Highlights:
* National governments should promote energy-efficient components and provide incentives for energy-efficient measures.
* A European specification for a range of energy-efficient transformers is needed.
* The feasibility to get one EU specification should be studied.
Energy-efficient transformers should be promoted through education of customers.
* An energy-efficient transformer should be given a sensational name.
Origens do colecionismo (Século XVI). Fatores que influenciaram a criação de museus no Século XIX. O Século XIX no Brasil. A relação entre Positivismo e musealidade. Os primeiros museus do Século XIX, no exterior e no Brasil e suas coleções.
As power factor falls below unity the current
in the system increases with the following effects: I
2R power
loss increases in cables and windings leading to overheating
and consequent reduction in equipment life; cost incurred by
power company increases and efficiency as a whole suffers
because more of the input is absorbed in meeting losses.
Distribution losses cost the utilities a very big amount of profit
and reduce life of equipment. The system is considered as
efficient when the loss level is low. So, attempts at power loss
minimization in order to reduce electricity cost, and improve
the efficiency of distribution systems are continuously made.
This paper investigates the losses in a 34-bus distribution
system and how the installation of capacitors at some points in
the system can significantly reduce losses in circuits and cables,
ensure that the rated voltage is applied to motors, lamps, etc, to
obtain optimum performance, ensure maximum power output
of transformers is utilized and not used in making-up losses,
enables existing transformers to carry additional load without
overheating or the necessity of capital cost of new
transformers, and achieve the financial benefits which will
result from lower maximum demand charges
Fea of pcb multilayer stack up high voltage planar transformer for aerospace...elelijjournal
High voltage planar transformer is a technology which can replace conventional transformer with its distinct advantages of saturation and cost efficiency. This paper includes, study and solution methods for PCB winding configuration in planar magnetic elements with multilayer
stack up of PCB Cu-tracks, producing High voltage power supply for aerospace application.With finite element analysis (FEA) simulations, different simulation outcomes are discussed for inspecting flux intensity and current density distribution with computing Electric field strength
and Magnetic fields. In principal conclusion of study, complete analysis and some practical design guidelines for
multilayer PCB stack up are discussed in this paper.
Influence choice of the injection nodes of energy source on on-line losses of...IJMER
International Journal of Modern Engineering Research (IJMER) is Peer reviewed, online Journal. It serves as an international archival forum of scholarly research related to engineering and science education.
International Journal of Modern Engineering Research (IJMER) covers all the fields of engineering and science: Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Computer Engineering, Agricultural Engineering, Aerospace Engineering, Thermodynamics, Structural Engineering, Control Engineering, Robotics, Mechatronics, Fluid Mechanics, Nanotechnology, Simulators, Web-based Learning, Remote Laboratories, Engineering Design Methods, Education Research, Students' Satisfaction and Motivation, Global Projects, and Assessment…. And many more.
Harmonic enhancement in microgrid with applications on sensitive loadsIJECEIAES
Power quality issues are an important and growing problem in microgrid. There are two reasons; the more active consumer is participating in the power sector, the use of renewable energy which having a great impact on voltage variation. This paper discusses power quality disturbance and especially harmonic distortion issues in microgrid, and suggests a solution to maintain the operation of the distribution system within power quality standard. To protect sensitive loads from harmonics produced by the grid and by renewable energy sources, passive harmonic filter has been proposed in this paper. The electrical system of a nuclear research reactor as sensitive loads is designed by using Electrical Transient Analyzer Program (ETAP) software. The results show these technical issues are presented with their influence on electrical voltage and harmonic specter.
Origens do colecionismo (Século XVI). Fatores que influenciaram a criação de museus no Século XIX. O Século XIX no Brasil. A relação entre Positivismo e musealidade. Os primeiros museus do Século XIX, no exterior e no Brasil e suas coleções.
As power factor falls below unity the current
in the system increases with the following effects: I
2R power
loss increases in cables and windings leading to overheating
and consequent reduction in equipment life; cost incurred by
power company increases and efficiency as a whole suffers
because more of the input is absorbed in meeting losses.
Distribution losses cost the utilities a very big amount of profit
and reduce life of equipment. The system is considered as
efficient when the loss level is low. So, attempts at power loss
minimization in order to reduce electricity cost, and improve
the efficiency of distribution systems are continuously made.
This paper investigates the losses in a 34-bus distribution
system and how the installation of capacitors at some points in
the system can significantly reduce losses in circuits and cables,
ensure that the rated voltage is applied to motors, lamps, etc, to
obtain optimum performance, ensure maximum power output
of transformers is utilized and not used in making-up losses,
enables existing transformers to carry additional load without
overheating or the necessity of capital cost of new
transformers, and achieve the financial benefits which will
result from lower maximum demand charges
Fea of pcb multilayer stack up high voltage planar transformer for aerospace...elelijjournal
High voltage planar transformer is a technology which can replace conventional transformer with its distinct advantages of saturation and cost efficiency. This paper includes, study and solution methods for PCB winding configuration in planar magnetic elements with multilayer
stack up of PCB Cu-tracks, producing High voltage power supply for aerospace application.With finite element analysis (FEA) simulations, different simulation outcomes are discussed for inspecting flux intensity and current density distribution with computing Electric field strength
and Magnetic fields. In principal conclusion of study, complete analysis and some practical design guidelines for
multilayer PCB stack up are discussed in this paper.
Influence choice of the injection nodes of energy source on on-line losses of...IJMER
International Journal of Modern Engineering Research (IJMER) is Peer reviewed, online Journal. It serves as an international archival forum of scholarly research related to engineering and science education.
International Journal of Modern Engineering Research (IJMER) covers all the fields of engineering and science: Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Computer Engineering, Agricultural Engineering, Aerospace Engineering, Thermodynamics, Structural Engineering, Control Engineering, Robotics, Mechatronics, Fluid Mechanics, Nanotechnology, Simulators, Web-based Learning, Remote Laboratories, Engineering Design Methods, Education Research, Students' Satisfaction and Motivation, Global Projects, and Assessment…. And many more.
Harmonic enhancement in microgrid with applications on sensitive loadsIJECEIAES
Power quality issues are an important and growing problem in microgrid. There are two reasons; the more active consumer is participating in the power sector, the use of renewable energy which having a great impact on voltage variation. This paper discusses power quality disturbance and especially harmonic distortion issues in microgrid, and suggests a solution to maintain the operation of the distribution system within power quality standard. To protect sensitive loads from harmonics produced by the grid and by renewable energy sources, passive harmonic filter has been proposed in this paper. The electrical system of a nuclear research reactor as sensitive loads is designed by using Electrical Transient Analyzer Program (ETAP) software. The results show these technical issues are presented with their influence on electrical voltage and harmonic specter.
Enhancing Energy Efficiency of Distribution Transformers through Energy Conse...Premier Publishers
This paper describes the various options of energy conservation methods to enhance the energy efficiency of transformers. The energy economics of using low loss core is also studied and given the results in this paper. The load management of distribution transformers have reduced the energy losses considerably in industries. In this paper, a detailed computer based evaluation of energy losses due to off-design operation and size mismatch of transformers, unbalanced secondary load, low power factor on the secondary are discussed for thermal power stations and process industries. Automation of transformer management is described as it can lead to considerable saving in energy. The energy conservation measures for distribution transformers have reduced the transformer losses by 10 – 15 % in industries.
In electrical engineering terminology, transformers are regarded as electrical machines, although they only convert one form of electricity into another form of electricity. Due to this relatively simple function, among other reasons, their losses are lower than those of any equipment converting electricity into some other form of energy. They are probably the most efficient machines ever devised by man.
Transformer efficiencies are around 80% for very small units used in domestic appliances and nearly 99% at the level of distribution networks. The efficiency further increases with increasing unit power rating. The largest units achieve efficiencies of up to 99.75% at rated load and even 99.8% at half load. At first glance, it looks rather unlikely that there is any savings potential left that would be commercially significant, but in fact there is.
It is true that the payback periods are fairly long, but a transformer has a lifetime expectancy of well over 40 years and the majority of all transformers are operated continuously at a high degree of loading. As a result, an improved transformer design, primarily through the use of more active material, will usually pay off several times over the lifespan of the transformer.
ethodology for determining the parameters of hightemperature superconducting...IJECEIAES
This paper substantiates a new adaptive method for determining parameters of high-temperature superconducting power transformers with current limiting function. The main focus is the design of current-limiting superconducting windings in the light of new restrictions on current density, magnetic induction, critical current and critical temperature. The presented method considers the nature of alternating current (AC) losses in a superconductor under nominal operating conditions, features of the dielectric medium (liquid nitrogen), as well as the reduced values of the short-circuit voltage (0.5 to 1.5%). The main design features of high-temperature superconducting (HTS) transformers are specified, and a prototype of a three-phase HTS transformer of 63 kVA with a short-circuit current limiting function is developed. It is shown that HTS units have some advantages over conventional transformers: a 90 to 95% active losses reduction, short-circuit current limitation function, explosion and fire safety, a 60% reduction in weight and size, and increased efficiency (up to 99.8%). Experimental studies confirm that the short-circuit current limitation function is safe and efficient. It is demonstrated that during the short-circuit current limitation, significant heat flows occur on the windings, which should not exceed the critical value above which the superconductor could not return to the superconducting state by itself.
IJRET : International Journal of Research in Engineering and Technology is an international peer reviewed, online journal published by eSAT Publishing House for the enhancement of research in various disciplines of Engineering and Technology. The aim and scope of the journal is to provide an academic medium and an important reference for the advancement and dissemination of research results that support high-level learning, teaching and research in the fields of Engineering and Technology. We bring together Scientists, Academician, Field Engineers, Scholars and Students of related fields of Engineering and Technology
PROJECT DESCRIPTION
DOWNLOAD
The main objective of this project is to develop a device for wireless power transfer. The concept of wireless power transfer was realized by Nikolas tesla. Wireless power transfer can make a remarkable change in the field of the electrical engineering which eliminates the use conventional copper cables and current carrying wires.
Based on this concept, the project is developed to transfer power within a small range. This project can be used for charging batteries those are physically not possible to be connected electrically such as pace makers (An electronic device that works in place of a defective heart valve) implanted in the body that runs on a battery.
The patient is required to be operated every year to replace the battery. This project is designed to charge a rechargeable battery wirelessly for the purpose. Since charging of the battery is not possible to be demonstrated, we are providing a DC fan that runs through wireless power.
This project is built upon using an electronic circuit which converts AC 230V 50Hz to AC 12V, High frequency. The output is fed to a tuned coil forming as primary of an air core transformer. The secondary coil develops a voltage of HF 12volt.
Thus the transfer of power is done by the primary(transmitter) to the secondary that is separated with a considerable distance(say 3cm). Therefore the transfer could be seen as the primary transmits and the secondary receives the power to run load.
Moreover this technique can be used in number of applications, like to charge a mobile phone, iPod, laptop battery, propeller clock wirelessly. And also this kind of charging provides a far lower risk of electrical shock as it would be galvanically isolated.
Optimal Placement of Distributed Generation on Radial Distribution System for...IJMER
International Journal of Modern Engineering Research (IJMER) is Peer reviewed, online Journal. It serves as an international archival forum of scholarly research related to engineering and science education.
International Journal of Modern Engineering Research (IJMER) covers all the fields of engineering and science: Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Computer Engineering, Agricultural Engineering, Aerospace Engineering, Thermodynamics, Structural Engineering, Control Engineering, Robotics, Mechatronics, Fluid Mechanics, Nanotechnology, Simulators, Web-based Learning, Remote Laboratories, Engineering Design Methods, Education Research, Students' Satisfaction and Motivation, Global Projects, and Assessment…. And many more.
TCSC AND SVC OPTIMAL LOCATION TO IMPROVE THE PERFORMANCE OF POWER SYSTEM WITH...eeiej_journal
Wind generation connection to power system affects steady state and transient stability. Furthermore, this
effect increases with the increase of wind penetration in generation capacity. In this paper optimal location
of FACTS devices is carried out to solve the steady state problems of wind penetration. Two case studies
are carried out on modified IEEE39 bus system one with wind reduction to 20% and the second with wind
penetration increase by 50% in the two cases system suffer from outage of one generator with load at bus
39 decreases from 1104 MW to 900 MW.
PROJECT DESCRIPTION
DOWNLOAD
The main objective of this project is to develop a device for wireless power transfer. The concept of wireless power transfer was realized by Nikolas tesla. Wireless power transfer can make a remarkable change in the field of the electrical engineering which eliminates the use conventional copper cables and current carrying wires.
Based on this concept, the project is developed to transfer power within a small range. This project can be used for charging batteries those are physically not possible to be connected electrically such as pace makers (An electronic device that works in place of a defective heart valve) implanted in the body that runs on a battery.
The patient is required to be operated every year to replace the battery. This project is designed to charge a rechargeable battery wirelessly for the purpose. Since charging of the battery is not possible to be demonstrated, we are providing a DC fan that runs through wireless power.
This project is built upon using an electronic circuit which converts AC 230V 50Hz to AC 12V, High frequency. The output is fed to a tuned coil forming as primary of an air core transformer. The secondary coil develops a voltage of HF 12volt.
Thus the transfer of power is done by the primary(transmitter) to the secondary that is separated with a considerable distance(say 3cm). Therefore the transfer could be seen as the primary transmits and the secondary receives the power to run load.
Moreover this technique can be used in number of applications, like to charge a mobile phone, iPod, laptop battery, propeller clock wirelessly. And also this kind of charging provides a far lower risk of electrical shock as it would be galvanically isolated.
MITIGATING ELECTRICAL DISTURBANCES WITH HYBRID DISTRIBUTION TRANSFORMERijscmcj
Hybrid transformers (HT) have the advantages of the conventional transformer, the regulatory abilities of
power electronic converters, and reduce the impact of the grid. The impacts of the existing grid are
voltage sag, voltage swell, harmonic distortion, and voltage unbalanced. The power electronic converter
has a controllable advantage such as regulating the voltage and can transfer only a fraction of the power.
The aim of the paper is to augment the conventional power distribution transformer with a partially rated
power electronic module to enhance flexibility and introduce new features to the distribution transformer.
In this paper, the proposed back-to-back converter included an active front rectifier and a modular
multilevel converter (MMC) was simulated by MATLAB/Simulink software. The proposed back-to-back
converter was used at the primary side of the distribution transformer to compensate for the voltage sag
and swell issues. The simulation results were obtained under different conditions such as various supply
voltages and various loads. Hence, the proposed system has the ability to regulate the output voltage
under various conditions with ±10%.
Electrical Engineering: An International Journal (EEIJ)ijccmsjournal
Hybrid transformers (HT) have the advantages of the conventional transformer, the regulatory abilities of
power electronic converters, and reduce the impact of the grid. The impacts of the existing grid are
voltage sag, voltage swell, harmonic distortion, and voltage unbalanced. The power electronic converter
has a controllable advantage such as regulating the voltage and can transfer only a fraction of the power.
The aim of the paper is to augment the conventional power distribution transformer with a partially rated
power electronic module to enhance flexibility and introduce new features to the distribution transformer.
In this paper, the proposed back-to-back converter included an active front rectifier and a modular
multilevel converter (MMC) was simulated by MATLAB/Simulink software. The proposed back-to-back
converter was used at the primary side of the distribution transformer to compensate for the voltage sag
and swell issues. The simulation results were obtained under different conditions such as various supply
voltages and various loads. Hence, the proposed system has the ability to regulate the output voltage
under various conditions with ±10%.
MITIGATING ELECTRICAL DISTURBANCES WITH HYBRID DISTRIBUTION TRANSFORMERijscmcj
Hybrid transformers (HT) have the advantages of the conventional transformer, the regulatory abilities of
power electronic converters, and reduce the impact of the grid. The impacts of the existing grid are
voltage sag, voltage swell, harmonic distortion, and voltage unbalanced. The power electronic converter
has a controllable advantage such as regulating the voltage and can transfer only a fraction of the power.
The aim of the paper is to augment the conventional power distribution transformer with a partially rated
power electronic module to enhance flexibility and introduce new features to the distribution transformer.
In this paper, the proposed back-to-back converter included an active front rectifier and a modular
multilevel converter (MMC) was simulated by MATLAB/Simulink software. The proposed back-to-back
converter was used at the primary side of the distribution transformer to compensate for the voltage sag
and swell issues. The simulation results were obtained under different conditions such as various supply
voltages and various loads. Hence, the proposed system has the ability to regulate the output voltage
under various conditions with ±10%
A Novel Approach of Harmonic Reduction with Transformer Connected 3-Phase Mul...IJMER
This paper proposes a multilevel inverter arrangement employing a series connected transformer to suppress 5th,7th,11th &13th order harmonics(generated by non-linear loads).In the proposed scheme sinusoidal pwm signal generation technique is used for three phase multilevel VSI in conjunction with series connected transformer .The proposed model eliminates the need of output filter inductor. With this control strategy harmonic components of output voltage and switching losses can be
minimized considerably. Simulation results verify the proposed concept and indicates that the transformer is capable of reducing the harmonics in the line
The conventional transformer in power infrastructure should be capable of meeting the demand for the load. The conventional transformer is structured and designed to handle high power. Also, the overload capacity of conventional transformers depends on the highest temperature and short-term overload. This paper represents the construction and working of the solid-state transformer which consists of AC to DC and DC to AC conversion which has low overload capability as compared to conventional transformers. Solid-state transformer finding applications in Solar and wind power generation electric vehicle battery management systems because of high-frequency operation, which is not possible in case of conventional transformers also smart transformer, provides flexible control of electric power distribution.
Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...IJAPEJOURNAL
Frequency dependence complete model is set up for describing the lightning transient behavior of the wind turbines (WTs).To get an appropriate wind turbine model, a high frequency models of surge arrester protecting the boost transformer, transformer and ground electrode soil ionization are implemented. The transient responses and Ground Potential Rise (GPR) can be obtained at different locations in the WTs and connected grid in the time domain as well as in the frequency domain using Fast Fourier Transform (FFT). To check the validity of the model, Surge arresters protection level at different locations, at i.e. LV, MV and HV, is compared with ABB manufacture data sheet, Also a comparison has been made between simple and frequency dependence model of overall wind farm components using ATP/EMTP. This paper provides an accurate simulation of wind farm components under transient condition.
A new generation of instruments and tools to monitor buildings performanceLeonardo ENERGY
What is the added value of monitoring the flexibility, comfort, and well-being of a building? How can occupants be better informed about the performance of their building? And how to optimize a building's maintenance?
The slides were presented during a webinar and roundtable with a focus on a new generation of instruments and tools to monitor buildings' performance, and their link with the Smart Readiness Indicator (SRI) for buildings as introduced in the EU's Energy Performance of Buildings Directive (EPBD).
Link to the recordings: https://youtu.be/ZCFhmldvRA0
Addressing the Energy Efficiency First Principle in a National Energy and Cli...Leonardo ENERGY
When designing energy and climate policies, EU Member States have to apply the Energy Efficiency First Principle: priority should be given to measures reducing energy consumption before other decarbonization interventions are adopted. This webinar summarizes elements of the energy and climate policy of Cyprus illustrating how national authorities have addressed this principle so far, and outline challenges towards its much more rigorous implementation that is required in the coming years.
More Related Content
Similar to Cost savings by low-loss distribution transformers in wind power plants
Enhancing Energy Efficiency of Distribution Transformers through Energy Conse...Premier Publishers
This paper describes the various options of energy conservation methods to enhance the energy efficiency of transformers. The energy economics of using low loss core is also studied and given the results in this paper. The load management of distribution transformers have reduced the energy losses considerably in industries. In this paper, a detailed computer based evaluation of energy losses due to off-design operation and size mismatch of transformers, unbalanced secondary load, low power factor on the secondary are discussed for thermal power stations and process industries. Automation of transformer management is described as it can lead to considerable saving in energy. The energy conservation measures for distribution transformers have reduced the transformer losses by 10 – 15 % in industries.
In electrical engineering terminology, transformers are regarded as electrical machines, although they only convert one form of electricity into another form of electricity. Due to this relatively simple function, among other reasons, their losses are lower than those of any equipment converting electricity into some other form of energy. They are probably the most efficient machines ever devised by man.
Transformer efficiencies are around 80% for very small units used in domestic appliances and nearly 99% at the level of distribution networks. The efficiency further increases with increasing unit power rating. The largest units achieve efficiencies of up to 99.75% at rated load and even 99.8% at half load. At first glance, it looks rather unlikely that there is any savings potential left that would be commercially significant, but in fact there is.
It is true that the payback periods are fairly long, but a transformer has a lifetime expectancy of well over 40 years and the majority of all transformers are operated continuously at a high degree of loading. As a result, an improved transformer design, primarily through the use of more active material, will usually pay off several times over the lifespan of the transformer.
ethodology for determining the parameters of hightemperature superconducting...IJECEIAES
This paper substantiates a new adaptive method for determining parameters of high-temperature superconducting power transformers with current limiting function. The main focus is the design of current-limiting superconducting windings in the light of new restrictions on current density, magnetic induction, critical current and critical temperature. The presented method considers the nature of alternating current (AC) losses in a superconductor under nominal operating conditions, features of the dielectric medium (liquid nitrogen), as well as the reduced values of the short-circuit voltage (0.5 to 1.5%). The main design features of high-temperature superconducting (HTS) transformers are specified, and a prototype of a three-phase HTS transformer of 63 kVA with a short-circuit current limiting function is developed. It is shown that HTS units have some advantages over conventional transformers: a 90 to 95% active losses reduction, short-circuit current limitation function, explosion and fire safety, a 60% reduction in weight and size, and increased efficiency (up to 99.8%). Experimental studies confirm that the short-circuit current limitation function is safe and efficient. It is demonstrated that during the short-circuit current limitation, significant heat flows occur on the windings, which should not exceed the critical value above which the superconductor could not return to the superconducting state by itself.
IJRET : International Journal of Research in Engineering and Technology is an international peer reviewed, online journal published by eSAT Publishing House for the enhancement of research in various disciplines of Engineering and Technology. The aim and scope of the journal is to provide an academic medium and an important reference for the advancement and dissemination of research results that support high-level learning, teaching and research in the fields of Engineering and Technology. We bring together Scientists, Academician, Field Engineers, Scholars and Students of related fields of Engineering and Technology
PROJECT DESCRIPTION
DOWNLOAD
The main objective of this project is to develop a device for wireless power transfer. The concept of wireless power transfer was realized by Nikolas tesla. Wireless power transfer can make a remarkable change in the field of the electrical engineering which eliminates the use conventional copper cables and current carrying wires.
Based on this concept, the project is developed to transfer power within a small range. This project can be used for charging batteries those are physically not possible to be connected electrically such as pace makers (An electronic device that works in place of a defective heart valve) implanted in the body that runs on a battery.
The patient is required to be operated every year to replace the battery. This project is designed to charge a rechargeable battery wirelessly for the purpose. Since charging of the battery is not possible to be demonstrated, we are providing a DC fan that runs through wireless power.
This project is built upon using an electronic circuit which converts AC 230V 50Hz to AC 12V, High frequency. The output is fed to a tuned coil forming as primary of an air core transformer. The secondary coil develops a voltage of HF 12volt.
Thus the transfer of power is done by the primary(transmitter) to the secondary that is separated with a considerable distance(say 3cm). Therefore the transfer could be seen as the primary transmits and the secondary receives the power to run load.
Moreover this technique can be used in number of applications, like to charge a mobile phone, iPod, laptop battery, propeller clock wirelessly. And also this kind of charging provides a far lower risk of electrical shock as it would be galvanically isolated.
Optimal Placement of Distributed Generation on Radial Distribution System for...IJMER
International Journal of Modern Engineering Research (IJMER) is Peer reviewed, online Journal. It serves as an international archival forum of scholarly research related to engineering and science education.
International Journal of Modern Engineering Research (IJMER) covers all the fields of engineering and science: Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Computer Engineering, Agricultural Engineering, Aerospace Engineering, Thermodynamics, Structural Engineering, Control Engineering, Robotics, Mechatronics, Fluid Mechanics, Nanotechnology, Simulators, Web-based Learning, Remote Laboratories, Engineering Design Methods, Education Research, Students' Satisfaction and Motivation, Global Projects, and Assessment…. And many more.
TCSC AND SVC OPTIMAL LOCATION TO IMPROVE THE PERFORMANCE OF POWER SYSTEM WITH...eeiej_journal
Wind generation connection to power system affects steady state and transient stability. Furthermore, this
effect increases with the increase of wind penetration in generation capacity. In this paper optimal location
of FACTS devices is carried out to solve the steady state problems of wind penetration. Two case studies
are carried out on modified IEEE39 bus system one with wind reduction to 20% and the second with wind
penetration increase by 50% in the two cases system suffer from outage of one generator with load at bus
39 decreases from 1104 MW to 900 MW.
PROJECT DESCRIPTION
DOWNLOAD
The main objective of this project is to develop a device for wireless power transfer. The concept of wireless power transfer was realized by Nikolas tesla. Wireless power transfer can make a remarkable change in the field of the electrical engineering which eliminates the use conventional copper cables and current carrying wires.
Based on this concept, the project is developed to transfer power within a small range. This project can be used for charging batteries those are physically not possible to be connected electrically such as pace makers (An electronic device that works in place of a defective heart valve) implanted in the body that runs on a battery.
The patient is required to be operated every year to replace the battery. This project is designed to charge a rechargeable battery wirelessly for the purpose. Since charging of the battery is not possible to be demonstrated, we are providing a DC fan that runs through wireless power.
This project is built upon using an electronic circuit which converts AC 230V 50Hz to AC 12V, High frequency. The output is fed to a tuned coil forming as primary of an air core transformer. The secondary coil develops a voltage of HF 12volt.
Thus the transfer of power is done by the primary(transmitter) to the secondary that is separated with a considerable distance(say 3cm). Therefore the transfer could be seen as the primary transmits and the secondary receives the power to run load.
Moreover this technique can be used in number of applications, like to charge a mobile phone, iPod, laptop battery, propeller clock wirelessly. And also this kind of charging provides a far lower risk of electrical shock as it would be galvanically isolated.
MITIGATING ELECTRICAL DISTURBANCES WITH HYBRID DISTRIBUTION TRANSFORMERijscmcj
Hybrid transformers (HT) have the advantages of the conventional transformer, the regulatory abilities of
power electronic converters, and reduce the impact of the grid. The impacts of the existing grid are
voltage sag, voltage swell, harmonic distortion, and voltage unbalanced. The power electronic converter
has a controllable advantage such as regulating the voltage and can transfer only a fraction of the power.
The aim of the paper is to augment the conventional power distribution transformer with a partially rated
power electronic module to enhance flexibility and introduce new features to the distribution transformer.
In this paper, the proposed back-to-back converter included an active front rectifier and a modular
multilevel converter (MMC) was simulated by MATLAB/Simulink software. The proposed back-to-back
converter was used at the primary side of the distribution transformer to compensate for the voltage sag
and swell issues. The simulation results were obtained under different conditions such as various supply
voltages and various loads. Hence, the proposed system has the ability to regulate the output voltage
under various conditions with ±10%.
Electrical Engineering: An International Journal (EEIJ)ijccmsjournal
Hybrid transformers (HT) have the advantages of the conventional transformer, the regulatory abilities of
power electronic converters, and reduce the impact of the grid. The impacts of the existing grid are
voltage sag, voltage swell, harmonic distortion, and voltage unbalanced. The power electronic converter
has a controllable advantage such as regulating the voltage and can transfer only a fraction of the power.
The aim of the paper is to augment the conventional power distribution transformer with a partially rated
power electronic module to enhance flexibility and introduce new features to the distribution transformer.
In this paper, the proposed back-to-back converter included an active front rectifier and a modular
multilevel converter (MMC) was simulated by MATLAB/Simulink software. The proposed back-to-back
converter was used at the primary side of the distribution transformer to compensate for the voltage sag
and swell issues. The simulation results were obtained under different conditions such as various supply
voltages and various loads. Hence, the proposed system has the ability to regulate the output voltage
under various conditions with ±10%.
MITIGATING ELECTRICAL DISTURBANCES WITH HYBRID DISTRIBUTION TRANSFORMERijscmcj
Hybrid transformers (HT) have the advantages of the conventional transformer, the regulatory abilities of
power electronic converters, and reduce the impact of the grid. The impacts of the existing grid are
voltage sag, voltage swell, harmonic distortion, and voltage unbalanced. The power electronic converter
has a controllable advantage such as regulating the voltage and can transfer only a fraction of the power.
The aim of the paper is to augment the conventional power distribution transformer with a partially rated
power electronic module to enhance flexibility and introduce new features to the distribution transformer.
In this paper, the proposed back-to-back converter included an active front rectifier and a modular
multilevel converter (MMC) was simulated by MATLAB/Simulink software. The proposed back-to-back
converter was used at the primary side of the distribution transformer to compensate for the voltage sag
and swell issues. The simulation results were obtained under different conditions such as various supply
voltages and various loads. Hence, the proposed system has the ability to regulate the output voltage
under various conditions with ±10%
A Novel Approach of Harmonic Reduction with Transformer Connected 3-Phase Mul...IJMER
This paper proposes a multilevel inverter arrangement employing a series connected transformer to suppress 5th,7th,11th &13th order harmonics(generated by non-linear loads).In the proposed scheme sinusoidal pwm signal generation technique is used for three phase multilevel VSI in conjunction with series connected transformer .The proposed model eliminates the need of output filter inductor. With this control strategy harmonic components of output voltage and switching losses can be
minimized considerably. Simulation results verify the proposed concept and indicates that the transformer is capable of reducing the harmonics in the line
The conventional transformer in power infrastructure should be capable of meeting the demand for the load. The conventional transformer is structured and designed to handle high power. Also, the overload capacity of conventional transformers depends on the highest temperature and short-term overload. This paper represents the construction and working of the solid-state transformer which consists of AC to DC and DC to AC conversion which has low overload capability as compared to conventional transformers. Solid-state transformer finding applications in Solar and wind power generation electric vehicle battery management systems because of high-frequency operation, which is not possible in case of conventional transformers also smart transformer, provides flexible control of electric power distribution.
Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...IJAPEJOURNAL
Frequency dependence complete model is set up for describing the lightning transient behavior of the wind turbines (WTs).To get an appropriate wind turbine model, a high frequency models of surge arrester protecting the boost transformer, transformer and ground electrode soil ionization are implemented. The transient responses and Ground Potential Rise (GPR) can be obtained at different locations in the WTs and connected grid in the time domain as well as in the frequency domain using Fast Fourier Transform (FFT). To check the validity of the model, Surge arresters protection level at different locations, at i.e. LV, MV and HV, is compared with ABB manufacture data sheet, Also a comparison has been made between simple and frequency dependence model of overall wind farm components using ATP/EMTP. This paper provides an accurate simulation of wind farm components under transient condition.
A new generation of instruments and tools to monitor buildings performanceLeonardo ENERGY
What is the added value of monitoring the flexibility, comfort, and well-being of a building? How can occupants be better informed about the performance of their building? And how to optimize a building's maintenance?
The slides were presented during a webinar and roundtable with a focus on a new generation of instruments and tools to monitor buildings' performance, and their link with the Smart Readiness Indicator (SRI) for buildings as introduced in the EU's Energy Performance of Buildings Directive (EPBD).
Link to the recordings: https://youtu.be/ZCFhmldvRA0
Addressing the Energy Efficiency First Principle in a National Energy and Cli...Leonardo ENERGY
When designing energy and climate policies, EU Member States have to apply the Energy Efficiency First Principle: priority should be given to measures reducing energy consumption before other decarbonization interventions are adopted. This webinar summarizes elements of the energy and climate policy of Cyprus illustrating how national authorities have addressed this principle so far, and outline challenges towards its much more rigorous implementation that is required in the coming years.
Auctions for energy efficiency and the experience of renewablesLeonardo ENERGY
Auctions are an emerging market-based policy instrument to promote energy efficiency that has started to gain traction in the EU and worldwide. This presentation provides an overview and comparison of several energy efficiency auctions and derives conclusions on the effects of design elements based on auction theory and on experiences of renewable energy auctions. We include examples from energy efficiency auctions in Brazil, Canada, Germany, Portugal, Switzerland, Taiwan, UK, and US.
A recording of this presentation can be viewed at:
https://youtu.be/aC0h4cXI9Ug
Energy efficiency first – retrofitting the building stock finalLeonardo ENERGY
Retrofitting the building stock is a challenging undertaking in many respects - including costs. Can it nevertheless qualify as a measure under the Energy Efficiency First principle? Which methods can be applied for the assessment and what are the results in terms of the cost-effectiveness of retrofitting the entire residential building stock? How do the results differ for minimization of energy use, CO2 emissions and costs? And which policy conclusions can be drawn?
This presentation was used during the 18th webinar in the Odyssee-Mure on Energy Efficiency Academy on February 3, 2022.
A link to the recording: https://youtu.be/4pw_9hpA_64
How auction design affects the financing of renewable energy projects Leonardo ENERGY
Recording available at https://youtu.be/lPT1o735kOk
Renewable energy auctions might affect the financing of renewable energy (RE) projects. This webinar presents the results of the AURES II project exploring this topic. It discusses how auction designs ranging from bid bonds to penalties and remuneration schemes impact financing and discusses creating a low-risk auction support framework.
This presentation discusses the contribution of Energy Efficiency Funds to the financing of energy efficiency in Europe. The analysis is based on the MURE database on energy efficiency policies. As an example, the German Energy Efficiency Fund is described in more detail.
This is the 17th webinar in the Odyssee-Mure on Energy Efficiency Academy.
Recordings are available on: https://youtu.be/KIewOQCgQWQ
(see updated version of this presentation:
https://www.slideshare.net/sustenergy/energy-efficiency-funds-in-europe-updated)
The Energy Efficiency First Principle is a key pillar of the European Green Deal. A prerequisite for its widespread application is to secure financing for energy efficiency investments.
This presentation discusses the contribution of Energy Efficiency Funds to the financing of energy efficiency in Europe. The analysis is based on the MURE database on energy efficiency policies. As an example, the German Energy Efficiency Fund is described in more detail.
This is the 17th webinar in the Odyssee-Mure on Energy Efficiency Academy.
Recordings are available on: https://youtu.be/KIewOQCgQWQ
Five actions fit for 55: streamlining energy savings calculationsLeonardo ENERGY
During the first year of the H2020 project streamSAVE, multiple activities were organized to support countries in developing savings estimations under Art.3 and Art.7 of the Energy Efficiency Directive (EED).
A fascinating output of the project so far is the “Guidance on Standardized saving methodologies (energy, CO2 and costs)” for a first round of five so-called Priority Actions. This Guidance will assist EU member states in more accurately calculating savings for a set of new energy efficiency actions.
This webinar presents this Guidance and other project findings to the broader community, including industry and markets.
AGENDA
14:00 Introduction to streamSAVE
(Nele Renders, Project Coordinator)
14:10 Views from the EU Commission and the link with Fit-for-55 (Anne-Katherina Weidenbach, DG ENER)
14:20 The streamSAVE guidance and its platform illustrated (Elisabeth Böck, AEA)
14:55 A view from industry: What is the added value of streamSAVE (standardized) methods in frame of the EED (Conor Molloy, AEMS ECOfleet)
14:55 Country experiences: the added value of standardized methods (Elena Allegrini, ENEA, Italy)
The recordings of the webinar can be found on https://youtu.be/eUht10cUK1o
This webinar analyses energy efficiency trends in the EU for the period 2014-2019 and the impact of COVID-19 in 2020 (based on estimates from Enerdata).
The speakers present the overall trend in total energy supply and in final energy consumption, as well as details by sector, alongside macro-economic data. They will explain the main drivers of the variation in energy consumption since 2014 and determine the impact of energy savings.
Speakers:
Laura Sudries, Senior Energy Efficiency Analyst, Enerdata
Bruno Lapillonne, Scientific Director, Enerdata
The recordings of the presentation (webinar) can be viewed at:
https://youtu.be/8RuK5MroTxk
Energy and mobility poverty: Will the Social Climate Fund be enough to delive...Leonardo ENERGY
Prior to the current soaring energy prices across Europe, the European Commission proposed, as part of the FitFor55 climate and energy package, the EU Social Climate Fund to mitigate the expected social impact of extending the EU ETS to transport and heating.
The report presented in this webinar provides an update of the European Energy Poverty Index, published for the first time in 2019, which shows the combined effect of energy and mobility poverty across Member States. Beyond the regular update of the index, the report provides analysis of the existing EU policy framework related to energy and transport poverty. France is used as a case study given the “yellow vest” movement, which was triggered by the proposed carbon tax on fuels.
Watch the recordings of the webinar:
https://youtu.be/i1Jdd3H05t0
Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?Leonardo ENERGY
This policy brief analyzes the main interacting mechanisms between the Energy Efficiency Directive (EED) and the EU Emission Trading Scheme (ETS). It presents a detailed top-down approach, based on the ODYSSEE energy indicators, to identify energy savings from the EU ETS.
The main task consists in isolating those factors that contribute to the change in energy consumption of industrial branches covered by the EU ETS, and the energy transformation sector (mainly the electricity sector).
Speaker:
Wolfgang Eichhammer (Head of the Competence Center Energy Policy and Energy Markets @Fraunhofer Institute for Systems and Innovation Research ISI)
The recordings of this webinar can be watched via:
https://youtu.be/TS6PxIvtaKY
Energy efficiency, structural change and energy savings in the manufacturing ...Leonardo ENERGY
The first part of the presentations presents the energy efficiency improvements in the manufacturing sector since 2000, and the role of structural change between the different branches and energy savings. It will compare the improvements in Denmark and other countries with EU average. This part is based on ODYSSEE data.
The second part of the presentation presents the development in Denmark in more detail, and it will compare the energy efficiency improvement, corrected for structural change, with the reported savings from the Energy Efficiency Obligation Scheme.
Recordings of the live webinar are on https://youtu.be/VVAdw_CS51A
Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)Leonardo ENERGY
This policy brief looks at questions ‘how to measure energy sufficiency’, ‘which policies and measures can be used to address energy sufficiency’ and ‘how they are used in Europe today’.
Energy sufficiency refers to a situation where everyone has access to the energy services they need, whilst the impacts of the energy system do not exceed environmental limits. The level of ambition needed to address energy sufficiency is higher than in the case of energy efficiency.
This is the 13th edition of the Odyssee-Mure on Energy Efficiency Academy, and number 519 in the Leonardo ENERGY series. The recording of the live presentation can be found on https://www.youtube.com/watch?v=jEAdYbI0wDI&list=PLUFRNkTrB5O_V155aGXfZ4b3R0fvT7sKz
The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...Leonardo ENERGY
The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Product Efficiency Call to Action, by Melanie Slade - IEA and Nicholas Jeffrey - UK BEIS
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
HEAP SORT ILLUSTRATED WITH HEAPIFY, BUILD HEAP FOR DYNAMIC ARRAYS.
Heap sort is a comparison-based sorting technique based on Binary Heap data structure. It is similar to the selection sort where we first find the minimum element and place the minimum element at the beginning. Repeat the same process for the remaining elements.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
We have compiled the most important slides from each speaker's presentation. This year’s compilation, available for free, captures the key insights and contributions shared during the DfMAy 2024 conference.
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSveerababupersonal22
It consists of cw radar and fmcw radar ,range measurement,if amplifier and fmcw altimeterThe CW radar operates using continuous wave transmission, while the FMCW radar employs frequency-modulated continuous wave technology. Range measurement is a crucial aspect of radar systems, providing information about the distance to a target. The IF amplifier plays a key role in signal processing, amplifying intermediate frequency signals for further analysis. The FMCW altimeter utilizes frequency-modulated continuous wave technology to accurately measure altitude above a reference point.
Cost savings by low-loss distribution transformers in wind power plants
1. 40330000-TDC 03-36488A
Cost savings by low-loss distribution transformers:
the influence of fluctuating loads and energy price on the economic
optimum
Arnhem, September 5, 2003
authors S. Bouwman, J.F. Groeman, W.T.J. Hulshorst
KEMA T&D Consulting
By order of European Copper Institute
authors: S. Bouwman, W.T.J. Hulshorst reviewed: J.F. Groeman
B 38 pages 1 annex PSK approved: J. Knijp
Utrechtseweg 310, 6812 AR Arnhem, The Netherlands
Telephone +31 26 3 56 91 11. Telefax +31 26 3 51 56 06.
3. - 3 - 40330000-TDC 03-36488A
CONTENTS
page
1 INTRODUCTION 4
1.1 Background 4
1.2 Scope and purpose 5
2 CONVENTIONAL LOSS EVALUATION METHOD 6
2.1 Types of losses in transformers 6
2.2 Transformer loss evaluation – A and B factors 7
2.3 Determination of A and B factors, limitations and uncertainties 10
3 STATISTICAL LOSS EVALUATION METHOD 11
3.1 Dealing with uncertainty 11
3.2 Monte Carlo simulation 12
3.3 A probabilistic methodology to determine the loss evaluation factors 12
3.4 Sensitivity Analysis 13
3.4.1 Influencial factors on the A factor 14
3.4.2 Influencial factors on the B factor 15
3.4.3 Influencial factors on the choice of the optimal transformer 15
3.5 Number of trials 16
4 CASE STUDY 1: INFLUENCE OF ELECTRICITY PRICE VOLATILITY 17
4.1 Case description 17
4.2 Conventional A and B factors 19
4.3 Statistically determined A and B factors 20
4.4 Discussion – selection of optimum transformers 21
5 TRANSFORMERS AT WIND TURBINES 22
5.1 The power of wind 22
5.2 Case study for energy-efficient transformers at wind turbines 24
5.3 Discussion – selection of optimum transformers 27
5.4 Market opportunities for transformers at wind turbines 29
6 CONCLUSIONS AND RECOMMENDATIONS 33
6.1 Conclusions 33
6.2 Recommendations 34
6.3 Action plan to promote energy-efficient distribution transformers 35
APPENDIX A: DATA SHEET TRANSFORMERS 38
4. - 4 - 40330000-TDC 03-36488A
1 INTRODUCTION
1.1 Background
Studies carried out in 1999 and 2001 by the European Copper Institute have revealed that
the scope for energy savings and CO2 reduction through the use of energy-efficient
distribution transformers in the EU is substantial. The savings potential is approximately 22
TWh/year for "public" electric utilities and approximately 5,5 TWh/year for industries and
offices. This savings potential can be achieved by application of energy-efficient
transformers, the extra investment cost of which is earned back by the energy savings.
For some industries and public utilities, energy-efficient transformers can save a lot of money
during the lifetime of the transformer.
In order to select the transformer with the optimum balance between investment cost and the
cost of no-load and load losses, loss evaluation during transformer purchasing is the usual
and appropriate method. The cost of losses is represented through an A and B factor (A
represents the loss evaluation for the no-load losses; B represents the loss evaluation for the
load losses).
Surprisingly, many industries and public utilities are not familiar with energy-efficient
transformers. Therefore, in earlier publications [1,3], the method of loss evaluation was given
and a software tool for calculation was developed [4].
It may be difficult to determine the A and B loss evaluation factors, as these factors provide a
capitalisation of future cost of losses and are depended on (expected) load patterns, load
growth and changes of energy prices. Usually, due to a lack of clairvoyance and to reduce
complexity, A and B are based just on average values. Little is known about the loss
evaluation for transformers if e.g. the peak loading and/or the variation of electricity price is
taken in account.
5. - 5 - 40330000-TDC 03-36488A
An example of the price
variation in the year 2002
is given in figure 1
(source: APX spot market
2002). This figure shows
that the average price for
energy at the APX spot
market was about 30
Euro/MW. However there
is a peak above 200
Euro/MW. It is unknown
whether these peaks can
be neglected for the loss
Evaluation. Figure 1: spot market prices
A similar question applies to (step-up) transformers of wind turbines: what is the effect of
such a strongly fluctuating source on the loss capitalisation?
1.2 Scope and purpose
The purpose of this report is to show the influence of
fluctuating loads and energy price on the loss evaluation
factors A and B and hence on the economic optimum for
distribution transformers.
Two cases are considered: an economic study based on
historical data from the forward market, and an economic
study into the A and B factor for wind turbines based on
historical data for wind-speed and a given wind turbine
characteristic.
The target group for this report are industries, utilities,
project developers of wind turbines and other customers
of energy efficient transformers.
Figure 2 Wind turbines
6. - 6 - 40330000-TDC 03-36488A
2 CONVENTIONAL LOSS EVALUATION METHOD
A power transformer normally consists of a pair of windings, primary (HV) and secondary
(LV), linked by a magnetic circuit or core. When an alternating voltage is applied to one of
these windings, generally the HV winding, a small current will flow which sets up an
alternating magnetic flux in the core. This alternating flux, linked to both windings, induces a
voltage in each of them. The current that is flowing in the situation that both windings are not
loaded is the magnetising current. For further reading about transformer losses is referred to
the J&P transformer book [11].
2.1 Types of losses in transformers
NO LOAD LOSSES
An unloaded transformer experiences losses. The magnetising current is required to take the
core through the alternating cycles of flux at a rate determined by system frequency (50 Hz).
In doing so energy is dissipated. This loss is known as the core loss, no load loss or iron
loss. The core loss is present whenever the transformer is energised. Thus they represent a
constant and therefore significant energy drain on any electrical system. In addition, the
alternating fluxes generate also alternating forces in the iron core and hence noise.
The core loss is made up of two components: the first one, the hysteresis loss, is
proportional to the frequency and dependent on the area of the hysteresis loop in the B-H
diagram, and therefore characteristic of the material and a function of the peak flux density.
The second component is the eddy current loss that is dependent on the square of the
frequency, the square of the thickness of the material and the resistivity. Minimising
hysteresis losses therefore implies application of a material having a minimum area of
hysteresis loops, while minimising eddy current loss is achieved by building up the core from
a laminate of thin strips and high resistivity.
LOAD LOSSES
The load loss of a transformer is that part of the losses generated by the load current and
which varies with the square of the load current. This falls into three categories:
• Resistive loss within the winding conductors and leads
• Eddy current loss in the winding conductors
• Eddy current loss in the tanks and structural steelwork.
The latter two categories are also referred to as “extra losses”.
Resistive loss follows Ohm’s law and can be decreased by reducing the number of winding
7. - 7 - 40330000-TDC 03-36488A
turns, by increasing the cross-sectional area of the turn conductor, or by a combination of
both. However, reducing the number of turns requires an increase of the flux i.e. an increase
in the core cross-section, which increases the iron weight and iron loss. So a trade-off has to
between made between the load loss and the no-load loss.
Eddy currents arise from the fact that not all the flux produced by one winding links to the
other winding. This flux leakage also leads to the short-circuit reactance or impedance of a
transformer. In the past, this reactance was simply considered an imperfection arising from
the unavoidable existence of leakage flux. Nowadays, the transformer impedance is a
valuable tool for the system designer to determine system fault levels to meet economic
limitations of the connected plant.
The path of eddy currents in winding conductors is complex. The magnitude of this leakage
flux depends on the geometry and construction of the transformer. The effect of leakage flux
within the transformer windings results in the presence of radial and axial flux changes at any
given point in space and any moment in time. These induce voltages, which cause currents
to flow perpendicular to the fluxes, which lead to losses. The magnitude of these currents
can be reduced by increasing the resistance of the path through which they flow, and this
can be effected by reducing the total cross-sectional area of the winding conductor, or by
subdividing this conductor into a large number of strands insulated from each other (in the
same way as laminating the core steel reduces eddy-current losses in the core). However,
the former alternative increases the overall winding resistance and thereby the resistive
losses. Conversely, if the overall conductor cross-section is increased with the object of
reducing resistive losses, one of the results is an increase of the eddy current losses. This
can only be offset by a reduction in strand cross-section and an increase in the total number
of strands. It is costly to wind a large number of conductors in parallel and so a manufacturer
will wish to limit the total number of strands in parallel. Also, the extra insulation resulting
from the increased number of strands results into a poorer winding space factor. It will be
evident that in a transformer having a low reactance, winding eddy currents are less of a
problem than one with high reactance.
On very high currents (>1000 A) fluxes generated at the main leads can give rise of eddy
current losses in the tank adjacent to these. Due to the leakage flux there are also eddy-
current losses in tanks and internal structural steelwork.
2.2 Transformer loss evaluation – A and B factors
The total owning cost of a transformer consists of several components, including the
8. - 8 - 40330000-TDC 03-36488A
purchase price, the value of energy losses, maintenance and repair costs over the lifetime,
and decommissioning cost. The purchase price and the energy losses are the two key
factors for comparison of different transformers.
In the industry it is very common that transformers are part of a turn key project. The
contractor is often interested in a transformer with a low purchase price. However the
user/owner of the transformer aims at buying the cheapest transformer, i.e. with the lowest
total owning cost, which complies with the requirements for a given application. Losses,
installation, maintenance, repair and decommissioning costs are seldom taken into account
by the contractor when choosing between transformers.
The utilities are not encouraged by their government and/or regulators to buy a transformer
with less losses. In most countries the energy savings of transformers with low losses are not
assigned to the utilities. This means it is not in the interest of a utility to invest in a
transformer with low losses (higher purchase price), since there is no pay back for the utility
during the life time of the transformer! This is contradictory to the public interest. Nowadays
some governments and regulators have realised this problem and want to change so the
utilities are stimulated to buy energy saving transformers.
When comparing two transformers with different purchase prices and/or different losses, one
must take into account that the purchase price is paid at the moment of purchase, while the
cost of losses comes into effect during the lifetime of the transformer. Usually the costs are
converted to the moment of purchase by assigning capital values. When transformers are
compared with respect to energy losses, the process is called loss evaluation.
In the basic loss evaluation process, three transformer figures are needed:
• purchase price
• load loss
• no-load loss.
For the specified load loss of a transformer, the purchaser can assign a cost figure per kW of
loss representing the capitalised value (net present value) of the load losses over the lifetime
of the transformer or a shorter time scale e.g. 5 or 10 years. This cost figure is based on the
expected transformer load over time and the average cost per kWh.
Similarly, for the no-load loss of a transformer, the purchaser can assign a cost figure per kW
of no-load loss representing the capitalised value of the no-load losses. This cost figure is
also based on the average cost per kWh and the interest rate chosen by the purchaser. As
nearly all transformers are connected to the grid for 100% of the time, and the no-load losses
9. - 9 - 40330000-TDC 03-36488A
are independent on the load, the load curve is not relevant. The average cost per kWh will
tend to be lower than for the load losses, as the latter will tend to coincide with peak loads, at
which time energy is very expensive.
If high capitalisation values for losses are chosen, transformers with low losses but with
higher investment cost tend to be favoured. If however capitalisation values are set to zero, a
purchaser effectively eliminates energy loss evaluation from the purchase decision, which
favours the cheapest transformer.
Thus, the capitalised cost (CC) of a transformer can be expressed as the sum of the
purchase price (Ct), the cost of no-load losses and the cost of the load losses, or as a
formula:
CC = Ct + A x Po + B x Pk
where A represents the assigned cost of no-load losses per watt, Po the value of the no-load
losses per watt, B the assigned cost of load losses per watt and Pk the value of the load
losses per watt. This formula can also be found in HD428 and HD538.
Po and Pk are transformer properties. A and B are properties that depend on the expected
loading of the transformer and energy prices. A and B are calculated as follows:
8760
)1(
1)1(
××
+⋅
−+
= CkWhn
n
ii
i
A (no-load loss capitalisation)
and
2
8760
)1(
1)1(
×××
+⋅
−+
=
r
l
kWhn
n
I
I
ii
i
B C (load loss capitalisation)
where:
i = interest rate [%/year]
n = lifetime [years]
CkWh = kWh price [EUR/kWh]
8760 = number of hours in a year [h/year]
IL = loading current [A]
Ir = rated current [A]
Usually, the loss evaluation figures A and B are submitted to the transformer manufacturers
in the request for quotation. They can in turn start the complicated process of transformer
design, to obtain a transformer design which performs best using the same formula. The
result of this open process should be the cheapest transformer, i.e. with the lowest total
10. - 10 - 40330000-TDC 03-36488A
owning cost, optimised for a given application.
For large transformers, above a few MVA, the costs of losses are so high, that transformers
are custom-built, tailored to the loss evaluation figures specified in the request for quotation
for a specific project.
For distribution transformers, often bought by large batches, the process is undertaken
infrequently, e.g. once every 5 years. This yields an optimum transformer design, which is
then kept for several years until energy prices or load profiles have changed dramatically. In
fact the loss levels established in HD428, HD538 and national standards reflect established
practice of preferred designs with respect to loss evaluation values.
2.3 Determination of A and B factors, limitations and uncertainties
In practice an ending up for A between less than 1 and 12 EUR/W and B ending up between
0,2 and 5 EUR/W is realistic.
The given formulae in chapter 2.2 assume that energy prices and the loading are constant
over the transformer life. As often the future loading of the transformer is not known at the
moment of buying the transformer. If the load grows over time, the growth rate must be
known.
Also, the applicable kWh price over the lifetime must be forecast. A tricky task! Finally, the
interest rate and the economic lifetime may be difficult to choose. In practice, therefore, there
may be a lot of guesswork in determining A and B factors. The choice of the factors A and B
is therefore difficult.
For this report, we provide a method based on historical data for determining the A and B
factor when
• the load of the transformer is fluctuating very fast (wind turbine),
• the electricity price is fluctuating (forward market).
For the transformers at wind turbines it is common to use the same transformers as used for
distribution. Since the direction of the loading is different (from LV to HV, where regular
distribution transformers have a direction from HV to LV), there can be a small difference in
the No-load losses, since the system voltage at the transformer is slightly higher. Appendix B
gives more technical information about this aspect. Since the extra no-load losses are small,
they are not taken in account in this study.
11. - 11 - 40330000-TDC 03-36488A
3 STATISTICAL LOSS EVALUATION METHOD
In [1] a definition of “to invest” is given. To invest means to employ general resources that
are available, or were obtained for a definite purpose that is directed toward the future. The
following characteristics are typical of investment:
• Multiperiod consideration: The benefits of an investment do not occur immediately, only at
a later time. So investments require a multi-period, long-term method of consideration.
• Uncertainty: Because investments have an effect in the future, every investment project is
encumbered with uncertainty. That means that the expected benefits are dependent upon
different influencing factors.
• Irreversibility: The means of payments are specialised for an investment project, that is,
they are tied up and are more or less irreversible, or otherwise reversibility is associated
with high costs.
3.1 Dealing with uncertainty
The model described in chapter 2 uses input parameters, which are uncertain. This
uncertainty rises from the following sources: The actual data are not available (of future load
curves) or the value varies unpredictably (future electricity prices). This lack of knowledge
about particular values, or the knowledge that some values may always vary contributes to
the model's uncertainty.
Traditionally, there are three basic ways to deal with uncertainty: Point estimates, Range
estimates, and What-if scenarios.
Point estimates are when you use what you think are the most likely values (technically
referred to as the mode) for the uncertain variables. These estimates are the easiest, but can
return very misleading results.
Range estimates typically calculate three scenarios: the best case, the worst case, and the
most likely case. These types of estimates can show you the range of outcomes, but not the
probability of any of these outcomes.
What-if scenarios as many scenarios as can be thought of are calculated. What is the worst
case or average case? This form of analysis is extremely time consuming, and results in lots
of data, but still doesn’t give you the probability of achieving different outcomes.
12. - 12 - 40330000-TDC 03-36488A
With the traditional loss evaluation method [4] the point estimate (average) was used to
calculated the capitalized costs of different transformers. Range estimates and what-if
scenarios can also be made with the deterministic version of Traloss1
.
Another way of capturing the uncertainty is to use the complete distributions of the input
variables. The complete distribution of the output values will be calculated. With this method
all possible outcomes are taking into account when making a decision. An easy to use
method for making calculations with distributions is Monte Carlo simulation.
3.2 Monte Carlo simulation
Monte Carlo simulation was named for Monte Carlo, Monaco, where the primary attractions
are casinos containing games of chance. The random behaviour in games of chance is
similar to how Monte Carlo simulation selects variable values at random to simulate a model.
For each uncertain variable (e.g. interest rates, energy prices, lifetime of the transformer,
loading, possible values are defined with a probability distribution. A simulation calculates
multiple scenarios of a model by repeatedly sampling values from the probability distributions
for the uncertain variables and using those values for the outputs. For these calculations
Crystal Ball 2000 has been used.
With Monte Carlo simulation a whole range of values for each uncertain variable can be
calculated. By using distributions of the input variables, the output will not be a single
number, but a distribution as well. This will be helpful for a better understanding of the
problem and a better determination of the risk taken by a certain decision (in this case the
risk taken by buying a certain transformer).
3.3 A probabilistic methodology to determine the loss evaluation factors
The uncertain parameters in the model described in §2.2 to determine the most efficient
transformer are:
• interest rate
• kWh price
• lifetime of the transformer
• loading current
• CO2 prices
• price of the transformers.
1
Software package developed at KEMA -TDC to evaluate the A and B factors for different situations.
13. - 13 - 40330000-TDC 03-36488A
Implementing these factors in the model results in a probabilistic model. To investigate the
effects on the choice of the most efficient transformer of probabilistic analysis we performed
two case studies. In these case studies we implemented the following parameters with
uncertainty: the electricity price (chapter 4) and the loading current (chapter 5). These cases
have been chosen for their practical applicability.
With this research the following questions can be answered:
• Is there a difference in the results using average prices or the distribution of the prices?
(chapter 4)
• Should another type of transformer be used in combination with a wind turbine? (chapter
5).
• What is the influence of probabilistic calculations on the A and B factor?
• Is Traloss (a deterministic model) good enough to determine the A and B factor (and with
these the optimal transformer for a certain user) or should a probabilistic model be used?
• Is it possible to find a rule of thumb between deterministic answers and probabilistic
answers?
The following assumptions have been made:
• Influence of harmonics in the loading is not included in this research (set to 0).
• Different scenario’s can be made for the CO2 prices. Therefore each case has been run
with three different CO2 prices (0, 10, 33 Eur/Ton).
• The choice of the best transformer to choose in a specific situation is based on the
capitalised cost.
3.4 Sensitivity Analysis
The outcomes of a sensitivity analysis on the probabilistic model (all uncertain input
parameters modelled in a probabilistic way) are described in this paragraph. The following
input parameters were tested for their influence on the different output values. The initial
values of these parameters can be found in brackets next to the input names:
• Interest rate (7%)
• Economic lifetime (20 years)
• Energy price (100 Euro/MWh)
• CO2 emission price (33 Eur/ton
• Purchase prices (see Table 1)
• Load kVA (246 kVA).
14. - 14 - 40330000-TDC 03-36488A
Table 1: Purchase prices of the different 1000 kVA transformers
Name Price (Euro)
Base case Oil CC’ 8,007
Alternative 1 Oil DD’ 10,353
Alternative 2 Dry HD 538 10,074
Alternative 3 Dry Low-Loss 11,108
3.4.1 INFLUENCIAL FACTORS ON THE A FACTOR
The parameters with the highest influence on A are (in order of highest appearance first):
• Energy price
• Interest
• Economic lifetime.
The other input parameters had no influence on A. Figure 3 illustrates these outcomes. In
this figure it can be seen that a 20% rise in energy price induces the A factor to rise from
9.28 to 11.14. The interest rate and the A factor have a negative correlation. This means that
a higher interest rate leads to a lower A factor.
A factor
7.00
8.00
9.00
10.00
11.00
12.00
-20.0%
-15.6%
-11.1%
-6.7%
-2.2%
2.2%
6.7%
11.1%
15.6%
20.0%
Percentage deviations from the base case
energy price
interest
economic lifetime
CO2 emissions cost
The spider chart illustrates the differences
between the minimum and maximum output values
by graphing a curve through all the input values
tested. Curves with steep slopes, positive or
negative, indicate that those input variables have a
large effect on the output, while curves that are
almost horizontal have little or no effect on the
output. The slopes of the lines also indicate
whether a positive change in the variable has a
positive or negative effect on the output.
Figure 3: Spider chart A factor
15. - 15 - 40330000-TDC 03-36488A
3.4.2 INFLUENCIAL FACTORS ON THE B FACTOR
The parameters with the highest influence on B are:
• The load
• Energy price
• Interest rate
• Economic lifetime
The other factors do not have an effect on the B factor. This is shown in Figure 4.
B factor
0.30
0.40
0.50
0.60
0.70
0.80
0.90
-20.0%
-15.6%
-11.1%
-6.7%
-2.2%
2.2%
6.7%
11.1%
15.6%
20.0%
Percentage deviations from the base case
Load
energy price
interest rate
economic lifetime
CO2 emissions cost
Figure 4: Spider chart B factor
3.4.3 INFLUENCIAL FACTORS ON THE CHOICE OF THE OPTIMAL TRANSFORMER
The same input parameters have been tested for their effect on the choice of a transformer.
These results are summarised in Figure 5. A value of 5 on the y-axis represents the base
case (Oil CC’) as the optimal solution, a value of 1 stands for alternative 1 (Oil DD’) being the
optimal solution.
16. - 16 - 40330000-TDC 03-36488A
Choice transformer
1
2
3
4
5
6
-20.0%
-15.6%
-11.1%
-6.7%
-2.2%
2.2%
6.7%
11.1%
15.6%
20.0%
Percentage deviations from the base case
energy price
purchase price base
case
purchase price
alternative 1
Load
Figure 5: Spider chart optimal choice of transformer
Figure 5 shows that the higher the purchase price of alternative 1, the more likely that the
base case will be chosen. A higher energy price leads to choosing a more energy efficient
option: alternative 1. The same argumentation is valid for the Load.
This sensitivity analysis has shown that the most important input parameter for the A factor is
the energy price and the most influencing parameter on the B factor is the load. Therefore
two case studies have been chosen where the energy price and the load fluctuate
respectively. To keep the case studies as practical as possible for the fluctuating load, a wind
turbine has been simulated (chapter 4) and for the fluctuating prices, the prices on the
forward market have been used for simulation (chapter 5).
3.5 Number of trials
To improve the accuracy of the simulations a certain number of trials have to be made. 1000
trials are sufficient to draw accurate conclusions of the data. Due to the way Traloss is made,
a random drawing out of the distributions has to be made for each hour of the year. The
average per year for the A and B factor was calculated afterwards. To get 1000 trials this
way 8,760,000 different scenarios were calculated for each case. Variation in the CO2
emission cost (discrete values of 0, 10 and 33) resulted in a total number of trials of: 2
(cases) * 3 (CO2 scenario’s) * 8760 (hours) * 1000 (trials) = 52,560,000 trials.
17. - 17 - 40330000-TDC 03-36488A
4 CASE STUDY 1: INFLUENCE OF ELECTRICITY PRICE VOLATILITY
Is there a difference in the results using average prices or the distribution of the prices? The
answer to this question will be given in this chapter.
4.1 Case description
As given in §3.3 the most important and at the same time fluctuating input parameter on the
A factor is the electricity price. The price that has to be paid depends on the type of
customer. For example large industries have their own electricity purchase department and
will trade on the long-term en short-term electricity markets to obtain the lowest price
possible. Smaller industries have contracts with trading companies for a fixed price for a
whole year. In this case two tariffs will be used: peak prices and base prices. Grid companies
buy their energy losses with standard contracts (like smaller industries). But if a grid
company uses more or less than the contracted amount of energy a clearance price has to
be paid. The following figure illustrates this principle.
hours
Contracted
base load at
base prices
7 23
Contracted
peak load at peak
prices
load
Actual load
Clearance
price
Figure 6 Contracted versus actual load of a grid company
The focus of this case study has been on the smaller industries. For such an industry only
the base load and the peak load have to be bought. For simplicity the assumption has been
made that the actual load follows the contracted load exactly. Also the no-load losses are
included in the contracted peak and base load and evaluated against the peak and base
prices respectively.
18. - 18 - 40330000-TDC 03-36488A
0
10
20
30
40
50
60
70
00-Jan-00
09-Apr-00
18-Jul-00
26-Oct-00
03-Feb-01
14-May-01
22-Aug-01
30-Nov-01
base prices 2000 & 2001 peak prices 2000 & 2001
Euro’s
Figure 7 Base and peak prices of the forward market
Prices of the forward market of 2000 and 2001 have been used to make a distribution of the
prices for the model. Figure 7 shows the base and peak prices of the historical data set. A
yearly pattern can be seen in this figure.
To use these data as input numbers in a Monte Carlo simulation the data have to be fitted
into a distribution. Figure 8 shows the fitted distributions of these data used for the Monte
Carlo simulation.
Distribution base and peak prices
0
0.02
0.04
0.06
0.08
0.1
0.12
0.14
25.23 32.23 39.23 46.23 53.23
Probability
base prices
peak prices
Figure 8 Fitted distributions of the base and peak prices
19. - 19 - 40330000-TDC 03-36488A
The base prices are beta distributed and the peak prices have an extreme value distribution.
The continuous base load lasts 8760 hours per year and is set to 500 kVA. Two third of the
year (5840 hours) a peak load is requested of 500 kVA on top of the base load.
The data of the four 1600 kVA transformers used in the simulations can be found in table 2,
the other (fixed) input values can be found in table 3.
Table 2 1600 kVA transformers
Name Price (Euro)
Base case Oil CC’ 10,865
Alternative 1 Oil DD’ 12,832
Alternative 2 Dry HD 538 14,451
Alternative 3 Dry Low-Loss 14,990
Table 3 Input values for the wind case
Variable Fixed value
interest rate 10%
ECONOMIC LIFETIME
5 years
CO2 emissions cost 0, 10 en 33 Eur/ton
CO2 emissions per kWh 0.4 kg/kWh
4.2 Conventional A and B factors
The average base price is 31.67 Euro/MWh. The average peak price is 46.13 Euro/MWh.
Three cases for the CO2 emission prices were calculated (CO2 emission prices of 0, 10 en
33 Eur/ton). The results of using these values to calculate the optimal transformer in the
Traloss model can be found in table 4.
Column 1 gives a short case description. The next column displays the A factor, the third
column the B factor. With a deterministic model standard deviations are not applicable (N/A).
In all the cases the Oil CC’ transformer was the best option. This is displayed in the last two
columns. A 1 stands for: “this transformer is optimal in this case”.
20. - 20 - 40330000-TDC 03-36488A
Table 4 Deterministic results price case
A factor (Euro / W) B factor (Euro / W) Optimal transformer
Average St. dev Oil CC’ Oil DD’
Deterministic CO2 0 1.29 0.37 N/A 1 0
Deterministic CO2 10
1.42
0.41 N/A 1 0
Deterministic CO2 33
1.73
0.50 N/A 1 0
Other factors that can be determined are the total CO2 emissions per type transformer,
capitalized costs, pay back time and the IRR (internal rate of return). The pay back time and
the IRR are calculated for the 3 alternatives in comparison of the base case. Table x shows
the results for the Oil C-C’ and the Oil D-D’ variants.
Table x Deterministic results of other outputs of Traloss
Deterministic CO2
0
Deterministic CO2
10
Deterministic CO2
33
CO2 emissions Oil C-C’ 20.3 20.3 20.3
CO2 emissions Oil D-D’ 17.3 17.3 17.3
Capitalized costs Oil C-C’ 18250 19020 20793
Capitalized costs Oil D-D’ 19109 19764 21270
Pay back time Oil D-D’ 7 6 5
IRR alternative Oil D-D’ N/A N/A N/A
4.3 Statistically determined A and B factors
Using the distribution of the peak and base prices (see Figure 8) the following results are
obtained. (see table 5). In this case also the three values of the CO2 emission prices were
used. With a probabilistic model the standard deviations of the A and B factor were
calculated. Even in these cases the Oil CC’ transformer was the optimal solution for all trials.
Therefore this transformer scored a 100%.
21. - 21 - 40330000-TDC 03-36488A
Table 5 Probabilistic results price case
A factor (Euro / W) B factor (Euro / W) Optimal transformer
Average St. dev Average St. dev Oil CC’ Oil DD’
Probabilistic CO2 0 1.29 9.5 e-4 0.37 2.5 e-4 100% 0%
Probabilistic CO2 10 1.42 9.5 e-4 0.41 2.5 e-4 100% 0%
Probabilistic CO2 33 1.73 9.6 e-4 0.50 2.6 e-4 100% 0%
Table x Probabilistic results of other outputs of Traloss
Probabilistic CO2
0
Probabilistic CO2
10
Probabilistic CO2
33
CO2 emissions Oil C-C’ 20.3 20.3 20.3
CO2 emissions Oil D-D’ 17.3 17.3 17.3
Capitalized costs Oil C-C’ 18250 19020 20793
Capitalized costs Oil D-D’ 19109 19764 21270
Pay back time Oil D-D’ 6.89 6.22 5.09
IRR Oil D-D’ N/A N/A 0.8%
It should be noted that only the averages of these quantities are displayed in table x. But
each quantity also has a probability distribution.
4.4 Discussion – selection of optimum transformers
For dealing with fluctuating prices it is not necessary to use a probabilistic version of Traloss,
even at prices with a larger deviation than the prices used above. For example, if the prices
of the spot market are inserted into the model (see Figure 1) then there still is no difference
between the deterministically determined B factor and the average B factor of the Monte
Carlo Simulations. Only the standard deviation of the B factor is much larger than the
standard deviations in table 5.
The spread on the prices does not have an influence on the optimal transformer choice. This
is due to the fact that the prices will fluctuate during the life of the transformer, but in the end
positive values and negative values will compensate each other. If there were a growth in the
prices or another trend, then this would have affected the optimal transformer choice. The
authors wish to recommend to review these effects.
22. - 22 - 40330000-TDC 03-36488A
5 TRANSFORMERS AT WIND TURBINES
The wind power industry is the world's fastest growing energy technology; leading is
Germany with an installed capacity of 12 GW, followed by Spain with 5 GW and Denmark 3
GW. According the 2003 European Wind Energy Conference (EWEC), the total installed
capacity in the EU was 23.8 GW by the end of 2002 and will grow to 40 GW in 2010 [5] and
according to [6] even to 60 GW in 2010.
A modern wind turbine usually has a step-up transformer (size and range equal to a
distribution transformer) either at the base of the tower or in the nacelle. Electrical
connections between wind turbines are usually at a voltage level of 10 kV or above. These
transformers are bought based on the limited sizes inside the wind turbines. If energy
efficient transformers can be used they should be placed next to the wind turbine.
To evaluate if an energy efficient transformer
can be used at wind turbines, the
deterministic method does not lead to the
correct A and B factor of the transformer,
since a variation in the load (wind turbine)
influences the values of the B factor and
therefore the optimal choice of transformer.
The influence of load variations on the A and
B factor will be answered in this chapter with
a case example. Fixed values of all input
factors have been used except the input
factor load. In case of a wind turbine this
factor depends on the wind speed.
5.1 The power of wind
The wind power density has a cubic
relationship with wind speed. For example,
the wind power density increases by a factor
of 8 for a doubling of the wind speed. The
wind velocity at a particular location varies in
speed and direction. Figure 9 shows the
wind map of Western Europe.
WIND RESOURCES AT 50 M ABOVE GROUND LEVE
Sheltered terrain Open plain At a sea coast Open sea Hills and ridges
Figure 9 Wind map in Europe
23. - 23 - 40330000-TDC 03-36488A
The total energy produced by a wind turbine depends on the wind speed. The general
pattern of the wind speed variation is distributed as a Weibull distribution as shown in figure
10 for the Northern European countries at sea coast.
The area under the curve is always exactly 1, since the probability that the wind will be
blowing at some wind speed including zero is 100%. The average value of the wind speed is
8.24 m/s. The statistical distribution of wind speed varies form place to place around the
globe. The Weibull distribution may thus vary, both in its shape, and in its mean value. The
assumption has been made that the Weibull distribution shown below is valid for the
Netherlands.
The power output of a wind
turbine is a function of wind
speed. The power curve
(power output (P) versus
wind speed (v) (P-v)) is
produced by plotting turbine
electrical power
measurements, which have
been averaged over a period
of several minutes, against
wind speed measurements.
Figure 11 shows the power
curve of a 750 kW wind
turbine.
The discrete values of the
Figure 10 Weibull distribution
0
187.5
375
562.5
750
937.5
1 3 5 7 9 11 13 15 17 19 21
windspeed (m/s)
kW
PV-curve Gompertz curve
Figure 11 Discrete PV curve transformed into a
continuous curve
24. - 24 - 40330000-TDC 03-36488A
power velocity (PV) curve have been transformed (by means of a Gompertz curve) to a
continuous version.
The key features of the power curve are:
• Cut-in wind speed (typically at 3 m/s), at which the wind turbine commences operation
• Cut-out wind speed (typically at 23 m/s), at which the wind turbine is shut down to avoid
damage.
Figure 12 shows the probability distribution of the transformer load. This is a combination of
the Weibull distribution function and the power curve of the wind turbine. Based on 8760
hours a year, the average loading of the wind turbine is 291 kW (38,8% of the full capacity).
The estimated energy production of the wind turbine is about 2550 MWh per year.
5.2 Case study for energy-efficient transformers at wind turbines
The given 750 kW wind turbine is used for a case study to calculate if energy-efficient
transformers can be used at wind turbines. For the connection to the grid a distribution
transformer of 1000 kVA is taken (for data about the transformer see appendix A). To
evaluate if an energy efficient transformer (Oil D-D’) can be used compared to an Oil C-C’
transformer the input values as given in table 6 are used in the Traloss model.
0%
5%
10%
15%
20%
25%
30%
<50
50-100
100-150
150-200
200-250
250-300
300-350
350-400
400-450
450-500
500-550
550-600
600-650
650-700
700-750
Loading [kVA]
distribution
Figure 12 Frequency distribution load
25. - 25 - 40330000-TDC 03-36488A
Table 6 Input values for the 750 kW wind turbine (case study)
Parameter Value
interest rate 7%
economic lifetime 20 years
energy price 100 Euro/MWh
CO2 emissions cost 0, 10 or 33 Eur/ton
CO2 emissions per kWh 0.4 kg/kWh
The energy price is based on the market price. The market price for the kilowatt-hour
produced can be established by the extent that the installation is used for the network power
supply. The market price is approximately 0.10 Euro/kWh (according to the Renewable
Energy Act in Germany[2]).
With the average load of the 750 kW wind turbine equal to 291 kW, the Traloss model with a
1000 kVA transformer gave the following results (table 7):
Table 7 Deterministic results wind case
A factor (Euro / W) B factor (Euro / W)
CO2 costs 0 euro/tonnes 9.28 0.79
CO2 costs 10 euro/tonnes
9.65
0.82
CO2 costs 33 euro/tonnes
10.51
0.89
Due to the long economic lifetime (20 years) the A factor is relatively high compared with
other case studies [1,3]. The B-factor is rather small. This can be explained by the average
loading of the transformer (just 29%). This means the average load losses are about 8.5% of
a full operated transformer.
Other factors that can be determined are the total CO2 emissions per type transformer,
capitalized costs, pay back time and the IRR (internal rate of return). The pay back time and
the IRR are calculated for the 3 alternatives in comparison of the base case. Table 8 shows
the results for the oil C-C' and oil D-D' variants, the capitalised costs of the D-D' transformer
being underlined.
26. - 26 - 40330000-TDC 03-36488A
Table 8 Results from the Traloss model
CO2 costs 0
euro/tonnes
CO2 costs 10
euro/tonnes
CO2 costs 33
euro/tonnes
CO2 emissions Oil C-C’ 6.7 t/a 6.7 t/a 6.7 t/a
CO2 emissions Oil D-D’ 5.7 t/a 5.7 t/a 5.7 t/a
Capitalized costs Oil C-C’ 25681 Euro 26388 Euro 28104 Euro
Capitalized costs Oil D-D’ 25376 Euro 25977 Euro 27359 Euro
Pay back time D-D’ 9 Years 9 Years 8 Years
IRR D-D’ 9% 9% 10%
Although the differences are rather small, in all situations the D-D’ energy-efficient
transformer is the most economical, having a pay-back period of about 8-9 years.
The above given results with Traloss should be compared with a statistical method on which
the A and B factors are statistically determined. Using the model with the load distributed as
given in figure 5.4 the following results were acquired:
Table 9 Probabilistic results wind case
A factor (Euro / W) B factor (Euro / W)
Average St. dev
CO2 costs at 0 euro/tonnes 9.28 1.43 0.02
CO2 costs at 10 euro/tonnes 9.65 1.48 0.02
CO2 costs at 33 euro/tonnes 10.51 1.62 0.02
The A factor is for all trials the same. This is due to the fact that the A factor is independent
of the load. The B factor is a lot higher than calculated with the traloss model. In this case the
changing of the B factor did not influence the choice of the transformer as can seen from
table 10. Nevertheless it shows that taking the average loading of the wind turbine is not
correct. By using the average load, the B factor will always be lower than using the loading
distribution. However not everybody uses statistical tools to evaluate which transformer is the
most economical.
27. - 27 - 40330000-TDC 03-36488A
Table 10 Probabilistic results of other outputs of Traloss
CO2 costs 0 euro/tonnes CO2 costs 10
euro/tonnes
CO2 costs 33
euro/tonnes
CO2 emissions oil C-C’ 8.99 8.98 8.99
CO2 emissions oil D-D’ 7.64 7.63 7.63
Capitalized costs oil C-C’ 31784 32720 34919
Capitalized costs oil D-D’ 30564 31359 33228
Pay back time oil D-D’
2
10.57 10.29 9.24
IRR oil D-D”
2
12% 13% 14%
It should be noted that only the averages of these quantities are displayed in table 10. But
each quantity also has a probability distribution.
5.3 Discussion – selection of optimum transformers
There is a large difference between the B factor determined deterministically and the B factor
determined probabilistically. This could result in a wrong transformer choice. The differences
should therefore be clarified.
The load has an asymmetric spread with a so-called bathtub curve (see figure 12). If this
load were fixed for the whole lifespan of a transformer only one B factor would have been
necessary to select the optimal transformer. In the deterministic case this has been done.
The load is assumed to be 291 (the average load). This resulted in a fixed B factor of 0.79.
But the load is distributed and therefore the B factor is distributed (see figure 13).
Frequency Chart
.000
.083
.166
.249
.332
0
829.7
3319
0.00 1.36 2.71 4.07 5.43
10,000 Trials 10,000 Displayed
Forecast: B factor
Figure 13 Distribution of the B factor
2
The Pay Back time and the IRR cannot be calculated for all cases. Therefore the average has been taken over the trials were
a positive pay back time and IRR have been found.
28. - 28 - 40330000-TDC 03-36488A
The transformer should be optimal for several different (fluctuating) loads and fluctuating B
factors. Therefore the average B factor for the lifespan of the transformer has been
calculated. This B factor has a spread that is much smaller (standard deviation is a
factor 8760 smaller, to be exact). The distribution of this B factor can be found in figure 14.
Frequency distribution B factor
0
0.02
0.04
0.06
0.08
0.1
0.12
0.14
0.16
0.18
0.2
1.56
1.57
1.58
1.59
1.6
1.61
1.62
1.63
1.64
1.65
1.66
1.67
1.68
1.69
1.7
frequency
Figure 14 Frequency distribution of the B-factor with CO2 costs 33 euro/tonnes
So far, the B factor was calculated from the average loading, based on the energy production
by the wind turbine during one year. If instead of the average load the average of the losses
were taken, the probabilistic B factor would have been found.
The average of the losses can be taken from figure 12. Since the load losses are quadratic
with the load, the average loss (based on the 750 kW wind turbine) equals 27% during a
year. The transformer loading at which the load loss equals 27% of the rated load loss,
equals 52% (390 kW). The average of the distribution of this quantity has to be used in
Traloss to find the average probabilistically determined B factor. So by changing the loading
of the transformer in the Traloss software to 390 kW, the following results are found:
29. - 29 - 40330000-TDC 03-36488A
Table 11 Deterministic results wind case
Loading = 390 kW Loading = 291 kWA factor (Euro /
W) B factor (Euro / W) B factor (Euro / W)
CO2 costs 0 euro/tonnes 9.28 1.41 0.79
CO2 costs 10
euro/tonnes
9.65
1.47 0.82
CO2 costs 33
euro/tonnes
10.51
1.60 0.89
As can seen from table 9, these B values met the values produced with the probabilistic
method. So without using a probabilistic tool it is possible to make an estimation of the B
factor if the loading changes. If the average losses are taken in account it is possible to use
the Traloss model for evaluation of the transformers instead of using a probabilistic model.
5.4 Market opportunities for transformers at wind turbines
Figure 15 gives the power installed in the EU by the end of 2002. The expected growth in
Europe of wind energy is according [6] from 23.8 GW by the end of 2002 up to between 40
and 60.0 GW in 2010. For this
study we take the average 50
GW. According to [6] the
average size of new wind
turbines being installed is
expected to grow over the next
decade from today’s figure of 1
MW to 1.3 MW in 2008 and 1.5
MW in 2013. If an average size
of 1.5 MW is taken, the total
number of wind turbines during
2003 – 2010 will be about
17500. It is expected that the
electricity price will be lower in
2010.
Figure 15 Installed wind power (MW) by the end of 2002 in EU
30. - 30 - 40330000-TDC 03-36488A
Presuming that a transformer of 1600 kVA will be used and the power curve is the same as
given in figure 5.3 (scaled up to 1500 kW) the consequences can be calculated for the
transformer market. Using the traloss model, the equivalent loading on which the same
losses are produced equals 780 kVA. The consequences of the larger physical size of
energy-efficient transformers have not been considered.
Table 12 shows the input data for the market situation in 2010. Also shown are the economic
loss evaluation factors resulting from the input data. We presumed that the electricity price is
75 Euro/MWh.
Table 12 Input data 1600 kVA oil type transformer
Transformer load Depending on the wind speed, average load 48,8%
Economic lifetime 20 year
Interest rate 7%
Energy price EUR 75 /MWh
A (no-load loss evaluation) EUR 6.96 /W
B (load loss evaluation) EUR 1.65 /W
Based on these values, the key output data are given in table 13.
Table 13 Outcome 1600 kVA transformer
Unit Oil C-C’ Oil D-D’ Difference
Transformer rating kVA 1600 1600
Rated no-load loss W 1700 1445 -225
Rated load loss W 14000 11900 -2100
Total annual losses kWh/a 44038 37432 -6606
CO2 emission @ 0.4 kg/kWh ton/a 17.6 15.0 -2.6
Purchase price EUR 10865 12832 1967
Present value no-load loss EUR 11832 10058 -1774
Present value load loss EUR 23158 19685 -3473
Capitalised costs EUR 45856 42574 -3282
Pay Back (years) 4
Internal rate of return 25%
Although the oil transformer with low losses (D-D’) has a purchase price that is 18% higher
than the oil transformer C-C’, it is clear that the D-D’ transformer is in fact the most
31. - 31 - 40330000-TDC 03-36488A
economical transformer. Even without evaluation of the CO2 emission values, the D-D’
transformer is the least expensive transformer during the lifetime (pay back period 3 years).
At a CO2 evaluation of 10 Euro the difference in capitalised costs is 3562 Euro (A factor =
7.33 Euro/W; B = 1.74 Euro/W; at a CO2 evaluation of 33 Euro the difference is 4205 Euro
(A = 8.19 Euro/W; B = 1.95 Euro/W).
Table 14 gives the potential annual energy and CO2 emission savings for wind energy, if
with all 17500 new wind turbines, until 2010, a 1600 kVA energy efficient oil type
transformers D-D’ are placed instead of the C-C’ transformer.
Table 14 Estimated annual electricity saving of transformers at wind energy in Europe by
2010
Economical sector Electricity
production (TWh)
Losses in distribution
transformers (GWh)
Savings
potential (GWh)
New wind energy 90 771 116
Application of transformers in all new wind turbines offers a savings potential of
approximately 116 GWh/year at 2010. The associated CO2 emission reduction would amount
to 46,000 tonnes/year, or 0,014% of the 340 Mton emission reduction target of the European
Union for 2012. It should be noted that the above given values can be even higher since:
• The expected 50 GW wind production capacity at 2010 may be higher
• More efficient transformer types could be employed, outside the range considered
• Replacement of existing wind turbines is not taken in account
• The transformers as given in study [3] are taken. These transformers are not optimised
for wind energy but for industry. Since the A and B factor are different compared with
industry, the optimised transformer for wind energy will have different losses.
32. - 32 - 40330000-TDC 03-36488A
Amorphous transformers at wind turbines
Since the A factor for wind turbine is relatively high, it was decided to perform a study with an
amorphous transformer. Although the information about these transformers is based on a 400
kVA transformer (see [1]), the benefits of using these transformer at wind turbine can be found
(in theory) by performing a study based on a 300 kW wind turbine with the adjusted PV curve
from the 750 kW wind turbine. Based on the losses, the power of the wind turbine is equivalent
to 156 kW.
If the lifetime is 20 years, the interest rate is 7% and the energy price is 100 Euro/MWh the A
factor is 9,28 Euro/W and the B factor 1,41 Euro/W. The results as shown in table 15 are
found when the amorphous transformer (Oil C-AMDT) is compared with a regular C-C’ oil
transformer:
Table 15:outcome 400 kVA transformer
Unit Oil C-C’ Oil C-AMDT Difference
Transformer rating kVA 400 400
Rated no-load loss W 610 160 -450
Rated load loss W 3850 3850 0
Total annual losses kWh/a 10473 6531 -3942
CO2 emission @ 0.4
kg/kWh
ton/a 4.2 2.6 -1.6
Purchase price EUR 4874 6787 1913
Present value no-load loss EUR 5661 1485 -4176
Present value load loss EUR 5435 5435 0
Capitalised costs EUR 15969 13706 -2263
Pay Back Time (years) 5
Internal rate of return 20%
This example shows that application of amorphous transformers in wind turbines promises
such high energy savings (~40%) that they would present a good economic case, despite the
significantly higher (~40%) purchase price.
NOTE: mass-scale application of amorphous-cored transformers has so far been limited to small with sizes < 100 kVA.
Development of transformers > 400 kVA has so far been very limited due to several technical limitations.
33. - 33 - 40330000-TDC 03-36488A
6 CONCLUSIONS AND RECOMMENDATIONS
6.1 Conclusions
• Determining A and B loss evaluation factors statistically, considering fluctuating energy
prices (no price trend), yields results equal to deterministically calculated figures e.g. by
the Traloss tool. Deterministic calculations are therefore appropriate to make transformer
investment decisions.
• The loss evaluation factor for the no-load (A factor) for transformers at wind turbines is
high compared to transformers placed at industries or public grids. Reasons are:
o The energy price for the production of power is higher at wind turbines (100
Euro/MWh).
o The lifetime of a wind turbine is long (20 years).
• The loss evaluation factor for the load (B factor) for transformers at wind turbines is
comparable with other distribution transformers. Although the energy price is high, the
average loading of the transformer is small, because of the fluctuation of the power
produced by the wind turbines.
• Although the energy production of a wind turbine is fluctuating (due to the wind speed
distribution and the power curve of a wind turbine), transformer losses can be calculated
easily by assuming a loading with equivalent losses.
• Energy savings of transformers at wind turbines can be calculated with the Traloss tool.
• Based on the wind speed distribution at sea in the Northern Europe, energy efficient
transformers economically justified.
• Since the wind energy market is growing rapidly, there is a market to promote the use of
energy-efficient transformers.
• The potential energy savings by application of energy efficient transformers at wind
turbines is about 116 GWh at 2010.
• The range of the transformers depends on the size of the wind turbines. Since the size of
the wind turbines is growing, the range of the transformers will also be growing. The
range of the transformers for the future years will be between 1000 and 2500 kVA.
• A study performed with a small wind turbine (300 kW) and an amorphous core
transformer, shows that at wind turbines amorphous transformers are the best choice.
• Energy efficient transformers tend to have larger weights and sizes than the transformers
placed so far at wind turbines.
34. - 34 - 40330000-TDC 03-36488A
6.2 Recommendations
• The price model was only calculated for a small industry. For a utility also the clearance
prices have to be included. Especially because a utility does not know its future load so
precisely. Therefore apart from the variation in prices, a variation (uncertainty) in the load
will arise. We propose to determine the influence of this combination.
• Instead of changing Traloss into a probabilistic model to deal with wind turbines it is
possible to find a method for different wind speeds and wind turbines to be included into
Traloss.
• The model has not tested the effect of a growth in a certain parameter (price, load). The
effects of this should be tested.
Some QUESTIONS & ANSWERS answered by the study presented in this report
Q: Is there a difference in the results using average prices or the distribution of the
prices?
A: No, there is no difference in the results. For fluctuating prices around a stable mean the
deterministic version of Traloss can be used for the optimal transformer selection.
Q: Is there a difference in the results using the average load or the distribution of
the load of a wind turbine?
A: Yes, there is a large difference in the B factor and in the optimal transformer choice.
Q: What is the influence of probabilistic calculations on the A and B factor?
A: The A and B factor will have a distribution as well. Because of the dependence of the B
factor to the load (in a quadratic way) there is a large difference between the deterministic
B factor and the probabilistic B factor.
Q: Is Traloss (a deterministic model) good enough to determine the A and B factor
(and with these the optimal transformer for a certain user) or should a probabilistic
model be used?
A: If there is only a fluctuation in the prices and not a growth the deterministic version of
Traloss is good enough to deal with this problem. For the fluctuations in the load there
has to be found a rule of thumb to deal with the uncertainty. Just taking the average loads
leads to wrong conclusions.
Q: Is it possible to find a rule of thumb between deterministic answers and
probabilistic answers?
A: Yes, this is possible.
35. - 35 - 40330000-TDC 03-36488A
• It is recommended to investigate the application potential for amorphous transformers in
wind turbines, including the technological feasibility.
6.3 Action plan to promote energy-efficient distribution transformers
2003
A&Bfactorsfor
public grids
A&Bfactors for
industry
A&Bfactors for
renewable
Writing technical specifications
for(industry)ORrenewable
transformers(dry+ oil)range
1000kVAupto2500kVA.
Writingtechnicalspecification
fortransformersinpublic grids
(dry+oil)range50kVA upto
1000kVA
Customerscanorder
energy-efficient
transformers
accordingEuropean
Standard.
Serialproduction of
energy-efficient
transformers
accordingEuropean
Standard.
Commitmentof
all parties to
the European
specification
(manufacturers,
Goverment,etc.)
Adoptingthe
specification
toaEuropean
StandardCenelec
Promotingenergy-efficienttransformersbyProphetandothers
1999 200X 200Y
Figure 16 Recommended action plan.
Since 1999 several studies on energy-efficient distribution transformers have been
performed. The results presented in this report and in [1,3] all have the same result:
technically and economically, energy-efficient distribution transformers are a real alternative
to conventional transformers. Next to the technical and economical issues, energy-efficient
transformers reduce the CO2 pollution. The studies so far focused on:
• Distribution transformers in public grids (50 kVA up to 1000 kVA)
• Distribution transformers located at industries (1000 kVA up to 4000 kVA)
• Distribution transformers at wind turbines (1000 and 1600 kVA).
However national governments and the EU do not yet facilitate or promote the use of energy-
efficient transformers. Even nowadays it is a rule that grid companies considering investing in
energy-efficient components, do not get the (economical) benefits. The users pay for the
losses in the grid, which means there is no financial incentive for the grid owner to buy
energy-efficient transformers. Regulators should pay attention to this problem, as it is strange
that governments, on one hand, want to lower the CO2 emissions, and on the other hand do
not give any incentive for energy-efficient components. First step: national governments
36. - 36 - 40330000-TDC 03-36488A
(or EU) should promote energy-efficient components and provide incentives for
energy-efficient measures.
Even if regulators do promote the use of energy-efficient transformers, it is not likely that
every transformer will be replaced with an energy-efficient transformer on the short term. The
technical lifetime of transformers is 30-50 years. However if a transformer should be replaced
energy-efficient transformers should be promoted.
In all the studies so far, the assumed purchase prices of the distribution transformers are
based on serial production. If it is not possible to build energy-efficient transformers in serial
production, the cost price of the transformers is expected to be that high, that it is not
possible to earn back the investment. Therefore all EU countries should work together to
specify a range of energy-efficient transformers. As long as customers do not know these
transformers, no one will buy them. The second step in the action plan is to make a
European specification for a range of energy-efficient transformers (to be made in
serial production). This is the most critical step, since every country has it own specification
and range. Before this step can be done the feasibility to get one EU specification
should be studied. This can be done for several customers. For example the transformers
with a range up to 1000 kVA can be manufactured specially for the grid owners and
transformers above 1000 kVA up to 2500 kVA should be made for industries and
renewables. Perhaps the range should be set up for oil- and dry-type transformers.
The third step is to promote energy-efficient transformers by education of (possible)
costumers. This means they should not only look at the purchase price of a transformer, but
should be capable to make their own calculation to see what the benefits of an energy-
efficient transformer for his/her company are. Education by writing articles or giving
presentations at conferences gives goods opportunity.
The last (or perhaps the first step) is to give an energy-efficient transformer a
sensational name instead of a D-D’ energy-efficient transformer. A good example of a
marketing aspect in the Netherlands is the way a grid company promotes renewable energy.
The company does not talk about renewable energy, but gave it the name “groene stroom”
(green current). The name became that well-known that some customers were asking
competitors for “groene stroom”. Why not give the energy-efficient transformer a name?
Maybe a purchaser feels more convenient if (s)he can say (s)he is buying “green
transformers” to make his/her contribution to the environment. Instead of given the
transformer a name it is also possible to give transformers energy labels (similar to cars and
household equipment).
37. - 37 - 40330000-TDC 03-36488A
References
[1] The scope for energy saving in the EU through the use of energy-efficient electricity
distribution transformers, European Copper Institute, December 1999.
[2] Article: “Financial considerations of Small-scale wind power installations” magazine
Renewable energy 2003, L. Pichler AG.
[3] Energy savings in industrial distribution transformers, W.T.J. Hulshorst, J.F.Groeman,
KEMA 2001
[4] www.efficient-transformers.org/traloss.htm
[5] European Wind Energy Conference & Exhibition in Madrid on 16, 17 and 18 june 2003.
[6] Wind Force12, EWEA 2002.
[11] J & P Transformer book, twelfth edition 1998, Martin J. Heathcote.
38. - 38 - 40330000-TDC 03-36488A
APPENDIX A: DATA SHEET TRANSFORMERS
For a previous study [3], Pauwels Trafo made basic designs for different types of
transformers rated between 1000 and 4000 kVA for industrial use. Since the range of these
transformers can also be used for transformers placed at wind energy, the same
transformers have been used in this document. Typical data of the transformers are given in
the table below.
As can be seen, four different transformers were chosen with rated powers of 1000, 1600,
2500 and 4000 kVA (second row). The information is based on oil-immersed transformers
and dry-type transformers. For each type of transformer calculations have been made with
the losses according to or in line with HD 428 or HD 538 and losses with 15% reduction. It
should be noted that the values given in table A are rough indications and can only be used
for the purpose of this study. The prices are based on the year 2001.
Table A Calculated losses for industry transformers (source: Pauwels)
rating kVA
HV kV
LV V
Uk %
LOSS-LEVEL Oil CC' Oil DD' Dry base Dry Low Oil CC' Oil DD' Dry base Dry Low Oil CC' Oil DD' Dry base Dry Low Oil CC' Oil DD' Dry base Dry Low
NO-LOAD LOSSES W 1100 935 2000 1735 1700 1445 2800 2670 2500 2125 4300 4130 3800 3230 7000 5540
LOAD LOSSES 75 ºC W 9500 8075 8600 7270 14000 11900 10000 9350 22000 18700 18000 14930 34000 28900 27000 26630
TOTAL MASS kg 2715 3157 2530 2800 3900 4210 3840 3900 4925 6065 5350 5410 8885 10108 7660 7710
HEIGHT mm 1890 1800 1560 1620 2090 2090 1830 1820 1925 1915 2040 2130 2485 2415 2470 2410
LENGTE mm 1500 1540 1710 1690 1875 1795 1920 1840 2360 2370 2160 1980 2545 2545 2310 2360
WIDTH mm 950 1800 940 940 1155 2090 940 940 1235 2370 1230 1230 1375 2545 1230 1230
T HS (F) K 65 65 100 100 65 65 100 100 65 65 100 100 65 65 100 100
T LS (H) K 65 65 100 100 65 65 100 100 65 65 100 100 65 65 100 100
SOUND POWER dB(A) 56 51 68 61 68 57 70 67 69 59 74 73 72 60 80 77
EFFICIENCY (*) % 98,94 99,10 98,94 99,10 99,02 99,17 99,20 99,25 99,02 99,17 99,11 99,24 99,06 99,20 99,15 99,20
UNIT COST Euro 8007 10353 10074 11108 10865 12832 14451 14990 13670 17887 17951 19073 24987 29402 25527 27494
UNIT COST % 100 129 126 139 100 118 133 138 100 131 131 140 100 118 102 110
(*) at full load and cos phi = 1
8
4000
10
420
86
1600
10
420
6
Typical Industry Transformer Parameters
1000
10
420
2500
10
420