The document discusses using the center line method to calculate quantities of materials for construction projects. It provides an example of calculating the brick work and PCC quantities for a wall by finding the center line length of the wall, multiplying by the width and depth, and accounting for deductions from openings like doors and windows. The total quantities calculated are 17.49 cubic meters of brick work and 4.24 cubic meters of PCC.