- The presentation outlines Pretium Resources' Brucejack high-grade underground gold project in British Columbia.
- Brucejack has proven and probable reserves of 6.9 million ounces of gold and is targeting commercial production in 2017.
- A 2014 feasibility study outlined an 18-year mine life producing an average of 404,000 ounces of gold per year at low operating costs of $448/ounce.
- Permitting is underway and the company expects to receive permits in 2015 to begin construction.
- The presentation describes Pretium Resources' high-grade underground Brucejack gold project in British Columbia, Canada, which is expected to begin commercial production in 2017.
- Brucejack has proven and probable reserves of 6.9 million ounces of gold and inferred resources of 6.7 million ounces of gold.
- The project is expected to produce an average of 504,000 ounces of gold annually over its first eight years of an 18-year mine life.
- The feasibility study estimates the project will generate over $2 billion in pre-tax net present value at a gold price of $1,100 per ounce.
- Pretium Resources owns the high-grade gold Brucejack Project in northern British Columbia which is expected to begin commercial production in 2017.
- The project has proven and probable reserves of 6.9 million ounces of gold and is forecast to produce on average 404,000 ounces annually over its 18 year mine life.
- A feasibility study estimates the project will generate over $2 billion in pre-tax net cash flow with an IRR of 34.7% at base case metal prices.
- Pretium Resources owns the high-grade gold Brucejack Project in northern British Columbia which is expected to begin commercial production in 2017.
- Brucejack has proven and probable reserves of 6.9 million ounces of gold and is forecast to produce an average of 404,000 ounces annually over its 18 year mine life.
- The project has a pre-tax net present value of $2.25 billion and internal rate of return of 34.7% at base case metal prices.
- The presentation summarizes Pretium Resources' Brucejack gold project in British Columbia, Canada.
- Brucejack has high-grade gold reserves of 6.9 million ounces and is targeting commercial production in 2017.
- The project has robust economics at gold prices as low as $800/oz, with an 18-year mine life and average annual production of over 400,000 ounces.
- Permitting is well advanced and detailed engineering and site preparation activities are underway to support construction start in 2015.
This document provides an overview of Pretium Resources' Brucejack gold project in British Columbia, Canada. Key points include:
- Brucejack has high-grade gold reserves of 6.9 million ounces in the Valley of the Kings and West Zone deposits.
- The project is expected to have an 18-year mine life producing an average of 404,000 ounces of gold per year.
- The feasibility study estimates strong project economics, with an after-tax IRR of 28.5% and NPV of $1.45 billion at a $1,100/oz gold price.
- Construction is planned to begin in 2015 pending permits, with the goal of achieving commercial production in 2017.
The document discusses Pretium Resources' Brucejack gold project located in British Columbia, Canada, including details on its high-grade reserves, robust economics, low costs, permitting process, and exploration potential. It highlights that Brucejack has estimated reserves of 6.9 million ounces of gold and is targeting initial commercial production in 2017, with an 18 year mine life. The project is expected to produce an average of over 400,000 ounces of gold annually at low all-in sustaining costs.
The document discusses Pretium Resources' Brucejack gold project located in British Columbia, Canada, including details on its high-grade reserves, robust economics, low costs, permitting process, and exploration potential. It highlights that Brucejack has proven and probable reserves of 6.9 million ounces of gold and is targeting initial commercial production in 2017. The project is expected to produce an average of 404,000 ounces of gold annually over its 18 year mine life.
- The document describes the Brucejack gold project located in British Columbia, Canada. It contains high-grade gold reserves and is targeting commercial production in 2017.
- The project is expected to produce an average of 504,000 ounces of gold annually over the first 8 years of an 18 year mine life at low cash costs. It has robust economics even at lower gold prices.
- Permitting is well advanced and community engagement has been ongoing. Detailed engineering is underway in advance of starting construction once final permits are received.
- The presentation describes Pretium Resources' high-grade underground Brucejack gold project in British Columbia, Canada, which is expected to begin commercial production in 2017.
- Brucejack has proven and probable reserves of 6.9 million ounces of gold and inferred resources of 6.7 million ounces of gold.
- The project is expected to produce an average of 504,000 ounces of gold annually over its first eight years of an 18-year mine life.
- The feasibility study estimates the project will generate over $2 billion in pre-tax net present value at a gold price of $1,100 per ounce.
- Pretium Resources owns the high-grade gold Brucejack Project in northern British Columbia which is expected to begin commercial production in 2017.
- The project has proven and probable reserves of 6.9 million ounces of gold and is forecast to produce on average 404,000 ounces annually over its 18 year mine life.
- A feasibility study estimates the project will generate over $2 billion in pre-tax net cash flow with an IRR of 34.7% at base case metal prices.
- Pretium Resources owns the high-grade gold Brucejack Project in northern British Columbia which is expected to begin commercial production in 2017.
- Brucejack has proven and probable reserves of 6.9 million ounces of gold and is forecast to produce an average of 404,000 ounces annually over its 18 year mine life.
- The project has a pre-tax net present value of $2.25 billion and internal rate of return of 34.7% at base case metal prices.
- The presentation summarizes Pretium Resources' Brucejack gold project in British Columbia, Canada.
- Brucejack has high-grade gold reserves of 6.9 million ounces and is targeting commercial production in 2017.
- The project has robust economics at gold prices as low as $800/oz, with an 18-year mine life and average annual production of over 400,000 ounces.
- Permitting is well advanced and detailed engineering and site preparation activities are underway to support construction start in 2015.
This document provides an overview of Pretium Resources' Brucejack gold project in British Columbia, Canada. Key points include:
- Brucejack has high-grade gold reserves of 6.9 million ounces in the Valley of the Kings and West Zone deposits.
- The project is expected to have an 18-year mine life producing an average of 404,000 ounces of gold per year.
- The feasibility study estimates strong project economics, with an after-tax IRR of 28.5% and NPV of $1.45 billion at a $1,100/oz gold price.
- Construction is planned to begin in 2015 pending permits, with the goal of achieving commercial production in 2017.
The document discusses Pretium Resources' Brucejack gold project located in British Columbia, Canada, including details on its high-grade reserves, robust economics, low costs, permitting process, and exploration potential. It highlights that Brucejack has estimated reserves of 6.9 million ounces of gold and is targeting initial commercial production in 2017, with an 18 year mine life. The project is expected to produce an average of over 400,000 ounces of gold annually at low all-in sustaining costs.
The document discusses Pretium Resources' Brucejack gold project located in British Columbia, Canada, including details on its high-grade reserves, robust economics, low costs, permitting process, and exploration potential. It highlights that Brucejack has proven and probable reserves of 6.9 million ounces of gold and is targeting initial commercial production in 2017. The project is expected to produce an average of 404,000 ounces of gold annually over its 18 year mine life.
- The document describes the Brucejack gold project located in British Columbia, Canada. It contains high-grade gold reserves and is targeting commercial production in 2017.
- The project is expected to produce an average of 504,000 ounces of gold annually over the first 8 years of an 18 year mine life at low cash costs. It has robust economics even at lower gold prices.
- Permitting is well advanced and community engagement has been ongoing. Detailed engineering is underway in advance of starting construction once final permits are received.
CIBC Whistler Conference Presentation Jan 23, 2015PretiumR
- The Brucejack Project is a high-grade underground gold project located in British Columbia, Canada that is targeting commercial production in 2017.
- It has proven and probable reserves of 2.9 million tonnes grading 6.9 g/t gold containing 0.6 million ounces of gold in the Valley of the Kings zone.
- The project is expected to produce an average of 404,000 ounces of gold per year over its 18 year mine life, generating robust economics even at lower gold prices.
BMO Capital Markets 24th Global Metals & Mining Conference PresentationPretiumR
The document discusses Pretium Resources' Brucejack gold project in British Columbia, Canada. It summarizes key details about the project including:
- High-grade underground gold reserves of 6.9 million ounces averaging 15.7 g/t gold.
- Robust project economics across different gold price scenarios, with an after-tax IRR of 28.5% and NPV of $1.45 billion at $1,100/oz gold.
- Mine life of 18 years producing an average of 404,000 ounces of gold per year at cash costs of $448/ounce.
- Targeting initial production in 2017 with mill construction and permitting underway.
- The Brucejack Project is a high-grade underground gold project located in British Columbia, Canada that is targeting commercial production in 2017.
- It has high-grade gold reserves in the Valley of the Kings and West Zone deposits totaling 6.9 million ounces of gold and 4.6 million ounces of silver.
- Financing of up to US$540 million is available, representing over 70% of the estimated US$746.7 million capital costs to develop the mine.
- Brucejack is a high-grade gold project located in British Columbia that is fully funded and permitted, with construction underway and commercial production targeted for 2017.
- It has high-grade gold reserves with an average grade of over 6 g/t gold. Underground mining will use longhole stoping with milling and processing on site.
- Economics are robust at various gold prices, with an after-tax IRR over 25% and NPV over $1.5 billion at a $1,100/oz gold price. All-in sustaining costs are estimated at $446/oz.
1. The Brucejack high-grade gold project in British Columbia is fully funded and permitted, with construction underway and commercial production targeted for 2017.
2. The project has high-grade reserves of 6.9 million ounces of gold and 4.6 million ounces of silver and is expected to produce an average of 404,000 ounces of gold per year over its 18-year mine life.
3. Economics are robust at a gold price of $1,100/oz, with an after-tax NPV of $1.55 billion and IRR of 27.4%, and all-in sustaining costs are estimated at $446/oz.
1) The Brucejack high-grade gold project in British Columbia is fully-permitted and construction is underway, with commercial production targeted for 2017.
2) The mine is expected to produce over 7 million ounces of gold over an 18-year mine life at an average grade of over 15 grams per tonne and average annual production of over 500,000 ounces.
3) Construction financing of US$540 million was secured in September 2015, funding over 70% of the estimated US$746 million in capital costs.
The corporate presentation provides an overview of Pretium Resources' high-grade Brucejack gold project located in British Columbia, Canada. Key highlights include high-grade reserves of over 6 million ounces of gold, projected annual production of over 500,000 ounces over the first eight years, and estimated mine life of 18 years. The feasibility study outlines a project with strong economics, including an after-tax IRR of 28.5% and NPV of $1.45 billion at base case metal prices. Permitting is underway and the project remains on schedule for first production in 2017.
1. Pretium Resources outlines plans for its high-grade underground Brucejack gold project in British Columbia, targeting commercial production in 2017.
2. A 2014 feasibility study indicates average annual production of 504,000 ounces of gold over the first eight years of the project's 18-year mine life from high-grade reserves.
3. Project economics are robust, with a pre-tax NPV of $2.25 billion and IRR of 34.7% at base case metal prices.
- The document is a corporate presentation for Pretium Resources Inc. outlining key details of the high-grade Brucejack gold project in British Columbia, Canada.
- The Brucejack project has proven and probable reserves of 2.9 million tonnes grading 6.9 g/t gold and 279 g/t silver for 0.6 million ounces of contained gold and 26 million ounces of contained silver.
- A feasibility study estimates average annual production of 504,000 ounces of gold over the first eight years of an 18-year mine life at estimated all-in sustaining costs of US$448/ounce and after-tax net present value of US$1.45 billion based on US$1,100
- The document is a presentation from CIBC's Mining Royalty Sector Conference in 2013 about creating sustainable value through high quality, long-life deposits.
- It discusses Hudbay Mineral's forward-looking statements and assumptions, projects in Manitoba and Peru, production growth expectations, mineral reserves and resources, funding options including a precious metals stream, and an overview of the Constancia copper project.
2013 Bank of America Merrill Lynch Global Metals, Mining & Steel ConferenceHudbayMinerals
Hudbay Minerals Inc. presented information on its mining projects and provided forward-looking statements regarding anticipated production levels and costs. The presentation discussed Hudbay's 777 mine in Manitoba, its Lalor and Reed projects also in Manitoba, and its Constancia project in Peru. Hudbay stated it expects substantial production growth at its operations between 2012 and 2015, with copper production anticipated to increase 390% and precious metals production projected to rise 115% over that period.
Pretivm owns the Brucejack and Snowfield gold projects in northern British Columbia. The Brucejack project contains a high-grade gold resource and over 5km of existing underground workings. A preliminary economic assessment completed in June 2011 outlined a high-grade underground gold mine at Brucejack. Drilling continues to expand resources with over 50,000 meters planned for 2011. The Snowfield project hosts a large gold-copper porphyry deposit and is included in a joint study with Seabridge examining developing it together with the adjacent KSM project. Pretivm is well funded with supportive shareholders to advance these projects toward production.
Hudbay's Annual and Special Meeting of ShareholdersHudbayMinerals
This document summarizes the annual and special meeting of shareholders for Hudbay Minerals Inc. held on May 10, 2013. It recognizes the passing of Bruce Barraclough in 1947-2013. It provides forward-looking information on Hudbay's production, projects, and financial expectations. However, it notes that actual results may differ due to risks in the mining industry and other factors beyond the company's control.
Hudbay's Annual And Special Meeting of ShareholdersHudbayMinerals
1. The document discusses Hudbay Minerals Inc., a mining company that applies 360-degree expertise to develop long-life, low-cost mines in the Americas.
2. It contains forward-looking statements about Hudbay's projects, operations, and financial and operating performance that are subject to risks and uncertainties.
3. The document provides cautionary notes about the risks of relying on forward-looking statements and explains key assumptions and risk factors that could cause actual results to differ materially.
The Troilus Gold Project is a former gold and copper mine in Quebec, Canada that was believed to be fully exploited after closing in 2010. Recent exploration over the past two years has grown the mineral resource by 129% to 4.71 million ounces of gold equivalent in the indicated category and 1.76 million ounces in the inferred category. The expanded deposit remains open along strike and at depth. Existing infrastructure from the previous mining operations such as roads, power, and a permitted tailings facility are expected to reduce capital costs and timelines for any future development.
RBC Capital Markets' Global Mining & Materials Conference HudbayMinerals
This document provides forward-looking information for Hudbay Minerals regarding its mining projects and production forecasts. It discusses Hudbay's 777, Lalor, and Reed mines in Manitoba and its Constancia project in Peru. The document notes that Hudbay expects to see significant production growth at its projects between 2012 and 2015, with copper production forecast to increase 390% and precious metals production 115%. It also provides an overview of recent developments and milestones at Hudbay's key projects.
Hudbay Minerals is creating sustainable value through high quality, long-life mining deposits. The company achieved several significant milestones in the second quarter of 2012, including beginning initial production at the Lalor mine and accelerating construction activities at the Reed project. Hudbay is on track to meet its 2012 production targets and cost guidance. Construction of the $1.5 billion Constancia project is underway, with financing secured.
This corporate presentation provides an overview of Pretium Resources Inc.'s Brucejack gold project in northern British Columbia, Canada. It highlights the project's high-grade gold resource located in a mining-friendly jurisdiction. The resource includes over 4 million ounces of gold in the measured and indicated categories at the Valley of the Kings zone, which remains open for expansion. A feasibility study is underway to evaluate developing the project. The presentation also cautions readers that mineral resources are not mineral reserves or proven deposits, and that project economics remain to be demonstrated.
1) The document summarizes information about the Denver Gold Forum in September 2015 and the Brucejack gold project in British Columbia, Canada.
2) The Brucejack project contains high-grade gold reserves in the Valley of the Kings and West Zone, with an after-tax NPV of $1.45 billion and IRR of 28.5% at a gold price of $1,100/ounce.
3) Construction financing of $540 million has been announced, consisting of a $350 million loan facility and a $150 million precious metals stream.
January 2013 presentation raq january 14 roth capitalPretiumR
- The corporate presentation outlines a major high-grade gold resource in Canada called the Valley of the Kings, containing 8.5 million ounces of indicated gold resources and 2.9 million ounces of inferred gold resources.
- An underground feasibility study is scheduled for Q2 2013, and the experienced management team aims to develop the mine at the Valley of the Kings zone.
- The document provides details on the exploration and ownership history of the Brucejack project area, including discovery of the high-grade Valley of the Kings zone in 2009-2010. It outlines the geology of the area and locations of the Valley of the Kings and West Zone deposits.
This document discusses three investment opportunities in Pretivm Resources Inc.: 1) The Snowfield Project presents an opportunity for long-term value through a bulk-tonnage gold deposit. 2) The adjacent Brucejack Project has the potential to host a high-grade gold-silver deposit. 3) Pretivm's management team aims to deliver value through advancing exploration and development of the Projects.
The document summarizes a presentation given at the Denver Gold Forum in September 2012. It discusses Pretivm Resources Inc.'s high-grade gold Brucejack Project located in British Columbia, Canada. The project contains over 10 million ounces of gold in the measured and indicated categories with an additional 8 million ounces in inferred. It also outlines plans to advance the project toward production by 2015 through underground exploration, engineering studies, and permitting.
CIBC Whistler Conference Presentation Jan 23, 2015PretiumR
- The Brucejack Project is a high-grade underground gold project located in British Columbia, Canada that is targeting commercial production in 2017.
- It has proven and probable reserves of 2.9 million tonnes grading 6.9 g/t gold containing 0.6 million ounces of gold in the Valley of the Kings zone.
- The project is expected to produce an average of 404,000 ounces of gold per year over its 18 year mine life, generating robust economics even at lower gold prices.
BMO Capital Markets 24th Global Metals & Mining Conference PresentationPretiumR
The document discusses Pretium Resources' Brucejack gold project in British Columbia, Canada. It summarizes key details about the project including:
- High-grade underground gold reserves of 6.9 million ounces averaging 15.7 g/t gold.
- Robust project economics across different gold price scenarios, with an after-tax IRR of 28.5% and NPV of $1.45 billion at $1,100/oz gold.
- Mine life of 18 years producing an average of 404,000 ounces of gold per year at cash costs of $448/ounce.
- Targeting initial production in 2017 with mill construction and permitting underway.
- The Brucejack Project is a high-grade underground gold project located in British Columbia, Canada that is targeting commercial production in 2017.
- It has high-grade gold reserves in the Valley of the Kings and West Zone deposits totaling 6.9 million ounces of gold and 4.6 million ounces of silver.
- Financing of up to US$540 million is available, representing over 70% of the estimated US$746.7 million capital costs to develop the mine.
- Brucejack is a high-grade gold project located in British Columbia that is fully funded and permitted, with construction underway and commercial production targeted for 2017.
- It has high-grade gold reserves with an average grade of over 6 g/t gold. Underground mining will use longhole stoping with milling and processing on site.
- Economics are robust at various gold prices, with an after-tax IRR over 25% and NPV over $1.5 billion at a $1,100/oz gold price. All-in sustaining costs are estimated at $446/oz.
1. The Brucejack high-grade gold project in British Columbia is fully funded and permitted, with construction underway and commercial production targeted for 2017.
2. The project has high-grade reserves of 6.9 million ounces of gold and 4.6 million ounces of silver and is expected to produce an average of 404,000 ounces of gold per year over its 18-year mine life.
3. Economics are robust at a gold price of $1,100/oz, with an after-tax NPV of $1.55 billion and IRR of 27.4%, and all-in sustaining costs are estimated at $446/oz.
1) The Brucejack high-grade gold project in British Columbia is fully-permitted and construction is underway, with commercial production targeted for 2017.
2) The mine is expected to produce over 7 million ounces of gold over an 18-year mine life at an average grade of over 15 grams per tonne and average annual production of over 500,000 ounces.
3) Construction financing of US$540 million was secured in September 2015, funding over 70% of the estimated US$746 million in capital costs.
The corporate presentation provides an overview of Pretium Resources' high-grade Brucejack gold project located in British Columbia, Canada. Key highlights include high-grade reserves of over 6 million ounces of gold, projected annual production of over 500,000 ounces over the first eight years, and estimated mine life of 18 years. The feasibility study outlines a project with strong economics, including an after-tax IRR of 28.5% and NPV of $1.45 billion at base case metal prices. Permitting is underway and the project remains on schedule for first production in 2017.
1. Pretium Resources outlines plans for its high-grade underground Brucejack gold project in British Columbia, targeting commercial production in 2017.
2. A 2014 feasibility study indicates average annual production of 504,000 ounces of gold over the first eight years of the project's 18-year mine life from high-grade reserves.
3. Project economics are robust, with a pre-tax NPV of $2.25 billion and IRR of 34.7% at base case metal prices.
- The document is a corporate presentation for Pretium Resources Inc. outlining key details of the high-grade Brucejack gold project in British Columbia, Canada.
- The Brucejack project has proven and probable reserves of 2.9 million tonnes grading 6.9 g/t gold and 279 g/t silver for 0.6 million ounces of contained gold and 26 million ounces of contained silver.
- A feasibility study estimates average annual production of 504,000 ounces of gold over the first eight years of an 18-year mine life at estimated all-in sustaining costs of US$448/ounce and after-tax net present value of US$1.45 billion based on US$1,100
- The document is a presentation from CIBC's Mining Royalty Sector Conference in 2013 about creating sustainable value through high quality, long-life deposits.
- It discusses Hudbay Mineral's forward-looking statements and assumptions, projects in Manitoba and Peru, production growth expectations, mineral reserves and resources, funding options including a precious metals stream, and an overview of the Constancia copper project.
2013 Bank of America Merrill Lynch Global Metals, Mining & Steel ConferenceHudbayMinerals
Hudbay Minerals Inc. presented information on its mining projects and provided forward-looking statements regarding anticipated production levels and costs. The presentation discussed Hudbay's 777 mine in Manitoba, its Lalor and Reed projects also in Manitoba, and its Constancia project in Peru. Hudbay stated it expects substantial production growth at its operations between 2012 and 2015, with copper production anticipated to increase 390% and precious metals production projected to rise 115% over that period.
Pretivm owns the Brucejack and Snowfield gold projects in northern British Columbia. The Brucejack project contains a high-grade gold resource and over 5km of existing underground workings. A preliminary economic assessment completed in June 2011 outlined a high-grade underground gold mine at Brucejack. Drilling continues to expand resources with over 50,000 meters planned for 2011. The Snowfield project hosts a large gold-copper porphyry deposit and is included in a joint study with Seabridge examining developing it together with the adjacent KSM project. Pretivm is well funded with supportive shareholders to advance these projects toward production.
Hudbay's Annual and Special Meeting of ShareholdersHudbayMinerals
This document summarizes the annual and special meeting of shareholders for Hudbay Minerals Inc. held on May 10, 2013. It recognizes the passing of Bruce Barraclough in 1947-2013. It provides forward-looking information on Hudbay's production, projects, and financial expectations. However, it notes that actual results may differ due to risks in the mining industry and other factors beyond the company's control.
Hudbay's Annual And Special Meeting of ShareholdersHudbayMinerals
1. The document discusses Hudbay Minerals Inc., a mining company that applies 360-degree expertise to develop long-life, low-cost mines in the Americas.
2. It contains forward-looking statements about Hudbay's projects, operations, and financial and operating performance that are subject to risks and uncertainties.
3. The document provides cautionary notes about the risks of relying on forward-looking statements and explains key assumptions and risk factors that could cause actual results to differ materially.
The Troilus Gold Project is a former gold and copper mine in Quebec, Canada that was believed to be fully exploited after closing in 2010. Recent exploration over the past two years has grown the mineral resource by 129% to 4.71 million ounces of gold equivalent in the indicated category and 1.76 million ounces in the inferred category. The expanded deposit remains open along strike and at depth. Existing infrastructure from the previous mining operations such as roads, power, and a permitted tailings facility are expected to reduce capital costs and timelines for any future development.
RBC Capital Markets' Global Mining & Materials Conference HudbayMinerals
This document provides forward-looking information for Hudbay Minerals regarding its mining projects and production forecasts. It discusses Hudbay's 777, Lalor, and Reed mines in Manitoba and its Constancia project in Peru. The document notes that Hudbay expects to see significant production growth at its projects between 2012 and 2015, with copper production forecast to increase 390% and precious metals production 115%. It also provides an overview of recent developments and milestones at Hudbay's key projects.
Hudbay Minerals is creating sustainable value through high quality, long-life mining deposits. The company achieved several significant milestones in the second quarter of 2012, including beginning initial production at the Lalor mine and accelerating construction activities at the Reed project. Hudbay is on track to meet its 2012 production targets and cost guidance. Construction of the $1.5 billion Constancia project is underway, with financing secured.
This corporate presentation provides an overview of Pretium Resources Inc.'s Brucejack gold project in northern British Columbia, Canada. It highlights the project's high-grade gold resource located in a mining-friendly jurisdiction. The resource includes over 4 million ounces of gold in the measured and indicated categories at the Valley of the Kings zone, which remains open for expansion. A feasibility study is underway to evaluate developing the project. The presentation also cautions readers that mineral resources are not mineral reserves or proven deposits, and that project economics remain to be demonstrated.
1) The document summarizes information about the Denver Gold Forum in September 2015 and the Brucejack gold project in British Columbia, Canada.
2) The Brucejack project contains high-grade gold reserves in the Valley of the Kings and West Zone, with an after-tax NPV of $1.45 billion and IRR of 28.5% at a gold price of $1,100/ounce.
3) Construction financing of $540 million has been announced, consisting of a $350 million loan facility and a $150 million precious metals stream.
January 2013 presentation raq january 14 roth capitalPretiumR
- The corporate presentation outlines a major high-grade gold resource in Canada called the Valley of the Kings, containing 8.5 million ounces of indicated gold resources and 2.9 million ounces of inferred gold resources.
- An underground feasibility study is scheduled for Q2 2013, and the experienced management team aims to develop the mine at the Valley of the Kings zone.
- The document provides details on the exploration and ownership history of the Brucejack project area, including discovery of the high-grade Valley of the Kings zone in 2009-2010. It outlines the geology of the area and locations of the Valley of the Kings and West Zone deposits.
This document discusses three investment opportunities in Pretivm Resources Inc.: 1) The Snowfield Project presents an opportunity for long-term value through a bulk-tonnage gold deposit. 2) The adjacent Brucejack Project has the potential to host a high-grade gold-silver deposit. 3) Pretivm's management team aims to deliver value through advancing exploration and development of the Projects.
The document summarizes a presentation given at the Denver Gold Forum in September 2012. It discusses Pretivm Resources Inc.'s high-grade gold Brucejack Project located in British Columbia, Canada. The project contains over 10 million ounces of gold in the measured and indicated categories with an additional 8 million ounces in inferred. It also outlines plans to advance the project toward production by 2015 through underground exploration, engineering studies, and permitting.
The document provides an overview of the Brucejack gold project located in British Columbia, Canada. It details high-grade gold reserves at the project, robust project economics, planned production levels over an 18-year mine life, and a recently announced $540 million construction financing package including a $350 million loan facility and $150 million precious metals stream. The financing funds over 70% of the estimated $746.7 million capital costs for the project and allows commercial production to begin targeting 2017.
1. Pretium Resources outlines plans for its high-grade underground Brucejack gold project in British Columbia, targeting commercial production in 2017.
2. A 2014 feasibility study indicates average annual production of 504,000 ounces of gold over the first eight years of the project's 18-year mine life from high-grade reserves.
3. Project economics are robust, with a pre-tax NPV of $2.25 billion and IRR of 34.7% at base case metal prices.
The document provides an overview of the Brucejack gold project located in British Columbia, Canada. Key points include:
- High-grade underground gold project with commercial production targeted for 2017.
- Robust economics with after-tax NPV of $1.45 billion and IRR of 28.5% at $1,100/oz gold price.
- Reserves of 6.9 million ounces of gold and 26 million ounces of silver in the Valley of the Kings and West Zone deposits.
- Fully financed $540 million construction package provides over 70% of estimated $746 million in capital costs.
- Project is fully permitted and engineering is 55% complete with long lead equipment procurement underway.
This corporate presentation provides an overview of a high-grade underground gold project located in British Columbia, Canada. Key points include:
1) The project is targeting commercial gold production in 2016 with an average annual production of over 400,000 ounces of gold over the first ten years of mine life.
2) Feasibility study results show strong economics including an internal rate of return of over 35% and net present value over $1.7 billion.
3) The project will utilize long-hole stoping mining methods to extract the high-grade gold mineralization found in a broad deformed stockwork system.
4) Community engagement efforts include providing employment and contracting opportunities for local First Nations groups.
Pretivm - Sprott Stansberry Natural Resource Symposium - july 2015PretiumR
1) The Brucejack Project is a high-grade underground gold project located in British Columbia, Canada with commercial production targeted for 2017.
2) It has high-grade gold reserves of 6.9 million ounces in the proven and probable categories. Economic analysis shows robust returns across different gold price scenarios.
3) The mine plan envisions an 18-year mine life producing an average of 404,000 ounces of gold per year at low all-in sustaining cash costs of $448 per ounce.
Pretium Resources owns projects in northern British Columbia that have the potential to deliver value through gold. The Snowfield Project presents an opportunity for long-term value from a bulk-tonnage deposit. The Brucejack Project has the potential to host a high-grade gold-silver deposit. Pretium Resources offers three investment opportunities: a strategic rationale, comparable projects that have created value, and the development of its projects.
- High-grade gold reserves of 6.6 million ounces at the Valley of the Kings deposit located in British Columbia, Canada, based on a feasibility study.
- Robust mineral resources totaling 8.5 million ounces of indicated gold and 2.9 million ounces of inferred gold at the Valley of the Kings deposit.
- Underground bulk sample underway from the high-grade Valley of the Kings zone to aid in mine planning and optimize economics for planned production starting in early 2016.
1. The corporate presentation outlines Pretium Resources' Brucejack high-grade gold project located in British Columbia, Canada, which is targeting commercial production in 2016.
2. The presentation provides details on the project's high-grade underground gold reserves and resources based on drilling from 2010-2013, including the December 2013 resource estimate for the Valley of the Kings which added measured resources and increased the gold grade.
3. The presentation introduces Pretium management and provides maps, cross-sections and plans showing the extensive high-grade gold intercepts encountered in drilling at the Brucejack project to date.
- The presentation outlines Pretium Resources' Brucejack high-grade underground gold project in British Columbia.
- Brucejack has proven and probable reserves of 6.9 million ounces of gold and is targeting commercial production in 2017.
- A 2014 feasibility study outlined an 18-year mine life producing an average of 404,000 ounces of gold per year at low operating costs of $448/ounce.
- Permitting is underway and financing options are being evaluated to fund the estimated $747 million capital costs.
This corporate presentation provides an overview of a high-grade underground gold project located in British Columbia, Canada. Key points include:
- Probable gold reserves of 6.6 million ounces grading 13.6 g/t gold.
- Feasibility study completed in 2013 showing strong project economics including average annual production of 425,700 ounces of gold over the first 10 years of mine life.
- Receipt of permits and environmental assessment certificate anticipated in 2014-2015 allowing for mine construction to be completed in 2015 and commercial production to begin in 2016.
- High-grade gold mineralization, competent ground conditions, and cost effective mining method provide opportunity for robust project economics.
This presentation discusses Pretium Resources Inc.'s high-grade gold Brucejack Project in northern British Columbia:
- The project contains a major high-grade gold resource, with 5.1 million ounces of indicated gold at 16.2 g/t and 5.1 million ounces of inferred gold at 35.0 g/t in the Valley of the Kings zone.
- An underground feasibility study is planned for the second quarter of 2013.
- The Valley of the Kings zone remains open in all directions and offers high-grade gold with a large resource size compared to other mines.
- The corporate presentation summarizes a significant high-grade gold resource of 8.5 million ounces of indicated gold and 2.9 million ounces of inferred gold located in British Columbia, Canada.
- An underground feasibility study is scheduled for Q2 2013 with the goal of achieving commercial gold production in early 2016.
- The Valley of the Kings deposit has a high average grade of 16.4 g/t gold for the indicated resource estimate, higher than many other global gold mines.
- The presentation summarizes Pretium Resources' Brucejack gold project in British Columbia, Canada.
- Brucejack has high-grade gold reserves of 6.9 million ounces and is targeting commercial production in 2017.
- The project has robust economics at gold prices of $800-$1,400 per ounce, with average annual production of 504,000 ounces over the first 8 years.
- Permitting is underway and detailed engineering is being completed to allow for construction start in 2015.
The document discusses a gold opportunity through Pretivm's Brucejack Project and Snowfield Project located in northern British Columbia. It provides details on the high-grade resources identified at Brucejack through extensive past drilling campaigns and underground development. A preliminary economic assessment completed in June 2011 for the high-grade portion of Brucejack showed potential for an underground mine producing gold-silver doré with favorable economics. The document also notes the long-term potential of the larger bulk-tonnage Snowfield Project.
1) The corporate presentation outlines Pretivm's Brucejack gold project located in northern British Columbia, Canada.
2) The project is planned to begin commercial production in 2016 and is expected to produce an average of 425,700 ounces of gold annually for the first 10 years of its 22 year mine life.
3) The feasibility study completed in 2013 estimated after-tax net present value of US$1.76 billion and internal rate of return of 35.7% for the project using base case metals prices and costs.
1) The Brucejack high-grade gold project in British Columbia is fully-permitted and construction is underway, with commercial production targeted for 2017.
2) The mine is expected to produce over 7 million ounces of gold over an 18-year mine life at an average grade of over 15 grams per tonne and average annual production of over 500,000 ounces.
3) Construction financing of US$540 million was secured in September 2015, funding over 70% of the estimated US$746 million in capital costs.
This corporate presentation summarizes Pretivm Resources' Brucejack gold project in British Columbia, Canada. Key highlights include high-grade underground gold reserves of over 6 million ounces, projected annual production of over 500,000 ounces over the first eight years, and estimated net present value over $1 billion based on the feasibility study. The presentation also provides details on project economics, mining plans, processing, permitting status, and anticipated project financing.
1. The corporate presentation outlines plans for the high-grade Brucejack gold project in British Columbia, Canada, which is targeting commercial production in 2017.
2. An updated feasibility study estimates 6.9 million ounces of gold reserves and low all-in sustaining costs of $448/ounce over the 18-year mine life.
3. Key milestones over the next 12 months include permitting, engineering work, and finalizing financing to make a production decision in the first half of 2015.
1) The Brucejack high-grade gold project in northern British Columbia is fully funded and permitted, with construction underway and commercial production targeted for 2017.
2) The project has estimated reserves of 6.9 million ounces of gold and 26.0 million ounces of silver and a mine life of 18 years producing on average 404,000 ounces of gold annually.
3) Economics of the project show strong returns with an after-tax IRR of 27.4% and NPV of $1.55 billion using $1,100/oz gold price and all-in sustaining costs of $446/oz over its mine life.
- Pretivm Resources is developing the high-grade underground Brucejack gold mine in northern British Columbia, with commercial production targeted for 2017.
- Brucejack hosts high-grade gold reserves of 6.9 million ounces in the Valley of the Kings, with an average grade of 15.7 g/t gold.
- Construction is well underway, with the project fully funded at an estimated capital cost of $696.8 million. Once in production, Brucejack is expected to be one of the highest-grade large-scale gold mines in the world.
1. The Brucejack high-grade gold project in British Columbia is fully funded and permitted, with construction underway and commercial production targeted for 2017.
2. The project has high-grade gold reserves in the Valley of the Kings zone, with proven and probable reserves of 6.9 million ounces of gold and 26 million ounces of silver.
3. Underground mining will use longhole stoping methods on 30m level spacing to extract ore grading over 15 g/t gold. Waste rock and tailings will be deposited in engineered facilities.
The document provides an overview of the Brucejack gold project located in British Columbia, Canada. Key points include:
- High-grade underground gold project with commercial production targeted for 2017.
- Robust economics with after-tax NPV of $1.45 billion and IRR of 28.5% at $1,100/oz gold price.
- Reserves of 6.9 million ounces of gold and 26 million ounces of silver with average annual production of 404,000 ounces over 18-year mine life.
- $746 million construction financing package covers over 70% of estimated capital costs.
- Project is fully permitted and engineering is 55% complete with long lead items in procurement.
The document summarizes plans for the Brucejack gold project in British Columbia, Canada. It outlines details of the high-grade gold reserves, robust project economics showing over $2 billion in NPV, planned production of over 500,000 ounces of gold annually for the first 8 years, and recently announced $540 million in financing including a $350 million loan facility and $150 million precious metals stream to fund over 70% of the estimated $746 million in capital costs needed to bring the project into commercial production by 4th quarter 2017.
This document provides an overview and update on the Brucejack gold project located in northern British Columbia, Canada. Key points include:
- Brucejack is a high-grade underground gold project that is fully permitted and funded, with commercial production targeted for 2017.
- Updated mineral reserves estimate shows 6.9 million ounces of gold and 4.6 million ounces of silver in the proven and probable categories.
- Underground infill drilling program was completed in 2015-2016 to upgrade resources closer to planned mining areas. Drilling intersected high gold grades, including 0.5m at 37,117 g/t Au and 0.5m at 41,582 g/t Au.
- Project economics from
This corporate presentation provides an overview of Pretium Resources' Brucejack high-grade gold project located in northern British Columbia, Canada. Key highlights include:
- The project contains over 6 million ounces of high-grade gold in the measured and indicated categories with an average grade of over 14 g/t gold.
- Underground mining is planned at a rate of 2,700 tonnes per day over a 22 year mine life to produce over 7 million ounces of gold.
- The 2014 feasibility study will incorporate updates to the resource model, mine plan, and processing based on recent bulk sampling, and is expected in Q2 2014.
- Permitting and environmental assessment applications are underway.
The document provides an overview of Pretium Resources Inc. and its Brucejack high-grade gold project in northern British Columbia. Construction is underway, with commercial production targeted for 2017. The project is fully funded and has high-grade reserves of 8.1 million ounces of gold. The economics are robust even at lower gold prices, with an after-tax IRR of 16.8-36.3% and payback of 3.5-5 years depending on gold price. The project is open in multiple directions, offering potential to expand resources and reserves as exploration continues.
The document summarizes information about Pretium Resources Inc.'s Brucejack gold project in British Columbia, Canada. Key points include:
- Brucejack is a high-grade underground gold mine that is fully funded and permitted, with construction underway and commercial production targeted for 2017.
- It has high-grade gold reserves of 6.9 million ounces in the Valley of the Kings zone. The mine life is estimated at 18 years with an average annual production of 504,000 ounces in the first eight years.
- The project has robust economics with an after-tax NPV of $1.55 billion and IRR of 27.4% at a $1,100/oz gold price. The project
1. Pretium Resources is advancing the high-grade Brucejack gold project located in northern British Columbia, Canada.
2. Construction is advancing at the Brucejack project, with the mill building nearing completion and underground infrastructure being developed.
3. The Brucejack project has high-grade gold reserves in the Valley of Kings and West Zone deposits totaling 15.6 million tonnes grading 16.1 g/t gold containing 8.1 million ounces of gold.
1) Pretivm Resources is advancing construction of its high-grade Brucejack gold mine in British Columbia, with commissioning targeted for early 2017.
2) The mine is fully funded and expected to produce an average of 504,000 ounces of gold annually for the first eight years of an 18-year mine life at low all-in sustaining costs.
3) Construction is nearing completion, with all major equipment delivered and installed, over 140,000 tonnes of ore stockpiled, and underground development advanced with 12 stopes prepared for production.
Similar to Corporate Presentation July 3, 2014 (14)
The document discusses Pretivm's Brucejack Mine, which has been generating cash since start-up in November 2019. It provides cautionary statements regarding the use of forward-looking information in the presentation. It also notes that certain technical and scientific information is derived from Pretivm's NI 43-101 technical report on the Brucejack Gold Mine from April 2019.
The document summarizes Pretivm's 2019 Mineral Reserve update for its Brucejack Mine. Key points include:
- The Valley of Kings Reserves were updated using updated costs, stope design parameters, and net smelter return model. No changes were made to the West Zone reserves.
- Mining costs were updated based on projected costs for 3,800 tonnes per day production, and are greater than the life of mine costs. The net smelter return cut-off increased to $185/tonne from $165/tonne previously.
- Total mining costs increased to $127.20/tonne from $91.30/tonne previously due to factors like increased development and use of
The document discusses Pretivm Resources' Brucejack Mine, a high-grade underground gold mine in British Columbia. It notes that the mine has consistently been profitable. It cautions readers that the presentation contains forward-looking statements regarding anticipated results, costs, plans, estimates, assumptions, and other projections that involve risks and uncertainties. It also provides notes to investors on the technical information sources, definitions of resource estimates, and explanations of non-IFRS financial metrics.
BMO Capital Markets 28th Global Metals & Mining ConferencePretiumR
1) The Brucejack Mine in British Columbia has consistently generated profits every quarter since start-up six quarters ago through high-grade underground gold production and low costs.
2) In 2018 the mine produced over 376,000 ounces of gold at a total cash cost of $764 per ounce on average and generated over $20 million in adjusted net earnings.
3) For 2019 the mine is targeting production of 390,000 to 420,000 ounces of gold at an all-in sustaining cost of $775 to $875 per ounce through continued ramp up to 3,800 tonnes per day.
Pretium resources q1 2018 conference call may 11 , 2018PretiumR
The document discusses Pretium Resources' Q1 2018 conference call about its Brucejack gold mine. Some key points:
- Pretium produced 75,689 ounces of gold in Q1 2018 and is ramping up to steady-state production mid-to-late 2018.
- Production levels improved month-over-month in Q1 with the implementation of improved grade control.
- All-in sustaining costs were $1,009/ounce in Q1 but are expected to decrease as production levels out.
- The company had $70.5 million in cash and $16.8 million in earnings in Q1 2018.
Pvg investors day presentation april 11 2018PretiumR
This document provides an overview of Pretium Resources' Brucejack gold mine in Canada. Some key points:
- Production is ramping up steadily, on track to meet guidance of 150,000-200,000 ounces for the first half of 2018.
- Grade control efforts including infill drilling and longhole sampling are improving short-term grade prediction to optimize mining.
- An independent review confirmed the geological model and noted some minor grade management issues being addressed. Further drilling is being done to improve grade control model resolution.
- The mine plan is being refined based on the improved grade control model to maximize high gold grades from the deposit.
Fourth Quarter 2017 Financial Results Webcast and Conference CallPretiumR
- The document discusses the ramp up of production at Pretium Resources' Brucejack Mine in northern British Columbia. Key highlights include producing over 150,000 ounces of gold in the first six months of operations and ending 2017 with a cash position of $56.3 million. Operations are being optimized to increase productivity and refine grade control. Guidance for 2018 anticipates gold production of 150,000-200,000 ounces at an all-in sustaining cost of $900-$1,000 per ounce sold.
1. The document discusses Pretium Resources' Brucejack Mine, an underground gold mine in British Columbia, Canada that is ramping up production.
2. In the first 6 months of production, the mine produced over 150,000 ounces of gold. Pretium is focused on optimizing operations, delivering on guidance of 150,000-200,000 ounces of gold production in 2018, and increasing the production rate to 3,800 tonnes per day.
3. Pretium also discusses organic growth opportunities through reserve expansion drilling and regional exploration, as well as positioning the Brucejack Mine to be a low-cost producer in 2019.
Ramping Up Brucejack - Presented at the BMO Capital Markets ConferencePretiumR
1. The Brucejack Mine is an underground gold mine in British Columbia that has produced over 150,000 ounces of gold in its first six months of operation.
2. Management is focused on optimizing operations through increasing operational efficiency, improving grade control, and delivering on its 2018 production guidance of 150,000-200,000 ounces of gold at an all-in sustaining cost of $900-$700 per ounce sold.
3. Exploration potential exists to expand resources locally and regionally around the Brucejack Mine.
1) The document discusses Brucejack, a high-grade underground gold mine in British Columbia that is ramping up production. In its first 6 months, it produced over 150,000 ounces of gold.
2) The company is focused on optimizing operations through grade control programs like reverse circulation drilling and a sample splitting station to reduce dilution and improve grade reconciliation.
3) Mineral reserves are estimated at over 8 million ounces of gold in proven and probable categories. The company is expanding stope accessibility in higher grade areas to increase production.
4) Production guidance for 2018 is 150,000 to 200,000 ounces of gold at an all-in sustaining cost of $675 to $825 per ounce
1) The document discusses Brucejack, a high-grade underground gold mine in British Columbia that is ramping up production. In its first 6 months, it produced over 150,000 ounces of gold.
2) The company is focused on optimizing operations through grade control programs like reverse circulation drilling and a sample splitting station to reduce dilution and improve grade reconciliation.
3) Mineral reserves are estimated at over 8 million ounces of gold in proven and probable categories. The company is expanding stope accessibility in higher grade areas to increase production.
4) Production guidance for the year is 150,000 to 200,000 ounces of gold at an all-in sustaining cost of $675 to $825 per
Ramping Up Brucejack – Presented at the Scotiabank Mining ConferencePretiumR
Pretium Resources is ramping up production at its high-grade Brucejack gold mine in British Columbia, Canada. In the third quarter of 2017, Brucejack produced over 82,000 ounces of gold and achieved commercial production rates. Pretium aims to further increase production and explore regional targets to expand reserves.
Ramping Up Brucejack Mine - Presented at the AFund Natural Resource Symposium...PretiumR
Pretium Resources is ramping up production at its high-grade Brucejack gold mine in British Columbia, Canada. The mine achieved commercial production rates in July 2017 and produced over 82,000 ounces of gold in the third quarter. Pretium aims to optimize operations and achieve steady-state production by the end of 2017. Exploration is also underway to expand reserves near Brucejack and in the surrounding region.
Pretium Resources is ramping up production at its high-grade Brucejack gold mine in British Columbia, Canada. The mine achieved commercial production rates in July 2017 and produced over 82,000 ounces of gold in the third quarter. Pretium aims to optimize ore blending and achieve steady-state production by the end of 2017. Exploration is also underway to expand reserves near Brucejack and in the surrounding region.
The document discusses Pretium Resources' Brucejack Mine in British Columbia, Canada. It provides details on:
1) Ramping up production at the high-grade underground gold mine, with commercial production expected to be reached by the end of Q4 2017.
2) The mine has high-grade gold reserves and is expected to have a mine life of 18 years at an average annual production rate of 404,000 ounces of gold.
3) Exploration potential exists to expand reserves both near Brucejack and at the Bowser regional target located 5km away.
Pretium Resources Inc. operates the high-grade gold Brucejack Mine in northern British Columbia, Canada. The summary discusses:
1) Brucejack has high-grade gold reserves of over 8 million ounces and an 18-year mine life at an average annual production of 404,000 ounces.
2) Commissioning of the mine and mill is underway, with commercial production expected by the end of 2017. Ramp up of production to steady state levels is the focus for the remainder of the year.
3) Exploration is targeting expansion of reserves within the mine area and at nearby targets such as Bowser to extend mine life.
The document provides information about a Brucejack Mine tour scheduled for August 15-17, 2017. It includes forward-looking statements and cautions about risks. The mine has been ramping up production, with wet commissioning complete in May and achieving commercial processing rates in July. Optimization of the mill is ongoing, focusing on gravity recoverable gold. Financially, the mine is targeting positive cash flow by the end of Q3 2017. The document also discusses reserve expansion potential, exploration at nearby Bowser, and plans to expand Brucejack production capacity. It provides details on the geology, structural geology, grade control processes, underground development including longhole stoping, and the ore handling system.
Pretium Resources is advancing the high-grade Brucejack gold mine in northern British Columbia, Canada. Commissioning of the mine is nearing completion as operations ramp up towards commercial production. The mine has high-grade gold reserves and is expected to have low operating costs. Pretium is also exploring for additional resources in the region around Brucejack.
RBC Global Mining & Materials Conference 2017PretiumR
- Brucejack is a high-grade underground gold mine located in British Columbia that is nearing commissioning and ramping up to commercial production. It has high-grade gold reserves and is expected to have low operating costs.
- The mine has an 18-year mine life and is expected to produce over 7 million ounces of gold over its lifetime at an average annual production rate of over 400,000 ounces. It has high gold and silver recoveries from its processing facilities.
- Economic studies show strong project economics across a range of gold prices, with an after-tax IRR of over 28% and payback of less than 3.5 years at a gold price of $1,100 per ounce. Commissioning
- The document discusses the Brucejack gold mine located in British Columbia, Canada. It provides details on the mine's high-grade gold reserves, planned production levels over an 18 year mine life, and robust project economics.
- Construction of the Brucejack mine has been advancing over the past few years, with ore now being introduced to the mill. Commissioning of the mine is nearing completion.
- The mine has the potential for further exploration in the surrounding areas to expand resources. Community engagement efforts have focused on employment and commercial opportunities for local First Nations groups.
This presentation by Thibault Schrepel, Associate Professor of Law at Vrije Universiteit Amsterdam University, was made during the discussion “Artificial Intelligence, Data and Competition” held at the 143rd meeting of the OECD Competition Committee on 12 June 2024. More papers and presentations on the topic can be found at oe.cd/aicomp.
This presentation was uploaded with the author’s consent.
This presentation by Juraj Čorba, Chair of OECD Working Party on Artificial Intelligence Governance (AIGO), was made during the discussion “Artificial Intelligence, Data and Competition” held at the 143rd meeting of the OECD Competition Committee on 12 June 2024. More papers and presentations on the topic can be found at oe.cd/aicomp.
This presentation was uploaded with the author’s consent.
This presentation by Yong Lim, Professor of Economic Law at Seoul National University School of Law, was made during the discussion “Artificial Intelligence, Data and Competition” held at the 143rd meeting of the OECD Competition Committee on 12 June 2024. More papers and presentations on the topic can be found at oe.cd/aicomp.
This presentation was uploaded with the author’s consent.
This presentation by OECD, OECD Secretariat, was made during the discussion “Artificial Intelligence, Data and Competition” held at the 143rd meeting of the OECD Competition Committee on 12 June 2024. More papers and presentations on the topic can be found at oe.cd/aicomp.
This presentation was uploaded with the author’s consent.
XP 2024 presentation: A New Look to Leadershipsamililja
Presentation slides from XP2024 conference, Bolzano IT. The slides describe a new view to leadership and combines it with anthro-complexity (aka cynefin).
This presentation by Professor Giuseppe Colangelo, Jean Monnet Professor of European Innovation Policy, was made during the discussion “The Intersection between Competition and Data Privacy” held at the 143rd meeting of the OECD Competition Committee on 13 June 2024. More papers and presentations on the topic can be found at oe.cd/ibcdp.
This presentation was uploaded with the author’s consent.
Why Psychological Safety Matters for Software Teams - ACE 2024 - Ben Linders.pdfBen Linders
Psychological safety in teams is important; team members must feel safe and able to communicate and collaborate effectively to deliver value. It’s also necessary to build long-lasting teams since things will happen and relationships will be strained.
But, how safe is a team? How can we determine if there are any factors that make the team unsafe or have an impact on the team’s culture?
In this mini-workshop, we’ll play games for psychological safety and team culture utilizing a deck of coaching cards, The Psychological Safety Cards. We will learn how to use gamification to gain a better understanding of what’s going on in teams. Individuals share what they have learned from working in teams, what has impacted the team’s safety and culture, and what has led to positive change.
Different game formats will be played in groups in parallel. Examples are an ice-breaker to get people talking about psychological safety, a constellation where people take positions about aspects of psychological safety in their team or organization, and collaborative card games where people work together to create an environment that fosters psychological safety.
Carrer goals.pptx and their importance in real lifeartemacademy2
Career goals serve as a roadmap for individuals, guiding them toward achieving long-term professional aspirations and personal fulfillment. Establishing clear career goals enables professionals to focus their efforts on developing specific skills, gaining relevant experience, and making strategic decisions that align with their desired career trajectory. By setting both short-term and long-term objectives, individuals can systematically track their progress, make necessary adjustments, and stay motivated. Short-term goals often include acquiring new qualifications, mastering particular competencies, or securing a specific role, while long-term goals might encompass reaching executive positions, becoming industry experts, or launching entrepreneurial ventures.
Moreover, having well-defined career goals fosters a sense of purpose and direction, enhancing job satisfaction and overall productivity. It encourages continuous learning and adaptation, as professionals remain attuned to industry trends and evolving job market demands. Career goals also facilitate better time management and resource allocation, as individuals prioritize tasks and opportunities that advance their professional growth. In addition, articulating career goals can aid in networking and mentorship, as it allows individuals to communicate their aspirations clearly to potential mentors, colleagues, and employers, thereby opening doors to valuable guidance and support. Ultimately, career goals are integral to personal and professional development, driving individuals toward sustained success and fulfillment in their chosen fields.
This presentation by Professor Alex Robson, Deputy Chair of Australia’s Productivity Commission, was made during the discussion “Competition and Regulation in Professions and Occupations” held at the 77th meeting of the OECD Working Party No. 2 on Competition and Regulation on 10 June 2024. More papers and presentations on the topic can be found at oe.cd/crps.
This presentation was uploaded with the author’s consent.
This presentation by OECD, OECD Secretariat, was made during the discussion “The Intersection between Competition and Data Privacy” held at the 143rd meeting of the OECD Competition Committee on 13 June 2024. More papers and presentations on the topic can be found at oe.cd/ibcdp.
This presentation was uploaded with the author’s consent.
This presentation by Tim Capel, Director of the UK Information Commissioner’s Office Legal Service, was made during the discussion “The Intersection between Competition and Data Privacy” held at the 143rd meeting of the OECD Competition Committee on 13 June 2024. More papers and presentations on the topic can be found at oe.cd/ibcdp.
This presentation was uploaded with the author’s consent.
The importance of sustainable and efficient computational practices in artificial intelligence (AI) and deep learning has become increasingly critical. This webinar focuses on the intersection of sustainability and AI, highlighting the significance of energy-efficient deep learning, innovative randomization techniques in neural networks, the potential of reservoir computing, and the cutting-edge realm of neuromorphic computing. This webinar aims to connect theoretical knowledge with practical applications and provide insights into how these innovative approaches can lead to more robust, efficient, and environmentally conscious AI systems.
Webinar Speaker: Prof. Claudio Gallicchio, Assistant Professor, University of Pisa
Claudio Gallicchio is an Assistant Professor at the Department of Computer Science of the University of Pisa, Italy. His research involves merging concepts from Deep Learning, Dynamical Systems, and Randomized Neural Systems, and he has co-authored over 100 scientific publications on the subject. He is the founder of the IEEE CIS Task Force on Reservoir Computing, and the co-founder and chair of the IEEE Task Force on Randomization-based Neural Networks and Learning Systems. He is an associate editor of IEEE Transactions on Neural Networks and Learning Systems (TNNLS).
2. 2
CAUTIONARY STATEMENT
Forward Looking Information
This Presentation contains “forward-looking information” and “forward looking statements” within the meaning of applicable Canadian and United States
securities legislation. Forward-looking information may include, but is not limited to, the anticipated production and developments in our operations in future
periods, information with respect to our planned exploration and development activities, the adequacy of our financial resources, the estimation of mineral
reserves and resources including the 2013 Valley of the Kings Mineral Resource estimate, realization of mineral reserve and resource estimates and timing of
development of our Brucejack Project, costs and timing of future exploration, results of future exploration and drilling, production and processing estimates,
capital and operating cost estimates, timelines and similar statements relating to the economic viability of the Brucejack Project, timing and receipt of
approvals, consents and permits under applicable legislation, our executive compensation approach and practice, the composition of our board of directors and
committees and adequacy of financial resources. Wherever possible, words such as “plans”, “expects”, “projects”, “assumes”, “budget”, “strategy”,
“scheduled”, “estimates”, “forecasts”, “anticipates”, “believes”, “intends”, “targets” and similar expressions or statements that certain actions, events or results
“may”, “could”, “would”, “might” or “will” be taken, occur or be achieved, or the negative forms of any of these terms and similar expressions, have been
used to identify forward-looking statements and information. Statements concerning mineral reserve and resource estimates may also be deemed to constitute
forward-looking information to the extent that they involve estimates of the mineralization that will be encountered if the property is developed. Any
statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or
performance are not statements of historical fact and may be forward-looking information. Forward-looking information is subject to a variety of known and
unknown risks, uncertainties and other factors that could cause actual events or results to differ from those expressed or implied by the forward-looking
information, including, without limitation, those risks identified in our Annual Information Form dated March 31, 2014 filed on SEDAR at www.sedar.com and
in the United States on Form 40-F through EDGAR at the SEC’s website at www.sec.gov. Forward-looking information is based on the expectations and
opinions of our management on the date the statements are made. The assumptions used in the preparation of such statements, although considered
reasonable at the time of preparation, may prove to be imprecise. We do not assume any obligation to update forward-looking information, whether as a result
of new information, future events or otherwise, other than as required by applicable law. For the reasons set forth above, prospective investors should not place
undue reliance on forward-looking information.
National Instrument 43-101
Technical and scientific information contained herein relating to the Projects is derived from National Instrument 43-101 (“NI 43-101”) compliant technical
reports (“Reports”) “Mineral Resources Update Technical Report” dated December 19, 2013 and “Feasibility Study and Technical Report on the Brucejack
Project, Stewart, BC” dated June 19, 2014. We have filed the Reports and Update under our profile at www.sedar.com. Technical and scientific information
not contained within the Reports for the Projects have been prepared under the supervision of Mr. Kenneth C. McNaughton, P.Eng. and Ian Chang, P.Eng.,
each of whom is an independent “qualified person” under NI 43-101.
This presentation uses the terms “measured resources”, “indicated resources” (together “M&I”) and “inferred resources”. Although these terms are recognized
and required by Canadian regulations (under NI 43-101), the United States Securities and Exchange Commission does not recognize them. Mineral resources
which are not mineral reserves do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental,
permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. There is no guarantee that all or any part of the mineral resource will be
converted into mineral reserves.
In addition, “inferred resources” have a great amount of uncertainty as to their existence, and economic and legal feasibility. It cannot be assumed that all or
any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian rules, estimates of inferred mineral resources may not
form the basis of feasibility or pre feasibility studies, or economic studies, except for a Preliminary Assessment as defined under NI 43-101. Investors are
cautioned not to assume that part or all of an inferred resource exists, or is economically or legally mineable.
Currency
Unless otherwise indicated, all dollar values herein are in Canadian $.
5. 5
HIGH-GRADE GOLD RESERVES(1,2)
Valley of the Kings
West Zone
Category Tonnes
(mil)
Gold
(g/t)
Silver
(g/t)
Contained
Gold
(mil oz)
Silver
(mil oz)
Proven 1.4 7.2 383 0.3 17.4
Probable 1.5 6.5 181 0.3 8.6
Total P&P 2.9 6.9 279 0.6 26.0
Valley of the Kings Mineral Reserve Estimate – June 2014 West Zone Mineral Reserve Estimate – June 2014
(1) Source: Feasibility Study and Technical Report Update on the Brucejack Project, dated June 19, 2014
(2) Base case metals prices of US$1,100/oz gold and US$17/oz silver
Category Tonnes
(mil)
Gold
(g/t)
Silver
(g/t)
Contained
Gold
(mil oz)
Silver
(mil oz)
Proven 2.1 15.6 12 1.1 0.8
Probable 11.5 15.7 10 5.8 3.9
Total P&P 13.6 15.7 11 6.9 4.6
6. 6
BRUCEJACK PROJECT ECONOMICS
(1) Source: Feasibility Study and Technical Report Update on the Brucejack Project, dated June 19, 2014
(2) NPV is discounted to July 2014.
June 2014 Feasibility Study (1)
Economic Results by Metal Price
Low Case Base Case High Case
Gold / Silver Price
(US$/ounce)
$800 / $15 $1,100 / $17 $1,400 / $21
Capex
(US$million)
$746.9 $746.9 $746.9
Net Cash Flow (US$)
$2.02 billion (pre-tax)
$1.34 billion (post-tax)
$4.16 billion (pre-tax)
$2.72 billion (post-tax)
$6.35 billion (pre-tax)
$4.13 billion (post-tax)
Net Present Value (2)
(5.0% discount) (US$)
$985 million (pre-tax)
$620 million (post-tax)
$2.25 billion (pre-tax)
$1.45 billion (post-tax)
$3.54 billion (pre-tax)
$2.28 billion (post-tax)
Internal Rate of
Return
20.3% (pre-tax)
16.5% (post-tax)
34.7% (pre-tax)
28.5% (post-tax)
47%(pre-tax)
38.7% (post-tax)
Payback (from start of
production period)
4.4 years (pre-tax)
4.5 years (post-tax)
2.7 years (pre-tax)
2.8 years (post-tax)
2.0 years (pre-tax)
2.1 years (post-tax)
Exchange Rate
(US$:C$)
0.92 0.92 0.92
7. 7
BRUCEJACK PROJECT PRODUCTION (1)
• Mine life of 18 years producing an estimated 7.27 million
ounces of gold
• Average annual production of 504,000 ounces of gold
over the first 8 years and 404,000 ounces of gold over
mine life
Gold and silver recoveries of 96.7% and 90.0% over mine
life
Production rate of 2,700 tonnes per day
(1) Source: Feasibility Study and Technical Report Update on the Brucejack Project, dated June 19, 2014
8. 8
BRUCEJACK CAPITAL COSTS
June 2014 Feasibility Study (1)
Capital Cost Summary
(US$ million)
Mine underground 179.5
Mine site (2) 210.8
Offsite Infrastructure 89.1
Total Direct Costs 479.4
Indirect Costs 127.5
Owner’s Costs 71.0
Contingency 69.0
Total Capital Cost 746.9
(1) Source: Feasibility Study and Technical Report Update on the Brucejack Project, dated June 19, 2014
(2) Includes mine site, mine site process, mine site utilities, mine site facilities, tailings facilities, mine site temporary facilities
and surface mobile equipment.
9. 9
BRUCEJACK OPERATING COSTS
June 2014 Feasibility Study (1)
Operating Costs Summary
(C$/tonne)
Mining 91.34 (2)
Processing 19.69
General & Administrative 30.87
Surface Services and Others 21.15
Total Operating Cost 163.05
(1) Source: Feasibility Study and Technical Report Update on the Brucejack Project, dated June 19, 2014
(2) LOM ore milled; if excluding the ore mined during preproduction, the estimated cost is C$91.78/t.
10. 10
COST: HIGH-GRADE ADVANTAGE
June 2014 Feasibility Study (1)
All-In Sustaining Cash Costs Life of Mine
(US$ million)
Total Cash Costs (2) 2,814.5
Reclamation Cost Accretion 27.5
Sustaining Capital Expenditure 320.6
All-in Sustaining Cash Costs 3,162.6
Gold Sales 7,067
All-in Sustaining Cash Costs
per Ounce
US$448/ounce
(1) Source: Feasibility Study and Technical Report Update on the Brucejack Project, dated June 19, 2014.
(2) Net of silver credits at Base Case silver price of $US17/ounce.
12. 12
VALLEY OF THE KINGS: STOCKWORK
S
N
Cleo West Drift 615L West Raise
Domain 20
~0.5 m
13. 13
LIFE OF MINE PLAN
Oblique view facing west
West Zone
Valley of the Kings
Infrastructure Area
Portals
14. 14
MINING METRICS (1)
30 m level spacing
Maximum of 45 m stope
lengths
15 m widths
Dilution Factors
– Primary Stopes: 7%
– Secondary Stopes: 15%
Mining Recovery Factors
– Primary Stopes: 97.5%
– Secondary Stopes: 92.5%
Average 12 stopes in the
mining and backfill cycle at
any time
(1) See Feasibility Study and Technical Report Update on the Brucejack Project, dated June 19, 2014
17. 17
Gravity and flotation
concentration
Producing gold/silver
concentrate and doré
Bulk sample processing with
single stage gravity and
flotation concentration yielded
gold recoveries averaging 98%
PROCESSING
18. 18
PERMITTING PROCESS
Scope and
Process
determined
1st Public
Comment
Period
Application
Submitted
Application
evaluated for
completeness
Application
review, 2nd
Public
Comment
Period
Assessment
Report
Referral to
Ministers
January 2013
Five Open
Houses in
November
2013
(Submitted
June 20, 2014)
(Completed by
July 25, 2014)
(Review stage 180 days)
Project
Description
Filed
Project
Decision by
Ministers
(Decision 45 days)
BC Environmental Assessment Office (EAO) manages it
Federal review coordinated by Federal Environmental
Assessment Agency (CEAA) for relevant areas
Provincial and Federal reviews are coordinated
For more information on assessment process: www.eao.gov.bc.ca/ea_process.html
(Anticipate
H1 2015)
19. 19
COMMUNITY ENGAGEMENT
Commercial relationships with local First
Nations during the exploration phase at
Brucejack have been mutually successful
Examples of Brucejack Project contracts with
First Nation development corporations
include camp construction, access road
maintenance, waste rock disposal
The proposed mine will provide
approximately 800 jobs during construction
and 500 jobs during operations
We will continue to extend both commercial
contract and employment opportunities to
locals whenever possible
20. 20
NEAREST FISH 20KM AWAY
CASCADE
BRUCEJACK
PROJECT
BRUCEJACK LAKE
(not fish habitat)
21. 21
FINANCING THE BRUCEJACK PROJECT
Various proposals in addition to equity have been
brought to us, including: royalty, forward sale, high-
yield debt, convertible notes, gold-linked bonds, project
debt, streaming
All options will be considered to maximize return
Anticipate financing plan to be finalized in Q4
22. 22
THE NEXT 12 MONTHS:
2014/H2
File Environmental Assessment
Certificate application
Updated Feasibility Study
In-fill drill program
Plan and implement underground
exploration program
Plan for excavation of additional 1,000
tonnes of high-grade ore
Potential production of additional 1,000
tonnes of high-grade ore
2015/H1
Anticipate receiving permits
Start construction
23. 23
HIGH-GRADE GOLD WITH SIZE
Data source: Companies
Valley of the Kings reserves based on Feasibility Study and Technical Report Update on the Brucejack Project, dated June 19, 2014
Kirkland Lake Mine
(Kirkland Lake)
Kensington
(Coeur)
Casa Berardi
(Hecla)
El Penon
(Yamana)
Red Lake
(Goldcorp)
Pogo Mine
(Sumitomo)
Valley of the Kings
Cerro Negro
(Goldcorp)
Eleonore
(Goldcorp)
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0
Proven
+
Probable
Gold
Grade
(g/t)
Proven + Probable Gold Reserves (mm oz)
24. 24
PRETIVM MANAGEMENT
Robert Quartermain, B.Sc., M.Sc., P.Geo, D.Sc.
President & Chief Executive Officer,
Director
Joseph Ovsenek, B.A. Sc., P.Eng., LLB
Executive Vice President & Chief Development Officer,
Director
Ken McNaughton, M.A. Sc., P.Eng.
Vice President & Chief Exploration Officer
Ian I Chang, M.A. Sc., P.Eng.
Vice President, Project Development
Michelle Romero, B.A., M.L.S.
Vice President, Corporate Relations
Kevin Torpy, B.Sc.
Director, Operations
Warwick Board, Ph.D., P.Geo.
Chief Geologist
Max Holtby, B.Sc., P. Geo.
Director, Permitting
James A Currie, P.Eng.
Vice President & Chief Operating Officer
Peter de Visser, CA
Chief Financial Officer
25. 25
SHAREHOLDING & ANALYST COVERAGE
(1) As of June 18, 2014; ownership calculated on an undiluted basis.
(2) As of June 18, 2014. Source: IPREO, SEDI
Top Shareholders(2)
(shares in millions)
Silver Standard Resources 18.986
Liberty Metals & Mining 6.850
Royce & Associates 5.546
Aristeia Capital, LLC 4.655
Sun Valley Gold, LLC 4.361
Robert Quartermain 2.808
Franklin Advisors, Inc. 2.749
Norges Bank Investment
TD Asset Management
2.457
1.959
Sprott Asset Management 1.854
Weiss Asset Management 1.837
Analyst Coverage
BMO John Hayes
CIBC Jeff Killeen
Citibank Alex Hacking
Cormark Securities Richard Gray
Cowen Securities Adam Graf
GMP Securities George Albino
H.C. Wainwright Jeff Wright
RBC Dan Rollins
Roth Capital Partners Joseph Reagor
Salman Partners Ash Guglani
Scotiabank Ovais Habib
Capital Structure(1)
Public Float 89.5
Silver Standard Shares 19.0
Total Issued & Outstanding Shares 108.5
Incentive Options 10.2
Total Fully Diluted Shares 118.7
Market Cap (at July 2, 2014) C$962 million
Working Capital (at Mar. 31, 2014) C$28.1 million
+ pending gold
sale receipts
(shares in millions)
Silver
Standard,
18 %
Institutions,
49%
Management,
4%
Retail,
29%
26. 26
APPENDIX: 2013 RESOURCE ESTIMATE
Valley of the Kings Mineral Resource estimate - December 2013(1),(4)
(Based on a cut-off grade of 5.0 grams of gold-equivalent/tonne(5))
Category
Tonnes
(millions)
Gold
(g/t)
Silver
(g/t)
Contained(3)
Gold
(million oz)
Silver
(million oz)
Measured 2.0 19.3 14.4 1.2 0.9
Indicated 13.4 17.4 14.3 7.5 6.1
M & I 15.3 17.6 14.3 8.7 7.0
Inferred(2) 5.9 25.6 20.6 4.9 3.9
(1) Mineral Resources which are not Mineral Reserves do not have demonstrated economic viability. The estimate of Mineral Resources may be materially affected by
environmental, permitting, legal, marketing, or other relevant issues. The Mineral Resources in this news release were estimated using the Canadian Institute of Mining,
Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on Reserve
Definitions and adopted by CIM Council.
(2) The quantity and grade of reported Inferred resources in this estimation are uncertain in nature and there has been insufficient exploration to define these Inferred Resources as
an Indicated or Measured Mineral Resource and it is uncertain if further exploration will result in upgrading them to an Indicated or Measured Mineral Resource category.
(3) Contained metal figures and totals may differ due to rounding of figures.
(4) The Mineral Resource estimate stated in Table 1 is defined using 10 m by 10 m by 10 m blocks in the in Valley of the Kings.
(5) The gold equivalent value is defined as AuEq = Au + Ag/53.
(6) See Brucejack Project Mineral Resources Update Technical Report dated December 19, 2013.
The updated Valley of the Kings Resource estimate announced in
December(6) added Measured gold Resources and increased gold grade:
27. 27
APPENDIX: 2013 RESOURCE MODEL – VALLEY OF THE KINGS
5-10
10-20
20-60
>60
Key (g/t Au)
December 2013 Mineral Resource
Measured and Indicated Blocks >5g/t Au.
Blocks are 10m x 10m x 10m
100 m
N
29. 29
APPENDIX: VALLEY OF THE KINGS M+I RESOURCE
Northing
(± 25 m)
M+I Gold*
(Oz.)
6258225 138,175
6258175 412,508
6258125 853,632
6258075 342,402
6258025 2,161,727
6257975 2,434,390
6257925 1,126,442
6257875 643,503
6257825 410,615
6257775 87,687
*Dec. 2013 M+I Mineral
Resource; ≥5.0 g/t Au.
1.20 1.87 1.53 2.28 1.17 0.52 0.52
M+I Au*
(Moz.)
Surface projection of December 2013 Mineral Resource estimate, with total ounces per 100 m Easting and 50 m Northing strips
30. 30
10.93m @ 43.57 ppm Au
0.5m @ 26.00 ppm Au
N
2014 SURFACE DRILLING: PLAN VIEW
<0.5
0.5-1.0
1.0-5.0
>20
5.0-20.0
Key (g/t Au)
Assay intervals
200m
Existing Underground
Development
SU-627
Latite Dykes
(projected from 1345m)
Latite Dykes
(projected from 1345m)
SU-628
SU-629
1.5m @ 19.05 ppm Au
0.5m @
17.95 ppm Au
SU-630
5m @ 17.34 ppm Au
1.5m @ 32.5 ppm Au
1m @ 11.35 ppm Au
0.5m @ 11.1 ppm Au
31. 31
10.93m @ 43.57 ppm Au
0.5m @ 26.00 ppm Au
N S
426765E: 500M WIDE SECTION
200m
<0.5
0.5-1.0
1.0-5.0
>20
5.0-20.0
Key (g/t Au)
(Assay intervals)
Fragmental
Volcanic Rocks
Polylithic
Conglomerate Volcanic
Flows
Volcaniclastic
Sediments
Volcanic Flows
5-10
10-20
>20
Key (g/t Au)
(Blocks)
(M&I + Inferred)
SU-627
Latite Dykes
SU-630
SU-628
SU-629
1.5m @ 19.05 ppm Au
0.5m @
17.95 ppm Au
5m @ 17.34 ppm Au
1.5m @ 32.5 ppm Au
1m @ 11.35 ppm Au
0.5m @ 11.1 ppm Au
32. 32
CONTACT:
Phone: 604-558-1784
Fax: 604-558-4784
Toll-free: 1-877-558-1784
invest@pretivm.com
www.pretivm.com
HEAD OFFICE:
Pretium Resources Inc.
570 Granville St.
Suite 1600
Vancouver, BC
Canada V6C 3P1
COMMON SHARES:
TSX/NYSE:PVG
Issued: 108.5 million
Fully diluted: 118.8 million
52-week hi/low:
$10.67/$2.83
Market cap: $962 million
(at July 2, 2014)
Advancing a major high-grade gold project in Canada
32