3. Construction Project
Time Management:
Construction Planning
Dr. Khaled Hesham Hyari
Department of Civil Engineering
The Hashemite University
2
• Project Time Management: It includes the
processes required to ensure timely
completion of the project.
• It includes:
–Activity definition
–Activity sequencing
–Activity resource Estimating
–Activity duration Estimating
–Schedule development
–Schedule control
Project Time Management
3
• Activity Definition: Identifying the specific
schedule activities that need to be performed to
produce the various project deliverables
• Activity Sequencing: Identifying and documenting
dependencies among schedule activities
• Activity Resource Estimating: Estimating the type
and quantities of resources required to perform
each schedule activity
• Activity Duration Estimating: Estimating the
number of work periods that will be needed to
complete individual schedule activities
Project Time Management II
4
• Schedule Development: Analyzing activity
sequences, durations, resource requirements, and
schedule constraints to create the project schedule
• Schedule Control: Controlling changes to the
project schedule
Project Time Management III
5
• What is Planning and Scheduling?
– Planning & Scheduling: provides a project
plan/schedule that is essential in project time
management.
• Project Time Management:
– Planning.
– Scheduling.
– Tracking and Control.
Planning and Scheduling What?
6
• Why do we Plan and Schedule?
• Planning & Scheduling is needed for:
– Scope recognition.
– Task definition & responsibility identification.
– Effective utilization of resources (labor,
material & equipment).
– Tracking and controlling project time and cost.
– Claims analysis, quantification and defense.
Planning and Scheduling Why?
7
• How do we Plan and Schedule?
• Planning Determines:
– What must be done?
– How it is to be performed?
– What sequential order it will follow?
• Planning Requires:
– Ability to visualize discrete work elements.
– Establishing interdependencies.
– Intimate knowledge of construction methods.
Planning and Scheduling How?
8
• Planning Steps:
– Generate WBS & Activity List.
– Estimate Activity Duration/Cost.
– Determine job logic (sequential relationships
among activities).
– Draw graphic presentation in a network.
Planning and Scheduling How?
9
• Activity: a single work task that consumes time and
has a recognizable start and finish times.
• Activity: A component of work performed during the
course of a project (PMBOK)
• Schedule Activity: A discrete scheduled
component of work performed during the course of a
project. A schedule activity normally has an
estimated duration, an estimated cost, and
estimated resource requirements. Schedule
activities are connected to other schedule activities
with logical relationships, and are decomposed from
work packages.
Generating WBS and Activities
10
• Guidelines for Identifying Activities:
– Area of responsibility (general contractor,
subcontractor).
– Location on site.
– Structural element (substructure,
superstructure, etc.)
– Craft or crew requirements.
– Equipment requirements.
– Material utilized (concrete, timber, steel, etc.)
Generating WBS and Activities
11
• Factors Affecting Level of Detail (Number
of Activities):
– Nature and size of project.
– Required level of detail.
– Which level of management will use the schedule.
• Schedule Hierarchy:
– Master project plan/schedule.
– Master subproject plan/schedule.
– Detailed subproject plan/schedule.
– Detailed work plan/schedule.
Generating WBS and Activities
12
• Work breakdown structure (WBS):
Describes the project scope of work in a
hierarchy of work packages, where each
abstract work package in the higher levels of
the hierarchy is subdivided into more
detailed work packages in lower levels of the
hierarchy.
Generating WBS and Activities
13
• Work breakdown structure: A deliverable-
oriented hierarchical decomposition of the work to
be executed by the project team to accomplish the
project objectives and create the required
deliverables
• It recognizes and defines the total scope of the
project
• Each descending level represents an increasingly
detailed definition of the project work
• The WBS is decomposed into work packages
Generating WBS and Activities
14
• Work Package:
– Is a well-defined scope of work that usually
terminates in a deliverable product.
– Each package may vary in size, but must be a
measurable and controllable unit of work to be
performed.
– It must be identifiable in a numerical accounting
system in order to permit the capture of both
budgeted & actual performance information.
– A work package is a work center. (Neil 1982)
Generating WBS and Activities
15
• Other Names of a Work Package:
– Estimating account.
– Line item.
– Cost account.
Generating WBS and Activities
16
• Uses of WBS:
– Identifying scope of work.
– Preparing preliminary budget.
– Cost estimating.
– Scheduling.
– Identifying cost & schedule at various levels of
details.
– Time & cost control.
– Identifying individual or departmental
responsibilities.
Generating WBS and Activities
17
• Types of Coding Systems:
–Standard code
–Project code
• Standard Code: is a systematic classification
& categorization of all items of work or cost
pertaining to a specific type of construction
(e.g. Building construction, Heavy
construction).
Generating WBS and Activities
18
• Purpose of Standard Code:
– Provides a comprehensive checklist of all items
of work that can be found in a specific type of
construction.
– Provides for uniformity, transfer & comparison of
information among projects.
• Example: Masterformat was developed through a
joint effort of 8 industry & professional associations
including:
– Construction Specifications Institute (CSI)
– Construction Specifications Canada (CSC)
Generating WBS and Activities
19
• Divisions:
1.General Requirements.
2.Site work.
3.Concrete.
4.Masonry.
5.Metals.
6.Woods & Plastics.
7.Thermal & Moisture
Protection.
8.Doors & Windows.
9. Finishes.
10.Specialties.
11.Equipment
12.Furnishings.
13.Special Construction.
14.Conveying Systems.
15.Mechanical.
16.Electrical.
Generating WBS and Activities
20
• Project Code: is
a systematic
classification &
categorization of
all items of work
or cost pertaining
to a specific
project.
Generating WBS and Activities
21
• Rules for Estimating Activity Duration:
– Evaluate activities one at a time.
– Assume normal level of resources.
– Assume normal working hours (No Overtime).
– Use consistent time units.
– Put project completion date OUT OF MIND.
• Activity Duration is often estimated based on:
– Experience and judgment.
– Quantity of work and crew daily output
Quantity of work
Activity Duration =
Crew daily output
Estimating Activity Duration
22
• Factors Affecting Activity Duration:
–Weather.
–Learning Curve.
–Overtime.
–Space Congestion.
–Design Changes & Rework.
Estimating Activity Duration
23
• Learning Curve:
based on the fact that
skill & productivity in
performing tasks
improve with
experience and
practice.
• Example: The tenth
activity takes less
time than the first.
Estimating Activity Duration
24
Estimating Activity Duration
25
• Construction Planning Restraints:
– Physical: (formwork must precede pouring
concrete).
– Resource:
• Availability of material.
• Availability of equipment.
• Availability of labor.
• Availability of money.
– Safety.
– Environment:
• Weather.
• Economical.
• Social.
• Political.
Determining Job Logic
26
• For each activity answer 3 questions:
– Which activities precede this activity?
– Which activities follow this activity?
– Which activities are concurrent with this
activity?
Determining Job Logic

More Related Content

Similar to 3-Construction Management.pdf

Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system projectalpha1unity
 
ITFT - Project Management
ITFT - Project ManagementITFT - Project Management
ITFT - Project ManagementPooja
 
L6.2 planing&scheduling
L6.2 planing&schedulingL6.2 planing&scheduling
L6.2 planing&schedulingmanusug
 
MIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project MMIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project MIlonaThornburg83
 
Unit 3 WorkBreakdownStructure.ppt related to project management
Unit 3 WorkBreakdownStructure.ppt related to project managementUnit 3 WorkBreakdownStructure.ppt related to project management
Unit 3 WorkBreakdownStructure.ppt related to project managementtanishkagupta907
 
Project management part 2
Project management part 2Project management part 2
Project management part 2hkbhadraa
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptxHafixFarhan
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterpreetidamakale
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Shrikant Kate
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptxProfDrAnbalaganChinn
 
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesvideoaakash15
 
3- Project Time Management.ppt
3- Project Time Management.ppt3- Project Time Management.ppt
3- Project Time Management.pptMohamadAGhareb
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTSAJJAD KHUDHUR ABBAS
 
Odoo OpenERP 7 construction management
Odoo OpenERP 7 construction managementOdoo OpenERP 7 construction management
Odoo OpenERP 7 construction managementpragmatic123
 
OpenERP Construction Module Version 7
OpenERP Construction Module Version 7OpenERP Construction Module Version 7
OpenERP Construction Module Version 7Pragmatic Techsoft
 

Similar to 3-Construction Management.pdf (20)

EpM
EpMEpM
EpM
 
Chapter 4
Chapter 4 Chapter 4
Chapter 4
 
Intro to PM.ppt
Intro to PM.pptIntro to PM.ppt
Intro to PM.ppt
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 
ITFT - Project Management
ITFT - Project ManagementITFT - Project Management
ITFT - Project Management
 
L6.2 planing&scheduling
L6.2 planing&schedulingL6.2 planing&scheduling
L6.2 planing&scheduling
 
MIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project MMIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project M
 
SPM 3.pdf
SPM 3.pdfSPM 3.pdf
SPM 3.pdf
 
Unit 3 WorkBreakdownStructure.ppt related to project management
Unit 3 WorkBreakdownStructure.ppt related to project managementUnit 3 WorkBreakdownStructure.ppt related to project management
Unit 3 WorkBreakdownStructure.ppt related to project management
 
Project management part 2
Project management part 2Project management part 2
Project management part 2
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptx
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
SPM_UNIT-2.pptx
SPM_UNIT-2.pptxSPM_UNIT-2.pptx
SPM_UNIT-2.pptx
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx
 
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
 
3- Project Time Management.ppt
3- Project Time Management.ppt3- Project Time Management.ppt
3- Project Time Management.ppt
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENT
 
Odoo OpenERP 7 construction management
Odoo OpenERP 7 construction managementOdoo OpenERP 7 construction management
Odoo OpenERP 7 construction management
 
OpenERP Construction Module Version 7
OpenERP Construction Module Version 7OpenERP Construction Module Version 7
OpenERP Construction Module Version 7
 

Recently uploaded

Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelDrAjayKumarYadav4
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...ssuserdfc773
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxNANDHAKUMARA10
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...josephjonse
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...ppkakm
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)ChandrakantDivate1
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementDr. Deepak Mudgal
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 

Recently uploaded (20)

Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 

3-Construction Management.pdf

  • 1. 3. Construction Project Time Management: Construction Planning Dr. Khaled Hesham Hyari Department of Civil Engineering The Hashemite University
  • 2. 2 • Project Time Management: It includes the processes required to ensure timely completion of the project. • It includes: –Activity definition –Activity sequencing –Activity resource Estimating –Activity duration Estimating –Schedule development –Schedule control Project Time Management
  • 3. 3 • Activity Definition: Identifying the specific schedule activities that need to be performed to produce the various project deliverables • Activity Sequencing: Identifying and documenting dependencies among schedule activities • Activity Resource Estimating: Estimating the type and quantities of resources required to perform each schedule activity • Activity Duration Estimating: Estimating the number of work periods that will be needed to complete individual schedule activities Project Time Management II
  • 4. 4 • Schedule Development: Analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule • Schedule Control: Controlling changes to the project schedule Project Time Management III
  • 5. 5 • What is Planning and Scheduling? – Planning & Scheduling: provides a project plan/schedule that is essential in project time management. • Project Time Management: – Planning. – Scheduling. – Tracking and Control. Planning and Scheduling What?
  • 6. 6 • Why do we Plan and Schedule? • Planning & Scheduling is needed for: – Scope recognition. – Task definition & responsibility identification. – Effective utilization of resources (labor, material & equipment). – Tracking and controlling project time and cost. – Claims analysis, quantification and defense. Planning and Scheduling Why?
  • 7. 7 • How do we Plan and Schedule? • Planning Determines: – What must be done? – How it is to be performed? – What sequential order it will follow? • Planning Requires: – Ability to visualize discrete work elements. – Establishing interdependencies. – Intimate knowledge of construction methods. Planning and Scheduling How?
  • 8. 8 • Planning Steps: – Generate WBS & Activity List. – Estimate Activity Duration/Cost. – Determine job logic (sequential relationships among activities). – Draw graphic presentation in a network. Planning and Scheduling How?
  • 9. 9 • Activity: a single work task that consumes time and has a recognizable start and finish times. • Activity: A component of work performed during the course of a project (PMBOK) • Schedule Activity: A discrete scheduled component of work performed during the course of a project. A schedule activity normally has an estimated duration, an estimated cost, and estimated resource requirements. Schedule activities are connected to other schedule activities with logical relationships, and are decomposed from work packages. Generating WBS and Activities
  • 10. 10 • Guidelines for Identifying Activities: – Area of responsibility (general contractor, subcontractor). – Location on site. – Structural element (substructure, superstructure, etc.) – Craft or crew requirements. – Equipment requirements. – Material utilized (concrete, timber, steel, etc.) Generating WBS and Activities
  • 11. 11 • Factors Affecting Level of Detail (Number of Activities): – Nature and size of project. – Required level of detail. – Which level of management will use the schedule. • Schedule Hierarchy: – Master project plan/schedule. – Master subproject plan/schedule. – Detailed subproject plan/schedule. – Detailed work plan/schedule. Generating WBS and Activities
  • 12. 12 • Work breakdown structure (WBS): Describes the project scope of work in a hierarchy of work packages, where each abstract work package in the higher levels of the hierarchy is subdivided into more detailed work packages in lower levels of the hierarchy. Generating WBS and Activities
  • 13. 13 • Work breakdown structure: A deliverable- oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables • It recognizes and defines the total scope of the project • Each descending level represents an increasingly detailed definition of the project work • The WBS is decomposed into work packages Generating WBS and Activities
  • 14. 14 • Work Package: – Is a well-defined scope of work that usually terminates in a deliverable product. – Each package may vary in size, but must be a measurable and controllable unit of work to be performed. – It must be identifiable in a numerical accounting system in order to permit the capture of both budgeted & actual performance information. – A work package is a work center. (Neil 1982) Generating WBS and Activities
  • 15. 15 • Other Names of a Work Package: – Estimating account. – Line item. – Cost account. Generating WBS and Activities
  • 16. 16 • Uses of WBS: – Identifying scope of work. – Preparing preliminary budget. – Cost estimating. – Scheduling. – Identifying cost & schedule at various levels of details. – Time & cost control. – Identifying individual or departmental responsibilities. Generating WBS and Activities
  • 17. 17 • Types of Coding Systems: –Standard code –Project code • Standard Code: is a systematic classification & categorization of all items of work or cost pertaining to a specific type of construction (e.g. Building construction, Heavy construction). Generating WBS and Activities
  • 18. 18 • Purpose of Standard Code: – Provides a comprehensive checklist of all items of work that can be found in a specific type of construction. – Provides for uniformity, transfer & comparison of information among projects. • Example: Masterformat was developed through a joint effort of 8 industry & professional associations including: – Construction Specifications Institute (CSI) – Construction Specifications Canada (CSC) Generating WBS and Activities
  • 19. 19 • Divisions: 1.General Requirements. 2.Site work. 3.Concrete. 4.Masonry. 5.Metals. 6.Woods & Plastics. 7.Thermal & Moisture Protection. 8.Doors & Windows. 9. Finishes. 10.Specialties. 11.Equipment 12.Furnishings. 13.Special Construction. 14.Conveying Systems. 15.Mechanical. 16.Electrical. Generating WBS and Activities
  • 20. 20 • Project Code: is a systematic classification & categorization of all items of work or cost pertaining to a specific project. Generating WBS and Activities
  • 21. 21 • Rules for Estimating Activity Duration: – Evaluate activities one at a time. – Assume normal level of resources. – Assume normal working hours (No Overtime). – Use consistent time units. – Put project completion date OUT OF MIND. • Activity Duration is often estimated based on: – Experience and judgment. – Quantity of work and crew daily output Quantity of work Activity Duration = Crew daily output Estimating Activity Duration
  • 22. 22 • Factors Affecting Activity Duration: –Weather. –Learning Curve. –Overtime. –Space Congestion. –Design Changes & Rework. Estimating Activity Duration
  • 23. 23 • Learning Curve: based on the fact that skill & productivity in performing tasks improve with experience and practice. • Example: The tenth activity takes less time than the first. Estimating Activity Duration
  • 25. 25 • Construction Planning Restraints: – Physical: (formwork must precede pouring concrete). – Resource: • Availability of material. • Availability of equipment. • Availability of labor. • Availability of money. – Safety. – Environment: • Weather. • Economical. • Social. • Political. Determining Job Logic
  • 26. 26 • For each activity answer 3 questions: – Which activities precede this activity? – Which activities follow this activity? – Which activities are concurrent with this activity? Determining Job Logic