DISTRICT HEAT PROJECT

          August 22, 2012
Key Points

   Project is within budget

   Ongoing operation is viable

   City’s risks are addressed

   Project goals are met
Recommended Action
   Authorize City Manager to proceed with project
   Notify the State and DOE of this decision
   Continue signing up customers
   Issue bids in September for receipt in October
   Review bids in November, consider project adjustments.
    Award contract.
   Consider options for use of available funds, possible
    additional assistance for connections.
   Begin construction in spring of 2013
   Provide Thermal Energy to Customers on 10/1/13
Presentation

   Overall Project Description and Funding Summary
   Project Costs
   Customer Commitments
   City/School heating costs
   Financing Package
   City’s Risk
   System Management, City Goals and Master Plan,
    Assumptions and Projections, City Votes
   Recommended Action
Project Goals
   Reduce emissions

   Replace oil with regional fuel source

   Stabilize heating costs for city/school

   Economic development opportunity for downtown

   City’s project costs within current expenses
Project Summary
   State Central Heating Plant – 40.2 MMBTU capacity

   City Distribution System – 9.71 MMBTU (24%) of state
    plant, ability to purchase up to 16.3 MMBTU

   Both Public and Private Customers

   Primarily Wood Chips for winter fuel (Oct – April)

   Summer Hot Water through system boilers
Overall Funding Summary
   Federal Department of Energy        $8.00 million
   State of Vermont Capital Funds      $7.00 million
   State of Vermont In Kind            $1.20 million
   City of Montpelier 2011 Bond        $2.00 million
   CEDF Grant                          $1.00 million
   CEDF Loan, 1%, deferred payment     $0.75 million
   Forest Service Grant (new)          $0.248 million
   Village Green Grant (new)           $0.10 million
   TOTAL                             $20.298 million
Funding Allocation
   State Funds for heat plant              $8.200 million
   DOE Grant to state for heat plant       $3.249 million
   DOE Grant to state for city capacity    $2.558 million
   City/CEDF funds to state for capacity   $1.077 million
   DOE Grant to city for dist. system      $2.193 million
   City/CEDF funds for dist. system        $2.673 million
   Other grant funds for dist. system      $0.348 million

   Total for Central Heating Plant         $15.047 million
   Total for Distribution System            $5.214 million
Overall City Funding Status
TOTAL Distribution System $               $5,214,419

Spent/Committed to date                     $899,651

Available Balance for Project           $4,314,768

Revised Project Cost Estimate            $3,732,351
   Project Balance                        $582,417 (17.71%)
   Contingencies (included in estimate)   $393,739 (11.97%)
   Combined “cushion”                     $976,156 (29.68%)
   May only need $1.45 M Bond instead of $2.0 M
Annual System Budget (2014)
   2011 Bond Payment @ $2.0 M          $169,191 (highest)
                 Bond @ $1.45 M = $122,663
   Contract with State                   $68,032
   2009 Bond Payment                     $20,376 (highest)
   Operations                            $10,228
   CEDF Loan Interest                     $7,500
   Total “Must Pay” Obligations         $275,327 (w/ $2 M Bond)
                  $228,799 (w/$1.45 M Bond)

   Cash Reserve (5% of rev.)            $12,992
   Operating/Admin 10 customers         $46,026 ($65,348 max)
   TOTAL                               $334,345

    With $1.45 M Bond                   $287,817
Customer Commitments using 2014
Capacity Rates

   City Complex (City Hall, Fire, Police)    $46,009
   Union Elementary School                   $77,350
   Vermont Mutual $151,830 prorated          $30,366
   GSA                                       $40,656
   County (Court House, Sheriff)             $14,738
   Everett (52, 46 & 27 State St)            $26,934
   Nedde (City Center)                       $26,257
   NECI/Nick (118 Main St)                   $12,949
   Jacobs (22 Elm/Jailhouse Common)           $8,165
   Beard (15 E. State St)                     $6,776
   TOTAL                                    $290,200
Customer Base
   10 Customers involve 15 Connections

   Initial System design = 34 Connections

   Commitments for 44% of connections

Additional connections create additional financial stability.
10 Cust. $3.73 M Project. $1.45 M Bond
 $900,000
                                        District Heat
 $800,000
                                   Annual Operating Budget
                                          Projection
 $700,000                                Annual Revenues
                                         Annual Expenses
 $600,000
                                         Annual Budget Balance
 $500,000                                Total Cash on Hand

 $400,000

 $300,000

 $200,000

 $100,000

       $0
             2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
($100,000)
City/School Fuel at $2.99/gallon
   City & UES use 60,600 gallons per year of oil

   Combined DH capacity fee = $123,359

   Combined DH energy fee = $58,063

   Total Combined DH cost = $181,422

   $181,422/60,600 gallons = $2.99 per gallon
Comparison to Oil
$6,000,000
                                             $5,555,435
                                                                 NPV COSTS & SAVINGS
                                                          of Oil and District Heat for City/School
$5,000,000

                            $4,384,564

$4,000,000
             $3,515,833

                                                             $3,034,069
$3,000,000                                                                      20 Year NPV Cost - Oil & DH
                                                $2,521,366
                                                                                20 Yr NPV savings with DH
                                                                                10 year NPV savings with DH
$2,000,000

                                $1,350,495

$1,000,000
                 $481,764                           $447,936
                                    $298,248
                    $120,695
       $0
              City/School Oil City/School Oil City/School Oil City/School DH,
              @ 3% increase      @ 5.25%      @ 8% increase      2.5% wood
                                 increase                         increase
Financing for Customer Connections
   Partnership with VT Economic Dev. Authority (VEDA)

   Village Green grant pays 10% of cost

   VEDA finances remaining 90% at 4% over 5-7 years

   Effective rate = 0% for 5 years, 1% for 7 years

   City will include repayment on DH bill
City Risk for not proceeding
   Cost of Oil in future starting at $3.00/gallon

    $900,000
                                  City/School with
    $800,000                      District Heat
                                  City/School oil @
    $700,000
                                  3%/year

    $600,000                      City/Schoo Oil @
                                  5.25%/year
    $500,000                      City/School Oil at
                                  8%/year
    $400,000

    $300,000

    $200,000

    $100,000

         $0
               2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
City’s Risks for Proceeding
   Project Costs running over

   Under budget, sufficient contingency, current bid climate,
    project sectioning options

   “Stuck” with Annual Operating Cost

   Full $2.0 M Bond. Minimal Customers – GSA, County,
    VM, Everett.
Bad Case Scenario
   Must Pay Obligations      $275,327
   City/School Energy Fees    $58,063
   TOTAL MUST PAY            $333,390
   Income (4 customers)      $112,694
   Net For City to Pay       $220,696

 Less City/School Capacity $123,359
 Less City/School Energy    $58,063
 TOTAL – City paying       $181,422
Net Added DH Costs for City $39,274
City Risk Comparison
City/School Oil prices
  $3.00/gallon for 60,600 gallons = $181,422
  $3.31/gallon for 60,600 gallons = $200,586
  $3.50/gallon for 60,600 gallons = $212,100

2009 Bond payment                = $20,376

City Costs with no DH = $201,798 to $232,476
Net Cost under Bad DH = $220,696
Other Considerations
   Operating costs and responsibilities are manageable
   Consistent with City Council 2012 Goals
   Consistent with City’s 2010 Master Plan
   City’s analysis “reasonable as to method and assumptions
    and the substance of the agreements to be reasonable in
    light of normal energy purchase and sale agreements”
   Public votes on this project:
       2003 Bond $250,000            1,273-875   59%
       2009 Re-use of the ’03 bond   1,024-745   57%
       2010 Charter amendments       2,826-755   78%
       2011 Bond $2,000,000            963-609   61%
Recommended Council Action
   Authorize City Manager to proceed with project
   Notify the State and DOE of this decision
   Continue signing up customers
   Issue bids in September for receipt in October
   Review bids in November, consider project adjustments.
    Award contract.
   Consider options for use of available funds, possible
    additional assistance for connections.
   Begin construction in spring of 2013
   Provide Thermal Energy to Customers on 10/1/13

Montpelier District Heat Project August 2012

  • 1.
    DISTRICT HEAT PROJECT August 22, 2012
  • 2.
    Key Points  Project is within budget  Ongoing operation is viable  City’s risks are addressed  Project goals are met
  • 3.
    Recommended Action  Authorize City Manager to proceed with project  Notify the State and DOE of this decision  Continue signing up customers  Issue bids in September for receipt in October  Review bids in November, consider project adjustments. Award contract.  Consider options for use of available funds, possible additional assistance for connections.  Begin construction in spring of 2013  Provide Thermal Energy to Customers on 10/1/13
  • 4.
    Presentation  Overall Project Description and Funding Summary  Project Costs  Customer Commitments  City/School heating costs  Financing Package  City’s Risk  System Management, City Goals and Master Plan, Assumptions and Projections, City Votes  Recommended Action
  • 5.
    Project Goals  Reduce emissions  Replace oil with regional fuel source  Stabilize heating costs for city/school  Economic development opportunity for downtown  City’s project costs within current expenses
  • 6.
    Project Summary  State Central Heating Plant – 40.2 MMBTU capacity  City Distribution System – 9.71 MMBTU (24%) of state plant, ability to purchase up to 16.3 MMBTU  Both Public and Private Customers  Primarily Wood Chips for winter fuel (Oct – April)  Summer Hot Water through system boilers
  • 8.
    Overall Funding Summary  Federal Department of Energy $8.00 million  State of Vermont Capital Funds $7.00 million  State of Vermont In Kind $1.20 million  City of Montpelier 2011 Bond $2.00 million  CEDF Grant $1.00 million  CEDF Loan, 1%, deferred payment $0.75 million  Forest Service Grant (new) $0.248 million  Village Green Grant (new) $0.10 million  TOTAL $20.298 million
  • 9.
    Funding Allocation  State Funds for heat plant $8.200 million  DOE Grant to state for heat plant $3.249 million  DOE Grant to state for city capacity $2.558 million  City/CEDF funds to state for capacity $1.077 million  DOE Grant to city for dist. system $2.193 million  City/CEDF funds for dist. system $2.673 million  Other grant funds for dist. system $0.348 million  Total for Central Heating Plant $15.047 million  Total for Distribution System $5.214 million
  • 10.
    Overall City FundingStatus TOTAL Distribution System $ $5,214,419 Spent/Committed to date $899,651 Available Balance for Project $4,314,768 Revised Project Cost Estimate $3,732,351  Project Balance $582,417 (17.71%)  Contingencies (included in estimate) $393,739 (11.97%)  Combined “cushion” $976,156 (29.68%)  May only need $1.45 M Bond instead of $2.0 M
  • 11.
    Annual System Budget(2014)  2011 Bond Payment @ $2.0 M $169,191 (highest) Bond @ $1.45 M = $122,663  Contract with State $68,032  2009 Bond Payment $20,376 (highest)  Operations $10,228  CEDF Loan Interest $7,500  Total “Must Pay” Obligations $275,327 (w/ $2 M Bond) $228,799 (w/$1.45 M Bond)  Cash Reserve (5% of rev.) $12,992  Operating/Admin 10 customers $46,026 ($65,348 max)  TOTAL $334,345 With $1.45 M Bond $287,817
  • 12.
    Customer Commitments using2014 Capacity Rates  City Complex (City Hall, Fire, Police) $46,009  Union Elementary School $77,350  Vermont Mutual $151,830 prorated $30,366  GSA $40,656  County (Court House, Sheriff) $14,738  Everett (52, 46 & 27 State St) $26,934  Nedde (City Center) $26,257  NECI/Nick (118 Main St) $12,949  Jacobs (22 Elm/Jailhouse Common) $8,165  Beard (15 E. State St) $6,776  TOTAL $290,200
  • 13.
    Customer Base  10 Customers involve 15 Connections  Initial System design = 34 Connections  Commitments for 44% of connections Additional connections create additional financial stability.
  • 14.
    10 Cust. $3.73M Project. $1.45 M Bond $900,000 District Heat $800,000 Annual Operating Budget Projection $700,000 Annual Revenues Annual Expenses $600,000 Annual Budget Balance $500,000 Total Cash on Hand $400,000 $300,000 $200,000 $100,000 $0 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 ($100,000)
  • 15.
    City/School Fuel at$2.99/gallon  City & UES use 60,600 gallons per year of oil  Combined DH capacity fee = $123,359  Combined DH energy fee = $58,063  Total Combined DH cost = $181,422  $181,422/60,600 gallons = $2.99 per gallon
  • 16.
    Comparison to Oil $6,000,000 $5,555,435 NPV COSTS & SAVINGS of Oil and District Heat for City/School $5,000,000 $4,384,564 $4,000,000 $3,515,833 $3,034,069 $3,000,000 20 Year NPV Cost - Oil & DH $2,521,366 20 Yr NPV savings with DH 10 year NPV savings with DH $2,000,000 $1,350,495 $1,000,000 $481,764 $447,936 $298,248 $120,695 $0 City/School Oil City/School Oil City/School Oil City/School DH, @ 3% increase @ 5.25% @ 8% increase 2.5% wood increase increase
  • 17.
    Financing for CustomerConnections  Partnership with VT Economic Dev. Authority (VEDA)  Village Green grant pays 10% of cost  VEDA finances remaining 90% at 4% over 5-7 years  Effective rate = 0% for 5 years, 1% for 7 years  City will include repayment on DH bill
  • 18.
    City Risk fornot proceeding  Cost of Oil in future starting at $3.00/gallon $900,000 City/School with $800,000 District Heat City/School oil @ $700,000 3%/year $600,000 City/Schoo Oil @ 5.25%/year $500,000 City/School Oil at 8%/year $400,000 $300,000 $200,000 $100,000 $0 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
  • 19.
    City’s Risks forProceeding  Project Costs running over  Under budget, sufficient contingency, current bid climate, project sectioning options  “Stuck” with Annual Operating Cost  Full $2.0 M Bond. Minimal Customers – GSA, County, VM, Everett.
  • 20.
    Bad Case Scenario  Must Pay Obligations $275,327  City/School Energy Fees $58,063  TOTAL MUST PAY $333,390  Income (4 customers) $112,694  Net For City to Pay $220,696  Less City/School Capacity $123,359  Less City/School Energy $58,063  TOTAL – City paying $181,422 Net Added DH Costs for City $39,274
  • 21.
    City Risk Comparison City/SchoolOil prices $3.00/gallon for 60,600 gallons = $181,422 $3.31/gallon for 60,600 gallons = $200,586 $3.50/gallon for 60,600 gallons = $212,100 2009 Bond payment = $20,376 City Costs with no DH = $201,798 to $232,476 Net Cost under Bad DH = $220,696
  • 22.
    Other Considerations  Operating costs and responsibilities are manageable  Consistent with City Council 2012 Goals  Consistent with City’s 2010 Master Plan  City’s analysis “reasonable as to method and assumptions and the substance of the agreements to be reasonable in light of normal energy purchase and sale agreements”  Public votes on this project:  2003 Bond $250,000 1,273-875 59%  2009 Re-use of the ’03 bond 1,024-745 57%  2010 Charter amendments 2,826-755 78%  2011 Bond $2,000,000 963-609 61%
  • 23.
    Recommended Council Action  Authorize City Manager to proceed with project  Notify the State and DOE of this decision  Continue signing up customers  Issue bids in September for receipt in October  Review bids in November, consider project adjustments. Award contract.  Consider options for use of available funds, possible additional assistance for connections.  Begin construction in spring of 2013  Provide Thermal Energy to Customers on 10/1/13