SlideShare a Scribd company logo
BUDDH INTERNATIONAL CIRCUIT
PRESENTED BY: CHANDRADARSHAN JAIN
M.PHARM + MBA (P’CEUTICS)
P007
About Project
India’s Racing Arena
Jaypee International Circuit
Location : Greater Noida ,UP, India
Capacity : 1,20,000
Owner : Jaypee Group
Operator : Jaypee Sports International
Limited
Start : 2007
Opened : Oct. 2011
Construction cost : INR 20 billion
Architect : Hermann Tike
Project Manager : Sameer Gaur
Area : 2,500 acres
Circuit : Fact Sheet
• Length: 5.14km
• Turns: 16
• Highest point of elevation: 14m
• Width of the track: Between 18m – 20m
•
• Top speeds on the circuit: About
• 320km/h, for an F1 car
• Total seating capacity: About 120,000
• Distance from New Delhi: 40km approx.
• Surface : Asphalt concrete with Graywacke
Facts about Construction
In constructing Circuit
4 million cubic ton of Earth
were removed
325000 tons of asphalt were
used
130000 metric cube of
concrete were used
450 km of fiber optic cables
were used
Project Objectives
 Bring the F1 closerto the fans and the indian masses
 Make india a multi-sport country
 Boost to the hotel and tourism industry
 Lift to the country profile
 Potential to generate huge revenues and employment opportunities
Stake
holder
• IOA ( Indian Olympic Association )
• FIA (Federation Internationale de l’Automobile )
• FOA (Formula One Administration )
• JPSK Sports Pvt Ltd
• Participating Teams
• Fans
Tilke GmbH of Aachen, Germany (Design partner)
L & T (General contractor)
Kimley-Horn & Associates (Transportation and urban planning )
Walter P Moore & Associates (Traffic planning and transportation engineering)
Terracon Consultants (Geotechnical engineering & material quality)
Carlson Brigance & Doering inc. (Surveying & infrastructure expertise)
Miro Rivera Architects (Specific designs for structures & facilities)
Siemens (Race control management system)
Teracom + BSNL (Modems)
Airtel (Communication)
BHEL (Power)
BEL (Surveillance equipment)
ESPN-STAR (Telecasting)
Request for proposalRequest for proposal Site Plan
Project Planning
• A main Grand Stand
• 10 Temporary stands to seat more 100000 people
• 3 story cantilever building with 41 garages
• A race control room
• A state art of media center to cater more than 600 media person
• 18 fully furnished team buildings
• Pit zones
• A medical building
• A challenging Circuit
Site Specification
Project Execution
Plan
1. Acquisition of land
2. Construction of roads
3. Construction of first layer of circuit
4. Construction of stadium
5. Construction of pit zones
6. Construction of second layer of circuit
7. Construction of medical building
8. Construction of final layer of circuit
Construction Project - WBS
Work process
In October 2009 Earthwork was started
to build the track
Earth to a layer of 25 cm were compacted to a degree of
97% to make an embankment which will not sink
In July 2010 Project came to Halt Due to
Nature’s Furry
In Oct 2010 Project Geared Up
• Asphalt Specialist Dr Rainer Hart joined the project to construct
the race track
• A high polishing aggregate was required for preventing tire
damage on high speed
• The aggregate was exported from nearly 300 km far from
constructing site
Construction of Race track
The race track was built in five layers :
1st
layer : 25 cm granular sub base
2nd
layer : 20 cm wet macadam
3rd
layer : 9 cm asphalt base coarse ( to withstand ith heavy forces)
4th
layer : 5 cm binder coarse ( to endure the shearing forces from fast running cars)
5th
layer : 4 cm wear in coarse ( asphalt paved over a bind coarse to complete the track)
Construction of main grand stand
Foundation of main grand stand was completely water logged. So the first task in constructing it was to
pump that water.
After pumping water the structure of main grand stand was build from concrete and steel
The main grand stand has :
 A height of 30 m
 Length of 138 m
 56 trusses weighing 40 metric ton each
 40 m cantilever roof with 50000 square meters of
insulated aluminium sheeting
Aluminium sheets were chosen for roofing the main
grand stand due to its durability flexibility and
light weight.
50000 square meter aluminium sheets of 0.9 cm
thickness and 55 m length were used for roofing
the main grand stand.
150 km of fiber optical cables and 450 km of data and electric cables were spread beneath
the track connecting various hi-tech equipment to control room.
This includes :
 Real time video surveillance of race track
 Digital signalling system
 Electronic time keeping system
 50 race track cameras
 33 marshal post
 32 digiflags
Crash barriers of latest technology are employed in circuit to
ensure safety of the each car drivers as well as other people
present in the circuit.
Tec-Pro barriers replacing the tire barriers are employed in
the circuit
Nearly 2000 barriers along with 10 km guard rail 15 km FIA
fencing and 16 km U-drain has been provided in the track
PIT LANE & PIT
GARAGES
Get ready for virtual tour !!!
Buddh international circuit

More Related Content

What's hot

India Heritage Transport Museum
India Heritage Transport MuseumIndia Heritage Transport Museum
India Heritage Transport Museum
Amalist Client Services
 
Indira Gandhi International Airport
Indira Gandhi International AirportIndira Gandhi International Airport
Indira Gandhi International Airport
Archana Kuppast
 
Shyam Thesis Report
Shyam Thesis ReportShyam Thesis Report
Shyam Thesis Report
Shyam Singh
 
Formula 1 impact
Formula 1 impactFormula 1 impact
Formula 1 impact943MANOJ
 
Yas Hotel, Abu Dhabi
Yas Hotel, Abu DhabiYas Hotel, Abu Dhabi
Yas Hotel, Abu Dhabi
Ar. M. Senthil [ senthilmani ]
 
Ihc case study ppt a3
Ihc case study ppt a3Ihc case study ppt a3
Ihc case study ppt a3Rohit Arora
 
FINAL Report AUTOMOBILE MUSEUM
FINAL Report AUTOMOBILE MUSEUMFINAL Report AUTOMOBILE MUSEUM
FINAL Report AUTOMOBILE MUSEUMRaktim Saha
 
Mahindra World City Jaipur, Special Economic Zone, Domestic Tariff Area, Engi...
Mahindra World City Jaipur, Special Economic Zone, Domestic Tariff Area, Engi...Mahindra World City Jaipur, Special Economic Zone, Domestic Tariff Area, Engi...
Mahindra World City Jaipur, Special Economic Zone, Domestic Tariff Area, Engi...
Prashant Yadav
 
National rail museum
National rail museumNational rail museum
National rail museum
Ar. Pragyaa Vashishtha
 
dlf-mall-of-india-case-study.pdf
dlf-mall-of-india-case-study.pdfdlf-mall-of-india-case-study.pdf
dlf-mall-of-india-case-study.pdf
PradeepKumar3041
 
Ferrari world, abu dhabi
Ferrari world, abu dhabiFerrari world, abu dhabi
Ferrari world, abu dhabi
Palak Khandelwal
 
Urban Design- International Convention Centre, Dwarka
Urban Design- International Convention Centre, DwarkaUrban Design- International Convention Centre, Dwarka
Urban Design- International Convention Centre, Dwarka
Arka Majhi
 
World Trade Center Noida | WTC Noida
World Trade Center Noida | WTC NoidaWorld Trade Center Noida | WTC Noida
World Trade Center Noida | WTC Noida
Prashant Singh
 
Indore street study
Indore street studyIndore street study
Indore street study
Prachi Gupta
 
Terminal 3_Indira Gandhi International Airport
Terminal 3_Indira Gandhi International AirportTerminal 3_Indira Gandhi International Airport
Terminal 3_Indira Gandhi International AirportAnkita Kolamkar
 
Common Wealth Games Village Housing.pdf
Common Wealth Games Village Housing.pdfCommon Wealth Games Village Housing.pdf
Common Wealth Games Village Housing.pdf
Deepika Verma
 
46721953 magarpatta-city
46721953 magarpatta-city46721953 magarpatta-city
46721953 magarpatta-cityBhairavi Gupta
 
Raghuleela mall, Vashi
Raghuleela mall, VashiRaghuleela mall, Vashi
Raghuleela mall, Vashiamupatil13
 
Back to future (thesis)
Back to future (thesis)Back to future (thesis)
Back to future (thesis)
Esra'a Hourani
 

What's hot (20)

India Heritage Transport Museum
India Heritage Transport MuseumIndia Heritage Transport Museum
India Heritage Transport Museum
 
Indira Gandhi International Airport
Indira Gandhi International AirportIndira Gandhi International Airport
Indira Gandhi International Airport
 
Shyam Thesis Report
Shyam Thesis ReportShyam Thesis Report
Shyam Thesis Report
 
Ramoji film city
Ramoji film cityRamoji film city
Ramoji film city
 
Formula 1 impact
Formula 1 impactFormula 1 impact
Formula 1 impact
 
Yas Hotel, Abu Dhabi
Yas Hotel, Abu DhabiYas Hotel, Abu Dhabi
Yas Hotel, Abu Dhabi
 
Ihc case study ppt a3
Ihc case study ppt a3Ihc case study ppt a3
Ihc case study ppt a3
 
FINAL Report AUTOMOBILE MUSEUM
FINAL Report AUTOMOBILE MUSEUMFINAL Report AUTOMOBILE MUSEUM
FINAL Report AUTOMOBILE MUSEUM
 
Mahindra World City Jaipur, Special Economic Zone, Domestic Tariff Area, Engi...
Mahindra World City Jaipur, Special Economic Zone, Domestic Tariff Area, Engi...Mahindra World City Jaipur, Special Economic Zone, Domestic Tariff Area, Engi...
Mahindra World City Jaipur, Special Economic Zone, Domestic Tariff Area, Engi...
 
National rail museum
National rail museumNational rail museum
National rail museum
 
dlf-mall-of-india-case-study.pdf
dlf-mall-of-india-case-study.pdfdlf-mall-of-india-case-study.pdf
dlf-mall-of-india-case-study.pdf
 
Ferrari world, abu dhabi
Ferrari world, abu dhabiFerrari world, abu dhabi
Ferrari world, abu dhabi
 
Urban Design- International Convention Centre, Dwarka
Urban Design- International Convention Centre, DwarkaUrban Design- International Convention Centre, Dwarka
Urban Design- International Convention Centre, Dwarka
 
World Trade Center Noida | WTC Noida
World Trade Center Noida | WTC NoidaWorld Trade Center Noida | WTC Noida
World Trade Center Noida | WTC Noida
 
Indore street study
Indore street studyIndore street study
Indore street study
 
Terminal 3_Indira Gandhi International Airport
Terminal 3_Indira Gandhi International AirportTerminal 3_Indira Gandhi International Airport
Terminal 3_Indira Gandhi International Airport
 
Common Wealth Games Village Housing.pdf
Common Wealth Games Village Housing.pdfCommon Wealth Games Village Housing.pdf
Common Wealth Games Village Housing.pdf
 
46721953 magarpatta-city
46721953 magarpatta-city46721953 magarpatta-city
46721953 magarpatta-city
 
Raghuleela mall, Vashi
Raghuleela mall, VashiRaghuleela mall, Vashi
Raghuleela mall, Vashi
 
Back to future (thesis)
Back to future (thesis)Back to future (thesis)
Back to future (thesis)
 

Similar to Buddh international circuit

Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaduct
Jayanta Sen
 
Presentation made during Key Note Addess
Presentation made during Key Note AddessPresentation made during Key Note Addess
Presentation made during Key Note Addess
IEI GSC
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_AkhtarJavad Akhtar
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
Rajesh Prasad
 
TRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfTRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdf
KARTHIKGOUD64
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
Rajesh Prasad
 
TRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGYTRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGY
Yatiraj Battul
 
transtech.pptx
transtech.pptxtranstech.pptx
transtech.pptx
pawankumar491710
 
Metro Work
Metro WorkMetro Work
Metro Work
Rajendra Kumar
 
ADTO Ringlock System introduction and projects list
ADTO Ringlock System introduction and projects listADTO Ringlock System introduction and projects list
ADTO Ringlock System introduction and projects list
Colin Cai
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
Aglaia Connect
 
Trench less Technology
Trench less Technology Trench less Technology
Trench less Technology
Abhimanyu Saraswat
 
Presentation : Future of Civil Engineering
Presentation : Future of Civil EngineeringPresentation : Future of Civil Engineering
Presentation : Future of Civil Engineering
IEI GSC
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
Aditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
Aditya Mane
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan
David H Moloney
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
Raghavendra Raghu
 
Bouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate PresentationBouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate Presentation
Pierre HUBERT
 
Brief introduction of Beijing Yueji
Brief introduction of Beijing YuejiBrief introduction of Beijing Yueji
Brief introduction of Beijing YuejiSales Manager Paul
 
Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014
Mohammed wahab
 

Similar to Buddh international circuit (20)

Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaduct
 
Presentation made during Key Note Addess
Presentation made during Key Note AddessPresentation made during Key Note Addess
Presentation made during Key Note Addess
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
TRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfTRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdf
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
TRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGYTRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGY
 
transtech.pptx
transtech.pptxtranstech.pptx
transtech.pptx
 
Metro Work
Metro WorkMetro Work
Metro Work
 
ADTO Ringlock System introduction and projects list
ADTO Ringlock System introduction and projects listADTO Ringlock System introduction and projects list
ADTO Ringlock System introduction and projects list
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Trench less Technology
Trench less Technology Trench less Technology
Trench less Technology
 
Presentation : Future of Civil Engineering
Presentation : Future of Civil EngineeringPresentation : Future of Civil Engineering
Presentation : Future of Civil Engineering
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
 
Bouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate PresentationBouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate Presentation
 
Brief introduction of Beijing Yueji
Brief introduction of Beijing YuejiBrief introduction of Beijing Yueji
Brief introduction of Beijing Yueji
 
Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014
 

Recently uploaded

English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 

Recently uploaded (20)

English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 

Buddh international circuit

  • 1. BUDDH INTERNATIONAL CIRCUIT PRESENTED BY: CHANDRADARSHAN JAIN M.PHARM + MBA (P’CEUTICS) P007
  • 2. About Project India’s Racing Arena Jaypee International Circuit Location : Greater Noida ,UP, India Capacity : 1,20,000 Owner : Jaypee Group Operator : Jaypee Sports International Limited Start : 2007 Opened : Oct. 2011 Construction cost : INR 20 billion Architect : Hermann Tike Project Manager : Sameer Gaur Area : 2,500 acres
  • 3. Circuit : Fact Sheet • Length: 5.14km • Turns: 16 • Highest point of elevation: 14m • Width of the track: Between 18m – 20m • • Top speeds on the circuit: About • 320km/h, for an F1 car • Total seating capacity: About 120,000 • Distance from New Delhi: 40km approx. • Surface : Asphalt concrete with Graywacke
  • 4. Facts about Construction In constructing Circuit 4 million cubic ton of Earth were removed 325000 tons of asphalt were used 130000 metric cube of concrete were used 450 km of fiber optic cables were used
  • 5. Project Objectives  Bring the F1 closerto the fans and the indian masses  Make india a multi-sport country  Boost to the hotel and tourism industry  Lift to the country profile  Potential to generate huge revenues and employment opportunities
  • 6. Stake holder • IOA ( Indian Olympic Association ) • FIA (Federation Internationale de l’Automobile ) • FOA (Formula One Administration ) • JPSK Sports Pvt Ltd • Participating Teams • Fans
  • 7. Tilke GmbH of Aachen, Germany (Design partner) L & T (General contractor) Kimley-Horn & Associates (Transportation and urban planning ) Walter P Moore & Associates (Traffic planning and transportation engineering) Terracon Consultants (Geotechnical engineering & material quality) Carlson Brigance & Doering inc. (Surveying & infrastructure expertise) Miro Rivera Architects (Specific designs for structures & facilities) Siemens (Race control management system) Teracom + BSNL (Modems) Airtel (Communication) BHEL (Power) BEL (Surveillance equipment) ESPN-STAR (Telecasting)
  • 8. Request for proposalRequest for proposal Site Plan Project Planning
  • 9. • A main Grand Stand • 10 Temporary stands to seat more 100000 people • 3 story cantilever building with 41 garages • A race control room • A state art of media center to cater more than 600 media person • 18 fully furnished team buildings • Pit zones • A medical building • A challenging Circuit Site Specification
  • 10. Project Execution Plan 1. Acquisition of land 2. Construction of roads 3. Construction of first layer of circuit 4. Construction of stadium 5. Construction of pit zones 6. Construction of second layer of circuit 7. Construction of medical building 8. Construction of final layer of circuit
  • 12. Work process In October 2009 Earthwork was started to build the track Earth to a layer of 25 cm were compacted to a degree of 97% to make an embankment which will not sink
  • 13. In July 2010 Project came to Halt Due to Nature’s Furry
  • 14. In Oct 2010 Project Geared Up • Asphalt Specialist Dr Rainer Hart joined the project to construct the race track • A high polishing aggregate was required for preventing tire damage on high speed • The aggregate was exported from nearly 300 km far from constructing site
  • 15. Construction of Race track The race track was built in five layers : 1st layer : 25 cm granular sub base 2nd layer : 20 cm wet macadam 3rd layer : 9 cm asphalt base coarse ( to withstand ith heavy forces) 4th layer : 5 cm binder coarse ( to endure the shearing forces from fast running cars) 5th layer : 4 cm wear in coarse ( asphalt paved over a bind coarse to complete the track)
  • 16. Construction of main grand stand Foundation of main grand stand was completely water logged. So the first task in constructing it was to pump that water. After pumping water the structure of main grand stand was build from concrete and steel The main grand stand has :  A height of 30 m  Length of 138 m  56 trusses weighing 40 metric ton each  40 m cantilever roof with 50000 square meters of insulated aluminium sheeting
  • 17. Aluminium sheets were chosen for roofing the main grand stand due to its durability flexibility and light weight. 50000 square meter aluminium sheets of 0.9 cm thickness and 55 m length were used for roofing the main grand stand.
  • 18. 150 km of fiber optical cables and 450 km of data and electric cables were spread beneath the track connecting various hi-tech equipment to control room. This includes :  Real time video surveillance of race track  Digital signalling system  Electronic time keeping system  50 race track cameras  33 marshal post  32 digiflags
  • 19. Crash barriers of latest technology are employed in circuit to ensure safety of the each car drivers as well as other people present in the circuit. Tec-Pro barriers replacing the tire barriers are employed in the circuit Nearly 2000 barriers along with 10 km guard rail 15 km FIA fencing and 16 km U-drain has been provided in the track
  • 20.
  • 21. PIT LANE & PIT GARAGES
  • 22.
  • 23.
  • 24.
  • 25.
  • 26.
  • 27. Get ready for virtual tour !!!