This document tracks invoices from September 2012 to February 2013 for construction suspension on the Honolulu Rail Transit Project. It shows the approved change order amounts, contractor invoices, differences between the two, and percentages for three contracts: West Oahu/Farrington Highway, Kamehameha Highway Guideway, and Maintenance and Storage Facility. The totals for all contracts show the approved amounts are 31% higher than contractor invoices.