History of CMMs

• CMM v1.0 (Software) was the first to
  be developed
• Others were developed subsequently:
    – SE CMM (Systems Engineering) CMM
    – Integrated Product Development CMM
    – SA (Software Acquisition) CMM
    – People CMM




3
Why Integrate?

• Adaptability to enterprise needs
    – designed for evolution to meet current
      and future enterprise-wide process
      improvement needs
    – can add new process areas, generic
      improvement approach still applies




4
CMMI - SE/ SW

• Systems Engineering
    – Covers the development of total systems,
      which may or may not include software
    – Focus on transforming customer needs,
      expectations, and constraints into
      product solutions and supporting those
      product solutions throughout the product
      life cycle
• Software Engineering
    – Covers the development of software
      systems
    – Focus on applying systematic, disciplined,
      and quantifiable approaches to the
      development, operation and
      maintenance of software
• CMMI - SE/SW covers both
5
Why Use CMMI SE/SW?

• Increased dependency between
  systems engineering and software
  engineering
• Low maturity of the interfaces
  between systems engineering and
  software engineering




6
What’s New in CMMI Ver 1.2




7
CMMI® Framework


•   Constellation: Collection of CMMI® components that includes the
    model, its training materials and appraisal-related documents for an
    area of interest. CMMI models for development, services and
    acquisition
•   Model for development provides amplifications for the systems
    engineering, software engineering, and hardware engineering
    disciplines
•   “Additions” used to expand constellations for specific additional
    content - CMMI® Dev has one such addition (CMMI® - Dev + IPPD) (In
    V1.1, IPPD was a discipline.)
•   Based on the initial efforts to maximize commonality among CMMI
    models, 16 of the 22 process areas of CMMI-DEV comprise the
    process improvement core for the three areas of interest currently
    being pursued: development, acquisition, and services.




8
Concept of Constellations

    • Latest version of CMMI i.e. CMMI
      ver 1.2 for Development was
      launched in Aug’06
    • Constellation: Collection of CMMI®
      components that includes the
      model, its training materials and
      appraisal-related documents for
      an area of interest
    • Other constellations in making
      – Acquisition
      – Services


9
Concept of Maturity

•    Software Process Maturity
      –   Extent to which a specific process is explicitly defined, managed, measured,
          controlled and effective
      –   Implies a potential growth in capability and indicates both the richness of an
          organization’s software process and the consistency with which it is applied in
          projects throughout the organization
•    Maturity Level
      –   A well defined evolutionary plateau toward achieving a mature software process
      –   Each level provides a layer in the foundation for continuous process improvement




10
Staged Approach

• Proven sequence of typical areas to
  focus on for improvement
• Permits comparison across
  organizations - assessment results can
  be summarized into a single rating
• Easy migration from SW-CMM    SM




11
The Five Levels of Process
                     Maturity
                                              Continuous                        Improvement
                                                                     Optimizing Institutionalize
                                                 Process
                                            Improvement                (5)      d




                                                         Quantitatively Process measured
                               Quantitative              Managed        and controlled
                               Management
                                                             (4)



                                                            Process characterized
                    Process                   Defined       for the organization
             Standardization                    (3)         and is proactive




                                Managed          Process characterized for
     Basic Project                               projects and is often
      Management                   (2)           reactive



                                         Process unpredictable,
                     Initial             poorly controlled and
                      (1)                reactive

      © Software Engineering Institute




12
Level 1 Process Areas




       There are no Process Areas at Level 1




13
The Initial Level (1)
     • Environment not stable for developing and
       maintaining systems
     • Inadequate management and engineering
       practices
     • Ineffective planning
     • Reaction-driven commitment systems
     • Emphasis on development and testing during crisis
     • Success depends on having exceptional people
     • Unpredictable process capability
     • Unpredictable schedules, budgets, functionality,
       and quality
     • Few stable processes




14
Level 2 Process Areas
 •   Focus is on enabling institutionalizing Project Management
     Practices



        Instilling basic
        discipline
        into project
        management             Requirements Management
        practices.                  Project Planning
        Each project
        may follow           Project Monitoring and Control
        their own           Supplier Agreement Management
        set of processes.      Measurement and Analysis
                         Process and Product Quality Assurance
                               Configuration Management




15
The Managed Level (2)
     •   Policies for managing projects
     •   Planning and managing based on experience
     •   Allows repeatability of successful practices
     •   Specific processes implemented by the projects
         may differ
     •   Realistic project commitments
     •   Costs, schedules and functionality tracked
     •   Requirements and work products are baselined
     •   Standards defined and conformed to
     •   Strong customer-supplier relationship with
         subcontractors
     •   A measurement process is in place




16
Level 3 Process Area
     •   Focus is on developing technical/ engineering practices
         integrating it with management practices and institutionalizing
         it.




         Developing                   Requirements Development
         engineering
         practices, integrating            Technical Solution
         them with management             Product Integration
         practices and                        Verification
         standardizing                         Validation
         processes across            Organizational Process Focus
         the organization      Organizational Process Definition + IPPD
                                        Organizational Training
                                Integrated Project Management + IPPD
                                           Risk Management
                                    Decision Analysis and Resolution




17
The Defined Level (3)

•    Organization-wide standard processes
•    Effective engineering practices
•    Integration of engineering and management processes
•    Reuse of organizational learning
•    Process Engineering Group (PEG)
•    Organization-wide training program
•    Project’s “Defined Process”
•    Good management insight into the technical progress on all
     projects




18
Level 4 Process Area
     •   Focus is on quantitatively managing project and organization
         wide performance




              Quantitatively
              manage
              organizational
              processes
                               Organizational Process Performance

                                Quantitative Project Management




19
The Quantitatively Managed
         Level (4)
• Quantitative goals for projects and processes
• Variation in process performance narrowed
• Meaningful variations can be distinguished from random
  variation
• Products are of high quality
• Projects are controlled quantitatively




20
Level 5 Process Area
     •   Focus is on continuously improving project and organizational
         capability




            Continuously
            improve project
            and
            organizational          Organizational Innovation and
            capability                       Deployment
            through
            innovations &           Causal Analysis and Resolution
            do root cause
            analysis for
            common causes




21
The Optimizing Level (5)

• Organization focused on process improvement
     – incremental advances in existing
       processes
     – innovations using new technologies and
       methods
• Proactive identification of weaknesses to strengthen
  processes
• Goal of preventing occurrence of defects through error-cause
  removal
• Cost-Benefit analyses of introducing new technologies and
  proposed process changes




22
Skipping Maturity Levels

• Counter-productive
• Each level builds a foundation for
  succeeding levels
• Required leverage for implementing
  processes effectively and efficiently
• However, processes described at a
  higher maturity level can be used




23
Continuous Model

     • Allows you to select the order of
       improvement that best meets your
       organization’s business objectives
     • Enables comparisons across and
       among organizations on a process-
       area-by-process-area basis
     • Provides an easy migration from
       models with a continuous
       representation to CMMI
     • Uses predefined sets of process
       areas to define an improvement
       path for an organization


24
Structure of PA




                       No common
                        features




25
http://www.qaiglobal.com
                                                                                                                                      INDIA

                                                                                                                                        USA

                                                                                                                                          UK

                                                                                                                                      CHINA

                                                                                                                                  MALAYSIA

                                                                                                                                SINGAPORE


    Click here for more on Software
    Process Improvement
                                                                                     CONTACT
                                                                                    US


QAI India:                            QAI USA:                             QAI Malaysia:
1010 - 1012, Ansal Towers, 38 Nehru   Windsor at Metro Center, 2101 Park   Level 36, Menara Citibank, 165, Jalan
Place                                 Center Dr., Suite 200, Orlando, FL   Ampang, 50450 Kuala Lumpur,
New Delhi - 110019, India             32835-7614                           Malaysia
Phone: +91- 11- 26219792, 26220580    Phone: +407-363-1111                 Phone: +603 2169 6241
conferences@qaiglobal.com             conferences@qaiglobal.com            conferences@qaiglobal.com




QAI UNICOM / UK:                      QAI Singapore:                       QAI China:
Unicom R&D House, One Oxford          391B Orchard Road #23-01,            Rm. 1211, No. 498 Guoshoujing Rd.
Road                                  Ngee Ann City Tower B,               Shanghai
Uxbridge, Middlesex, London, United   Singapore - 238874                   Zhangjiang Hi-Tech Park, Pudong New
Kingdom, Zip: UB9 4DA                 Phone:+65-6225-8139                  Area,
Phone : +44 (0)1895 256484            conferences@qaiglobal.com            Shanghai, China Zip: 201203
conferences@qaiglobal.com                                                  Phone : +86-21-51314155
                                                                           conferences@qaiglobal.com




www.qaiglobal.c                                                                                                © QAI India Limited. All rights QAI
                                                                                                                                           © reserved.
                                               All rights reserved. No part of this document may be reproduced or distributed in any form or by
                                                any means, or stored in a database or retrieval system, without prior written permission of QAI

CMMI Version 1.2

  • 1.
    CMMI: Version 1.2 Basics A presentation by QAI INDIA | USA | UK © QAI India Limited. All rights|reserved. | CHINA | MALAYSIA SINGAPORE
  • 2.
  • 3.
    History of CMMs •CMM v1.0 (Software) was the first to be developed • Others were developed subsequently: – SE CMM (Systems Engineering) CMM – Integrated Product Development CMM – SA (Software Acquisition) CMM – People CMM 3
  • 4.
    Why Integrate? • Adaptabilityto enterprise needs – designed for evolution to meet current and future enterprise-wide process improvement needs – can add new process areas, generic improvement approach still applies 4
  • 5.
    CMMI - SE/SW • Systems Engineering – Covers the development of total systems, which may or may not include software – Focus on transforming customer needs, expectations, and constraints into product solutions and supporting those product solutions throughout the product life cycle • Software Engineering – Covers the development of software systems – Focus on applying systematic, disciplined, and quantifiable approaches to the development, operation and maintenance of software • CMMI - SE/SW covers both 5
  • 6.
    Why Use CMMISE/SW? • Increased dependency between systems engineering and software engineering • Low maturity of the interfaces between systems engineering and software engineering 6
  • 7.
    What’s New inCMMI Ver 1.2 7
  • 8.
    CMMI® Framework • Constellation: Collection of CMMI® components that includes the model, its training materials and appraisal-related documents for an area of interest. CMMI models for development, services and acquisition • Model for development provides amplifications for the systems engineering, software engineering, and hardware engineering disciplines • “Additions” used to expand constellations for specific additional content - CMMI® Dev has one such addition (CMMI® - Dev + IPPD) (In V1.1, IPPD was a discipline.) • Based on the initial efforts to maximize commonality among CMMI models, 16 of the 22 process areas of CMMI-DEV comprise the process improvement core for the three areas of interest currently being pursued: development, acquisition, and services. 8
  • 9.
    Concept of Constellations • Latest version of CMMI i.e. CMMI ver 1.2 for Development was launched in Aug’06 • Constellation: Collection of CMMI® components that includes the model, its training materials and appraisal-related documents for an area of interest • Other constellations in making – Acquisition – Services 9
  • 10.
    Concept of Maturity • Software Process Maturity – Extent to which a specific process is explicitly defined, managed, measured, controlled and effective – Implies a potential growth in capability and indicates both the richness of an organization’s software process and the consistency with which it is applied in projects throughout the organization • Maturity Level – A well defined evolutionary plateau toward achieving a mature software process – Each level provides a layer in the foundation for continuous process improvement 10
  • 11.
    Staged Approach • Provensequence of typical areas to focus on for improvement • Permits comparison across organizations - assessment results can be summarized into a single rating • Easy migration from SW-CMM SM 11
  • 12.
    The Five Levelsof Process Maturity Continuous Improvement Optimizing Institutionalize Process Improvement (5) d Quantitatively Process measured Quantitative Managed and controlled Management (4) Process characterized Process Defined for the organization Standardization (3) and is proactive Managed Process characterized for Basic Project projects and is often Management (2) reactive Process unpredictable, Initial poorly controlled and (1) reactive © Software Engineering Institute 12
  • 13.
    Level 1 ProcessAreas There are no Process Areas at Level 1 13
  • 14.
    The Initial Level(1) • Environment not stable for developing and maintaining systems • Inadequate management and engineering practices • Ineffective planning • Reaction-driven commitment systems • Emphasis on development and testing during crisis • Success depends on having exceptional people • Unpredictable process capability • Unpredictable schedules, budgets, functionality, and quality • Few stable processes 14
  • 15.
    Level 2 ProcessAreas • Focus is on enabling institutionalizing Project Management Practices Instilling basic discipline into project management Requirements Management practices. Project Planning Each project may follow Project Monitoring and Control their own Supplier Agreement Management set of processes. Measurement and Analysis Process and Product Quality Assurance Configuration Management 15
  • 16.
    The Managed Level(2) • Policies for managing projects • Planning and managing based on experience • Allows repeatability of successful practices • Specific processes implemented by the projects may differ • Realistic project commitments • Costs, schedules and functionality tracked • Requirements and work products are baselined • Standards defined and conformed to • Strong customer-supplier relationship with subcontractors • A measurement process is in place 16
  • 17.
    Level 3 ProcessArea • Focus is on developing technical/ engineering practices integrating it with management practices and institutionalizing it. Developing Requirements Development engineering practices, integrating Technical Solution them with management Product Integration practices and Verification standardizing Validation processes across Organizational Process Focus the organization Organizational Process Definition + IPPD Organizational Training Integrated Project Management + IPPD Risk Management Decision Analysis and Resolution 17
  • 18.
    The Defined Level(3) • Organization-wide standard processes • Effective engineering practices • Integration of engineering and management processes • Reuse of organizational learning • Process Engineering Group (PEG) • Organization-wide training program • Project’s “Defined Process” • Good management insight into the technical progress on all projects 18
  • 19.
    Level 4 ProcessArea • Focus is on quantitatively managing project and organization wide performance Quantitatively manage organizational processes Organizational Process Performance Quantitative Project Management 19
  • 20.
    The Quantitatively Managed Level (4) • Quantitative goals for projects and processes • Variation in process performance narrowed • Meaningful variations can be distinguished from random variation • Products are of high quality • Projects are controlled quantitatively 20
  • 21.
    Level 5 ProcessArea • Focus is on continuously improving project and organizational capability Continuously improve project and organizational Organizational Innovation and capability Deployment through innovations & Causal Analysis and Resolution do root cause analysis for common causes 21
  • 22.
    The Optimizing Level(5) • Organization focused on process improvement – incremental advances in existing processes – innovations using new technologies and methods • Proactive identification of weaknesses to strengthen processes • Goal of preventing occurrence of defects through error-cause removal • Cost-Benefit analyses of introducing new technologies and proposed process changes 22
  • 23.
    Skipping Maturity Levels •Counter-productive • Each level builds a foundation for succeeding levels • Required leverage for implementing processes effectively and efficiently • However, processes described at a higher maturity level can be used 23
  • 24.
    Continuous Model • Allows you to select the order of improvement that best meets your organization’s business objectives • Enables comparisons across and among organizations on a process- area-by-process-area basis • Provides an easy migration from models with a continuous representation to CMMI • Uses predefined sets of process areas to define an improvement path for an organization 24
  • 25.
    Structure of PA No common features 25
  • 26.
    http://www.qaiglobal.com INDIA USA UK CHINA MALAYSIA SINGAPORE Click here for more on Software Process Improvement CONTACT US QAI India: QAI USA: QAI Malaysia: 1010 - 1012, Ansal Towers, 38 Nehru Windsor at Metro Center, 2101 Park Level 36, Menara Citibank, 165, Jalan Place Center Dr., Suite 200, Orlando, FL Ampang, 50450 Kuala Lumpur, New Delhi - 110019, India 32835-7614 Malaysia Phone: +91- 11- 26219792, 26220580 Phone: +407-363-1111 Phone: +603 2169 6241 conferences@qaiglobal.com conferences@qaiglobal.com conferences@qaiglobal.com QAI UNICOM / UK: QAI Singapore: QAI China: Unicom R&D House, One Oxford 391B Orchard Road #23-01, Rm. 1211, No. 498 Guoshoujing Rd. Road Ngee Ann City Tower B, Shanghai Uxbridge, Middlesex, London, United Singapore - 238874 Zhangjiang Hi-Tech Park, Pudong New Kingdom, Zip: UB9 4DA Phone:+65-6225-8139 Area, Phone : +44 (0)1895 256484 conferences@qaiglobal.com Shanghai, China Zip: 201203 conferences@qaiglobal.com Phone : +86-21-51314155 conferences@qaiglobal.com www.qaiglobal.c © QAI India Limited. All rights QAI © reserved. All rights reserved. No part of this document may be reproduced or distributed in any form or by any means, or stored in a database or retrieval system, without prior written permission of QAI