Example:
Find out quantities of following items of work
i. Excavation ii. PCC iii. UCR work iii. Brick Work
Step 1: To calculate Total center line distance of walls
TL=3.3 x 2+ 4.3 x 2+3.3 x 3 = 25.1 m
OR TL=7.6 x 2+ 3.3 x 3=25.1
3m x 3m 4m x 3m
0.5m
GL
FLOOR PLAN 0.9m
1.2m
7.6
7.3 m
3.3 m 3.3 m
2.75m
0.5m
0.2m
0.3m
0.5m
Saiyyed73@gmail.com
Measurement sheet:
Sr.no.
Work description Unit No’s Length Width Height/
Depth
Quantity Total
Quantity
i. Excavation (B-1.2m) M3 1 24.5 1.2 0.7 20.58
TL=C/C L – ½ x B
=25.1- ½ x 1.2
=24.5 m
ii. PCC Work (B-1.2m)
TL=C/C L – ½ x B
=25.1- ½ x 1.2
=24.5 m
M3 1 24.5 1.2 0.2 5.88
ii. UCR work (B-0.9m)
TL=C/C L – ½ x B
=25.1- ½ x 0.9
=24.2 m
M3 1 24.2 0.9 0.5 10.89
ii. UCR work (B-0.5m)
TL=C/C L – ½ x B
=25.1- ½ x 0.5
=24.85 m
M3 1 24.85 0.5 0.5 6.21
iii. Brick Work (B-0.3m)
TL=C/C L – ½ x B
=25.1- ½ x 0.3
=24.8 m
M3 1 24.8 0.3 2.75 20.46

Center line method 6

  • 1.
  • 2.
    Saiyyed73@gmail.com Example: Find out quantitiesof following items of work i. Excavation ii. PCC iii. UCR work iii. Brick Work Step 1: To calculate Total center line distance of walls TL=3.3 x 2+ 4.3 x 2+3.3 x 3 = 25.1 m OR TL=7.6 x 2+ 3.3 x 3=25.1 3m x 3m 4m x 3m 0.5m GL FLOOR PLAN 0.9m 1.2m 7.6 7.3 m 3.3 m 3.3 m 2.75m 0.5m 0.2m 0.3m 0.5m
  • 3.
    Saiyyed73@gmail.com Measurement sheet: Sr.no. Work descriptionUnit No’s Length Width Height/ Depth Quantity Total Quantity i. Excavation (B-1.2m) M3 1 24.5 1.2 0.7 20.58 TL=C/C L – ½ x B =25.1- ½ x 1.2 =24.5 m ii. PCC Work (B-1.2m) TL=C/C L – ½ x B =25.1- ½ x 1.2 =24.5 m M3 1 24.5 1.2 0.2 5.88 ii. UCR work (B-0.9m) TL=C/C L – ½ x B =25.1- ½ x 0.9 =24.2 m M3 1 24.2 0.9 0.5 10.89 ii. UCR work (B-0.5m) TL=C/C L – ½ x B =25.1- ½ x 0.5 =24.85 m M3 1 24.85 0.5 0.5 6.21 iii. Brick Work (B-0.3m) TL=C/C L – ½ x B =25.1- ½ x 0.3 =24.8 m M3 1 24.8 0.3 2.75 20.46