SlideShare a Scribd company logo
1 of 2
Below is a summary of the surveying elements I have carried out not necessarily
identified on my CV
Cala Homes (Following sponsorship by them on my degree) I was a project manager
responsible for several developments in a normal surveying role but also had to act
for Cala finance in taking on recovery of developments that had been funded by Cala
but failed. These varied between 10 and 52 units and required placing and
management of contracts/subcontracts in value between £50k and £7.5m to allow
completion and recovery of funding. Several sites were worked on with the land
department for viability and land purchase exercises. I was responsible for all
surveying and construction matters. All monthly reporting was carried and we had
the use of the most efficient surveying software packages.
Rialto Homes I was senior surveyor on a £50m build, luxury development in London
(127 apartments plus leisure facilities) which included deep basement and high rise
RC frame. During the process the superstructure structural design failed requiring the
appointment of a new engineer, respective major insurance claim. The concrete frame
contractor was already contracted and as such required on the spot daily re-measures
with release of information, renegotiating and approval of new works to maintain
production. These had to be approved by not only the insurers but also the JV
representatives (Gardiner and Theobold). Production was maintained with express
rebar deliveries and final account maintained. All other subcontract appointments
were placed in line with programme requirements. Client variations to some units
exceeded £250k and hence had to manage these with a dedicated team. There was
also the normal monthly reports/CVR etc.
Barratt Homes there were 2 projects. One was high rise development (£25m build)
whereby I had to manage the consultants and main contractor to agree the main
shell and core works. During initial works I managed to negotiate for the fit out of all
apartments with some nominated suppliers and sub-contractors and then went on to
approve subsequent applications, variations and payments together with all reporting
and CVR requirements.
There was also the associated management of all consultants.
In addition I managed a luxury development of 9 high end units with a build value of
£15m with all respective surveying duties and full control of on-site construction.
The Commercial director at Cala Homes became the MD at Barretts and so worked
with him over 5 years.
Taylor Wimpey I managed the project in Newport with a £60m main contract
negotiated from competitive tender with Taylor Woodrow. This involved managing
the appointed consultants for both the commercial and technical sides of the
contract.working closely I also had to work closely with the internal surveyors on the
domestic build as these were non standard apartments. The project had major civil
works including a flood defence on the second highest tidal range in the world and
deep excavations through existing major structures requiring remeasuring and
payments etc. This also involved the management of all consultants and associated
consortium members including government.
Later on I worked again with Taylor Wimpey as a PM but in more of a construction
and design role on a difficult consortium regeneration project, this being the 3rd
term with them exceeding 5 years in total with them.
Whilst in Dubai and Oman there was a heavy involvement in the contract/surveying
side including negotiations with the banks to secure the funding facility on a £200m
construction project.
Most recently at Penguin, was responsible for negotiating and confirming variation,
extension of time, loss and adjustment, valuations, contesting payless notice, change
orders/notices.
You can also view my profile on ‘Linkedin.com’.
I would appreciate the opportunity to discuss this position on 07787 508758 or 01242
675000 and look forward to hearing from you.
Many Thanks,
Colin Ward

More Related Content

What's hot

C.V. Eng. Abdulqader 10-8-2015
C.V. Eng. Abdulqader 10-8-2015C.V. Eng. Abdulqader 10-8-2015
C.V. Eng. Abdulqader 10-8-2015Abdulqader Khaled
 
CV Details 2016
CV Details 2016CV Details 2016
CV Details 2016Liam Henry
 
Jeff's cv - 2015 version
Jeff's  cv - 2015 versionJeff's  cv - 2015 version
Jeff's cv - 2015 versionJeffrey Hunt
 
Engr. adnan khan
Engr. adnan khanEngr. adnan khan
Engr. adnan khanAdnan khan
 
Playing nice with the neighbors dealing with adjoining properties during cons...
Playing nice with the neighbors dealing with adjoining properties during cons...Playing nice with the neighbors dealing with adjoining properties during cons...
Playing nice with the neighbors dealing with adjoining properties during cons...francistoriaga
 
Resume Oct 2015 Revision 2
Resume Oct 2015 Revision 2Resume Oct 2015 Revision 2
Resume Oct 2015 Revision 2David Seaward
 

What's hot (7)

C.V. Eng. Abdulqader 10-8-2015
C.V. Eng. Abdulqader 10-8-2015C.V. Eng. Abdulqader 10-8-2015
C.V. Eng. Abdulqader 10-8-2015
 
CV Details 2016
CV Details 2016CV Details 2016
CV Details 2016
 
Jeff's cv - 2015 version
Jeff's  cv - 2015 versionJeff's  cv - 2015 version
Jeff's cv - 2015 version
 
Engr. adnan khan
Engr. adnan khanEngr. adnan khan
Engr. adnan khan
 
Playing nice with the neighbors dealing with adjoining properties during cons...
Playing nice with the neighbors dealing with adjoining properties during cons...Playing nice with the neighbors dealing with adjoining properties during cons...
Playing nice with the neighbors dealing with adjoining properties during cons...
 
Aug 2016
Aug 2016Aug 2016
Aug 2016
 
Resume Oct 2015 Revision 2
Resume Oct 2015 Revision 2Resume Oct 2015 Revision 2
Resume Oct 2015 Revision 2
 

Similar to Colin Ward Surveying summary

CV_Andy_Coupland (1)
CV_Andy_Coupland (1)CV_Andy_Coupland (1)
CV_Andy_Coupland (1)Andy Coupland
 
James Nolan experience in Energy, renewables, Waste to Energy and Waste to Oil
James Nolan experience in Energy, renewables, Waste to Energy and Waste to OilJames Nolan experience in Energy, renewables, Waste to Energy and Waste to Oil
James Nolan experience in Energy, renewables, Waste to Energy and Waste to OilJames Nolan
 
Resume - David Steele 14.05.15
Resume - David Steele 14.05.15Resume - David Steele 14.05.15
Resume - David Steele 14.05.15David Steele
 
CURRICULUM VITAE 12.03.16
CURRICULUM VITAE  12.03.16CURRICULUM VITAE  12.03.16
CURRICULUM VITAE 12.03.16Stephen Baird
 
Fbs Portfolio 2011 2012
Fbs Portfolio 2011   2012Fbs Portfolio 2011   2012
Fbs Portfolio 2011 2012Tom Stack
 
Adrians Job ApplicationRecent 2015
Adrians Job ApplicationRecent 2015Adrians Job ApplicationRecent 2015
Adrians Job ApplicationRecent 2015Adrian Taylor
 
New brochure 240311
New brochure 240311New brochure 240311
New brochure 240311weydon23
 
Master_Resume__Ron_White_9
Master_Resume__Ron_White_9Master_Resume__Ron_White_9
Master_Resume__Ron_White_9Ron White
 
The building consultancy booklet
The building consultancy bookletThe building consultancy booklet
The building consultancy bookletEdwin Leting
 
Resume November 2016
Resume November 2016Resume November 2016
Resume November 2016John Brennan
 
Fluid Portfolio Summer 2012
Fluid Portfolio Summer 2012Fluid Portfolio Summer 2012
Fluid Portfolio Summer 2012Tom Stack
 
Steven Castellano.resume.2016
Steven Castellano.resume.2016Steven Castellano.resume.2016
Steven Castellano.resume.2016steven castellano
 
R&M Property Group Ltd brochure - 2018
R&M Property Group Ltd  brochure - 2018R&M Property Group Ltd  brochure - 2018
R&M Property Group Ltd brochure - 2018Thomas McKenna
 
Steven Castellano.resume.2016
Steven Castellano.resume.2016Steven Castellano.resume.2016
Steven Castellano.resume.2016steven castellano
 
Case study brownfield redevelopment
Case study   brownfield redevelopmentCase study   brownfield redevelopment
Case study brownfield redevelopmentmlister1216
 
Mike Okey CV FM1 Linked in
Mike Okey  CV FM1 Linked inMike Okey  CV FM1 Linked in
Mike Okey CV FM1 Linked inMike Okey
 
resume for john rhynold 2015 #2
resume for john rhynold 2015 #2resume for john rhynold 2015 #2
resume for john rhynold 2015 #2john rhynold
 

Similar to Colin Ward Surveying summary (20)

CV_Andy_Coupland (1)
CV_Andy_Coupland (1)CV_Andy_Coupland (1)
CV_Andy_Coupland (1)
 
AnthonyCurrent HTR
AnthonyCurrent HTRAnthonyCurrent HTR
AnthonyCurrent HTR
 
James Nolan experience in Energy, renewables, Waste to Energy and Waste to Oil
James Nolan experience in Energy, renewables, Waste to Energy and Waste to OilJames Nolan experience in Energy, renewables, Waste to Energy and Waste to Oil
James Nolan experience in Energy, renewables, Waste to Energy and Waste to Oil
 
zk resume
zk resumezk resume
zk resume
 
Resume - David Steele 14.05.15
Resume - David Steele 14.05.15Resume - David Steele 14.05.15
Resume - David Steele 14.05.15
 
CURRICULUM VITAE 12.03.16
CURRICULUM VITAE  12.03.16CURRICULUM VITAE  12.03.16
CURRICULUM VITAE 12.03.16
 
Fbs Portfolio 2011 2012
Fbs Portfolio 2011   2012Fbs Portfolio 2011   2012
Fbs Portfolio 2011 2012
 
Adrians Job ApplicationRecent 2015
Adrians Job ApplicationRecent 2015Adrians Job ApplicationRecent 2015
Adrians Job ApplicationRecent 2015
 
New brochure 240311
New brochure 240311New brochure 240311
New brochure 240311
 
Master_Resume__Ron_White_9
Master_Resume__Ron_White_9Master_Resume__Ron_White_9
Master_Resume__Ron_White_9
 
The building consultancy booklet
The building consultancy bookletThe building consultancy booklet
The building consultancy booklet
 
Resume November 2016
Resume November 2016Resume November 2016
Resume November 2016
 
Fluid Portfolio Summer 2012
Fluid Portfolio Summer 2012Fluid Portfolio Summer 2012
Fluid Portfolio Summer 2012
 
Steven Castellano.resume.2016
Steven Castellano.resume.2016Steven Castellano.resume.2016
Steven Castellano.resume.2016
 
resume 2014
resume 2014resume 2014
resume 2014
 
R&M Property Group Ltd brochure - 2018
R&M Property Group Ltd  brochure - 2018R&M Property Group Ltd  brochure - 2018
R&M Property Group Ltd brochure - 2018
 
Steven Castellano.resume.2016
Steven Castellano.resume.2016Steven Castellano.resume.2016
Steven Castellano.resume.2016
 
Case study brownfield redevelopment
Case study   brownfield redevelopmentCase study   brownfield redevelopment
Case study brownfield redevelopment
 
Mike Okey CV FM1 Linked in
Mike Okey  CV FM1 Linked inMike Okey  CV FM1 Linked in
Mike Okey CV FM1 Linked in
 
resume for john rhynold 2015 #2
resume for john rhynold 2015 #2resume for john rhynold 2015 #2
resume for john rhynold 2015 #2
 

Colin Ward Surveying summary

  • 1. Below is a summary of the surveying elements I have carried out not necessarily identified on my CV Cala Homes (Following sponsorship by them on my degree) I was a project manager responsible for several developments in a normal surveying role but also had to act for Cala finance in taking on recovery of developments that had been funded by Cala but failed. These varied between 10 and 52 units and required placing and management of contracts/subcontracts in value between £50k and £7.5m to allow completion and recovery of funding. Several sites were worked on with the land department for viability and land purchase exercises. I was responsible for all surveying and construction matters. All monthly reporting was carried and we had the use of the most efficient surveying software packages. Rialto Homes I was senior surveyor on a £50m build, luxury development in London (127 apartments plus leisure facilities) which included deep basement and high rise RC frame. During the process the superstructure structural design failed requiring the appointment of a new engineer, respective major insurance claim. The concrete frame contractor was already contracted and as such required on the spot daily re-measures with release of information, renegotiating and approval of new works to maintain production. These had to be approved by not only the insurers but also the JV representatives (Gardiner and Theobold). Production was maintained with express rebar deliveries and final account maintained. All other subcontract appointments were placed in line with programme requirements. Client variations to some units exceeded £250k and hence had to manage these with a dedicated team. There was also the normal monthly reports/CVR etc. Barratt Homes there were 2 projects. One was high rise development (£25m build) whereby I had to manage the consultants and main contractor to agree the main shell and core works. During initial works I managed to negotiate for the fit out of all apartments with some nominated suppliers and sub-contractors and then went on to approve subsequent applications, variations and payments together with all reporting and CVR requirements. There was also the associated management of all consultants. In addition I managed a luxury development of 9 high end units with a build value of £15m with all respective surveying duties and full control of on-site construction. The Commercial director at Cala Homes became the MD at Barretts and so worked with him over 5 years.
  • 2. Taylor Wimpey I managed the project in Newport with a £60m main contract negotiated from competitive tender with Taylor Woodrow. This involved managing the appointed consultants for both the commercial and technical sides of the contract.working closely I also had to work closely with the internal surveyors on the domestic build as these were non standard apartments. The project had major civil works including a flood defence on the second highest tidal range in the world and deep excavations through existing major structures requiring remeasuring and payments etc. This also involved the management of all consultants and associated consortium members including government. Later on I worked again with Taylor Wimpey as a PM but in more of a construction and design role on a difficult consortium regeneration project, this being the 3rd term with them exceeding 5 years in total with them. Whilst in Dubai and Oman there was a heavy involvement in the contract/surveying side including negotiations with the banks to secure the funding facility on a £200m construction project. Most recently at Penguin, was responsible for negotiating and confirming variation, extension of time, loss and adjustment, valuations, contesting payless notice, change orders/notices. You can also view my profile on ‘Linkedin.com’. I would appreciate the opportunity to discuss this position on 07787 508758 or 01242 675000 and look forward to hearing from you. Many Thanks, Colin Ward