SlideShare a Scribd company logo
COMMERCIAL MANAGEMENT SCENARIOS

Lecture 2
Q: You are employed as a Commercial Manager with a large Main Contractor. You have
full commercial responsibility for the construction of a new school in Trim, Co Meath.
The estimator handed you the full tender documentation from when the job was at tender
stage at an internal pre-start meeting. You have agreed with senior management that the
profit budget on the contract is 6%. You are now four months into a 12 month project and
your latest monthly CVR is showing a profit of 9%. The Surveying Director has called
you in to update him on progress, and a full financial outlook for the contract has been
requested.
You know the following facts:
    1. Although the contract is showing a profit of 9%, your current preliminaries
        budget has been exceeded by 5k to date and you estimate that the overall
        preliminaries budget will not cover your actual preliminaries at the end of the
        contract.

     2. The quotation used at tender stage for the painting package was from a
        subcontractor who has now gone into liquidation. You had 15% mark up on this
        package in your profit budget. If you use the next quotation from tender stage you
        will have only 5% profit on this package.

     3. The estimator made a mistake when pricing the carpet item on the BOQ and
        priced Ulster Carpet instead of Tretford and didn’t qualify the tender. Tretford
        costs €20/m2 more than Ulster and there is 500m2 of this item. You will be losing
        10k on this package if this situation stands.

You want to make the Commercial Director aware of these items, but you don’t want to
come to the table without proactive advice on possible solutions to the three problems.

Make a note of possible solutions to the three problems you are dealing with.

Ans:
1) You will carry out an actual preliminaries v’s budget report and
           • Highlight the areas or prelims where over spend was occurring so action
               can be taken.
           • Advise the surveying director where savings can be made i.e. site
               supervision.
           • Meet with the contracts manager and discuss possible ways of cutting the
               programme.

2)

                                          Page 1
•   You will approach the second sub-contractor and try and get him to reduce his
         rates.
     •   You will seek further quotations for the same package.
     •   You will check the BOQ for over-measure
     •   Approach the architect on changing the specification

3)
     •   Approach the architect/client and offer 50% of the savings to change to Ulster
         Carpet – make it worthwhile
     •   Seek better quotations on Tretford – check abroad
     •   Scan the BOQ for savings in other areas
     •   Check the measure on the carpet

Lecture 3
Q: You are employed as a Commercial Manager with a large Main Contractor. You have
full commercial responsibility for the construction of a new multi million euro office
development in Dublin City Centre. As part of your role, you are responsible for
compiling interim valuations for the contract, chasing up QS recommendations and
architects certificates, and forwarding this documentation to the financial department for
invoicing.
You are sending in your valuations on time every month, however the clients QS is
taking three weeks to forward his recommendation to the architect. He claims that you
are inflating the valuations with variations which are not agreed, and applying for work
which is not completed.
Your financial director has highlighted the fact that the company cashflow is suffering as
a result of your contract.

What do you think is the best course of action to resolve this situation?

Ans:
     •   Meet with the clients QS
     •   Agree a set of valuation dates and point out that under the contract there is an
         agreed time span in relation to issuing of certificates
     •   Arrange a system where you will make the clients QS aware of all upcoming
         variations if you are aware of them and try to agree costs before they occur
     •   Try to arrange meetings on site before the valuations are submitted
     •   Keep photographic record

Lecture 4
Q: You are newly employed as a Commercial Manager with a medium sized
Groundworks Subcontractor. Your Managing Director has called you in to attend a
meeting relating to a €2m pipelaying project on which he wants your advice. He states
that the contract originally contained 8000m of 400mm diameter pvc watermain and this
has now increased to 8900m. He points out that the additional 900m of pipework is a
variation and he wants to apply on a dayworks basis for this work. What is your advice?

                                            Page 2
Ans:
   •   It is a variation
   •   Valuing the work depends on the circumstances: location, obstacles or barriers,
       access etc
   •   If possible, base it on BOQ rates
   •   If not entirely identical, adjust bill rates to suit
   •   May have to build up a new rate from scratch
   •   Use dayworks only as a last resort

Lecture 5
Q: You are employed as a Commercial Manager with a large Main Contractor. You have
full commercial responsibility for the construction of a new office development in
Clonee, Co Meath. The subcontractor who is carrying out the roofing and cladding
package is causing problems on the contract.
    (1) Although he commenced work on his agreed commencement date, he is now 2
        weeks beyond his completion date with 10% of his work package still to do.

   (2) You had no scaffold in place, and he has sent you in 4 weeks of daywork charges
       for having to use an aerial platform.

   (3) He has left packaging and boxes all over the site and will not tidy up.

   (4) There was an additional 60m2 of Kingspan cladding required where the BOQ was
       under measured, and he has sent in daywork sheets to cover this item, which is
       working out three times more expensive than if BOQ rates were used.



       The subcontractor is meeting you in the morning and wants to bring his account
       up to date. He has threatened that if there is not a cheque ready for him by the
       close of business tomorrow for the balance of all work done, he is going to start
       pulling cladding sheets off the building.



       What advice are you going to give him in that meeting?

Ans:
1) Draw the subcontractors attention to the contract he signed
          - Pre-start meeting – the contract conditions were fully explained
          - No Letter for extension of time was sent in
          - Main contractor is responsible for his sub-contractors hence any delays
             will result in countercharges
          - Last resort- expel sub-contractor off site or bring in more resources and
             countercharge from subbies account
                                         Page 3
2) Tell sub-contractor to check list of agreed attendances as these form part of the
   contract.
   Sub-contractor has a valid case if these items are not listed on his attendances sheet

3) Check pre-start minutes of contract to see who is responsible.
   Give subbie two days to clean up site unless very urgent.
   If he doesn’t clean site, get your own operatives to clean up and countercharge at
   market rates for labour and skips – unless nominated sub-contarctor.

4) Use rates in BOQ unless not similar conditions – dayworks are used as a last resort

5) Refer to payment terms in contract – advise that it is criminal damage – gardai !

Lecture 7
Q: You are employed as a Commercial Manager on a €40million multi purpose office
and apartment development. You are 4 months into a 24 month project. This is a flagship
project for your company and your reputation and future career are linked to this project
having a successful outcome. The third interim certificate has been faxed to you from the
Architects office, and your internal costing department has sent you their cost report for
the project to date. You have quickly subtracted the costs figure from the value amount
and to your horror is showing a loss of -25%. Your financial director is meeting you on
site in three hours. He wants an update on the financial standing of the project as he is
calculating the Christmas bonus payments for all on site staff the following morning.
How are you going to spend the next three hours?

Ans:
   1) Don’t panic
   2) Cost Value Reconciliation
         • Interim valuation may be under valued
         • Possible mistakes on QS recommendation
         • Costs may be up to a different date
         • Ensure comparing apples with apples

If still negative:
     • Check if you undervalued the work
     • Check Prelims actual v’s budget
     • Check if you have over paid subbies or suppliers (bulk orders)

Lecture 8
Q: You are newly employed as a commercial manager with a small civil engineering sub-
contractor. You have financial responsibility for numerous contracts of varying value.
The sub-contractor has no idea whether he is making money on these jobs or not! He has
a vague idea from job to job, and only really knows at the end of the year whether the
company is making a profit. You are the first commercial manager to be employed by his


                                          Page 4
company and he wants advice on how you can determine the profit on each individual
contract as they progress.

What is your advice?

Ans:
      •   Separate the contracts and allocate job numbers thus allocating costs to each
          contract as necessary
      •   Prepare budgets for the profit on each contract (excel sheet – profit in each item)
      •   Prepare a prelims budget
      •   Prepare a cost value reconciliation on a monthly basis – prepare actual v’s budget
          for prelims – identify overspending – take action
      •   Final CVR based on Final Account

Lecture 9
Q: You are newly employed as a commercial manager with a small building main
contractor. The managing director wants your advice on the following:
   (a) Implementing a quality assurance system for the company. He feels that it will
       cost his company a lot of money to set up and wants to know where he will see
       financial returns on this money
   (b) At present, he uses standard skips to dispose of waste, and he wants your opinion
       from a cost point of view on why he should segregate waste on site.

      What is your advice?

Ans:
(a)
      •   Prequalification for new work -            Credibility/Trustworthy/Reliability
      •   Good Management procedures -               Efficiency
      •   Use of standard forms protects the company e.g. claims

(b)
      •   Standard skips are charged at the highest rate
      •   Large reductions for specific skips – Steel 100% / Timber 50% / Gypsum ?
      •   Re-use and recycle
      •   A tidy site – better run – cost effective

Lecture 10
Q: Build up a rate for blockwork from the following information:

Blockwork; 100mm thick; in cement mortar (1:3) block size 440x215x100mm

Constants
Blocks                                          10nr/m2 of blockwork
Mortar                                          0.007m3/m2 of blockwork

                                            Page 5
Blocklayer                                   0.4 hours/m2 of blockwork
Labourer                                     0.2 hours/m2 of blockwork

Costs
Labourer                                     €19 per hour
Blocklayer                                   €30 per hour
Blocks                                       €800 per thousand
Mortar                                       €95 per m3
Waste on Blocks                              5%
Waste on Mortar                              15%
Profit & Overheads                           12%

Ans:
Materials
Blocks        10nr/m2        €800/1000x10=       €8.00 + 5% =            € 8.40
Mortar                       €95 per m3 x 0.007= €0.67 + 15% =           € 0.77

Labour
Blocklayer                   0.4hrs x €30                         =      €12.00
Labourer                     0.2 hrs x €19                        =      € 3.80

Sub Total                                                                €24.99
+ P & O @ 12%                                                            €2.996
TOTAL                        Rate per m2 of Blockwork                    €27.97

Lecture 10B
Q: You are newly employed as a commercial manager with a medium sized
Groundworks subcontractor. You have lined up 4 major contracts which will keep your
company busy for the coming two years despite the current economic climate. All of
these contracts are for the renewal of watermains in rural areas. The company does not
own its own plant and the managing director has approached you, seeking your advice on
whether the company should continue hiring plant or is it a good time to purchase plant?

What is your advice?

Ans:
Advantages of hiring plant:
   • Low maintenance costs
   • Contractors money not tied up in expensive plant – cashflow!
   • Easy to return idle plant
   • Plant hire company will supply skilled operatives/drivers
   • Can hire for minimum period

Disadvantages of hiring plant:
   • You don’t own the plant – money paid out


                                        Page 6
•   Particular machines may not be available from the hire company
   •   Possible problems with standing time
   •   No tax benefits

Conclusion: To purchase as you have continuous work for 2 years for the same type of
plant

Lecture 13
Q: You are employed as a site manager with a medium sized contractor. You are
managing the construction of a new €2m primary school which happens to be in the area
where you live. You are on first name terms with the school board of management. The
chairman of that board has approached you on site and instructed you to change the
skirtings in the school from MDF to red Deal. You have just started the second fix
carpentry and the MDF is already on site!

How do you proceed?

Ans:
   1) Firstly you advise the chairman from the Board of Management that you cannot
      proceed without an architect’s instruction.
   2) You make contact with the architect and advise him of the request
   3) You or the commercial manager compile a cost for the variation – include a
      restocking charge from the supplier for taking back unusable materials
   4) Do not proceed without an architect’s instruction
   5) Confirmation of verbal instruction in some cases

Lecture 14a
Q: You are employed as a Commercial Manager with a large Main Contractor. You have
full commercial responsibility for the construction of a new Community Centre in Navan,
Co. Meath. The estimator handed you the full tender documentation from when the job
was at tender stage at an internal pre-start meeting. You have agreed with senior
management that the profit budget on the contract is 8%. You are now four months into a
12 month project and your latest monthly CVR is showing a profit of 16%. The
Surveying Director has called you in to update him on progress, and a full financial
outlook for the contract has been requested.
You know the following facts:
    1. Although the contract is showing a profit of 16%, your current preliminaries
        budget has been exceeded by 15k to date and you estimate that the overall
        preliminaries budget will not cover your actual preliminaries at the end of the
        contract.

   2. The quotation used at tender stage for the flooring package was from a
      subcontractor who has now gone into liquidation. You had 25% mark up on this
      package in your profit budget. If you use the next quotation from tender stage you
      will have only 1% profit on this package.

                                        Page 7
3. The estimator made a mistake when pricing the paving works on the BOQ and
        priced 100mm tarmacadam instead of 200mm and didn’t qualify the tender.
        200mm tarmacadam costs €14/m2 more than 100mm and there is 10,000m2 of
        this item. You will be losing 140k on this package if this situation stands.

You want to make the Commercial Director aware of these items, but you don’t want to
come to the table without proactive advice on possible solutions to the three problems.

Make a note of possible solutions to the three problems you are dealing with.

Ans:
1) Prepare actual preliminaries v’s budget report and
           • Highlight the areas or prelims where over spend was occurring so action
               can be taken.
           • Advise the surveying director where savings can be made i.e. site
               supervision.
           • Revise your prelims budget for rest of contract – taking agreed saving into
               account
           • Meet with the contracts manager and discuss possible ways of cutting the
               programme.

2)
     •   Contact second place sub-contractor and try and get him to reduce his rates.
     •   You will seek further quotations for the same package.
     •   You will check the BOQ for over-measure
     •   Approach the architect on changing the specification

3)
     •   Approach the architect/client and offer 50% of the savings to change to Ulster
         Carpet – make it worthwhile
     •   Seek better quotations for 200mm tarmacadam
     •   Scan the BOQ for savings in other areas and off set against this item
     •   Check the measure on the tarmacadam to see if it was over measured

Lecture 14b
Q: You are employed as a Commercial Manager with a large Main Contractor. You have
full commercial responsibility for the construction of a new multi million euro office
development in Dublin City Centre. As part of your role, you are responsible for
compiling interim valuations for the contract, chasing up QS recommendations and
architects certificates, and forwarding this documentation to the financial department for
invoicing.
You are sending in your valuations on time every month, however the clients QS is
cutting every valuation by 50%. He claims that you are inflating the valuations with
variations which are not agreed, and applying for work which is not completed.


                                           Page 8
Your financial director has highlighted the fact that the company cashflow is suffering as
a result of your contract.

What do you think is the best course of action to resolve this situation?

Ans:
   •   Meet with the clients QS
   •   Firstly because there is such a difference (50%)
           - Compile evaluations with clients QS prior to submitting
           - Have the disputes sorted as they arise
   •   Try to agree variations as they happen
   •   Keep good photographic record
   •   If you cannot agree after this, you can go to conciliation and then to arbitration of
       necessary

Lecture 14c
Q: You are newly employed as a Commercial Manager with a medium sized
Groundworks Subcontractor. Your Managing Director has called you in to attend a
meeting relating to a €2m pipelaying project on which he wants your advice. He states
that the contract originally contained 8000m of 400mm diameter pvc watermain and this
has now increased to 8900m. He points out that the additional 900m of pipework is in the
public road while the other 8000m was through grass verge. There is 50m of this
additional pipework in an alleyway with no access for an excavator. The clients QS
insists that this work will be carried out at the same BOQ rate which applied to the
original 8000m variation. What is your advice?

Ans:
   •    Firstly everyone is agreed that this is a variation
   •    Advise clients QS that only a comparable BOQ rate can be used
   •    A new rate must be compiled based on
            - traffic management
            - different backfilling
            - reinstatement
            - rate of production
50m – daywork – best option because it’s difficult to evaluate whats involved and build
up a rate (unforeseen)

Lecture 14d
Q: You are employed as a Commercial Manager with a large Main Contractor. You have
full commercial responsibility for the construction of a new office development in
Clonee, Co Meath. The domestic subcontractor who is carrying out the glazing package
is causing problems on the contract.
    1) He didn’t commence work on his agreed commencement date, he is now 3 weeks
        beyond his completion date with 20% of his work package still to do.


                                          Page 9
2) He has sent you in 6 weeks of daywork charges for having to use an aerial
      platform.

   3) He has left packaging and boxes all over the site and will not tidy up.

   4) There was an additional 5no. additional windows required which were missed in
      the BOQ, and he has sent in daywork sheets to cover these items, which is
      working out three times more expensive than if BOQ rates were used.



       The subcontractor is meeting you in the morning and wants to bring his account
       up to date.

       What advice are you going to give him in that meeting?

Ans:
   1) Draw the subcontractors attention to the contract he signed
         - Pre-start meeting – the contract conditions were fully explained
         - No Letter for extension of time was sent in
         - Main contractor is responsible for his sub-contractors hence any delays
             will result in countercharges
         - Last resort- expel sub-contractor off site or bring in more resources and
             countercharge from subbies account

   2) Tell sub-contractor to check list of agreed attendances as these form part of the
      contract.
   Sub-contractor has a valid case if these items are not listed on his attendances sheet

   3) Check pre-start minutes of contract to see who is responsible.
   Give subbie notice to clean up site.
   If he doesn’t clean site, get your own operatives to clean up and countercharge at
   market rates for labour and skips – unless nominated sub-contarctor.

   4) If comparable rates in BOQ then use that rate unless different conditions (ie all
       other windows were on ground floor and new ones on 5th Floor) – in this case
       adjust existing rates and if no other option use Dayworks

Lecture 14e
Q: You are employed as a Commercial Manager on a €40million multi purpose office
and apartment development. You are 4 months into a 24 month project. You have just
completed the CVR for that month and its showing a loss of 20%. You know that you
have achieved the budgeted profit on all the subcontractor packages to date, which were
averaging 15% profit. Your financial director wants an update on the financial standing
of the project.
How will you source the necessary information?

                                         Page 10
Ans:
   •   You have achieved the budgeted profit with sub-contractors so problem doesn’t
       lie here – look at possible problems from other areas
   •   Check Preliminaries
   •   Interim Valuation could have been under valued
   •   QS/Architect could have undervalued
   •   Incorrect cost allocation – check material delivery dockets
   •   Subcontractor could have been overpaid
   •   Check initial budget for errors

Lecture 14f
Q: You are newly employed as a Commercial Manager with a medium sized
Groundworks Subcontractor. You have lined up 4 small contracts which will keep your
company busy for the coming 6 months and there is no guarantee of work after that. All
of these contracts are for the renewal of watermains in rural areas. The company does not
own its own plant and the Managing Director has approached you, seeking your advice
on what the advantages and disadvantages of hiring plant are, and what is the best option
in his case?
What is your advice?

Ans:
Advantages of hiring plant:
   • Low maintenance costs
   • Contractors money not tied up in expensive plant – cashflow!
   • Easy to return idle plant
   • Plant hire company will supply skilled operatives/drivers
   • Can hire for minimum period
   • No requirement for a depot or yard
   • Less insurance costs

Disadvantages of hiring plant:
   • You don’t own the plant – money paid out – can be expensive over long term
      period
   • Particular machines may not be available from the hire company when needed
   • Possible problems with standing time
   • No tax benefits

Conclusion: To purchase as you have continuous work for 2 years for the same type of
plant

Lecture 16
Q: You are employed as a Commercial Manager with a medium sized Main Contractor.
You are in the process of agreeing a Final Account for a completed office block with the

                                        Page 11
clients QS. There is a major dispute between you and the clients QS over a large variation
on the cladding package where the thickness of the panel had not been stated in the BOQ
description. You had priced 60mm which was detailed in small print on the Architectural
drawings while 80mm was required. The clients QS has stated that the 80mm thickness
was shown on the engineers drawing, and as an experienced builder, you should have
known that 80mm was needed! The form of contract used was the RIAI standard yellow
form. Your Managing Director wants to take a court case against the client to get this
issue resolved. What is your advice?

Ans:
Strong case as this is an architectural panel issue and not a structural panel issue therefore
the architectural drawings would have preference giving the builder a strong case
Suggest negotiation at senior level
RIAI form of contract so conciliation must be entered into before other binding
resolutions are considered
If above fail                   Mini Trial
                                Expert determination
Then Arbitration

Lecture 17
Q: You have started your own building company, tendering for projects ranging in size
from €100k to €2m. A new client has approached you and is interested in constructing a
Nursing Home on a site which he already owns. He has one schematic drawing showing
the floor plan (one storey building) and wants an idea of what it will cost to construct.
What advice will you give him?

Ans:
   •   You can prepare a basic cost plan on the limited information available
   •   Cost plan will be provisional
   •   Cost plan can be prepared in two ways:
                1) cost per m2 (superficial)        2) Cost per Unit (per bed)
   •   If client has a budget – work back from that
   •   Pricing – normally previous work of a similar nature
   •   New Builder – own experience/local PQS/Bruce Shaw handbook/Spons etc
   •   Price depends on location/site/market conditions/specifications/time etc




                                          Page 12

More Related Content

What's hot

PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - Assignment
Quo Ming
 
Talk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBE
Talk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBETalk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBE
Talk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBE
Francis Ho
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
Felix Vong
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction Contract
Tom Joseph Mukasa
 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: Group
Farah Sham
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
SN Panigrahi, PMP
 
Professional practce assignment report
Professional practce assignment reportProfessional practce assignment report
Professional practce assignment report
Syafiq Zariful
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
Kai Yun Pang
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
Daniel Ross
 
Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar
Saket Bansal
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
Gerald R. (Jerry) Genge
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
Lee Pei Gie
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
CNC
 
International construction contract
International construction contractInternational construction contract
International construction contract
Global Negotiator
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
Arissa Loh
 
Reduce GHG Emissions by 40% in Manila, Philippines by 2030
Reduce GHG Emissions by 40% in Manila, Philippines by 2030Reduce GHG Emissions by 40% in Manila, Philippines by 2030
Reduce GHG Emissions by 40% in Manila, Philippines by 2030
ESD UNU-IAS
 
NEC Engineering and Construction Contract (ECC) - compensation events webinar
NEC Engineering and Construction Contract (ECC) -  compensation events webinarNEC Engineering and Construction Contract (ECC) -  compensation events webinar
NEC Engineering and Construction Contract (ECC) - compensation events webinar
Association for Project Management
 
Study manual icab chapter 4, Management Information, ICAB
Study manual icab chapter 4, Management Information, ICABStudy manual icab chapter 4, Management Information, ICAB
Study manual icab chapter 4, Management Information, ICAB
Sazzad Hossain, ITP, MBA, CSCA™
 

What's hot (20)

PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - Assignment
 
Talk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBE
Talk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBETalk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBE
Talk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBE
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction Contract
 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: Group
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
 
Professional practce assignment report
Professional practce assignment reportProfessional practce assignment report
Professional practce assignment report
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
 
Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
 
International construction contract
International construction contractInternational construction contract
International construction contract
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
 
Reduce GHG Emissions by 40% in Manila, Philippines by 2030
Reduce GHG Emissions by 40% in Manila, Philippines by 2030Reduce GHG Emissions by 40% in Manila, Philippines by 2030
Reduce GHG Emissions by 40% in Manila, Philippines by 2030
 
NEC Engineering and Construction Contract (ECC) - compensation events webinar
NEC Engineering and Construction Contract (ECC) -  compensation events webinarNEC Engineering and Construction Contract (ECC) -  compensation events webinar
NEC Engineering and Construction Contract (ECC) - compensation events webinar
 
Study manual icab chapter 4, Management Information, ICAB
Study manual icab chapter 4, Management Information, ICABStudy manual icab chapter 4, Management Information, ICAB
Study manual icab chapter 4, Management Information, ICAB
 

Similar to Commercial Management Scenarios

Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
SHKLaw
 
APPENDIX 1 Project Brief Approval FormHousingProperty M.docx
APPENDIX 1 Project Brief Approval FormHousingProperty M.docxAPPENDIX 1 Project Brief Approval FormHousingProperty M.docx
APPENDIX 1 Project Brief Approval FormHousingProperty M.docx
rossskuddershamus
 
APPENDIX 1 Project Brief Approval FormHousingProperty M.docx
APPENDIX 1 Project Brief Approval FormHousingProperty M.docxAPPENDIX 1 Project Brief Approval FormHousingProperty M.docx
APPENDIX 1 Project Brief Approval FormHousingProperty M.docx
armitageclaire49
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
ByishimoBTCChef
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
Adi Iskandar Iliyas
 
saint leo prm520 full course (discussions assignments quizes group projects) ...
saint leo prm520 full course (discussions assignments quizes group projects) ...saint leo prm520 full course (discussions assignments quizes group projects) ...
saint leo prm520 full course (discussions assignments quizes group projects) ...
Elsie Obat
 
Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...
Browne Jacobson LLP
 
Industrial construction in Mexico
Industrial construction in MexicoIndustrial construction in Mexico
Industrial construction in MexicoCOPACHISA
 
[Era] cost reduction guide - issue 1 - property and premises costs
[Era]   cost reduction guide - issue 1 - property and premises costs[Era]   cost reduction guide - issue 1 - property and premises costs
[Era] cost reduction guide - issue 1 - property and premises costsManuel A. Velazquez
 
Cost Reduction Guide Issue 1 Property And Premises Costs
Cost Reduction Guide Issue 1 Property And Premises CostsCost Reduction Guide Issue 1 Property And Premises Costs
Cost Reduction Guide Issue 1 Property And Premises Costsymw15
 
Pathways To Scalability Scalable Residential Retrofitting
Pathways To Scalability   Scalable Residential RetrofittingPathways To Scalability   Scalable Residential Retrofitting
Pathways To Scalability Scalable Residential Retrofitting
Recurve
 
Cbb 512 assignment_1
Cbb 512 assignment_1Cbb 512 assignment_1
Cbb 512 assignment_1Maatla Moadi
 
How To Select A Contractor
How To Select A ContractorHow To Select A Contractor
How To Select A Contractor
Watermark & Company
 
Booming City Seminar.pdf
Booming City Seminar.pdfBooming City Seminar.pdf
Booming City Seminar.pdf
Kegler Brown Hill + Ritter
 
Property And Premises
Property And PremisesProperty And Premises
Property And Premises
Alan Birse
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
Archistudent Portal
 

Similar to Commercial Management Scenarios (20)

Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
APPENDIX 1 Project Brief Approval FormHousingProperty M.docx
APPENDIX 1 Project Brief Approval FormHousingProperty M.docxAPPENDIX 1 Project Brief Approval FormHousingProperty M.docx
APPENDIX 1 Project Brief Approval FormHousingProperty M.docx
 
APPENDIX 1 Project Brief Approval FormHousingProperty M.docx
APPENDIX 1 Project Brief Approval FormHousingProperty M.docxAPPENDIX 1 Project Brief Approval FormHousingProperty M.docx
APPENDIX 1 Project Brief Approval FormHousingProperty M.docx
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
 
saint leo prm520 full course (discussions assignments quizes group projects) ...
saint leo prm520 full course (discussions assignments quizes group projects) ...saint leo prm520 full course (discussions assignments quizes group projects) ...
saint leo prm520 full course (discussions assignments quizes group projects) ...
 
Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...
 
Industrial construction in Mexico
Industrial construction in MexicoIndustrial construction in Mexico
Industrial construction in Mexico
 
[Era] cost reduction guide - issue 1 - property and premises costs
[Era]   cost reduction guide - issue 1 - property and premises costs[Era]   cost reduction guide - issue 1 - property and premises costs
[Era] cost reduction guide - issue 1 - property and premises costs
 
Cost Reduction Guide Issue 1 Property And Premises Costs
Cost Reduction Guide Issue 1 Property And Premises CostsCost Reduction Guide Issue 1 Property And Premises Costs
Cost Reduction Guide Issue 1 Property And Premises Costs
 
uap doc 207-208
uap doc 207-208uap doc 207-208
uap doc 207-208
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
Pathways To Scalability Scalable Residential Retrofitting
Pathways To Scalability   Scalable Residential RetrofittingPathways To Scalability   Scalable Residential Retrofitting
Pathways To Scalability Scalable Residential Retrofitting
 
Cbb 512 assignment_1
Cbb 512 assignment_1Cbb 512 assignment_1
Cbb 512 assignment_1
 
How To Select A Contractor
How To Select A ContractorHow To Select A Contractor
How To Select A Contractor
 
Booming City Seminar.pdf
Booming City Seminar.pdfBooming City Seminar.pdf
Booming City Seminar.pdf
 
Property And Premises
Property And PremisesProperty And Premises
Property And Premises
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 

More from CKMCforstudents

Soil retention systems revision notes
Soil retention systems revision notesSoil retention systems revision notes
Soil retention systems revision notes
CKMCforstudents
 
Advanced Construction Technology Project
Advanced Construction Technology ProjectAdvanced Construction Technology Project
Advanced Construction Technology Project
CKMCforstudents
 
Sustainable design and build revision
Sustainable design and build revisionSustainable design and build revision
Sustainable design and build revisionCKMCforstudents
 
DT117/4 Sustainable design and build revision
DT117/4 Sustainable design and build revisionDT117/4 Sustainable design and build revision
DT117/4 Sustainable design and build revisionCKMCforstudents
 
Green roofs pres
Green roofs presGreen roofs pres
Green roofs pres
CKMCforstudents
 
Water efficiency paul boylan
Water efficiency   paul boylanWater efficiency   paul boylan
Water efficiency paul boylanCKMCforstudents
 
Biomass
BiomassBiomass
Wood fuel presentation(davido s)
Wood fuel presentation(davido s)Wood fuel presentation(davido s)
Wood fuel presentation(davido s)
CKMCforstudents
 
Wood fuel presentation
Wood fuel presentationWood fuel presentation
Wood fuel presentation
CKMCforstudents
 
Water efficiency
Water efficiencyWater efficiency
Water efficiency
CKMCforstudents
 
Water efficiency
Water efficiencyWater efficiency
Water efficiency
CKMCforstudents
 
Timber frame construction presentation`gr
Timber frame construction presentation`grTimber frame construction presentation`gr
Timber frame construction presentation`gr
CKMCforstudents
 
Timber frame construction
Timber frame constructionTimber frame construction
Timber frame construction
CKMCforstudents
 
Thermal imaging mark ensor
Thermal imaging mark ensorThermal imaging mark ensor
Thermal imaging mark ensor
CKMCforstudents
 
Sustainable drainage systems (autosaved)(tg)
Sustainable drainage systems (autosaved)(tg)Sustainable drainage systems (autosaved)(tg)
Sustainable drainage systems (autosaved)(tg)
CKMCforstudents
 
Subs above ground thomas geoghegan
Subs above ground thomas geogheganSubs above ground thomas geoghegan
Subs above ground thomas geoghegan
CKMCforstudents
 

More from CKMCforstudents (20)

Soil retention systems revision notes
Soil retention systems revision notesSoil retention systems revision notes
Soil retention systems revision notes
 
MMC Revision Notes
MMC Revision NotesMMC Revision Notes
MMC Revision Notes
 
Advanced Construction Technology Project
Advanced Construction Technology ProjectAdvanced Construction Technology Project
Advanced Construction Technology Project
 
Sustainable design and build revision
Sustainable design and build revisionSustainable design and build revision
Sustainable design and build revision
 
DT117/4 Sustainable design and build revision
DT117/4 Sustainable design and build revisionDT117/4 Sustainable design and build revision
DT117/4 Sustainable design and build revision
 
Green roofs pres
Green roofs presGreen roofs pres
Green roofs pres
 
Green roofs pres
Green roofs presGreen roofs pres
Green roofs pres
 
Water efficiency paul boylan
Water efficiency   paul boylanWater efficiency   paul boylan
Water efficiency paul boylan
 
Water efficiency
Water efficiencyWater efficiency
Water efficiency
 
Air tightness
Air tightnessAir tightness
Air tightness
 
Biomass
BiomassBiomass
Biomass
 
Wood fuel presentation(davido s)
Wood fuel presentation(davido s)Wood fuel presentation(davido s)
Wood fuel presentation(davido s)
 
Wood fuel presentation
Wood fuel presentationWood fuel presentation
Wood fuel presentation
 
Water efficiency
Water efficiencyWater efficiency
Water efficiency
 
Water efficiency
Water efficiencyWater efficiency
Water efficiency
 
Timber frame construction presentation`gr
Timber frame construction presentation`grTimber frame construction presentation`gr
Timber frame construction presentation`gr
 
Timber frame construction
Timber frame constructionTimber frame construction
Timber frame construction
 
Thermal imaging mark ensor
Thermal imaging mark ensorThermal imaging mark ensor
Thermal imaging mark ensor
 
Sustainable drainage systems (autosaved)(tg)
Sustainable drainage systems (autosaved)(tg)Sustainable drainage systems (autosaved)(tg)
Sustainable drainage systems (autosaved)(tg)
 
Subs above ground thomas geoghegan
Subs above ground thomas geogheganSubs above ground thomas geoghegan
Subs above ground thomas geoghegan
 

Recently uploaded

The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
RitikBhardwaj56
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Akanksha trivedi rama nursing college kanpur.
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
Priyankaranawat4
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
AyyanKhan40
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
Academy of Science of South Africa
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
Celine George
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
Top five deadliest dog breeds in America
Top five deadliest dog breeds in AmericaTop five deadliest dog breeds in America
Top five deadliest dog breeds in America
Bisnar Chase Personal Injury Attorneys
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
eBook.com.bd (প্রয়োজনীয় বাংলা বই)
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
Israel Genealogy Research Association
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
TechSoup
 
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdfMASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
goswamiyash170123
 
DRUGS AND ITS classification slide share
DRUGS AND ITS classification slide shareDRUGS AND ITS classification slide share
DRUGS AND ITS classification slide share
taiba qazi
 
World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024
ak6969907
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
chanes7
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
Wasim Ak
 
Advantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO PerspectiveAdvantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO Perspective
Krisztián Száraz
 
Assignment_4_ArianaBusciglio Marvel(1).docx
Assignment_4_ArianaBusciglio Marvel(1).docxAssignment_4_ArianaBusciglio Marvel(1).docx
Assignment_4_ArianaBusciglio Marvel(1).docx
ArianaBusciglio
 
How to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold MethodHow to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold Method
Celine George
 

Recently uploaded (20)

The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
Top five deadliest dog breeds in America
Top five deadliest dog breeds in AmericaTop five deadliest dog breeds in America
Top five deadliest dog breeds in America
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
 
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdfMASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
 
DRUGS AND ITS classification slide share
DRUGS AND ITS classification slide shareDRUGS AND ITS classification slide share
DRUGS AND ITS classification slide share
 
World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
 
Advantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO PerspectiveAdvantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO Perspective
 
Assignment_4_ArianaBusciglio Marvel(1).docx
Assignment_4_ArianaBusciglio Marvel(1).docxAssignment_4_ArianaBusciglio Marvel(1).docx
Assignment_4_ArianaBusciglio Marvel(1).docx
 
How to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold MethodHow to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold Method
 

Commercial Management Scenarios

  • 1. COMMERCIAL MANAGEMENT SCENARIOS Lecture 2 Q: You are employed as a Commercial Manager with a large Main Contractor. You have full commercial responsibility for the construction of a new school in Trim, Co Meath. The estimator handed you the full tender documentation from when the job was at tender stage at an internal pre-start meeting. You have agreed with senior management that the profit budget on the contract is 6%. You are now four months into a 12 month project and your latest monthly CVR is showing a profit of 9%. The Surveying Director has called you in to update him on progress, and a full financial outlook for the contract has been requested. You know the following facts: 1. Although the contract is showing a profit of 9%, your current preliminaries budget has been exceeded by 5k to date and you estimate that the overall preliminaries budget will not cover your actual preliminaries at the end of the contract. 2. The quotation used at tender stage for the painting package was from a subcontractor who has now gone into liquidation. You had 15% mark up on this package in your profit budget. If you use the next quotation from tender stage you will have only 5% profit on this package. 3. The estimator made a mistake when pricing the carpet item on the BOQ and priced Ulster Carpet instead of Tretford and didn’t qualify the tender. Tretford costs €20/m2 more than Ulster and there is 500m2 of this item. You will be losing 10k on this package if this situation stands. You want to make the Commercial Director aware of these items, but you don’t want to come to the table without proactive advice on possible solutions to the three problems. Make a note of possible solutions to the three problems you are dealing with. Ans: 1) You will carry out an actual preliminaries v’s budget report and • Highlight the areas or prelims where over spend was occurring so action can be taken. • Advise the surveying director where savings can be made i.e. site supervision. • Meet with the contracts manager and discuss possible ways of cutting the programme. 2) Page 1
  • 2. You will approach the second sub-contractor and try and get him to reduce his rates. • You will seek further quotations for the same package. • You will check the BOQ for over-measure • Approach the architect on changing the specification 3) • Approach the architect/client and offer 50% of the savings to change to Ulster Carpet – make it worthwhile • Seek better quotations on Tretford – check abroad • Scan the BOQ for savings in other areas • Check the measure on the carpet Lecture 3 Q: You are employed as a Commercial Manager with a large Main Contractor. You have full commercial responsibility for the construction of a new multi million euro office development in Dublin City Centre. As part of your role, you are responsible for compiling interim valuations for the contract, chasing up QS recommendations and architects certificates, and forwarding this documentation to the financial department for invoicing. You are sending in your valuations on time every month, however the clients QS is taking three weeks to forward his recommendation to the architect. He claims that you are inflating the valuations with variations which are not agreed, and applying for work which is not completed. Your financial director has highlighted the fact that the company cashflow is suffering as a result of your contract. What do you think is the best course of action to resolve this situation? Ans: • Meet with the clients QS • Agree a set of valuation dates and point out that under the contract there is an agreed time span in relation to issuing of certificates • Arrange a system where you will make the clients QS aware of all upcoming variations if you are aware of them and try to agree costs before they occur • Try to arrange meetings on site before the valuations are submitted • Keep photographic record Lecture 4 Q: You are newly employed as a Commercial Manager with a medium sized Groundworks Subcontractor. Your Managing Director has called you in to attend a meeting relating to a €2m pipelaying project on which he wants your advice. He states that the contract originally contained 8000m of 400mm diameter pvc watermain and this has now increased to 8900m. He points out that the additional 900m of pipework is a variation and he wants to apply on a dayworks basis for this work. What is your advice? Page 2
  • 3. Ans: • It is a variation • Valuing the work depends on the circumstances: location, obstacles or barriers, access etc • If possible, base it on BOQ rates • If not entirely identical, adjust bill rates to suit • May have to build up a new rate from scratch • Use dayworks only as a last resort Lecture 5 Q: You are employed as a Commercial Manager with a large Main Contractor. You have full commercial responsibility for the construction of a new office development in Clonee, Co Meath. The subcontractor who is carrying out the roofing and cladding package is causing problems on the contract. (1) Although he commenced work on his agreed commencement date, he is now 2 weeks beyond his completion date with 10% of his work package still to do. (2) You had no scaffold in place, and he has sent you in 4 weeks of daywork charges for having to use an aerial platform. (3) He has left packaging and boxes all over the site and will not tidy up. (4) There was an additional 60m2 of Kingspan cladding required where the BOQ was under measured, and he has sent in daywork sheets to cover this item, which is working out three times more expensive than if BOQ rates were used. The subcontractor is meeting you in the morning and wants to bring his account up to date. He has threatened that if there is not a cheque ready for him by the close of business tomorrow for the balance of all work done, he is going to start pulling cladding sheets off the building. What advice are you going to give him in that meeting? Ans: 1) Draw the subcontractors attention to the contract he signed - Pre-start meeting – the contract conditions were fully explained - No Letter for extension of time was sent in - Main contractor is responsible for his sub-contractors hence any delays will result in countercharges - Last resort- expel sub-contractor off site or bring in more resources and countercharge from subbies account Page 3
  • 4. 2) Tell sub-contractor to check list of agreed attendances as these form part of the contract. Sub-contractor has a valid case if these items are not listed on his attendances sheet 3) Check pre-start minutes of contract to see who is responsible. Give subbie two days to clean up site unless very urgent. If he doesn’t clean site, get your own operatives to clean up and countercharge at market rates for labour and skips – unless nominated sub-contarctor. 4) Use rates in BOQ unless not similar conditions – dayworks are used as a last resort 5) Refer to payment terms in contract – advise that it is criminal damage – gardai ! Lecture 7 Q: You are employed as a Commercial Manager on a €40million multi purpose office and apartment development. You are 4 months into a 24 month project. This is a flagship project for your company and your reputation and future career are linked to this project having a successful outcome. The third interim certificate has been faxed to you from the Architects office, and your internal costing department has sent you their cost report for the project to date. You have quickly subtracted the costs figure from the value amount and to your horror is showing a loss of -25%. Your financial director is meeting you on site in three hours. He wants an update on the financial standing of the project as he is calculating the Christmas bonus payments for all on site staff the following morning. How are you going to spend the next three hours? Ans: 1) Don’t panic 2) Cost Value Reconciliation • Interim valuation may be under valued • Possible mistakes on QS recommendation • Costs may be up to a different date • Ensure comparing apples with apples If still negative: • Check if you undervalued the work • Check Prelims actual v’s budget • Check if you have over paid subbies or suppliers (bulk orders) Lecture 8 Q: You are newly employed as a commercial manager with a small civil engineering sub- contractor. You have financial responsibility for numerous contracts of varying value. The sub-contractor has no idea whether he is making money on these jobs or not! He has a vague idea from job to job, and only really knows at the end of the year whether the company is making a profit. You are the first commercial manager to be employed by his Page 4
  • 5. company and he wants advice on how you can determine the profit on each individual contract as they progress. What is your advice? Ans: • Separate the contracts and allocate job numbers thus allocating costs to each contract as necessary • Prepare budgets for the profit on each contract (excel sheet – profit in each item) • Prepare a prelims budget • Prepare a cost value reconciliation on a monthly basis – prepare actual v’s budget for prelims – identify overspending – take action • Final CVR based on Final Account Lecture 9 Q: You are newly employed as a commercial manager with a small building main contractor. The managing director wants your advice on the following: (a) Implementing a quality assurance system for the company. He feels that it will cost his company a lot of money to set up and wants to know where he will see financial returns on this money (b) At present, he uses standard skips to dispose of waste, and he wants your opinion from a cost point of view on why he should segregate waste on site. What is your advice? Ans: (a) • Prequalification for new work - Credibility/Trustworthy/Reliability • Good Management procedures - Efficiency • Use of standard forms protects the company e.g. claims (b) • Standard skips are charged at the highest rate • Large reductions for specific skips – Steel 100% / Timber 50% / Gypsum ? • Re-use and recycle • A tidy site – better run – cost effective Lecture 10 Q: Build up a rate for blockwork from the following information: Blockwork; 100mm thick; in cement mortar (1:3) block size 440x215x100mm Constants Blocks 10nr/m2 of blockwork Mortar 0.007m3/m2 of blockwork Page 5
  • 6. Blocklayer 0.4 hours/m2 of blockwork Labourer 0.2 hours/m2 of blockwork Costs Labourer €19 per hour Blocklayer €30 per hour Blocks €800 per thousand Mortar €95 per m3 Waste on Blocks 5% Waste on Mortar 15% Profit & Overheads 12% Ans: Materials Blocks 10nr/m2 €800/1000x10= €8.00 + 5% = € 8.40 Mortar €95 per m3 x 0.007= €0.67 + 15% = € 0.77 Labour Blocklayer 0.4hrs x €30 = €12.00 Labourer 0.2 hrs x €19 = € 3.80 Sub Total €24.99 + P & O @ 12% €2.996 TOTAL Rate per m2 of Blockwork €27.97 Lecture 10B Q: You are newly employed as a commercial manager with a medium sized Groundworks subcontractor. You have lined up 4 major contracts which will keep your company busy for the coming two years despite the current economic climate. All of these contracts are for the renewal of watermains in rural areas. The company does not own its own plant and the managing director has approached you, seeking your advice on whether the company should continue hiring plant or is it a good time to purchase plant? What is your advice? Ans: Advantages of hiring plant: • Low maintenance costs • Contractors money not tied up in expensive plant – cashflow! • Easy to return idle plant • Plant hire company will supply skilled operatives/drivers • Can hire for minimum period Disadvantages of hiring plant: • You don’t own the plant – money paid out Page 6
  • 7. Particular machines may not be available from the hire company • Possible problems with standing time • No tax benefits Conclusion: To purchase as you have continuous work for 2 years for the same type of plant Lecture 13 Q: You are employed as a site manager with a medium sized contractor. You are managing the construction of a new €2m primary school which happens to be in the area where you live. You are on first name terms with the school board of management. The chairman of that board has approached you on site and instructed you to change the skirtings in the school from MDF to red Deal. You have just started the second fix carpentry and the MDF is already on site! How do you proceed? Ans: 1) Firstly you advise the chairman from the Board of Management that you cannot proceed without an architect’s instruction. 2) You make contact with the architect and advise him of the request 3) You or the commercial manager compile a cost for the variation – include a restocking charge from the supplier for taking back unusable materials 4) Do not proceed without an architect’s instruction 5) Confirmation of verbal instruction in some cases Lecture 14a Q: You are employed as a Commercial Manager with a large Main Contractor. You have full commercial responsibility for the construction of a new Community Centre in Navan, Co. Meath. The estimator handed you the full tender documentation from when the job was at tender stage at an internal pre-start meeting. You have agreed with senior management that the profit budget on the contract is 8%. You are now four months into a 12 month project and your latest monthly CVR is showing a profit of 16%. The Surveying Director has called you in to update him on progress, and a full financial outlook for the contract has been requested. You know the following facts: 1. Although the contract is showing a profit of 16%, your current preliminaries budget has been exceeded by 15k to date and you estimate that the overall preliminaries budget will not cover your actual preliminaries at the end of the contract. 2. The quotation used at tender stage for the flooring package was from a subcontractor who has now gone into liquidation. You had 25% mark up on this package in your profit budget. If you use the next quotation from tender stage you will have only 1% profit on this package. Page 7
  • 8. 3. The estimator made a mistake when pricing the paving works on the BOQ and priced 100mm tarmacadam instead of 200mm and didn’t qualify the tender. 200mm tarmacadam costs €14/m2 more than 100mm and there is 10,000m2 of this item. You will be losing 140k on this package if this situation stands. You want to make the Commercial Director aware of these items, but you don’t want to come to the table without proactive advice on possible solutions to the three problems. Make a note of possible solutions to the three problems you are dealing with. Ans: 1) Prepare actual preliminaries v’s budget report and • Highlight the areas or prelims where over spend was occurring so action can be taken. • Advise the surveying director where savings can be made i.e. site supervision. • Revise your prelims budget for rest of contract – taking agreed saving into account • Meet with the contracts manager and discuss possible ways of cutting the programme. 2) • Contact second place sub-contractor and try and get him to reduce his rates. • You will seek further quotations for the same package. • You will check the BOQ for over-measure • Approach the architect on changing the specification 3) • Approach the architect/client and offer 50% of the savings to change to Ulster Carpet – make it worthwhile • Seek better quotations for 200mm tarmacadam • Scan the BOQ for savings in other areas and off set against this item • Check the measure on the tarmacadam to see if it was over measured Lecture 14b Q: You are employed as a Commercial Manager with a large Main Contractor. You have full commercial responsibility for the construction of a new multi million euro office development in Dublin City Centre. As part of your role, you are responsible for compiling interim valuations for the contract, chasing up QS recommendations and architects certificates, and forwarding this documentation to the financial department for invoicing. You are sending in your valuations on time every month, however the clients QS is cutting every valuation by 50%. He claims that you are inflating the valuations with variations which are not agreed, and applying for work which is not completed. Page 8
  • 9. Your financial director has highlighted the fact that the company cashflow is suffering as a result of your contract. What do you think is the best course of action to resolve this situation? Ans: • Meet with the clients QS • Firstly because there is such a difference (50%) - Compile evaluations with clients QS prior to submitting - Have the disputes sorted as they arise • Try to agree variations as they happen • Keep good photographic record • If you cannot agree after this, you can go to conciliation and then to arbitration of necessary Lecture 14c Q: You are newly employed as a Commercial Manager with a medium sized Groundworks Subcontractor. Your Managing Director has called you in to attend a meeting relating to a €2m pipelaying project on which he wants your advice. He states that the contract originally contained 8000m of 400mm diameter pvc watermain and this has now increased to 8900m. He points out that the additional 900m of pipework is in the public road while the other 8000m was through grass verge. There is 50m of this additional pipework in an alleyway with no access for an excavator. The clients QS insists that this work will be carried out at the same BOQ rate which applied to the original 8000m variation. What is your advice? Ans: • Firstly everyone is agreed that this is a variation • Advise clients QS that only a comparable BOQ rate can be used • A new rate must be compiled based on - traffic management - different backfilling - reinstatement - rate of production 50m – daywork – best option because it’s difficult to evaluate whats involved and build up a rate (unforeseen) Lecture 14d Q: You are employed as a Commercial Manager with a large Main Contractor. You have full commercial responsibility for the construction of a new office development in Clonee, Co Meath. The domestic subcontractor who is carrying out the glazing package is causing problems on the contract. 1) He didn’t commence work on his agreed commencement date, he is now 3 weeks beyond his completion date with 20% of his work package still to do. Page 9
  • 10. 2) He has sent you in 6 weeks of daywork charges for having to use an aerial platform. 3) He has left packaging and boxes all over the site and will not tidy up. 4) There was an additional 5no. additional windows required which were missed in the BOQ, and he has sent in daywork sheets to cover these items, which is working out three times more expensive than if BOQ rates were used. The subcontractor is meeting you in the morning and wants to bring his account up to date. What advice are you going to give him in that meeting? Ans: 1) Draw the subcontractors attention to the contract he signed - Pre-start meeting – the contract conditions were fully explained - No Letter for extension of time was sent in - Main contractor is responsible for his sub-contractors hence any delays will result in countercharges - Last resort- expel sub-contractor off site or bring in more resources and countercharge from subbies account 2) Tell sub-contractor to check list of agreed attendances as these form part of the contract. Sub-contractor has a valid case if these items are not listed on his attendances sheet 3) Check pre-start minutes of contract to see who is responsible. Give subbie notice to clean up site. If he doesn’t clean site, get your own operatives to clean up and countercharge at market rates for labour and skips – unless nominated sub-contarctor. 4) If comparable rates in BOQ then use that rate unless different conditions (ie all other windows were on ground floor and new ones on 5th Floor) – in this case adjust existing rates and if no other option use Dayworks Lecture 14e Q: You are employed as a Commercial Manager on a €40million multi purpose office and apartment development. You are 4 months into a 24 month project. You have just completed the CVR for that month and its showing a loss of 20%. You know that you have achieved the budgeted profit on all the subcontractor packages to date, which were averaging 15% profit. Your financial director wants an update on the financial standing of the project. How will you source the necessary information? Page 10
  • 11. Ans: • You have achieved the budgeted profit with sub-contractors so problem doesn’t lie here – look at possible problems from other areas • Check Preliminaries • Interim Valuation could have been under valued • QS/Architect could have undervalued • Incorrect cost allocation – check material delivery dockets • Subcontractor could have been overpaid • Check initial budget for errors Lecture 14f Q: You are newly employed as a Commercial Manager with a medium sized Groundworks Subcontractor. You have lined up 4 small contracts which will keep your company busy for the coming 6 months and there is no guarantee of work after that. All of these contracts are for the renewal of watermains in rural areas. The company does not own its own plant and the Managing Director has approached you, seeking your advice on what the advantages and disadvantages of hiring plant are, and what is the best option in his case? What is your advice? Ans: Advantages of hiring plant: • Low maintenance costs • Contractors money not tied up in expensive plant – cashflow! • Easy to return idle plant • Plant hire company will supply skilled operatives/drivers • Can hire for minimum period • No requirement for a depot or yard • Less insurance costs Disadvantages of hiring plant: • You don’t own the plant – money paid out – can be expensive over long term period • Particular machines may not be available from the hire company when needed • Possible problems with standing time • No tax benefits Conclusion: To purchase as you have continuous work for 2 years for the same type of plant Lecture 16 Q: You are employed as a Commercial Manager with a medium sized Main Contractor. You are in the process of agreeing a Final Account for a completed office block with the Page 11
  • 12. clients QS. There is a major dispute between you and the clients QS over a large variation on the cladding package where the thickness of the panel had not been stated in the BOQ description. You had priced 60mm which was detailed in small print on the Architectural drawings while 80mm was required. The clients QS has stated that the 80mm thickness was shown on the engineers drawing, and as an experienced builder, you should have known that 80mm was needed! The form of contract used was the RIAI standard yellow form. Your Managing Director wants to take a court case against the client to get this issue resolved. What is your advice? Ans: Strong case as this is an architectural panel issue and not a structural panel issue therefore the architectural drawings would have preference giving the builder a strong case Suggest negotiation at senior level RIAI form of contract so conciliation must be entered into before other binding resolutions are considered If above fail Mini Trial Expert determination Then Arbitration Lecture 17 Q: You have started your own building company, tendering for projects ranging in size from €100k to €2m. A new client has approached you and is interested in constructing a Nursing Home on a site which he already owns. He has one schematic drawing showing the floor plan (one storey building) and wants an idea of what it will cost to construct. What advice will you give him? Ans: • You can prepare a basic cost plan on the limited information available • Cost plan will be provisional • Cost plan can be prepared in two ways: 1) cost per m2 (superficial) 2) Cost per Unit (per bed) • If client has a budget – work back from that • Pricing – normally previous work of a similar nature • New Builder – own experience/local PQS/Bruce Shaw handbook/Spons etc • Price depends on location/site/market conditions/specifications/time etc Page 12