressure 0 500 1000 1500 response with the observed settlement behavior. The Time(sec.) distribution of pore fluid pressure around the model footing Figure 12: Pore fluid pressure ratio observed just after the shaking is drawn for each model in Figure 13. beneath the model footings The corresponding pressure ratio is also drawn in Figure 14. A point of caution regarding these figures, the contours were created from a limited number of pressure transducer readings so that the profiles far from the location of the transducers might not be correct. The small circles shown in the figures indicate the location of the pore pressure transducers. Figure 12 indicates that in all four models the soil near the bottom of the box liquefied significantly. The magnitude of the pore fluid pressure ratio of model B in Figure 14 can be seen to be very small due to the effects of the load transferred through the base plate of the model. The pore pressure ratios for models C and D showed a more centered area with a low ratio as there was significant load transfer through the connecting plate at the surface. The distribution of pore fluid pressure ratio when the settlement increase rate decreased is shown in Figure 15. During these tests, it was found that, after the pore fluid pressure ratio decreased to about 0.6 - 0.7, there was a x100 kPa (a) Model A (b) Model B (c) Model C (d) Model D Figure 13: Contour of pore fluid pressure just after the end of shaking (a) Model A (b) Model B (c) Model C (d) Model D Figure 14: Contour of pore fluid pressure ratio just after the end of shaking 7 2441
  • 8. (a) Model A (b) Model B (c) Model D Figure 15: Contour of pore fluid pressure ratio when the degree of settlement increase dropped decrease in the rate at which settlement increased. This trend was consistently observed throughout all the tests including the first series in this study. CONCLUSIONS A series of dynamic centrifuge tests were conducted on isolated foundations of power transmission towers to examine the effectiveness of countermeasures against the settlement due to liquefaction. Three types of countermeasures were tested: in the first the four footings were connected at base level, in the second the connection was made at ground surface level and in the third the footings were connected at ground surface level and in addition sheet piles were installed around the footings. The following conclusions were drawn: 1. The most effective method of reducing the settlement of the footing was to connect the four footings at base level. The settlement was reduced by as much as 70 % compared to the case without any countermeasures. In this method, the soil inside the four footings possibly behaved as one unit together as like one large footing, and the pressure transferred to the soil beneath the plates worked effectively to reduce the pore fluid ratios in the soil. 2. Even using a method to connect four footings at ground surface level can reduce the settlement by about 30 %. This was because the surface plate could be a resistant structure against the settlement, and thus the load transferred to the soil through the footings reduced. The pore fluid pressure ratios inside the four footings might also be smaller, which led to the model behavior more likely as a unit together with sand. 3. Under the testing conditions in this paper, the effects of the sheet piles on the settlement reduction were small. It may be necessary to examine the effects of the length of the sheet piles on the settlement. 4. Considering actual site conditions which are generally seen in Japan, the existence of an unliquefiable layer at the soil surface may influence the settlement behavior, especially when a surface plate is used as a countermeasure as used in models C and D. These effects will also be examined in the next stage. ACKNOWLEDGEMENTS The authors would like to express sincere appreciation to Mr. T. Fujiwara of Taisei Corporation for his great assistance during the tests. This study was organized by the Association for Development of Earthquake Prediction. The authors also would like to express sincere appreciation to the members in the committee for the fruitful discussions and suggestions. REFERENCES 1. Kawasaki, K. Sakai, T., Yasuda, S. and Satoh, M. (1998), “Earthquake-induced settlement of an isolated footing for power transmission tower”, Proc. Centrifuge 98, Tokyo, Balkema, pp271-276. 2. Kawasaki, K. et al. (1996), “Dynamic centrifuge modeling of an isolated footing for transmission line tower”, Proc. 6th Japan – US Workshop on Earthquake Resistant Design of Lifeline Facilities and Countermeasures against Soil Liquefaction, pp243-258. 3. Nagura, K., Tanaka, M., Kawasaki, K. and Higuchi, Y. (1994), “Development of an earthquake simulator for the TAISEI centrifuge, Proc. Centrifuge 94, Singapore, Balkema, pp151-156. 4. Sakemi, T., Sakai, T., Satoh, M. and Yasuda, S. (1998), ‘Centrifuge modeling of power transmission tower Part 4 (Four footings model)’, Proc. Annual Convention, JSCE, III-A181, pp360-361 (in Japanese). 8 2441