SlideShare a Scribd company logo
1. Reasons of Cost overrun:
a) 1110- Preliminary Expenses: Due to additional requirement of GT survey, Bore logs to finalise
the location of tunnel portals and bridge piers & abutment, cost has been increased by Rs
9.98 Crs.
b) 1120- Land: Cost escalation due to delays in handing over of land by Forest Deptt. and taking
up the works of the project for about 11 years. Increase in base rate in Forest and revenue
land due to change in land rule, cost of land increased. Land for adit tunnels, approach road of
main tunnels was not considered in DE. Cost of land has increased by Rs. 414.13 Crs.
c) 1130- Structural Engineering works (Formation): In compare to DE, adit length has increased.
Due to land restriction, protection work in yard changed from DE. Due to high cutting, hillside
protection with permanent anchor with shotcrete has been considered and RE wall has been
introduced due to high filling. Due to increase in tunnel length and cavern length in Tessta
station, and price escalation, Cost has increased by Rs. 3763.76 Crs.
d) 1140- Structural Engineering works (P-way): Due the change in rail section, sleeper section
and its fitting and escalation in price, Cost has increased by Rs. 298.75 Crs. In DE, there was no
provision of BLT. Same has been considered in Re as per railway board instruction.
REASON FOR COST OVERRUN
e) 1150- Structural Engineering works (Bridges): After finalization of alignment, span arrangement of
bridges has changed w.r.t. DE, leading to requirement of 13 Major bridges as compared to only 2
major bridges originally. Cost of bridges has increased by Rs. 548.67 Crs.
f) 1160- Structural Engineering works (Station Building): Due to increase in no. of quarter and other
structures and considering Rangpo station as world class station and additional facilities required at
station yards as per operational requirement, cost has increased by Rs. 386.38 Crs.
g) 1180- General charges (Establishment): Due to increase in cost in above mentioned sub-head, D&G
charged has increased by Rs. 303.97 Crs.
h) 1190- General charges (other than Establishment):Due to increase in cost in above mentioned sub-
head, D&G charged has increased. Further 1% cost against Environmental related works and 0.5%
against sport development has been considered and Railway board circular which was not in DE.
Due to this cost has increased by Rs. 187.99 Crs.
i) Additional 6% of GST has been kept in RE due to change in GST rate from 12% to 18% as per Govt.
circular.
j) Escalation due to PVC @20% has been considered on the balance work.
REASON FOR COST OVERRUN (Contd..)
k) Provision of E&M in tunnels: As per DE, sanctioned cost for Electrical work is Rs. 90.49 Cr. In DE,
Railway Electrification work was not included. In proposed RE, revised cost is Rs. 1577.14Cr. for E&M
works and Rs.171.59 Cr. for Railway Electrification works. Proposed RE cost is Rs.1748.73 Cr. Other
than escalation, variation in this cost is Rs. 1512.67 Cr due to change in power supply arrangement,
addition of DG set, Yard Illumination, Utilities shifting work, now integrated substation is proposed for
OHE & Tunnel at Rangpo, change in nos of quarters, consideration of Tunnel ventilation for the tunnels
having length more than 4 Km or nearby 4 Km i.e. T-1, T-4,T-6,T-7, Underground Teesta Station, T-8 &
T-10, provision of scope for SCADA, firefighting and safety system in tunnel.
Railway Electrification has been included in the RE as per Railway board letter no.
2015/W1/NF/NL/Sivok-Rangpo/Pt-1 dt. 15.07.2022 .
REASON FOR COST OVERRUN (Contd..)
l) Provision of S&T : As per DE, sanctioned cost for S&T work is Rs. 75.48 Cr. As per proposed RE, this
amount proposed is Rs. 225.89 Cr with a variation of Rs. 150.40 Cr on account of escalation other than
price escalation. This variation is due to (i) Provision of Centralized Architecture of Electronic
Interlocking for Multiple stations for the entire section in lieu of Relay interlocking at all four stations,
(ii) Provision of IP based Tunnel communication in entire section. (iii) Provision of CCTV surveillance
system, Radio Communication, fire retardant low smoke cable, in Tunnel, (iv) Provision of
PA/Emergency call system for tunnel longer than 2 km, (v) Take off point will be from Sivok where
complete yard remodeling with shifting of entire existing Station yard 1s involved. This variation also
includes increase in GST from 12% to 18% and Rs. 16.91 Cr. against IRCON's profit.
m) Provision of Mechanical :The sanctioned DE amount for Mechanical department work is Rs. 0.28 Cr
which is increased to Rs. 93.06 Cr in the proposed RE. There is an increase of Rs. 92.79 Cr in the RE.
Provision of only M&P work has been kept which increased by Rs. 92.79 Cr in the RE as per
requirement.
REASON FOR COST OVERRUN (Contd..)

More Related Content

Similar to Cost Overrun SRRP.pptx

Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019
Munir Hussain
 
59323623 1943-g-g-001-r c
59323623 1943-g-g-001-r c59323623 1943-g-g-001-r c
59323623 1943-g-g-001-r c
homeworkping4
 
Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...
Jogani Reinforcement
 
Buddha international circuit material
Buddha international circuit materialBuddha international circuit material
Buddha international circuit material
Utkarsh Rastogi
 
Technological and Cost based comparison of NGPON
Technological and Cost based comparison of NGPONTechnological and Cost based comparison of NGPON
Technological and Cost based comparison of NGPON
RAHUL KANEKAR
 
Plan for all, build for 5G. Strategies for designing a heterogeneous fiber ne...
Plan for all, build for 5G. Strategies for designing a heterogeneous fiber ne...Plan for all, build for 5G. Strategies for designing a heterogeneous fiber ne...
Plan for all, build for 5G. Strategies for designing a heterogeneous fiber ne...
Comsof
 
Buddh international circuit
Buddh international circuitBuddh international circuit
Buddh international circuit
Chandradarshan Jain
 
Crossrail - Integrated Assurance, 17 May 2016,
Crossrail - Integrated Assurance, 17 May 2016, Crossrail - Integrated Assurance, 17 May 2016,
Crossrail - Integrated Assurance, 17 May 2016,
Association for Project Management
 
Jamsheer P_CV (1)
Jamsheer P_CV (1)Jamsheer P_CV (1)
Jamsheer P_CV (1)jamsheer p
 
New Persentation
New PersentationNew Persentation
New PersentationTarek Fagal
 
Amended CV of Eng. Ibrahim A.A. march 2015
Amended CV of Eng. Ibrahim A.A.   march 2015Amended CV of Eng. Ibrahim A.A.   march 2015
Amended CV of Eng. Ibrahim A.A. march 2015Ibrahim Consultant
 
Performance evaluation of comprehensive bandwidth utilization for 10-gigabit ...
Performance evaluation of comprehensive bandwidth utilization for 10-gigabit ...Performance evaluation of comprehensive bandwidth utilization for 10-gigabit ...
Performance evaluation of comprehensive bandwidth utilization for 10-gigabit ...
journalBEEI
 
smartparkannb.pdf
smartparkannb.pdfsmartparkannb.pdf
smartparkannb.pdf
ssuserdee857
 
Tower sharing concept
Tower sharing conceptTower sharing concept
Tower sharing conceptPaul Jacob
 
Tower sharing concept
Tower sharing conceptTower sharing concept
Tower sharing conceptPaul Jacob
 
Project Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptProject Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.ppt
AkdDeshmukh
 
Sirrs Materials Day 2010 - C-Power
Sirrs Materials Day 2010 - C-PowerSirrs Materials Day 2010 - C-Power
Sirrs Materials Day 2010 - C-PowerSirris
 

Similar to Cost Overrun SRRP.pptx (20)

Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019
 
59323623 1943-g-g-001-r c
59323623 1943-g-g-001-r c59323623 1943-g-g-001-r c
59323623 1943-g-g-001-r c
 
DML CV 17
DML CV 17DML CV 17
DML CV 17
 
Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...
 
Buddha international circuit material
Buddha international circuit materialBuddha international circuit material
Buddha international circuit material
 
Technological and Cost based comparison of NGPON
Technological and Cost based comparison of NGPONTechnological and Cost based comparison of NGPON
Technological and Cost based comparison of NGPON
 
Plan for all, build for 5G. Strategies for designing a heterogeneous fiber ne...
Plan for all, build for 5G. Strategies for designing a heterogeneous fiber ne...Plan for all, build for 5G. Strategies for designing a heterogeneous fiber ne...
Plan for all, build for 5G. Strategies for designing a heterogeneous fiber ne...
 
Buddh international circuit
Buddh international circuitBuddh international circuit
Buddh international circuit
 
Crossrail - Integrated Assurance, 17 May 2016,
Crossrail - Integrated Assurance, 17 May 2016, Crossrail - Integrated Assurance, 17 May 2016,
Crossrail - Integrated Assurance, 17 May 2016,
 
Jamsheer P_CV (1)
Jamsheer P_CV (1)Jamsheer P_CV (1)
Jamsheer P_CV (1)
 
New Persentation
New PersentationNew Persentation
New Persentation
 
Amended CV of Eng. Ibrahim A.A. march 2015
Amended CV of Eng. Ibrahim A.A.   march 2015Amended CV of Eng. Ibrahim A.A.   march 2015
Amended CV of Eng. Ibrahim A.A. march 2015
 
Highway Project
Highway ProjectHighway Project
Highway Project
 
Resume
ResumeResume
Resume
 
Performance evaluation of comprehensive bandwidth utilization for 10-gigabit ...
Performance evaluation of comprehensive bandwidth utilization for 10-gigabit ...Performance evaluation of comprehensive bandwidth utilization for 10-gigabit ...
Performance evaluation of comprehensive bandwidth utilization for 10-gigabit ...
 
smartparkannb.pdf
smartparkannb.pdfsmartparkannb.pdf
smartparkannb.pdf
 
Tower sharing concept
Tower sharing conceptTower sharing concept
Tower sharing concept
 
Tower sharing concept
Tower sharing conceptTower sharing concept
Tower sharing concept
 
Project Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptProject Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.ppt
 
Sirrs Materials Day 2010 - C-Power
Sirrs Materials Day 2010 - C-PowerSirrs Materials Day 2010 - C-Power
Sirrs Materials Day 2010 - C-Power
 

Recently uploaded

J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 

Recently uploaded (20)

J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 

Cost Overrun SRRP.pptx

  • 1. 1. Reasons of Cost overrun: a) 1110- Preliminary Expenses: Due to additional requirement of GT survey, Bore logs to finalise the location of tunnel portals and bridge piers & abutment, cost has been increased by Rs 9.98 Crs. b) 1120- Land: Cost escalation due to delays in handing over of land by Forest Deptt. and taking up the works of the project for about 11 years. Increase in base rate in Forest and revenue land due to change in land rule, cost of land increased. Land for adit tunnels, approach road of main tunnels was not considered in DE. Cost of land has increased by Rs. 414.13 Crs. c) 1130- Structural Engineering works (Formation): In compare to DE, adit length has increased. Due to land restriction, protection work in yard changed from DE. Due to high cutting, hillside protection with permanent anchor with shotcrete has been considered and RE wall has been introduced due to high filling. Due to increase in tunnel length and cavern length in Tessta station, and price escalation, Cost has increased by Rs. 3763.76 Crs. d) 1140- Structural Engineering works (P-way): Due the change in rail section, sleeper section and its fitting and escalation in price, Cost has increased by Rs. 298.75 Crs. In DE, there was no provision of BLT. Same has been considered in Re as per railway board instruction. REASON FOR COST OVERRUN
  • 2. e) 1150- Structural Engineering works (Bridges): After finalization of alignment, span arrangement of bridges has changed w.r.t. DE, leading to requirement of 13 Major bridges as compared to only 2 major bridges originally. Cost of bridges has increased by Rs. 548.67 Crs. f) 1160- Structural Engineering works (Station Building): Due to increase in no. of quarter and other structures and considering Rangpo station as world class station and additional facilities required at station yards as per operational requirement, cost has increased by Rs. 386.38 Crs. g) 1180- General charges (Establishment): Due to increase in cost in above mentioned sub-head, D&G charged has increased by Rs. 303.97 Crs. h) 1190- General charges (other than Establishment):Due to increase in cost in above mentioned sub- head, D&G charged has increased. Further 1% cost against Environmental related works and 0.5% against sport development has been considered and Railway board circular which was not in DE. Due to this cost has increased by Rs. 187.99 Crs. i) Additional 6% of GST has been kept in RE due to change in GST rate from 12% to 18% as per Govt. circular. j) Escalation due to PVC @20% has been considered on the balance work. REASON FOR COST OVERRUN (Contd..)
  • 3. k) Provision of E&M in tunnels: As per DE, sanctioned cost for Electrical work is Rs. 90.49 Cr. In DE, Railway Electrification work was not included. In proposed RE, revised cost is Rs. 1577.14Cr. for E&M works and Rs.171.59 Cr. for Railway Electrification works. Proposed RE cost is Rs.1748.73 Cr. Other than escalation, variation in this cost is Rs. 1512.67 Cr due to change in power supply arrangement, addition of DG set, Yard Illumination, Utilities shifting work, now integrated substation is proposed for OHE & Tunnel at Rangpo, change in nos of quarters, consideration of Tunnel ventilation for the tunnels having length more than 4 Km or nearby 4 Km i.e. T-1, T-4,T-6,T-7, Underground Teesta Station, T-8 & T-10, provision of scope for SCADA, firefighting and safety system in tunnel. Railway Electrification has been included in the RE as per Railway board letter no. 2015/W1/NF/NL/Sivok-Rangpo/Pt-1 dt. 15.07.2022 . REASON FOR COST OVERRUN (Contd..)
  • 4. l) Provision of S&T : As per DE, sanctioned cost for S&T work is Rs. 75.48 Cr. As per proposed RE, this amount proposed is Rs. 225.89 Cr with a variation of Rs. 150.40 Cr on account of escalation other than price escalation. This variation is due to (i) Provision of Centralized Architecture of Electronic Interlocking for Multiple stations for the entire section in lieu of Relay interlocking at all four stations, (ii) Provision of IP based Tunnel communication in entire section. (iii) Provision of CCTV surveillance system, Radio Communication, fire retardant low smoke cable, in Tunnel, (iv) Provision of PA/Emergency call system for tunnel longer than 2 km, (v) Take off point will be from Sivok where complete yard remodeling with shifting of entire existing Station yard 1s involved. This variation also includes increase in GST from 12% to 18% and Rs. 16.91 Cr. against IRCON's profit. m) Provision of Mechanical :The sanctioned DE amount for Mechanical department work is Rs. 0.28 Cr which is increased to Rs. 93.06 Cr in the proposed RE. There is an increase of Rs. 92.79 Cr in the RE. Provision of only M&P work has been kept which increased by Rs. 92.79 Cr in the RE as per requirement. REASON FOR COST OVERRUN (Contd..)