The document describes a series of dynamic centrifuge tests that examined methods to reduce settlement of power transmission tower foundations during earthquakes. The tests modeled four isolated tower footing foundations on a liquefiable sand layer. Three countermeasure types were examined: 1) a base plate connecting the footings, 2) a surface plate connecting the footings at ground level, and 3) a surface plate with surrounding sheet piles. Test results showed that the base plate reduced settlement by up to 70% while the surface plate reduced it by 30%. The surrounding sheet piles showed relatively small effectiveness due to inadequate length compared to the foundation width.
Deflagration in Magnetism, J. Tejada, A. Hernández-Mínguez, F. Macià, S. Vélez and J.M. Hernández
Grup de Magnetisme, Dept. de Física Fonamental, Universitat de Barcelona
This lecture describes the measurement and amount of residual stresses in extruded and welded profiles which have to be accounted for in design; it introduces the subject of corrosion and of preventive design measures; it describes the behavior and properties of structural aluminium alloys at ambient, low and elevated temperatures; it gives useful examples of structural applications of extrusions. Background in mechanical and structural engineering disciplines is assumed.
Deflagration in Magnetism, J. Tejada, A. Hernández-Mínguez, F. Macià, S. Vélez and J.M. Hernández
Grup de Magnetisme, Dept. de Física Fonamental, Universitat de Barcelona
This lecture describes the measurement and amount of residual stresses in extruded and welded profiles which have to be accounted for in design; it introduces the subject of corrosion and of preventive design measures; it describes the behavior and properties of structural aluminium alloys at ambient, low and elevated temperatures; it gives useful examples of structural applications of extrusions. Background in mechanical and structural engineering disciplines is assumed.
2010 12 14 Byrd Decommissioning In The UsaRobert Byrd
A summary of offshore facility decommissioning issues in the USA. Presented to the Society for Underwater Technology, London, UK, December 2010, by Robert C. Byrd, Ph.D., P.E.
An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...Altair
In this study, a computer simulation model of a rigid impactor loading laterally a roadside W152x13.4 post has been developed. The interaction of cohesionless soil with a post was studied and compared to an existing dynamic test results from a published literature. Two approaches to simulate the soil have been studied: the continuum method where the soil is modeled as a solid element with Drucker and Prager material law, and the subgrade method where the soil reaction is simulated by a series of nonlinear springs. An improved method of the subgrade approach has been developed where the soil is modeled as a system of parallel springs and dampers with a lumped mass attached to the post. A simple procedure to calculate the lumped soil mass and the damping coefficient is presented.
2010 12 14 Byrd Decommissioning In The UsaRobert Byrd
A summary of offshore facility decommissioning issues in the USA. Presented to the Society for Underwater Technology, London, UK, December 2010, by Robert C. Byrd, Ph.D., P.E.
An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...Altair
In this study, a computer simulation model of a rigid impactor loading laterally a roadside W152x13.4 post has been developed. The interaction of cohesionless soil with a post was studied and compared to an existing dynamic test results from a published literature. Two approaches to simulate the soil have been studied: the continuum method where the soil is modeled as a solid element with Drucker and Prager material law, and the subgrade method where the soil reaction is simulated by a series of nonlinear springs. An improved method of the subgrade approach has been developed where the soil is modeled as a system of parallel springs and dampers with a lumped mass attached to the post. A simple procedure to calculate the lumped soil mass and the damping coefficient is presented.
TALAT Lecture 2711: Design of a Helicopter DeckCORE-Materials
This lecture presents design of the main structural parts of an aluminium alloy helicopter deck. The design of a bolted connection on the supporting structure is also presented.
A presentation on the Dry Stack Tailings design associated with the Rosemont Copper Project developed by the AMEC Consulting Company. This presentation was given to the Forest Service and their contractors during technical transfer meetings in November 2008.
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualityInflectra
In this insightful webinar, Inflectra explores how artificial intelligence (AI) is transforming software development and testing. Discover how AI-powered tools are revolutionizing every stage of the software development lifecycle (SDLC), from design and prototyping to testing, deployment, and monitoring.
Learn about:
• The Future of Testing: How AI is shifting testing towards verification, analysis, and higher-level skills, while reducing repetitive tasks.
• Test Automation: How AI-powered test case generation, optimization, and self-healing tests are making testing more efficient and effective.
• Visual Testing: Explore the emerging capabilities of AI in visual testing and how it's set to revolutionize UI verification.
• Inflectra's AI Solutions: See demonstrations of Inflectra's cutting-edge AI tools like the ChatGPT plugin and Azure Open AI platform, designed to streamline your testing process.
Whether you're a developer, tester, or QA professional, this webinar will give you valuable insights into how AI is shaping the future of software delivery.
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Albert Hoitingh
In this session I delve into the encryption technology used in Microsoft 365 and Microsoft Purview. Including the concepts of Customer Key and Double Key Encryption.
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...DanBrown980551
Do you want to learn how to model and simulate an electrical network from scratch in under an hour?
Then welcome to this PowSyBl workshop, hosted by Rte, the French Transmission System Operator (TSO)!
During the webinar, you will discover the PowSyBl ecosystem as well as handle and study an electrical network through an interactive Python notebook.
PowSyBl is an open source project hosted by LF Energy, which offers a comprehensive set of features for electrical grid modelling and simulation. Among other advanced features, PowSyBl provides:
- A fully editable and extendable library for grid component modelling;
- Visualization tools to display your network;
- Grid simulation tools, such as power flows, security analyses (with or without remedial actions) and sensitivity analyses;
The framework is mostly written in Java, with a Python binding so that Python developers can access PowSyBl functionalities as well.
What you will learn during the webinar:
- For beginners: discover PowSyBl's functionalities through a quick general presentation and the notebook, without needing any expert coding skills;
- For advanced developers: master the skills to efficiently apply PowSyBl functionalities to your real-world scenarios.
Transcript: Selling digital books in 2024: Insights from industry leaders - T...BookNet Canada
The publishing industry has been selling digital audiobooks and ebooks for over a decade and has found its groove. What’s changed? What has stayed the same? Where do we go from here? Join a group of leading sales peers from across the industry for a conversation about the lessons learned since the popularization of digital books, best practices, digital book supply chain management, and more.
Link to video recording: https://bnctechforum.ca/sessions/selling-digital-books-in-2024-insights-from-industry-leaders/
Presented by BookNet Canada on May 28, 2024, with support from the Department of Canadian Heritage.
GraphRAG is All You need? LLM & Knowledge GraphGuy Korland
Guy Korland, CEO and Co-founder of FalkorDB, will review two articles on the integration of language models with knowledge graphs.
1. Unifying Large Language Models and Knowledge Graphs: A Roadmap.
https://arxiv.org/abs/2306.08302
2. Microsoft Research's GraphRAG paper and a review paper on various uses of knowledge graphs:
https://www.microsoft.com/en-us/research/blog/graphrag-unlocking-llm-discovery-on-narrative-private-data/
JMeter webinar - integration with InfluxDB and GrafanaRTTS
Watch this recorded webinar about real-time monitoring of application performance. See how to integrate Apache JMeter, the open-source leader in performance testing, with InfluxDB, the open-source time-series database, and Grafana, the open-source analytics and visualization application.
In this webinar, we will review the benefits of leveraging InfluxDB and Grafana when executing load tests and demonstrate how these tools are used to visualize performance metrics.
Length: 30 minutes
Session Overview
-------------------------------------------
During this webinar, we will cover the following topics while demonstrating the integrations of JMeter, InfluxDB and Grafana:
- What out-of-the-box solutions are available for real-time monitoring JMeter tests?
- What are the benefits of integrating InfluxDB and Grafana into the load testing stack?
- Which features are provided by Grafana?
- Demonstration of InfluxDB and Grafana using a practice web application
To view the webinar recording, go to:
https://www.rttsweb.com/jmeter-integration-webinar
Connector Corner: Automate dynamic content and events by pushing a buttonDianaGray10
Here is something new! In our next Connector Corner webinar, we will demonstrate how you can use a single workflow to:
Create a campaign using Mailchimp with merge tags/fields
Send an interactive Slack channel message (using buttons)
Have the message received by managers and peers along with a test email for review
But there’s more:
In a second workflow supporting the same use case, you’ll see:
Your campaign sent to target colleagues for approval
If the “Approve” button is clicked, a Jira/Zendesk ticket is created for the marketing design team
But—if the “Reject” button is pushed, colleagues will be alerted via Slack message
Join us to learn more about this new, human-in-the-loop capability, brought to you by Integration Service connectors.
And...
Speakers:
Akshay Agnihotri, Product Manager
Charlie Greenberg, Host
UiPath Test Automation using UiPath Test Suite series, part 3DianaGray10
Welcome to UiPath Test Automation using UiPath Test Suite series part 3. In this session, we will cover desktop automation along with UI automation.
Topics covered:
UI automation Introduction,
UI automation Sample
Desktop automation flow
Pradeep Chinnala, Senior Consultant Automation Developer @WonderBotz and UiPath MVP
Deepak Rai, Automation Practice Lead, Boundaryless Group and UiPath MVP
Essentials of Automations: Optimizing FME Workflows with ParametersSafe Software
Are you looking to streamline your workflows and boost your projects’ efficiency? Do you find yourself searching for ways to add flexibility and control over your FME workflows? If so, you’re in the right place.
Join us for an insightful dive into the world of FME parameters, a critical element in optimizing workflow efficiency. This webinar marks the beginning of our three-part “Essentials of Automation” series. This first webinar is designed to equip you with the knowledge and skills to utilize parameters effectively: enhancing the flexibility, maintainability, and user control of your FME projects.
Here’s what you’ll gain:
- Essentials of FME Parameters: Understand the pivotal role of parameters, including Reader/Writer, Transformer, User, and FME Flow categories. Discover how they are the key to unlocking automation and optimization within your workflows.
- Practical Applications in FME Form: Delve into key user parameter types including choice, connections, and file URLs. Allow users to control how a workflow runs, making your workflows more reusable. Learn to import values and deliver the best user experience for your workflows while enhancing accuracy.
- Optimization Strategies in FME Flow: Explore the creation and strategic deployment of parameters in FME Flow, including the use of deployment and geometry parameters, to maximize workflow efficiency.
- Pro Tips for Success: Gain insights on parameterizing connections and leveraging new features like Conditional Visibility for clarity and simplicity.
We’ll wrap up with a glimpse into future webinars, followed by a Q&A session to address your specific questions surrounding this topic.
Don’t miss this opportunity to elevate your FME expertise and drive your projects to new heights of efficiency.
Key Trends Shaping the Future of Infrastructure.pdfCheryl Hung
Keynote at DIGIT West Expo, Glasgow on 29 May 2024.
Cheryl Hung, ochery.com
Sr Director, Infrastructure Ecosystem, Arm.
The key trends across hardware, cloud and open-source; exploring how these areas are likely to mature and develop over the short and long-term, and then considering how organisations can position themselves to adapt and thrive.
Securing your Kubernetes cluster_ a step-by-step guide to success !KatiaHIMEUR1
Today, after several years of existence, an extremely active community and an ultra-dynamic ecosystem, Kubernetes has established itself as the de facto standard in container orchestration. Thanks to a wide range of managed services, it has never been so easy to set up a ready-to-use Kubernetes cluster.
However, this ease of use means that the subject of security in Kubernetes is often left for later, or even neglected. This exposes companies to significant risks.
In this talk, I'll show you step-by-step how to secure your Kubernetes cluster for greater peace of mind and reliability.
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
Counter mesaures aginst liquefaction induced settlemnt for ohl
1. 2441
COUNTERMEASURES AGAINST LIQUEFACTION INDUCED SETTLEMENT
FOR POWER TRANSMISSION TOWERS
Hidenori ABO1, Kenichi HORIKOSHI2, Susumu YASUDA3 And Masayuki SATOH4
SUMMARY
After the 1995 Hyogoken Nambu earthquake, it has been recognized that restoring service facility
from the damage is critical for urgent recovery of city function. Among lifelines, power
transmission towers are highly important electrical components, some of which are required to
survive with only minor damage even after a strong earthquake. In the past earthquakes such as
1964 Niigata earthquake, transmission towers were inclined due to the effects of soil liquefaction.
It is therefore important to develop a method for estimating seismic performance of transmission
towers during and after earthquakes. A series of dynamic centrifuge tests were conducted by
modeling an isolated footing of a tower on sand. In these tests, four isolated footings were
modeled together on a liquefiable sand layer and the effectiveness of three types of
countermeasures against settlement due to liquefaction was examined. These countermeasures
were designed to connect the four footings to each other, and the types of connections modeled
were: 1) a plate at the base of the footing, 2) a plate at soil surface level, and 3) a surface plate with
surrounding sheet piles. The seismic performances of these countermeasures were compared with
that of a tower without any countermeasures. The results show that the base plate can prevent the
settlement by as much as 70 %, and that even the surface plate can prevent the settlement by 30 %.
The test results also show that, in the modeled conditions, the effectiveness of the surrounding
sheet pile walls was relatively small. This result was considered to be a consequence of an
inadequate length of the sheet piles compared with the width of the foundation.
INTRODUCTION
It has been recognized that power transmission towers are very important facilities which affect the post-
earthquake recovery of city services. The damages of towers due to soil liquefaction were reported after Niigata
earthquake in 1964, as shown in Figure 1. The inclination and the settlement of the towers were the main
damages according to the report. The 1995 Hyogoken Nambu Earthquake revealed that much wider types of
soil might liquefy due to strong earthquake motions. Power transmission towers sometimes use ‘isolated
footing’ type foundations, with each of the four legs of the tower supported on an independent footing. Given
the importance of these towers it is important to develop a method for evaluating the settlement of such isolated
footings on liquefiable soils during and after earthquakes.
1
Power System Engineering Department, Tokyo Electric Power Co., Tokyo, Japan Email: T0632711@pmail.tepco.co.jp
2
Taisei Research Institute, Taisei Corporation, Yokohama, Japan Email: kenichi.horikoshi@sakura.taisei.co.jp
3
Department of Civil Engineering, Tokyo Denki University, Saitama, Japan Email: yasuda@g.dendai.ac.jp
4
Advanced Engineering Operation Center, Tokyo Electric Power Service Co., Ltd., Tokyo, Japan Email:sato@aed.tepsco.co.jp
2. The authors conducted a series of dynamic
centrifuge tests to examine the settlement of
power transmission towers during and after
liquefaction, as already reported by Kawasaki et
al [1][2]. In the first phase of this study,
attention was placed on finding factors which
govern the settlement of isolated footings. The
four main variables in the tests were relative
density of soil, magnitude of input motion,
number of cycles of motion, and width of the
footing. A typical isolated footing designed to
support one of the legs of a power transmission
tower was extensively tested. Finally, based on
the results of the centrifuge tests, a simple Figure 1: Inclined power transmission towers seen after
method to estimate the settlement was presented. Niigata earthquake, 1964
The predicted settlement was expressed in a
conventional form by using a number of
deviating factors which relate to the above four factors. From the results of more than 30 tests, the following
empirical equation was proposed for estimating the settlement of the transmission towers:
S = S o ⋅ C1 ⋅ C 2 Cm ⋅ D1 ⋅ D 2 Dn (1)
where, S is the settlement of transmission tower, So is the settlement of tower under particular standard
conditions defined below, C1-Cm are deviating factors from So relevant to the actual ground condition and input
motion, and D1-Dn are deviating factors from So relevant to the specific structure under consideration. In the
proposed method, the factors taken into account were: thickness of liquefiable layer (C1), thickness of
unliquefiable layer (C2), relative density (C3), grain size (C4), factor related to degree of liquefaction (C5),
width of footing (D1) and load intensity (D2).
Each deviating factor is shown graphically in Figure 2. In the tests, the conditions set as the standard conditions
were:
C1 : 13.2 m, C2 : 0 m, C3 : 40 %, C4 : D50 = 0.161 mm (Toyoura sand), C5 : FL = 1,
D1 : 3.2 m and D2 : 28.4 kPa.
2
C1 C2 C3 C4
1.5
Factor
1
0.5
0
0 2 4 6 8 10 12 0 1 2 3 4 5 6 0 10 20 30 40 50 60 0 0.1 0.2 0.3 0.4 0.5
Liquifiable layer thickness Unliquefiable layer
-1/2Footing width (m) Relative density (%) D (mm)
thickness(m) 50
2
C5 D1 D2
1.5
Factor
1
0.5
0 0 1 2 3 4 5 -20 0 20 40 60
0 0.5 1 1.5 2
FL Footing width (m) Additional pressure (kPa)
Figure 2: Deviating factors obtained a series of centrifuge tests
It should be noted that, a more accurate estimation of the settlement requires an additional, extensive review of
the field observations and an effort is currently being made for refining the proposed method, which will be
presented in the near future.
After examining the factors which govern the footing settlement, the authors conducted another series of
dynamic centrifuge tests to examine the effectiveness of three methods for reducing the settlement of the
2 2441
3. Plate connected to each footing Vertical load
Isolated footing Circular laminar box
A10
A6
86
P14
55
P7 A9 P13
350
A4
210
100
P3
55 P1
Toyoura sand Toyoura sand
Pore fluid pressure transducers 400
Accelerometers P14 Installed only for model D (with sheet piles)
Displacement transducers Unit : mm
(a) PLAN (b) SECTION
Figure 3: Schematic figure of centrifuge model
footings. The results obtained from the second series of tests are presented in this paper. It should be noted
that countermeasures for reducing the settlement considered in this paper are for already existing isolated tower
footings, rather than for newly constructed footings.
MODEL DESIGNS AND TEST PROCEDURES
The details of the centrifuge machine used in this study were described by Nagura et al. [3]. The machine has
an effective radius of 2.65 m and has an electrohydraulic servo-controlled shaking table designed for conducting
dynamic tests. A centrifugal acceleration of 50 g was applied to a 1/50 model (here, ‘g’ denotes gravity).
Figure 3 shows a schematic figure of the centrifuge setup designed for the study. Four independent footings,
which support a transmission tower, were modeled. The model shown in the figure corresponds to ‘Model C’ in
this paper (see Figure 4 in the next section). A circular laminar box with an inside diameter of 400 mm was
used as the soil box. The material of the model footing was made by mixing cement, sand and iron powder.
The width of the model footing was 50 mm (2.5 m at prototype scale) and a weight of 18.3 tons per footing at
prototype scale was applied vertically. The distance between two footings in the model was set at 100 mm (5.0
m). Toyoura sand with a height of 350 mm (17.5 m) was used as a soil sample. The properties of Toyoura
sand are summarized in Table 1.
Table 1: Properties of Toyoura sand
Density of soil particle (g/cm3) Maximum density (g/cm3) Minimum density (g/cm3) Mean grain size (mm)
2.661 1.654 1.349 0.162
Dry Toyoura sand was first poured into the soil box. After placing four model footings on the sand and placing
the surface sand at the prescribed level, the sand was saturated with silicon oil with a viscosity 50 times higher
than that of water. The relative density of the soil was set at about 40-45 % prior to the shaking. Before
starting the main shaking test, the model was spun to observe the initial settlement due to a centrifugal
acceleration of 50 g. The test models with and without countermeasures for reducing the settlement are shown
in Figure 4. The models tested were:
Model A: Without any countermeasures.
Model B: Connecting the base of all footings by a concrete plate.
Model C: Connecting the four footings by a concrete plate at ground surface level.
3 2441
4. 10.5 m
Concrete Plate Concrete Plate Concrete Plate
Isolated footing 10.5 m Sheet piles
(Type III)
4.3 m
Concrete plate
(t = 150 mm)
Model A Model B Model C Model D
(no countermeasure) (Base plate) (Surface plate) (Surface plate + Sheet piles)
Figure 4: Countermeasures modeled in the study
Model D: In addition to connecting the four footings by a concrete plate at ground surface level, as in Model
C, the footings were surrounded by sheet pile walls.
The models A and B were tested and reported by Sakemi et al [4]. The base and surface plates in the models
were made by plastic plate with a thickness of 5 mm, which corresponds to a concrete plate of about 150 mm at
prototype scale. Sandpaper was attached on the surface of the plastic plate to create a rough surface. The
model B was thought to be the most effective as the four footings behave as one single foundation with respect
to the soil above the base plate. However, constructing such a base plate of footings of already existing towers
during the tower operation is not only difficult but may also be unrealistic.
Other two models C and D were proposed as feasible alternatives to the model B. A photograph of model C is
shown in Figure 5. In both models C and D, the plate connecting the four isolated footings was attached at the
ground surface level, which is not only much easier but is, also, more economic. It was considered that the use
of a surface plate would reduce the stress transferred to the isolated footings as the plate itself would provide
additional resistance against settlement of the tower. Model D is similar to model C but in addition to the
surface plate, sheet pile walls were placed around the four footings. The bending rigidity of the sheet piles was
set equivalent to Type III sheet piles in Japan.
The above models were excited by a sinusoidal horizontal wave with 20 cycles at 50 Hz which is equivalent to
20 cycles at 1 Hz for the prototype model. The motion shown in Figure 6 was applied to the base of the model.
The peak acceleration corresponding to the motion was set at 4.5 g at model scale (90 gal at prototype scale).
During the tests, pore fluid pressure, acceleration and the settlement of the soil surface were measured as well as
the settlement of the model footing. The locations of the transducers are shown in Figure 3.
TEST RESULTS
Acceleration Response:
The observed acceleration responses for the models A and C are compared in Figures 7 to 9. Figure 7 shows the
response of the accelerometer A10 (at the soil surface, see Figure 3), Figure 8 shows the response of A9 (on soil
below near the center of the model), and Figure 9 shows the response of A6 (in the model footing). In all three
figures, the acceleration response did not fade away right up to the end of the shaking even though the soil
liquefied significantly.
100
Input Acc. (gal)
50
0
-50
-100
0 10 20 30 40
Time (sec.)
Figure 5: Photograph of Model C Figure 6: Input acceleration
4 2441
5. 200
Acceleration (gal)
200
Acceleration (gal)
Model A Model C
100 100
0 0
-100 -100
-200 -200
0 10 20 30 40 0 10 20 30 40
Time (sec) Time (sec)
Figure 7: Acceleration response observed at soil surface (Models A & C, A10)
200
Acceleration (gal)
200
Acceleration (gal)
Model A Model C
100 100
0 0
-100 -100
-200 -200
0 10 20 30 40 0 10 20 30 40
Time (sec) Time (sec)
Figure 8: Acceleration response observed below the center of footing (Models A & C, A9)
Acceleration (gal)
200
Acceleration (gal)
200 Model A Model C
100 100
0 0
-100 -100
-200 -200
0 10 20 30 40 0 10 20 30 40
Time (sec) Time (sec)
Figure 9: Acceleration response in the model footing (Models A & C, A6)
Figures 7 and 8 show clearly the difference between the acceleration responses of models A and C. The
response of the model D was close to that of the model C. The magnitude of the acceleration of model A was
higher than those observed in the other three models, and the response of model A was also more complex. Since
each footing was set independently in model A, the acceleration response of the four footings was considered not
to be completely the same, and this might influence the acceleration response of the soil around the model. It
was also considered that, models B, C, and D, in which the four footings were connected together, behaved as a
single unit, which could lead to a much higher effective mass in these models than in model A.
-50 0
Settlement ratio to Model A
0 Model B
Settlement (mm)
Model B 0.2
50
100 0.4
Model D Model D
150 0.6
200 Model C 0.8 Model C
250 Model A
300 1
0 200 400 600 800 1000 0 200 400 600 800 1000
Time (sec.) Time (sec.)
(a) Observed settlement at prototype scale (b) Settlement ratio to Model A
Figure 10: Settlement of model footings
Settlement
Figure 10 and Table 2 summarize the settlement of the models during and after the shaking at prototype scale.
The settlement shown in the figures and the table is the average of the four footings settlements. In the figure,
only the initial 20 seconds corresponds to the shaking period, i.e. the settlement continued after the shaking.
The following observations can be made from Figure 10:
As expected, model B, in which the connecting plate was attached at the base of the footings, was the most
effective way of reducing the settlement. The final settlement measured in model B was as low as 80 mm,
compared with that of 250 mm in model A (without countermeasure), i.e. the settlement reduced by about
70 %. The settlement during the shaking period itself was significantly smaller in model B than those
5 2441
6. observed in the other models. An explanation of this behavior is the much smaller pore fluid pressure ratio
beneath the model, as shown later in this paper.
Although the measured settlements of models C and D were larger than that of model B, their settlements
were about 2/3 of that of model A, i.e. the settlement was reduced by about 30 % by connecting the four
independent footings at the ground surface level.
The results of the tests in this study showed the effect of the surrounding sheet piles on the settlement to be
small. The final settlement in model D was about 61% of model A. It was considered that the relatively
short length of the sheet piles used in model D could be the reason for the small difference in the final
settlements of models C and D.
Table 2: Settlement of model footings
Model Relative Maximum Settlement Final settlement
Density input during Footing Soil surface
(%) acceleration shaking (mm) (mm)
(gal) (mm)
A: Without any countermeasures 39.6 91 200 250 Not measured
B: Base plate 43.7 93 75 75 80
C: Surface plate 45.5 88 70 174 81
D: Surface plate + Sheet piles 45.1 86 64 154 55
Input acceleration and settlement are shown at prototype scale
Pore Fluid Pressure
The pore fluid pressure responses of the four models at various locations are shown in Figure 11. The figures
show that the rate of increase in the pore fluid pressure to be relatively slower in models A and B compared to
models C and D. This difference in behavior was considered to be the result of the slight difference in the shape
of the created input motions. The following observations can be made from the figures:
・ As shown later, the excess pore fluid ratio outside the influenced area seemed to increase close to unity,
indicating that the soil in this area liquefied significantly.
・ Although the instrumented depths for transducers P7 and P13 were the same, the increase in the excess
pore fluid pressure was smaller for P7 in the models C and D. In the case of model B, the rate of increase
in the pore fluid pressure was slightly slower compared with the other models. This might be related to
the very small settlement of the footing during and after the shaking, which was caused by higher confining
pressure.
・ The increase in the pore fluid pressure for P14 in model D was considerably small. This may be as a result
of the sheet pile walls around the model footing which prevented an increase.
Figure 12 shows the pore fluid pressure ratio at a depth just beneath the model footing for models A, B and D.
The effective overburden pressure was estimated by using Boussinesq solution. Note that, for model D, the
150 Shaking period Model A Shaking period Model B
150
120 P1 120 P1
Ex. PFP (kPa)
Ex. PFP (kPa)
90 P3 90
P3
60 60
30 P7 P7 & P13
30
0 0
0 20 40 60 80 100 0 20 40 60 80 100
Time(Sec.) Time (sec)
(a) Model A (b) Model B
150 Shaking period Shaking Period Model D
Model C 150
120 P1 120 P1
Ex. PFP (kPa)
Ex. PFP (kPa)
90 P3 90 P3
60 P13 60 P14
30 P13
P7 30 P7
0 0
0 20 40 60 80 100 0 20 40 60 80 100
Time (sec.) Time (sec.)
(c) Model C (d) Model D
Figure 11: Pore fluid pressure response observed for Models A - D
6 2441
7. effects of the load transferred directly from the surface plate
were ignored for simplicity in calculating the initial 1 Model A
overburden pressure. The peak pressure ratio for model A Model B
0.8 Model D
PFP ratio
(without any countermeasures) was close to unity and model B
0.6
shows the lowest value of about 0.5. Figure 12 clearly shows
that the lower the pore fluid pressure ratio below the model 0.4
footings was, the smaller the footing settlement became. 0.2
0
It is also very important to relate the pore fluid pressure 0 500 1000 1500
response with the observed settlement behavior. The Time(sec.)
distribution of pore fluid pressure around the model footing Figure 12: Pore fluid pressure ratio observed
just after the shaking is drawn for each model in Figure 13. beneath the model footings
The corresponding pressure ratio is also drawn in Figure 14.
A point of caution regarding these figures, the contours were
created from a limited number of pressure transducer readings so that the profiles far from the location of the
transducers might not be correct. The small circles shown in the figures indicate the location of the pore
pressure transducers. Figure 12 indicates that in all four models the soil near the bottom of the box liquefied
significantly. The magnitude of the pore fluid pressure ratio of model B in Figure 14 can be seen to be very
small due to the effects of the load transferred through the base plate of the model. The pore pressure ratios for
models C and D showed a more centered area with a low ratio as there was significant load transfer through the
connecting plate at the surface.
The distribution of pore fluid pressure ratio when the settlement increase rate decreased is shown in Figure 15.
During these tests, it was found that, after the pore fluid pressure ratio decreased to about 0.6 - 0.7, there was a
x100 kPa
(a) Model A (b) Model B (c) Model C (d) Model D
Figure 13: Contour of pore fluid pressure just after the end of shaking
(a) Model A (b) Model B (c) Model C (d) Model D
Figure 14: Contour of pore fluid pressure ratio just after the end of shaking
7 2441
8. (a) Model A (b) Model B (c) Model D
Figure 15: Contour of pore fluid pressure ratio when the degree of settlement increase dropped
decrease in the rate at which settlement increased. This trend was consistently observed throughout all the tests
including the first series in this study.
CONCLUSIONS
A series of dynamic centrifuge tests were conducted on isolated foundations of power transmission towers to
examine the effectiveness of countermeasures against the settlement due to liquefaction. Three types of
countermeasures were tested: in the first the four footings were connected at base level, in the second the
connection was made at ground surface level and in the third the footings were connected at ground surface level
and in addition sheet piles were installed around the footings. The following conclusions were drawn:
1. The most effective method of reducing the settlement of the footing was to connect the four footings at
base level. The settlement was reduced by as much as 70 % compared to the case without any
countermeasures. In this method, the soil inside the four footings possibly behaved as one unit together
as like one large footing, and the pressure transferred to the soil beneath the plates worked effectively to
reduce the pore fluid ratios in the soil.
2. Even using a method to connect four footings at ground surface level can reduce the settlement by about
30 %. This was because the surface plate could be a resistant structure against the settlement, and thus
the load transferred to the soil through the footings reduced. The pore fluid pressure ratios inside the
four footings might also be smaller, which led to the model behavior more likely as a unit together with
sand.
3. Under the testing conditions in this paper, the effects of the sheet piles on the settlement reduction were
small. It may be necessary to examine the effects of the length of the sheet piles on the settlement.
4. Considering actual site conditions which are generally seen in Japan, the existence of an unliquefiable
layer at the soil surface may influence the settlement behavior, especially when a surface plate is used
as a countermeasure as used in models C and D. These effects will also be examined in the next stage.
ACKNOWLEDGEMENTS
The authors would like to express sincere appreciation to Mr. T. Fujiwara of Taisei Corporation for his great
assistance during the tests. This study was organized by the Association for Development of Earthquake
Prediction. The authors also would like to express sincere appreciation to the members in the committee for the
fruitful discussions and suggestions.
REFERENCES
1. Kawasaki, K. Sakai, T., Yasuda, S. and Satoh, M. (1998), “Earthquake-induced settlement of an isolated footing for power
transmission tower”, Proc. Centrifuge 98, Tokyo, Balkema, pp271-276.
2. Kawasaki, K. et al. (1996), “Dynamic centrifuge modeling of an isolated footing for transmission line tower”, Proc. 6th Japan –
US Workshop on Earthquake Resistant Design of Lifeline Facilities and Countermeasures against Soil Liquefaction, pp243-258.
3. Nagura, K., Tanaka, M., Kawasaki, K. and Higuchi, Y. (1994), “Development of an earthquake simulator for the TAISEI
centrifuge, Proc. Centrifuge 94, Singapore, Balkema, pp151-156.
4. Sakemi, T., Sakai, T., Satoh, M. and Yasuda, S. (1998), ‘Centrifuge modeling of power transmission tower Part 4 (Four footings
model)’, Proc. Annual Convention, JSCE, III-A181, pp360-361 (in Japanese).
8 2441