SlideShare a Scribd company logo
1/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Chiller vs VRF system
LG Electronics Inc.
LGEHQ CAC Team
2/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
1. Design Comparison
VRF is very simplified refrigerant piping system. More flexible than water piping.
Chiller
MULTI V Plus Ⅱ (VRF)
Chiller system
• Outdoor unit (air-cooled type)
• Indoor unit
• Refrigerant piping
• Chiller
• FCU (Fan Coil Unit)
• AHU (Air Handling Unit)
System
composition
Feature
• Cooling tower
• Water piping, Duct working
• Water pumps
System concept
Design Commissioning
Operation Maintenance
Installation Reliability
3/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Network
Feature Chiller system
• Complicated wiring
MULTI V Plus Ⅱ (VRF)
• Simple wiring
Design Commissioning
Operation Maintenance
Installation Reliability
Easy network wiring
1. Design Comparison Network design
ACP
4/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
1. Design Comparison Total management
Design Commissioning
Operation Maintenance
Installation Reliability
[Manufacturer]
VAV boxes
supplier
Control
system
Feature Chiller system MULTI V Plus Ⅱ (VRF)
(For VRF) Manufacturer provide all equipment
• Simple control structure
No additional control provider
• Central control and energy monitoring with
low cost available
• Complicated control structure, additional
control manager in the system needed,
increasing cost
• Third part control provider needed,
interconnectivity problems.
5/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Design Commissioning
MULTI V Plus Ⅱ (VRF)
Chiller system
• The systems condition only the
necessary rooms with regard
to user demands.
• The systems commonly condition the entire building
at predetermined times, with no regard to user demands.
(very hot midnight, weekend, holiday etc)
Capacity
control
Feature
After office hours operation, VRF could be operated for the user demands.
<Better Capacity operation>
Operating Area
< Limited operation>
Individual operation
Operation Maintenance
Installation Reliability
2. Operation Comparison
6/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Temperature
control
Feature Chiller system
Require
1℃ or 2℃
MULTI V Plus Ⅱ (VRF)
Very precise
± 0.5℃
Precise temperature control
30
25
20
15
10 20 30 40 50 60 70
Cooling
MIN.
Chiller system
MULTI V system
Room
temp.
 0.5 0 C from set point
Design Commissioning
Operation Maintenance
Installation Reliability
Temp. control
2. Operation Comparison
7/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
VRF system doesn’t need a duct space.
Space
Efficiency
Feature MULTI V Plus Ⅱ (VRF)
• Small refrigerant space
Chiller system
• Large duct space
Design Commissioning
Operation Maintenance
Installation Reliability
Space (Duct working)
3. Installation Comparison
8/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Chiller
Pump
Boiler
Cooling
tower
(On the rooftop)
(Machine room drawing)
Outdoor
Unit
(On the rooftop)
(Rooftop drawing)
VRF system is no need for a machine room.
Installation
space
Feature MULTI V Plus Ⅱ (VRF)
• No need a machine room
Chiller system
• Need a machine room
Design Commissioning
Operation Maintenance
Installation Reliability
Installation space
3. Installation Comparison
9/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Efficient use of space is possible for VRF system
Chiller system
Space
Efficiency
Feature
P P
1/3
CHILLER SYSTEM
• Large pipe shaft is needed for water piping
MULTI V Plus Ⅱ (VRF)
VRF System
• Small pipe shaft is needed
Design Commissioning
Operation Maintenance
Installation Reliability
Space (Pipe shaft)
3. Installation Comparison
10/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
VRF system expansion is very easy with extra outdoor & indoor unit.
Chiller system
System
Expansion
Feature
• Capacity addition is difficult
as additional mechanical room, pump, cooling tower,
panel and piping is required.
MULTI V Plus Ⅱ (VRF)
• System Expansion is Easy
+
Design Commissioning
Operation Maintenance
Installation Reliability
System expansion
3. Installation Comparison
11/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
1 step Commissioning
6 steps Commissioning
MULTI V Plus Ⅱ (VRF)
Chiller system
Commissioning
Feature
There are a lot of commissioning points for the chiller system
• 6 Steps Commissioning • 1 Step Commissioning
Water cooled chiller (3)
(4)
Design Commissioning
Operation Maintenance
Installation Reliability
NO. of commissioning point
4. Commissioning Comparison
12/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Maintenance
Feature
Maintenance costs for a Multi V is lower than chilled water systems.
Water cooled chiller (3)
(4)
MULTI V Plus Ⅱ (VRF)
• Filter cleaning
• Heat exchanger cleaning
• Cycle check by notebook (LG MV)
Chiller system
• Filter cleaning
• Duct cleaning
• Water pipe – maintenance
• Periodical oil change, overhaul
• Pump
• Water treatment
• Cooling tower cleaning
Design Commissioning
Operation Maintenance
Installation Reliability
Maintenance list
5. Maintenance Comparison
13/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
(For Chiller Water treatment is required for clean water)
<Polluted Cooling Tower>
Water
treatment
Feature Chiller system
• Water treatment is required
(deficient service can cause legionary disease in the system)
MULTI V Plus Ⅱ (VRF)
• No water treatment is needed
Design Commissioning
Operation Maintenance
Installation Reliability
Water treatment
5. Maintenance Comparison
14/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Scale
cleaning
Feature Chiller system MULTI V Plus Ⅱ (VRF)
< The system is consist of refrigerant pipes >
• No water pipes : No scale (use refrigerant)
• Need to clean the water pipes
System efficiency drop & origin of germs
After 2~3year After 5~6year After 7~8year
10% 25~30% 35~40%
thickness of scale
Energy
Loss
Unit : mm
Unit : %
(For Chiller) Maintenance & cleaning periodically by exclusive company
Design Commissioning
Operation Maintenance
Installation Reliability
Scale cleaning
5. Maintenance Comparison
15/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Maintenance Staff
5. Maintenance Comparison
Design Commissioning
Operation Maintenance
Installation Reliability
Maintenance
Staff
Feature Chiller system MULTI V Plus Ⅱ (VRF)
(For Chiller) Certified maintenance staff is needed
• No need special maintenance staff.
• Economic and easy maintenance
• The system requires certified maintenance
staff not only for chillers but also pumps,
boilers, cooling towers etc.
• More expensive maintenance cost.
<NO Maintenance Staff>
< Maintenance Staff>
16/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Pipe Erosion
6. Reliability Comparison
Design Commissioning
Operation Maintenance
Installation Reliability
Pipe
Erosion
Feature Chiller system MULTI V Plus Ⅱ (VRF)
(For Chiller) Certified maintenance staff is needed
• Refrigerant does not cause corrosion therefore
no pipe damage occurred
• Pipe erosion can cause leakage.
• System capacity reduction.
• Brines use increase corrosion, anti corrosion
additives needed
<Cooper Pipe>
< Water pipe leakage >
17/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Category Product
Initial Cost
(USD)
Initial Cost
(USD)Total
Water
Cooled C
hiller
Chiller Price 355,484
877,097
AHU / Cooling T
ower / Pump, Pr
ice
148,065
Installation 383,871
VRV
Multi V 874,498
1,109,660
Installation 235,161
•April 2008
•Cooling Only
•Air Duct Included
Initial Cost Running Cost Maintenance Cost Total cost
• Type of Building: Shopping Mall
• Total area 9,000 m2 : 6 storey Building :1,500 m2/floor
• Actual cooling area : 1,500 m2 * 80 % * 6 Floor = 7,200 m2
• Cooling Load (Tr) / m2 : 700 Tr *12000 Btu/Hr = 1,166 Btu/m2
• Equipment : Water cooled chiller /Multi V unit
- Water Cooled Chiller :Trane Water cooled chiller
350 Tr x 2 set =700 Tr + 300 Back up
Pump’s =400 Tr x 2 set
AHU = 8000 CFM x 36 set
Cooling Tower =1200 Gpm x 3 +3 Back up
- VRF System :LG Multi V Plus II
48 Hp x 19 set=912 Hp 726 Tr
• Air conditioning time : Operation
- 13 hour a day (09:00 ~ 22:00)
- 30 days a month
- average load by month
 Equipments & Installation cost
MULTI V vs Chiller
7. Economic analysis
18/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Multi V running cost is 65 % compare to chiller
Category Product
Running
Cost
(USD)Tota
l
Water
Cooled C
hiller
Chiller Price
308,697
AHU / Coolin
g Tower / Pu
mp, Price
Multi V Price 200,158
•Based on KW data chiller/Multi V
•Based on, Thailand electrical standard
•ARI-Air conditioning & Refrigeration Institute
$0k
$100k
$200k
$300k
$400k
y
e
a
r
2
n
d
4
t
h
6
t
h
8
t
h
1
0
t
h
1
2
t
h
1
4
t
h
Chiller
Multi V
Running cost
Savings up to
15th yr : 35%
Chiller
Multi V
 Electrical cost
MULTI V vs Chiller
7. Economic analysis
Initial Cost Running Cost Maintenance Cost Total cost
19/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Category Price
Maintenance
Cost
(USD)Total
Water
Cooled C
hiller
Chiller Price
32,177
AHU / Cooling
Tower / Pump,
Price
Multi V Price 11,468
$0k
$100k
$200k
$300k
$400k
y
e
a
r
2
n
d
4
t
h
6
t
h
8
t
h
1
0
t
h
1
2
t
h
1
4
t
h
Chiller
Multi V
Chiller
Multi V
Maintenance
Cost savings
Up to 15th yr
: 66%
•Maintenance breakdown
•Chiller system -31 USD / Rt / yr.- 6 times/yr
•Multi V- 48 USD / Indoor / yr.- 6 times/yr
- 145 USD / Outdoor / yr.- 6 times/yr
Multi V maintenance cost is 24 % compare to chiller
 Maintenance cost
MULTI V vs Chiller
7. Economic analysis
Initial Cost Running Cost Maintenance Cost Total cost
20/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Category Chiller system VRF system Remarks
Economic
Analysis
Initial cost (USD) 877,097 927,057
Running cost
(USD)
308,698 200,158
Shopping
mall
6F,
9,000㎡
Maintenace cost
(USD)
32,177 11,468
Total cost (USD) 1,217,972 1,138,683
BEP - 1.7 years
7. Economic analysis
Initial Cost Running Cost Maintenance Cost Total cost
21/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
LCC (Life Cycle Cost for 15 years) : Chiller 5.99 M$ > Multi V 4.27 M$ (71%)
BEP (Break Even Point) : 1.7 Years
LCC (15 years) BEP
1st year 2nd year 3rd year 4th year
- 20K$
+10K$
+40K$
+70K$
BEP :
1.7 Years
$0k
$1000k
$2000k
$3000k
$4000k
$5000k
$6000k
$7000k
year
1st
2nd
3rd
4th
5th
6th
7th
8th
9th
10th
11th
12th
13th
14th
15th
Chiller
Multi V
Cost savings
: 29%
BEP :
1.7 Years
8. LCC
22/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Chiller Multi V
1,228
1,109
877
32
308 200
11
1,321
7%
Product &
Installation
Maintenance
Electrical Fee
Chiller Multi V
5,992
23%
15%
8%
77% 73%
4%
4,274
35%
Product &
Installation
Maintenance
Electrical Fee
Initial Cost (1st year)
( K US$ )
LCC (15 years)
8. LCC
23/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Type of building : Shopping mall
Water cooled Chiller :350 TR x 2 set=700 Tr + 300Tr (back up)
VRF system:48 Hp x 19 set = 912 Hp (726TR)
Commercial Building : (Shopping Mall - 9,000㎡ Total Area) - 6 storey building:1500 ㎡ per floor
Actual cooling area : 1,500㎡ * 80% * 6F = 7,200㎡
Cooling load(TR) / ㎡ : 700TR * 12,000Btu/h/TR 7,200 ㎡ = 1167 Btu/㎡
Capacity Price EA Sub total (THB) % Sub total (USD)
350 RT 3,960,000 2 7,920,000 255,484
300 RT 3,100,000 1 3,100,000 100,000
400 RT 500,000 2 1,000,000 32,258
400 RT 500,000 1 500,000 16,129
1200 GPM 100,000 3 300,000 9,677
840 GPM 90,000 3 270,000 8,710
8,000 CFM 70,000 36 2,520,000 81,290
15,610,000 57% 503,548
9,000,000 33% 290,323
2,900,000 11% 93,548
11,900,000 43% 383,871
27,510,000 100% 887,419
48 Hp 957,000 19 18,183,000 586,548
Indoor unit ceiling duct 10 Hp 91,355 90 8,221,950 265,224
2,915 90 262,350 8,463
81,125 1 81,125 2,617
141,570 1 141,570 4,567
1,650 57 94,050 3,034
3,300 38 125,400 4,045
27,109,445 79% 874,498
Indoor unit ceiling duct
36,000 90 3,240,000 104,516
7,290,000 21% 235,161
34,399,445 100% 1,109,660
I lot
back up cooling tower (open type)
Duct working
45,000
back up chiller (screw type)
Wired remote controller
Centrol controller (ACP)
Centrol control software (AC Manager)
Sub total
Total (Product + Installation)
Pump (Evaporator) + 1 back up
AHU
Outdoor unit
Sub total
130,645
Y branch
ODU joint
90 4,050,000
VRF Sub total
Sub total
Outdoor unit
Total (Product + Installation)
Product
Installation
duct work
piping & electrical work
Water Cooled
Chiller
(Screw
type)
Classification
Pipe & Insulation
Valve & Acc.
Power & Control
Product
Installation
Chiller (screw type)
Cooling tower (open type)
Pump (Condenser) + 1 back up
App. Cost estimation
24/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Energy
consumption
/ unit
Total
energy
consumption
(kW) (kW)
271 2 542
14.9 2 29.84 Load 100% 75% 50% 25%
55.2 6 331.2 Chillier 542 179 84 47
2.35 48 112.8 Others 474 474 474 474
1015.84 Total 1016 653 558 521
Outdoor Unit 48 HP-R410a 42 19 798
Indoor Unit 10 HP CCD 0.8 90 72 Load 100% 75% 50% 25%
870.0 VRF 870 609 287 165
13
30
100% kW portion
1% 100% 542 100% Used by Schedule 4.2.2 condition
42% 75% 179.2 33% electrical charge in Thailand
45% 50% 83.9 15% THB / month USD
12% 25% 47.2 9% VRF 517,076 16,680
Chiller 797,469 25,725
Gap 280,393 9,045
Operation
hours
kWh / day kWh / month
Operation
hours
kWh / day kWh / month
0.1 113.1 3,393.0 0.1 132.06 3,961.78
5.5 3,325.1 99,754.2 5.5 3,565.60 106,967.95 VRF 200,158
5.9 1,679.5 50,386.1 5.9 3,262.78 97,883.37 Chiller 308,698
1.6 257.9 7,736.0 1.6 812.82 24,384.67
13.0 5,375.6 161,269.3 13.0 7,773.3 233,197.8
■ VRF system
Cooling load portion IPLV
100% cooling load
VRF (MULTI V system) Chiller system
75% cooling load
50% cooling load
25% cooling load
VRF
AHU-10 tr
Total
operating time / day (hours)
operating day / month
Chiller
Power consumption
Load
operating cost 1
year
■ Chiller system
Category EA
Total
Power consumption under partial load
Water
Cooled
Chiller
(Screw
type)
Chiller-350 Tr
Cooling tower-1260 GPM
Pump-50 Hp
App. Actual running cost
25/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
Cost Unit
350 RT 105,000 Baht/unit 2 210,000
400 RT 60,000 Baht/unit 2 120,000
1200 GPM 15,600 Baht/unit 6 93,600
15 RT 2,000 Baht/unit 70 140,000
2 persons 20,000 Baht/unit 12 240,000
803,600
840 Hp 3,000 Baht/unit 90 270,000
Outdoor unit 4,500 19 85,500
355,500
THB USD Remarks
Chiller 997,500 32,177 6 times / year
270,000 6 times / year
85,500 6 times / year
355,500 11,468
Pump
Total
VRF
1500 THB / indoor unit, year
4500 THB / ODU module, year
950 THB / RT, year
Control engineer
Chiller
(Screw
type)
Chiller (Screw type)
Cooling tower
AHU
Total
Total
VRF
Indoor unit
A note
Category Capacity
Maintenance cost
EA
Maintenance
cost / year
App. Maintenance cost
26/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc.
ARI Released The New Standard in 2003
Available through
the ARI web site:
WWW.ARI.ORG
Portion by cooling load (%)
IPLV
OR
APLV
=
0.01 + 0.42 + 0.45 + 0.12
A B C D
1
kW / kW (ARI Part load weighting factors)
1% 42% 45% 12%
100% 75% 50% 25%
WEIGHTED (%)
ARI550/590-2003
Cooling Load
App. Energy efficiency (IPLV)

More Related Content

What's hot

Comparison between vrv vrf brands &amp; suppliers @ uae market-July 2017-by g...
Comparison between vrv vrf brands &amp; suppliers @ uae market-July 2017-by g...Comparison between vrv vrf brands &amp; suppliers @ uae market-July 2017-by g...
Comparison between vrv vrf brands &amp; suppliers @ uae market-July 2017-by g...
Juma Yousef J. Saleh جمعة يوسف جمعة صالح
 
Chapter 1 hvac
Chapter 1 hvacChapter 1 hvac
Chapter 1 hvac
wanmohdhanis
 
AIR CONDITIONING SYSTEM DESINGING
AIR CONDITIONING SYSTEM DESINGINGAIR CONDITIONING SYSTEM DESINGING
AIR CONDITIONING SYSTEM DESINGING
INDUSTRIAL ENGINEERING
 
Hvac presentation for beginers
Hvac presentation for beginersHvac presentation for beginers
Hvac presentation for beginers
guestf11b52
 
Design, Installation and Testing of the VRF System
Design, Installation and Testing of the VRF SystemDesign, Installation and Testing of the VRF System
Design, Installation and Testing of the VRF System
Socheat Veng
 
HVAC Fundamentals
HVAC  FundamentalsHVAC  Fundamentals
HVAC Fundamentals
GAUTAM KOPPALA (JORGE)
 
HVAC Basics
HVAC BasicsHVAC Basics
HVAC Basics
Jitendra Jha
 
Ductwork
DuctworkDuctwork
Ductwork
guestf11b52
 
Chiller water systems
Chiller water systemsChiller water systems
Chiller water systems
RIDDHESH VARIK
 
VARIABLE REFRIGERANT FLOW(VRF) ppt
VARIABLE REFRIGERANT FLOW(VRF)  pptVARIABLE REFRIGERANT FLOW(VRF)  ppt
VARIABLE REFRIGERANT FLOW(VRF) ppt
Ezhil Raj s
 
Hvac Equipment and Maintenance
Hvac Equipment and MaintenanceHvac Equipment and Maintenance
Hvac Equipment and Maintenance
Vaisakh Subash
 
HVAC Presentation.pptx
HVAC Presentation.pptxHVAC Presentation.pptx
HVAC Presentation.pptx
YoussefEssam27
 
VRF II VRV
VRF II VRVVRF II VRV
VRF II VRV
Ashutosh
 
Practical benefits of VRV VRF system compare to other systems by Eng. Juma_Ge...
Practical benefits of VRV VRF system compare to other systems by Eng. Juma_Ge...Practical benefits of VRV VRF system compare to other systems by Eng. Juma_Ge...
Practical benefits of VRV VRF system compare to other systems by Eng. Juma_Ge...
Juma Yousef J. Saleh جمعة يوسف جمعة صالح
 
Introduction to hvac systems
Introduction to hvac systemsIntroduction to hvac systems
Introduction to hvac systems
michaeljmack
 
HVAC Air Balance 101
HVAC Air Balance 101HVAC Air Balance 101
HVAC Air Balance 101
Luci Feie
 
Basics of HVAC - Part 1 (Heating Ventilation Air Conditioning)
Basics of HVAC - Part 1 (Heating Ventilation Air Conditioning)Basics of HVAC - Part 1 (Heating Ventilation Air Conditioning)
Basics of HVAC - Part 1 (Heating Ventilation Air Conditioning)
MOHAMMED KHAN
 
Comparison between Systems
Comparison between SystemsComparison between Systems
Comparison between Systems
Victor Ashkenazy
 
Heat Load Calculation
Heat Load CalculationHeat Load Calculation
Heat Load Calculation
Jitendra Jha
 
Dc inverter vrf installation instructions and Tips
Dc inverter vrf installation instructions and TipsDc inverter vrf installation instructions and Tips
Dc inverter vrf installation instructions and Tips
Simon MECO FanCoil Unit
 

What's hot (20)

Comparison between vrv vrf brands &amp; suppliers @ uae market-July 2017-by g...
Comparison between vrv vrf brands &amp; suppliers @ uae market-July 2017-by g...Comparison between vrv vrf brands &amp; suppliers @ uae market-July 2017-by g...
Comparison between vrv vrf brands &amp; suppliers @ uae market-July 2017-by g...
 
Chapter 1 hvac
Chapter 1 hvacChapter 1 hvac
Chapter 1 hvac
 
AIR CONDITIONING SYSTEM DESINGING
AIR CONDITIONING SYSTEM DESINGINGAIR CONDITIONING SYSTEM DESINGING
AIR CONDITIONING SYSTEM DESINGING
 
Hvac presentation for beginers
Hvac presentation for beginersHvac presentation for beginers
Hvac presentation for beginers
 
Design, Installation and Testing of the VRF System
Design, Installation and Testing of the VRF SystemDesign, Installation and Testing of the VRF System
Design, Installation and Testing of the VRF System
 
HVAC Fundamentals
HVAC  FundamentalsHVAC  Fundamentals
HVAC Fundamentals
 
HVAC Basics
HVAC BasicsHVAC Basics
HVAC Basics
 
Ductwork
DuctworkDuctwork
Ductwork
 
Chiller water systems
Chiller water systemsChiller water systems
Chiller water systems
 
VARIABLE REFRIGERANT FLOW(VRF) ppt
VARIABLE REFRIGERANT FLOW(VRF)  pptVARIABLE REFRIGERANT FLOW(VRF)  ppt
VARIABLE REFRIGERANT FLOW(VRF) ppt
 
Hvac Equipment and Maintenance
Hvac Equipment and MaintenanceHvac Equipment and Maintenance
Hvac Equipment and Maintenance
 
HVAC Presentation.pptx
HVAC Presentation.pptxHVAC Presentation.pptx
HVAC Presentation.pptx
 
VRF II VRV
VRF II VRVVRF II VRV
VRF II VRV
 
Practical benefits of VRV VRF system compare to other systems by Eng. Juma_Ge...
Practical benefits of VRV VRF system compare to other systems by Eng. Juma_Ge...Practical benefits of VRV VRF system compare to other systems by Eng. Juma_Ge...
Practical benefits of VRV VRF system compare to other systems by Eng. Juma_Ge...
 
Introduction to hvac systems
Introduction to hvac systemsIntroduction to hvac systems
Introduction to hvac systems
 
HVAC Air Balance 101
HVAC Air Balance 101HVAC Air Balance 101
HVAC Air Balance 101
 
Basics of HVAC - Part 1 (Heating Ventilation Air Conditioning)
Basics of HVAC - Part 1 (Heating Ventilation Air Conditioning)Basics of HVAC - Part 1 (Heating Ventilation Air Conditioning)
Basics of HVAC - Part 1 (Heating Ventilation Air Conditioning)
 
Comparison between Systems
Comparison between SystemsComparison between Systems
Comparison between Systems
 
Heat Load Calculation
Heat Load CalculationHeat Load Calculation
Heat Load Calculation
 
Dc inverter vrf installation instructions and Tips
Dc inverter vrf installation instructions and TipsDc inverter vrf installation instructions and Tips
Dc inverter vrf installation instructions and Tips
 

Similar to Chiller-vs-vrf.ppt

Transformer_Cooling 2015 Doble LOAT Conference
Transformer_Cooling 2015 Doble LOAT ConferenceTransformer_Cooling 2015 Doble LOAT Conference
Transformer_Cooling 2015 Doble LOAT Conference
Kevin Riley
 
Dekon vrf system brief introduction
Dekon vrf system brief introductionDekon vrf system brief introduction
Dekon vrf system brief introduction
Simon MECO FanCoil Unit
 
Catalogo Air Cooled Scroll Chiller LG.pdf
Catalogo Air Cooled Scroll Chiller LG.pdfCatalogo Air Cooled Scroll Chiller LG.pdf
Catalogo Air Cooled Scroll Chiller LG.pdf
KarenGrau3
 
Comparative Analysis of HVAC System Based on Life Cycle Cost Analysis
Comparative Analysis of HVAC System Based on Life Cycle Cost AnalysisComparative Analysis of HVAC System Based on Life Cycle Cost Analysis
Comparative Analysis of HVAC System Based on Life Cycle Cost Analysis
IJERA Editor
 
MCE 2016 - G.Tonin - CAREL
MCE 2016 - G.Tonin - CARELMCE 2016 - G.Tonin - CAREL
MCE 2016 - G.Tonin - CAREL
Centro Studi Galileo
 
Air source heat pump Brochure-BLUEWAY
Air source heat pump Brochure-BLUEWAYAir source heat pump Brochure-BLUEWAY
Air source heat pump Brochure-BLUEWAY
Roger Luo
 
JFTOT IV
JFTOT IVJFTOT IV
JFTOT IV
wchupin
 
ELGi EV Series Air Compressor Pitch PPT For Fortis Hospital
ELGi EV Series Air Compressor Pitch PPT For Fortis HospitalELGi EV Series Air Compressor Pitch PPT For Fortis Hospital
ELGi EV Series Air Compressor Pitch PPT For Fortis Hospital
VijayEngineeringandM1
 
EV Series PPT - Fortis Hospital..pptx
EV Series PPT - Fortis Hospital..pptxEV Series PPT - Fortis Hospital..pptx
EV Series PPT - Fortis Hospital..pptx
VijayEngineeringandM1
 
Presentation on Green Data Centres
Presentation on Green Data CentresPresentation on Green Data Centres
Presentation on Green Data Centres
IGBC Green Building Congress
 
The ErP Directive and its impact on switchgear
The ErP Directive and its impact on switchgearThe ErP Directive and its impact on switchgear
The ErP Directive and its impact on switchgear
Eaton - Europe, Middle East & Africa
 
M.reda cv
M.reda cvM.reda cv
M.reda cv
Mohammed Reda
 
M.reda cv
M.reda cvM.reda cv
M.reda cv
Mohammed Reda
 
M.Reda CV
M.Reda CVM.Reda CV
M.Reda CV
Mohammed Reda
 
Why use PGT Vaporizers
Why use PGT VaporizersWhy use PGT Vaporizers
Why use PGT Vaporizers
Pegoraro Gas Technologies Srl
 
IRJET- Experimental Analysis on Liquid-Cooled Minichannel Heatsink for Pe...
IRJET-  	  Experimental Analysis on Liquid-Cooled Minichannel Heatsink for Pe...IRJET-  	  Experimental Analysis on Liquid-Cooled Minichannel Heatsink for Pe...
IRJET- Experimental Analysis on Liquid-Cooled Minichannel Heatsink for Pe...
IRJET Journal
 
Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3
Nicholas Naing
 
Pitch Deck von ThermoCube für Investoren
Pitch Deck von ThermoCube für InvestorenPitch Deck von ThermoCube für Investoren
Pitch Deck von ThermoCube für Investoren
VisioneerUG
 
KBC decision making tool optimal planning scheduling utility
KBC decision making tool optimal planning scheduling utilityKBC decision making tool optimal planning scheduling utility
KBC decision making tool optimal planning scheduling utility
KBC (A Yokogawa Company)
 
Ake btu measurement system
Ake btu measurement systemAke btu measurement system
Ake btu measurement system
akevincent
 

Similar to Chiller-vs-vrf.ppt (20)

Transformer_Cooling 2015 Doble LOAT Conference
Transformer_Cooling 2015 Doble LOAT ConferenceTransformer_Cooling 2015 Doble LOAT Conference
Transformer_Cooling 2015 Doble LOAT Conference
 
Dekon vrf system brief introduction
Dekon vrf system brief introductionDekon vrf system brief introduction
Dekon vrf system brief introduction
 
Catalogo Air Cooled Scroll Chiller LG.pdf
Catalogo Air Cooled Scroll Chiller LG.pdfCatalogo Air Cooled Scroll Chiller LG.pdf
Catalogo Air Cooled Scroll Chiller LG.pdf
 
Comparative Analysis of HVAC System Based on Life Cycle Cost Analysis
Comparative Analysis of HVAC System Based on Life Cycle Cost AnalysisComparative Analysis of HVAC System Based on Life Cycle Cost Analysis
Comparative Analysis of HVAC System Based on Life Cycle Cost Analysis
 
MCE 2016 - G.Tonin - CAREL
MCE 2016 - G.Tonin - CARELMCE 2016 - G.Tonin - CAREL
MCE 2016 - G.Tonin - CAREL
 
Air source heat pump Brochure-BLUEWAY
Air source heat pump Brochure-BLUEWAYAir source heat pump Brochure-BLUEWAY
Air source heat pump Brochure-BLUEWAY
 
JFTOT IV
JFTOT IVJFTOT IV
JFTOT IV
 
ELGi EV Series Air Compressor Pitch PPT For Fortis Hospital
ELGi EV Series Air Compressor Pitch PPT For Fortis HospitalELGi EV Series Air Compressor Pitch PPT For Fortis Hospital
ELGi EV Series Air Compressor Pitch PPT For Fortis Hospital
 
EV Series PPT - Fortis Hospital..pptx
EV Series PPT - Fortis Hospital..pptxEV Series PPT - Fortis Hospital..pptx
EV Series PPT - Fortis Hospital..pptx
 
Presentation on Green Data Centres
Presentation on Green Data CentresPresentation on Green Data Centres
Presentation on Green Data Centres
 
The ErP Directive and its impact on switchgear
The ErP Directive and its impact on switchgearThe ErP Directive and its impact on switchgear
The ErP Directive and its impact on switchgear
 
M.reda cv
M.reda cvM.reda cv
M.reda cv
 
M.reda cv
M.reda cvM.reda cv
M.reda cv
 
M.Reda CV
M.Reda CVM.Reda CV
M.Reda CV
 
Why use PGT Vaporizers
Why use PGT VaporizersWhy use PGT Vaporizers
Why use PGT Vaporizers
 
IRJET- Experimental Analysis on Liquid-Cooled Minichannel Heatsink for Pe...
IRJET-  	  Experimental Analysis on Liquid-Cooled Minichannel Heatsink for Pe...IRJET-  	  Experimental Analysis on Liquid-Cooled Minichannel Heatsink for Pe...
IRJET- Experimental Analysis on Liquid-Cooled Minichannel Heatsink for Pe...
 
Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3
 
Pitch Deck von ThermoCube für Investoren
Pitch Deck von ThermoCube für InvestorenPitch Deck von ThermoCube für Investoren
Pitch Deck von ThermoCube für Investoren
 
KBC decision making tool optimal planning scheduling utility
KBC decision making tool optimal planning scheduling utilityKBC decision making tool optimal planning scheduling utility
KBC decision making tool optimal planning scheduling utility
 
Ake btu measurement system
Ake btu measurement systemAke btu measurement system
Ake btu measurement system
 

Recently uploaded

Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
ramrag33
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 
An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...
IJECEIAES
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
PKavitha10
 
Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
bijceesjournal
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
RamonNovais6
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
GauravCar
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
Mahmoud Morsy
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 

Recently uploaded (20)

Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 
An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
 
Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 

Chiller-vs-vrf.ppt

  • 1. 1/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Chiller vs VRF system LG Electronics Inc. LGEHQ CAC Team
  • 2. 2/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. 1. Design Comparison VRF is very simplified refrigerant piping system. More flexible than water piping. Chiller MULTI V Plus Ⅱ (VRF) Chiller system • Outdoor unit (air-cooled type) • Indoor unit • Refrigerant piping • Chiller • FCU (Fan Coil Unit) • AHU (Air Handling Unit) System composition Feature • Cooling tower • Water piping, Duct working • Water pumps System concept Design Commissioning Operation Maintenance Installation Reliability
  • 3. 3/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Network Feature Chiller system • Complicated wiring MULTI V Plus Ⅱ (VRF) • Simple wiring Design Commissioning Operation Maintenance Installation Reliability Easy network wiring 1. Design Comparison Network design ACP
  • 4. 4/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. 1. Design Comparison Total management Design Commissioning Operation Maintenance Installation Reliability [Manufacturer] VAV boxes supplier Control system Feature Chiller system MULTI V Plus Ⅱ (VRF) (For VRF) Manufacturer provide all equipment • Simple control structure No additional control provider • Central control and energy monitoring with low cost available • Complicated control structure, additional control manager in the system needed, increasing cost • Third part control provider needed, interconnectivity problems.
  • 5. 5/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Design Commissioning MULTI V Plus Ⅱ (VRF) Chiller system • The systems condition only the necessary rooms with regard to user demands. • The systems commonly condition the entire building at predetermined times, with no regard to user demands. (very hot midnight, weekend, holiday etc) Capacity control Feature After office hours operation, VRF could be operated for the user demands. <Better Capacity operation> Operating Area < Limited operation> Individual operation Operation Maintenance Installation Reliability 2. Operation Comparison
  • 6. 6/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Temperature control Feature Chiller system Require 1℃ or 2℃ MULTI V Plus Ⅱ (VRF) Very precise ± 0.5℃ Precise temperature control 30 25 20 15 10 20 30 40 50 60 70 Cooling MIN. Chiller system MULTI V system Room temp.  0.5 0 C from set point Design Commissioning Operation Maintenance Installation Reliability Temp. control 2. Operation Comparison
  • 7. 7/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. VRF system doesn’t need a duct space. Space Efficiency Feature MULTI V Plus Ⅱ (VRF) • Small refrigerant space Chiller system • Large duct space Design Commissioning Operation Maintenance Installation Reliability Space (Duct working) 3. Installation Comparison
  • 8. 8/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Chiller Pump Boiler Cooling tower (On the rooftop) (Machine room drawing) Outdoor Unit (On the rooftop) (Rooftop drawing) VRF system is no need for a machine room. Installation space Feature MULTI V Plus Ⅱ (VRF) • No need a machine room Chiller system • Need a machine room Design Commissioning Operation Maintenance Installation Reliability Installation space 3. Installation Comparison
  • 9. 9/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Efficient use of space is possible for VRF system Chiller system Space Efficiency Feature P P 1/3 CHILLER SYSTEM • Large pipe shaft is needed for water piping MULTI V Plus Ⅱ (VRF) VRF System • Small pipe shaft is needed Design Commissioning Operation Maintenance Installation Reliability Space (Pipe shaft) 3. Installation Comparison
  • 10. 10/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. VRF system expansion is very easy with extra outdoor & indoor unit. Chiller system System Expansion Feature • Capacity addition is difficult as additional mechanical room, pump, cooling tower, panel and piping is required. MULTI V Plus Ⅱ (VRF) • System Expansion is Easy + Design Commissioning Operation Maintenance Installation Reliability System expansion 3. Installation Comparison
  • 11. 11/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. 1 step Commissioning 6 steps Commissioning MULTI V Plus Ⅱ (VRF) Chiller system Commissioning Feature There are a lot of commissioning points for the chiller system • 6 Steps Commissioning • 1 Step Commissioning Water cooled chiller (3) (4) Design Commissioning Operation Maintenance Installation Reliability NO. of commissioning point 4. Commissioning Comparison
  • 12. 12/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Maintenance Feature Maintenance costs for a Multi V is lower than chilled water systems. Water cooled chiller (3) (4) MULTI V Plus Ⅱ (VRF) • Filter cleaning • Heat exchanger cleaning • Cycle check by notebook (LG MV) Chiller system • Filter cleaning • Duct cleaning • Water pipe – maintenance • Periodical oil change, overhaul • Pump • Water treatment • Cooling tower cleaning Design Commissioning Operation Maintenance Installation Reliability Maintenance list 5. Maintenance Comparison
  • 13. 13/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. (For Chiller Water treatment is required for clean water) <Polluted Cooling Tower> Water treatment Feature Chiller system • Water treatment is required (deficient service can cause legionary disease in the system) MULTI V Plus Ⅱ (VRF) • No water treatment is needed Design Commissioning Operation Maintenance Installation Reliability Water treatment 5. Maintenance Comparison
  • 14. 14/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Scale cleaning Feature Chiller system MULTI V Plus Ⅱ (VRF) < The system is consist of refrigerant pipes > • No water pipes : No scale (use refrigerant) • Need to clean the water pipes System efficiency drop & origin of germs After 2~3year After 5~6year After 7~8year 10% 25~30% 35~40% thickness of scale Energy Loss Unit : mm Unit : % (For Chiller) Maintenance & cleaning periodically by exclusive company Design Commissioning Operation Maintenance Installation Reliability Scale cleaning 5. Maintenance Comparison
  • 15. 15/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Maintenance Staff 5. Maintenance Comparison Design Commissioning Operation Maintenance Installation Reliability Maintenance Staff Feature Chiller system MULTI V Plus Ⅱ (VRF) (For Chiller) Certified maintenance staff is needed • No need special maintenance staff. • Economic and easy maintenance • The system requires certified maintenance staff not only for chillers but also pumps, boilers, cooling towers etc. • More expensive maintenance cost. <NO Maintenance Staff> < Maintenance Staff>
  • 16. 16/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Pipe Erosion 6. Reliability Comparison Design Commissioning Operation Maintenance Installation Reliability Pipe Erosion Feature Chiller system MULTI V Plus Ⅱ (VRF) (For Chiller) Certified maintenance staff is needed • Refrigerant does not cause corrosion therefore no pipe damage occurred • Pipe erosion can cause leakage. • System capacity reduction. • Brines use increase corrosion, anti corrosion additives needed <Cooper Pipe> < Water pipe leakage >
  • 17. 17/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Category Product Initial Cost (USD) Initial Cost (USD)Total Water Cooled C hiller Chiller Price 355,484 877,097 AHU / Cooling T ower / Pump, Pr ice 148,065 Installation 383,871 VRV Multi V 874,498 1,109,660 Installation 235,161 •April 2008 •Cooling Only •Air Duct Included Initial Cost Running Cost Maintenance Cost Total cost • Type of Building: Shopping Mall • Total area 9,000 m2 : 6 storey Building :1,500 m2/floor • Actual cooling area : 1,500 m2 * 80 % * 6 Floor = 7,200 m2 • Cooling Load (Tr) / m2 : 700 Tr *12000 Btu/Hr = 1,166 Btu/m2 • Equipment : Water cooled chiller /Multi V unit - Water Cooled Chiller :Trane Water cooled chiller 350 Tr x 2 set =700 Tr + 300 Back up Pump’s =400 Tr x 2 set AHU = 8000 CFM x 36 set Cooling Tower =1200 Gpm x 3 +3 Back up - VRF System :LG Multi V Plus II 48 Hp x 19 set=912 Hp 726 Tr • Air conditioning time : Operation - 13 hour a day (09:00 ~ 22:00) - 30 days a month - average load by month  Equipments & Installation cost MULTI V vs Chiller 7. Economic analysis
  • 18. 18/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Multi V running cost is 65 % compare to chiller Category Product Running Cost (USD)Tota l Water Cooled C hiller Chiller Price 308,697 AHU / Coolin g Tower / Pu mp, Price Multi V Price 200,158 •Based on KW data chiller/Multi V •Based on, Thailand electrical standard •ARI-Air conditioning & Refrigeration Institute $0k $100k $200k $300k $400k y e a r 2 n d 4 t h 6 t h 8 t h 1 0 t h 1 2 t h 1 4 t h Chiller Multi V Running cost Savings up to 15th yr : 35% Chiller Multi V  Electrical cost MULTI V vs Chiller 7. Economic analysis Initial Cost Running Cost Maintenance Cost Total cost
  • 19. 19/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Category Price Maintenance Cost (USD)Total Water Cooled C hiller Chiller Price 32,177 AHU / Cooling Tower / Pump, Price Multi V Price 11,468 $0k $100k $200k $300k $400k y e a r 2 n d 4 t h 6 t h 8 t h 1 0 t h 1 2 t h 1 4 t h Chiller Multi V Chiller Multi V Maintenance Cost savings Up to 15th yr : 66% •Maintenance breakdown •Chiller system -31 USD / Rt / yr.- 6 times/yr •Multi V- 48 USD / Indoor / yr.- 6 times/yr - 145 USD / Outdoor / yr.- 6 times/yr Multi V maintenance cost is 24 % compare to chiller  Maintenance cost MULTI V vs Chiller 7. Economic analysis Initial Cost Running Cost Maintenance Cost Total cost
  • 20. 20/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Category Chiller system VRF system Remarks Economic Analysis Initial cost (USD) 877,097 927,057 Running cost (USD) 308,698 200,158 Shopping mall 6F, 9,000㎡ Maintenace cost (USD) 32,177 11,468 Total cost (USD) 1,217,972 1,138,683 BEP - 1.7 years 7. Economic analysis Initial Cost Running Cost Maintenance Cost Total cost
  • 21. 21/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. LCC (Life Cycle Cost for 15 years) : Chiller 5.99 M$ > Multi V 4.27 M$ (71%) BEP (Break Even Point) : 1.7 Years LCC (15 years) BEP 1st year 2nd year 3rd year 4th year - 20K$ +10K$ +40K$ +70K$ BEP : 1.7 Years $0k $1000k $2000k $3000k $4000k $5000k $6000k $7000k year 1st 2nd 3rd 4th 5th 6th 7th 8th 9th 10th 11th 12th 13th 14th 15th Chiller Multi V Cost savings : 29% BEP : 1.7 Years 8. LCC
  • 22. 22/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Chiller Multi V 1,228 1,109 877 32 308 200 11 1,321 7% Product & Installation Maintenance Electrical Fee Chiller Multi V 5,992 23% 15% 8% 77% 73% 4% 4,274 35% Product & Installation Maintenance Electrical Fee Initial Cost (1st year) ( K US$ ) LCC (15 years) 8. LCC
  • 23. 23/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Type of building : Shopping mall Water cooled Chiller :350 TR x 2 set=700 Tr + 300Tr (back up) VRF system:48 Hp x 19 set = 912 Hp (726TR) Commercial Building : (Shopping Mall - 9,000㎡ Total Area) - 6 storey building:1500 ㎡ per floor Actual cooling area : 1,500㎡ * 80% * 6F = 7,200㎡ Cooling load(TR) / ㎡ : 700TR * 12,000Btu/h/TR 7,200 ㎡ = 1167 Btu/㎡ Capacity Price EA Sub total (THB) % Sub total (USD) 350 RT 3,960,000 2 7,920,000 255,484 300 RT 3,100,000 1 3,100,000 100,000 400 RT 500,000 2 1,000,000 32,258 400 RT 500,000 1 500,000 16,129 1200 GPM 100,000 3 300,000 9,677 840 GPM 90,000 3 270,000 8,710 8,000 CFM 70,000 36 2,520,000 81,290 15,610,000 57% 503,548 9,000,000 33% 290,323 2,900,000 11% 93,548 11,900,000 43% 383,871 27,510,000 100% 887,419 48 Hp 957,000 19 18,183,000 586,548 Indoor unit ceiling duct 10 Hp 91,355 90 8,221,950 265,224 2,915 90 262,350 8,463 81,125 1 81,125 2,617 141,570 1 141,570 4,567 1,650 57 94,050 3,034 3,300 38 125,400 4,045 27,109,445 79% 874,498 Indoor unit ceiling duct 36,000 90 3,240,000 104,516 7,290,000 21% 235,161 34,399,445 100% 1,109,660 I lot back up cooling tower (open type) Duct working 45,000 back up chiller (screw type) Wired remote controller Centrol controller (ACP) Centrol control software (AC Manager) Sub total Total (Product + Installation) Pump (Evaporator) + 1 back up AHU Outdoor unit Sub total 130,645 Y branch ODU joint 90 4,050,000 VRF Sub total Sub total Outdoor unit Total (Product + Installation) Product Installation duct work piping & electrical work Water Cooled Chiller (Screw type) Classification Pipe & Insulation Valve & Acc. Power & Control Product Installation Chiller (screw type) Cooling tower (open type) Pump (Condenser) + 1 back up App. Cost estimation
  • 24. 24/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Energy consumption / unit Total energy consumption (kW) (kW) 271 2 542 14.9 2 29.84 Load 100% 75% 50% 25% 55.2 6 331.2 Chillier 542 179 84 47 2.35 48 112.8 Others 474 474 474 474 1015.84 Total 1016 653 558 521 Outdoor Unit 48 HP-R410a 42 19 798 Indoor Unit 10 HP CCD 0.8 90 72 Load 100% 75% 50% 25% 870.0 VRF 870 609 287 165 13 30 100% kW portion 1% 100% 542 100% Used by Schedule 4.2.2 condition 42% 75% 179.2 33% electrical charge in Thailand 45% 50% 83.9 15% THB / month USD 12% 25% 47.2 9% VRF 517,076 16,680 Chiller 797,469 25,725 Gap 280,393 9,045 Operation hours kWh / day kWh / month Operation hours kWh / day kWh / month 0.1 113.1 3,393.0 0.1 132.06 3,961.78 5.5 3,325.1 99,754.2 5.5 3,565.60 106,967.95 VRF 200,158 5.9 1,679.5 50,386.1 5.9 3,262.78 97,883.37 Chiller 308,698 1.6 257.9 7,736.0 1.6 812.82 24,384.67 13.0 5,375.6 161,269.3 13.0 7,773.3 233,197.8 ■ VRF system Cooling load portion IPLV 100% cooling load VRF (MULTI V system) Chiller system 75% cooling load 50% cooling load 25% cooling load VRF AHU-10 tr Total operating time / day (hours) operating day / month Chiller Power consumption Load operating cost 1 year ■ Chiller system Category EA Total Power consumption under partial load Water Cooled Chiller (Screw type) Chiller-350 Tr Cooling tower-1260 GPM Pump-50 Hp App. Actual running cost
  • 25. 25/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. Cost Unit 350 RT 105,000 Baht/unit 2 210,000 400 RT 60,000 Baht/unit 2 120,000 1200 GPM 15,600 Baht/unit 6 93,600 15 RT 2,000 Baht/unit 70 140,000 2 persons 20,000 Baht/unit 12 240,000 803,600 840 Hp 3,000 Baht/unit 90 270,000 Outdoor unit 4,500 19 85,500 355,500 THB USD Remarks Chiller 997,500 32,177 6 times / year 270,000 6 times / year 85,500 6 times / year 355,500 11,468 Pump Total VRF 1500 THB / indoor unit, year 4500 THB / ODU module, year 950 THB / RT, year Control engineer Chiller (Screw type) Chiller (Screw type) Cooling tower AHU Total Total VRF Indoor unit A note Category Capacity Maintenance cost EA Maintenance cost / year App. Maintenance cost
  • 26. 26/14 Copyright ⓒ 2008 All rights reserved LG Electronics Inc. ARI Released The New Standard in 2003 Available through the ARI web site: WWW.ARI.ORG Portion by cooling load (%) IPLV OR APLV = 0.01 + 0.42 + 0.45 + 0.12 A B C D 1 kW / kW (ARI Part load weighting factors) 1% 42% 45% 12% 100% 75% 50% 25% WEIGHTED (%) ARI550/590-2003 Cooling Load App. Energy efficiency (IPLV)