SlideShare a Scribd company logo
1
OPTIMIZING SUB-CONTRACTOR SELECTION
BY BRANCH AND BOUND ALGORITHM
Bowen Deng
Bhanu Pratap Singh Sandu
(Group 33)
Graduate Students, Department of Civil and Environmental Engineering,
University of Illinois, Urbana-Champaign
Email: bowend3@illinois.edu , bsandu2@illinois.edu
Khaled A El-Rayes
Professor
University of Illinois, Urbana-Champaign
Email: elrayes@illinois.edu
2
ABSTRACT
Obviously it is a good news for a construction company to win the bid for a huge potential amount
of profit. However, when they lack the capability to finish the construction activities by themselves
it would be another story. Usually they have to choose appropriate subcontractors to do the
unfinished job. Subcontractors may be various from experience, cost, time, quality and many other
factors which can have impacts on the selection by a main contractor on a certain project. How to
choose subcontractors wisely has become a hotspot issue to many construction companies. Many
literatures have recorded the attempts to select subcontractors with a consideration of as many
possible factors as they can. Some of them are connected with mathematical models and algorithms.
This paper is on the purpose of optimizing the selection of subcontractors on the basis of existing
methods---the Branch and Bound algorithm. So a literature review is given after stating the
problem. And a numerical example is also included to better explain the optimization process.
PROBLEM STATEMENT
Nowadays construction companies are working so hard to make a living through the fierce
competition. It is always a good news for a construction company to win a bid by defeating all the
3
competitors. However, as the rapid development of construction industry, construction projects
nowadays are becoming bigger and harder than before.
Main contractors in today’s construction industry cannot complete the entire construction projects
on their own. Some projects are so complicated that they need contractors with specific previous
working experience. So it is necessary to subcontract some parts of the construction projects to
competitive subcontractors.
Here comes the question, how to choose subcontractors wisely? Many literatures have already
recorded attempts to assisting the selection of subcontractors by using various mathematical
algorithms and computer models. But they all have their limitations. Some of them are not as
accurate as people think. So in this paper, the main purpose is to optimize the existing method by
doing literature review and modifications.
To optimize the selection process is so important that it should catch people’s attention. It is known
that there are so many candidates in the market with different construction background and
experience. If the main contractor chooses an appropriate subcontractor, the construction activity
could be completed ahead of schedule and under the budget. Instead, a wrong candidate may result
4
in various possible troubles like short of experience, poor construction quality or some other
potential conflicts. Therefore, the optimization of subcontractor selection is of great significance
to all the main contractors.
This paper selects a branch and bond algorithm as a basis to explore the further optimization of
subcontractors in construction industry. The issue is to review the original models and equations,
and find out which part of the original model can be improved. Although there are many possible
factors which may have impacts on the selection like the relationship between contractors, the
working experience and construction quality, the paper only chooses the most important factors to
do the optimization, project schedule and overall cost. Construction quality is not discussed here
because it is too subjective to get a quantitative measure.
OBJECTIVES
The objective of this paper is to study the existing subcontractor selection method by doing
literature review. After that try to optimize it by make some modifications to the original models
and develop a new model to solve the problem.
5
BRANCH AND BOUND ALGORITHM (BB)
In this paper, a Branch and Bound algorithm is selected as the basis of optimization. The Branch
and Bound algorithm (BB) is an algorithm designed for optimization problems. As it is named, the
Branch and Bound algorithm (BB) is used to present all the feasible solutions of a problem into
branches of a tree. And the optimal solution could be found through those branches. The basic idea
of the Branch and Bound algorithm (BB) is the solution space reduction. A problem which has
several constraints can be treated like a certain space. The solution is in that space. To find out the
solution among other options rapidly, the space should be reduced. When operating the Branch
and Bound algorithm (BB), the space of all the feasible solutions is divided into many subsets like
branches. And calculate the thresholds or the upper and lower bounds for those feasible solutions
in each branch. After that, abandon those branches whose bonds are already out of the range. Then
the solution space will be decreased. Keep doing this until find out the optimal solution.
The selection of subcontractors can be transferred into this Branch and Bound algorithm (BB)
problem. Each subcontractor has a construction time and project cost. They are put into the Space.
After solution space reduction, the optimal subcontractor can be found by using different bonds.
6
LITERATURE REVIEW
1. The paper by (Talluri, Baker, & Sarkis, 1999) first realize the importance of selecting
appropriate partner for the job and propose a two phase quantitative framework to optimize
the partner selection problems. In the first phase, data envelopment analysis is utilized to
determine possible candidates for each type of work. Then in the second phase, an integer
goal programming model is introduced to select which possible candidate is the most
appropriate. But there are some limitations exposed during the optimization process. When
imputing initial data, the data may not be that accurate because it is obtained via an
optimization which makes the solution a sub-optimal one. Also when considering the
factors affecting the partner selection, the realistic situation seems more complicated than
the assumptions. So this model needs further modifications to be applied to the current
situation.
2. The paper by (Ip, Yung, & Wang, 2003) presents a branch and bound algorithm solution
for sub-contractor selection in agile manufacturing environment. They embed the project
7
schedule into the branch and bound algorithm models. To solve this problem, they separate
it into two levels. The first level is to use branch and bonds to choose optimal
subcontractors. Then the second level is to schedule the project and minimize the loan
interest.
At the beginning they define a concept called objective value Z(x) considering both money
requirement and project completion time. Then they sequence the activities according to
the means of the bid costs. After initial bounds and search index are set, they start to use
Branch and Bound Algorithm to search for the optimal solution. The principle of Branch
and Bound Algorithm (BB) is the solution space reduction by cutting branches. In each
branch, one activity is assigned to a candidate contractor. After calculating the objective
value Z(x) they compare it with the Bound. The branch would be abandoned if the objective
value Z(x) is more than the Bound. If it is not, the branch would go on and go to the next
step.
8
PROPOSED METHODOLOGY
The proposed methodology incorporates two new performance indices for cost and time namely
Cost performance index (Cpi) and Time performance index (Tpi).
The way these indices would be quantified is purely based on past performances of the
subcontractors. Now this past information is really important for our factors. Generally, if a
contractor has a working experience with multiple subs, the contractor can easily acquire this
information. Even if there is a sub-contractor who is working for the first time with the contractor,
this would not necessarily mean that the sub-contractor is new to the field, just that it is the first
time the duo is working together. Even for sub-contractors like this the historical data can be
obtained by analyzing their past construction works. This way no assumptions would have to be
made and all the data would be easily available too. But if a sub-contractor is however new to the
construction field, this model cannot be applied to them. But it is very unlikely that a contractor
will even consider an inexperienced sub-contractor for such a huge project, almost all the sub-
contractors considered would be highly experienced professionals. And therefore we do not need
to worry about applying our model to brand new sub-contractors.
9
The concept is that, for every 1% increase or decrease in the scheduled cost or time of the
subcontractors, based on the past performances, we would assign them an increased or decreased
Cpi and Tpi. Now these past records taken would be averaged and used. For example, if the
subcontractor has been delayed by 10% time for one project and 5% time for another, the average
taken would be 7.5%. And thus an increase in the bid time for this subcontractor would be made
by 7.5%. The same would be done for the cost aspect based on their cost performances.
The main objective here is to select the optimal combination of subcontractors so that we can
minimize the time and cost for all the jobs in the project.
For example, if we were to select one of three subcontractors for an activity (say excavation) we
would have the following information:
Subcontractor 1 2 3
Job Excavation Excavation Excavation
Time 5 days 4 days 3 days
Cost $20,000 $22,500 $25,000
10
However, after applying Cpi and Tpi, these numbers will change:
Subcontractor 1 2 3
Job Excavation Excavation Excavation
Time 5 days 4 days 3 days
Cost $20,000 $22,500 $25,000
Past performances
Avg time delay of
10%
Avg cost increase by
10%
Avg time cut short by
5%
Avg cost increase by
5%
Avg time cut short by
10%
On average always on
budget
Cpi influenced Cost
value
20k x Cpi =
20k x 1.1 = 22k
22k x Cpi =
22k x 1.05 = 23.1k
25k x Cpi =
25k x 1 = 25k
Tpi influence Time
value
5 x Tpi =
5 x 1.1 = 5.5 days
4 x Tpi =
4 x 0.95 = 3.8 days
3 x Tpi =
3 x 0.9 = 2.7 days
Now that we have seen what the factors are about, we will look into the existing model
proposed by Ip, Yung and Wang and how we influence and further optimize it.
Since sub-projects contracted by partners consist of an activity network with precedence, each
partner works in the project as a ring in a chain (Elmaghraby, 1977). Because the main contractor
11
gets paid in installments, this can be considered as the cash flow. This investment cannot always
meet the requirements from the sub-project contractors and thus the main contractor often takes a
loan of certain amount from the bank and pay them interest. Because of the complexity of the
selection of the sub-contractor, it is not easily solved by general mathematical programming
methods. However, Branch and Bound method is powerful tool to solve this kind of combinatorial
optimizations (Taha, 1975).
The model proposed by Ip, Yung and Wang is described as follows:
1. Problem and model of sub-contractor selection
2. Inefficient and ideal candidates
3. Branch and bound algorithm embedded project scheduling
4. Numerical analysis
Problem and model of sub-contractor selection:
All the notations are listed below:
n = number of jobs included in project
D = due-date of project
12
b = penalty cost for tardiness of a period
a = rate of first payment to sub-contractors
r = interest rate of loan from bank
f(t) = cash flow paid to the main contractor by the project owner in period t
F = total investment for the project from owner
(i.k) = connected job pair
H = set of all connected job pairs
mi = number of candidates bidding for job i
bij = bid cost of candidate j for job i
pij = bid completion time of candidate j for job i
Cpij = cost performance index of candidate j for job i
Tpij = time performance index of candidate j for job i
(The above mentioned factors are what we plan to introduce to the model).
cn = completion time of final job, i.e. the completion time of the project
xij = 0–1 assignment variable. xij = 1 means the job i is contracted to j
13
x = matrix variable for all xij: It is a completed selection
Z(x) = objective value achieved by selection x
si = beginning time of job i in selection x
ci = completion time of job i in selection x
Ok = index of job sequenced at kth place with the kth larger mean cost
I(Ok) = assigned candidate index of job Ok (the job at the k-place in the sequence)
(Ip, Yung, & Wang, 2003)
The sub-contractor selection problem is stated as: say the main contractor wins a bid for a big
project and is not able to complete the whole project by its own capacity and resources, therefore
subcontracting a number of sub projects. The objective here is to select an optimal combination of
sub-contractors for all the jobs such as to minimize the total cost and time.
Defining the variables,
xij(t) =
1, job i is contracted to candidate j and begins at period t
0, otherwise
14
Then the problem can be described by the following model (adding Cpij and Tpij where needed)
(Ip, Yung, & Wang, 2003)
The factors Cpij and Tpij have been added to the existing models and were not a part of the model
before.
So whenever the model uses a cost factor, we multiply the cost performance index to modify and
further optimize the solution. Same is done for the time factor.
Inefficient and ideal candidates:
Since the size of the solution space is,
It clearly shows that even for a small scale problem with 10 jobs and 3 candidates the solution
min
x
Z(x) = bijCpij xij
t=1
cn
∑
j=1
mi
∑
i=1
n
∑ (t)
+r α bijCpij xij (τ )+ (1−α) bijCpij xij (τ − pijTpij )− f (τ )
τ =1
t
∑
τ =1
t
∑
j=1
mi
∑
i=1
n
∑
τ =1
t
∑
j=1
mi
∑
i=1
n
∑
⎡
⎣
⎢
⎤
⎦
⎥
t=1
cn
∑
+
+ β cn − D[ ]+
s.t.
xij (t) = 1,i = 1,2,...,n,
t=1
cn
∑
j=1
mi
∑
(t + pijTpij )xij (t)
t=1
cn
∑
j=1
mi
∑
≤ txkj (t),∀(i,k) ∈H
t=1
cn
∑
j=1
mk
∑
(t + pnjTpij )xnj (t) = cn
t=1
cn
∑
j=1
mn
∑ ,
xij (t) = 1or0,∀i, j,t,
N =
i=1
n
Πmi
15
space is very large, 310
= 59,049. This is too high a number and therefore a reduction in the solution
space is required. This reduction comes in the format of a theorem used by Ip et al, which says,
the candidate j of job I is inefficient if there exists a candidate k for the same job with,
bik £ bij, pik < pij or bik < bij, pik £ pij (Ip, Yung, & Wang, 2003).
Using this theorem, we can ignore all inefficient candidates without the loss of an optimal solution
and thus the solution space is reduced considerably.
Branch and bound algorithm embedded project scheduling:
The idea of the proposed branch and bound algorithm is to select the optimal partner combination
by branch and bound at the first level of algorithm and to schedule all jobs with a fixed partner
combination at the second level (Ip, Yung, & Wang, 2003).
Numerical Analysis:
The algorithm was coded by Ip et al on FORTRAN and run on a Pentium II/366 machine and
satisfactory results were achieved. The example they took was a real life construction problem of
the construction of a coal-fire power station. Atotal of 16 jobs were set and a due date of 36 months
was also set. Additional details are: loan interest rate = 0.6% per month, 55% payment for all jobs
16
will be made in advance and the rest of the payment when the job was done. A total investment of
$72.75 million was to be made.
Table 1: The job list and the cost and time values for each job
Number	 Job	 Cost	(million	$)	 Time	(months)	
1	 Total	design	of	system	 2.75	 6	
2	 Design	of	railway	for	coal	 0.3	 4	
3	 Construction	of	railway	 3.75	 10	
4	 Design	of	boiler	system	 1.75	 6	
5	 Manufacturing	of	boilers	 18.5	 12	
6	 Design	of	buildings	 2	 6	
7	 Construction	of	buildings	 6.5	 10	
8	 Design	of	generators	 1.5	 6	
9	 Design	of	electric	transmission	 	 1.5	 6	
10	 Manufacturing	of	generators	 13.5	 12	
11	 Assembling	of	boilers	 1	 3	
12	 Manufacturing	of	transmission	equipment	 6.75	 12	
13	
Design	and	assembly	of	computer	control	
system	 7	 16	
14	 Assembling	of	generators	 1.25	 3	
15	 Assembling	of	transmission	system	 1.75	 3	
16	 System	inspection	and	test	running	 3	 5
17
Table 2: Number of candidates for the job
Job	 Number	of	candidates	
1	 4	
2	 6	
3	 5	
4	 2	
5	 2	
6	 7	
7	 4	
8	 8	
9	 3	
10	 4	
11	 5	
12	 3	
13	 6	
14	 3	
15	 4	
16	 2	
Table 3: List of candidates for each job
Job	number	
Candidate	
code	 Cost	(million	$)	
Time	
(months)	
	 A1	 2.7	 4	
	 A2	 2.4	 5	
1	 A3	 2.175	 5	
	 A4	 1.8	 6
18
B1	 0.285	 4	
	 B2	 0.3	 3	
	 B3	 0.375	 3	
2	 B4	 0.27	 5	
	 B5	 0.225	 6	
	 B6	 0.33	 3	
	
C1	 3	 12	
	 C2	 3.375	 11	
3	 C3	 3.75	 10	
	 C4	 4.05	 8	
	 C5	 2.775	 13	
	
4	 D1	 1.5	 6	
	 D2	 1.8	 4	
	
5	 E1	 18	 12	
	 E2	 19.5	 10	
	
F1	 1.8	 4	
	 F2	 2.1	 4	
	 F3	 1.5	 5	
6	 F4	 2.175	 3	
	 F5	 1.2	 7	
	 F6	 1.35	 6	
	 F7	 1.05	 8	
	
G1	 1.8	 5	
7	 G2	 2.1	 4
19
	
G3	 1.5	 7	
	 G4	 1.2	 8	
	
H1	 5.25	 12	
	 H2	 4.5	 13	
	 H3	 5.7	 11	
8	 H4	 6	 10	
	 H5	 7.2	 8	
	 H6	 6.75	 8	
	 H7	 6.3	 10	
	 H8	 6.45	 10	
	
I1	 1.65	 5	
9	 I2	 1.2	 7	
	 I3	 1.8	 4	
	
J1	 14.7	 10	
10	 J2	 13.2	 12	
	 J3	 12	 13	
	 J4	 15.75	 8	
	
K1	 0.9	 3	
	 K2	 0.75	 3	
11	 K3	 1.05	 2	
	 K4	 0.6	 4	
	 K5	 0.825	 3	
	
L1	 6	 12	
12	 L2	 5.7	 14
20
	
L3	 7.2	 10	
	
M1	 4.5	 18	
	 M2	 5.7	 17	
	 M3	 7.5	 12	
13	 M4	 8.25	 10	
	 M5	 9	 8	
	 M6	 7.2	 15	
	
N1	 1.2	 4	
14	 N2	 1.8	 2	
	 N3	 1.5	 3	
	
P1	 1.8	 2	
15	 P2	 1.5	 3	
	 P3	 1.2	 3	
	 P4	 0.9	 5	
	
16	 Q1	 2.4	 6	
	 Q2	 3	 5	
Now, the model runs the mentioned values and tries to optimize the sub-contractor selection based
on the values of their individual cost and time of completion. We can clearly see here how much
focused this model is on these time-cost values.
So when run by the model, an optimal selection of sub-contractors for respective jobs is achieved.
21
Table 4: The sub-contractors of optimal solution
The solution by Ip et al of above data set with the model resulted in the following optimal solution:
Job	
number	
Sub-
contractor	
Cost	
(million	$)	 Proc.	Time	
Beginning	
time	
Time	of	
completion	
1	 A1	 2.7	 4	 1	 5	
2	 B2	 0.3	 3	 1	 4	
3	 C5	 2.775	 13	 4	 17	
4	 D2	 1.8	 4	 5	 9	
5	 E1	 18	 12	 13	 25	
6	 F7	 1.05	 8	 9	 17	
7	 G2	 2.1	 4	 9	 13	
8	 H6	 6.75	 8	 17	 25	
9	 I3	 1.8	 4	 13	 17	
10	 J3	 12	 13	 14	 27	
11	 K3	 1.05	 2	 25	 27	
12	 L1	 6	 12	 17	 29	
13	 M3	 7.5	 12	 19	 31	
14	 N2	 1.8	 2	 27	 29	
15	 P1	 1.8	 2	 29	 31	
16	 Q2	 3	 5	 31	 36	
In this solution we can see that the optimal selection of sub-contractors is satisfactory since all the
jobs are completed within the duration of 36 months and with a budget of $70.5 million. So the
contractor makes a profit of $2.25 million.
22
But imagine if some of these sub-contractors fail to deliver on time or within the budget. If that
happens, and there is a reasonable probability that it could happen, the contractor’s profit will end
up being reduced and he might have to pay the tardiness penalty as well. This would seriously
impact the profit of the project and make the entire project a failed venture.
Now here is where our factors for cost and time performance (Cpi and Tpi) come in. We multiply
the existing time and cost promised by each sub-contractor by their individual cost and time
performance index. This gives us their updated cost and time for completion of the activity.
For example, for job 1 four sub-contractors had submitted their cost and time values as below:
Job	number	
Candidate	
code	 Cost	(million	$)	
Time	
(months)	
	 A1	 2.7	 4	
	 A2	 2.4	 5	
1	 A3	 2.175	 5	
	 A4	 1.8	 6	
But this model did not consider their past performance, and now if we do, suppose for example,
all four candidates have the following past performances:
23
Candidate	code	 Time	performance	 	 Cost	performance	
A1	
On	average	the	candidate	has	
been	5%	behind	schedule;	 	
Tpi	=	1.05	
On	average	the	candidate	has	
always	been	on	budget;	
Cpi	=	1	
A2	
On	average	the	candidate	has	
been	10%	behind	schedule;	
Tpi	=	1.10	
On	average	the	candidate	has	been	
5%	over	budget;	
Cpi	=	1.05
A3	
On	average	the	candidate	has	
been	5%	ahead	of	schedule;	
Tpi	=	0.95	
On	average	the	candidate	has	been	
3%	over	budget;	 	
Cpi	=	1.03
A4	
On	average	the	candidate	has	
been	10%	ahead	of	schedule;	
Tpi	=	0.9	
On	average	the	candidate	has	been	
10%	over	budget;	 	
Cpi	=	1
And thus the new values for time and cost of the four candidates will be:
Job	number	
Candidate	
code	
Cost	(million	$)	
Cpi	Influenced	cost	
Time	(months)	
Tpi	influenced	time	
	 A1	 2.7	x	1	=	2.7	 4	x	1.05	=	4.2	 	 	 	
1	 A2	 2.4	x	1.05	=	2.52	 5	x	1.10	=	5.5	
	 A3	 2.175	x	1.03	=	2.24	 5	x	0.95	=	4.75	
	 A4	 1.8	x	1.1	=	1.98	 6	x	0.9	=	5.4
24
Now if these values are used to optimize the selection, it will definitely influence the results and
new sub-contractors may get selected based on their efficient past performances.
This is because the model heavily focuses on the cost and time performance of each candidate, and
if those values are influenced, the result will undoubtedly be influenced and further optimized
because these new values would be more realistic and accurate. By using these factors to update
the model, we somewhat eliminate any surprises that might come from the sub-contractors and
make sure that our end profit is secure and maximum. This is the whole idea behind our updated
model. Because the model is so heavily focused on the values of cost and time, if we influence
those values, we will influence the result. Similarly, if we can further optimize the time and cost
values, we will further optimize the model and thus the final solution.
25
EXPECTED CONTRIBUTION
The existing model is designed to select an optimal group of sub-contractors based on their time
and cost bids for the job. However, the model doesn’t take into account the historical data of the
past performances of these individual candidates. That is what this paper proposes. The
contribution we expect to impart is that when optimizing such models to get such a group of sub-
contractors, each of them be judged on the past performances too. This way many judgmental
errors and time delays can be avoided even before the construction starts.
If we look at the industry at large, this would be beneficial to any party which tries to optimize its
sub-contractor selection by updating their model with cost and time performance indices. It would
result in a huge amount of cost savings and more importantly the saving of time.
26
References
Elmaghraby, S. E. (1977). Activity Networks - Project Planning and control by Network
Models. New York, NY, USA: Wiley, New York.
Ip, W., Yung, K., & Wang, D. (2003). Branch and Bound algorithm for sub-contractor selection
in agile manufacturing environment. The Hong Kong Polytechnic Unversity ,
Department of Manufacturing Engineering. Hong Kong: Elsevier.
Taha, H. (1975). Integer Programming Theory, Applications and Computations. New York,
NY, USA: Academic Press.
Talluri, S., Baker, R., & Sarkis, J. (1999). A framework for designing efficient value chain
networks. International Journal of Production Economics, Elsevier.

More Related Content

What's hot

IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET Journal
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET Journal
 
AN APPROACH FOR SOFTWARE EFFORT ESTIMATION USING FUZZY NUMBERS AND GENETIC AL...
AN APPROACH FOR SOFTWARE EFFORT ESTIMATION USING FUZZY NUMBERS AND GENETIC AL...AN APPROACH FOR SOFTWARE EFFORT ESTIMATION USING FUZZY NUMBERS AND GENETIC AL...
AN APPROACH FOR SOFTWARE EFFORT ESTIMATION USING FUZZY NUMBERS AND GENETIC AL...
csandit
 
An approach for software effort estimation using fuzzy numbers and genetic al...
An approach for software effort estimation using fuzzy numbers and genetic al...An approach for software effort estimation using fuzzy numbers and genetic al...
An approach for software effort estimation using fuzzy numbers and genetic al...
csandit
 
5.0 Subcontractor Selection Ass3 Sem2 '09
5.0 Subcontractor Selection Ass3 Sem2 '095.0 Subcontractor Selection Ass3 Sem2 '09
5.0 Subcontractor Selection Ass3 Sem2 '09Praveen Premkumar
 
Final hrm project 2003
Final hrm project 2003Final hrm project 2003
Final hrm project 2003Adil Shaikh
 
time-cost-quality.pdf
time-cost-quality.pdftime-cost-quality.pdf
time-cost-quality.pdf
sam26a
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
Melvin Lim
 
Planning can we do with out it?
Planning can we do with out it?Planning can we do with out it?
Planning can we do with out it?
Catherine Bendell
 
Top down
Top downTop down
Top downNino Ho
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
Hasif Alias
 
PM3 ARTICALS
PM3 ARTICALSPM3 ARTICALS
PM3 ARTICALSra na
 
Specific experience criteria in contractor selection
Specific experience criteria in contractor selectionSpecific experience criteria in contractor selection
Specific experience criteria in contractor selection
Ajay Adhikari
 
Forecasting the final cost of iraqi public school projects using regression a...
Forecasting the final cost of iraqi public school projects using regression a...Forecasting the final cost of iraqi public school projects using regression a...
Forecasting the final cost of iraqi public school projects using regression a...Gafel Kareem
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
Timun Loh
 
International Journal of Engineering Inventions (IJEI),
International Journal of Engineering Inventions (IJEI), International Journal of Engineering Inventions (IJEI),
International Journal of Engineering Inventions (IJEI),
International Journal of Engineering Inventions www.ijeijournal.com
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
Yong Sy
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
Lee Pei Gie
 

What's hot (20)

IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
AN APPROACH FOR SOFTWARE EFFORT ESTIMATION USING FUZZY NUMBERS AND GENETIC AL...
AN APPROACH FOR SOFTWARE EFFORT ESTIMATION USING FUZZY NUMBERS AND GENETIC AL...AN APPROACH FOR SOFTWARE EFFORT ESTIMATION USING FUZZY NUMBERS AND GENETIC AL...
AN APPROACH FOR SOFTWARE EFFORT ESTIMATION USING FUZZY NUMBERS AND GENETIC AL...
 
An approach for software effort estimation using fuzzy numbers and genetic al...
An approach for software effort estimation using fuzzy numbers and genetic al...An approach for software effort estimation using fuzzy numbers and genetic al...
An approach for software effort estimation using fuzzy numbers and genetic al...
 
5.0 Subcontractor Selection Ass3 Sem2 '09
5.0 Subcontractor Selection Ass3 Sem2 '095.0 Subcontractor Selection Ass3 Sem2 '09
5.0 Subcontractor Selection Ass3 Sem2 '09
 
Final hrm project 2003
Final hrm project 2003Final hrm project 2003
Final hrm project 2003
 
Procurement system
Procurement systemProcurement system
Procurement system
 
time-cost-quality.pdf
time-cost-quality.pdftime-cost-quality.pdf
time-cost-quality.pdf
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Planning can we do with out it?
Planning can we do with out it?Planning can we do with out it?
Planning can we do with out it?
 
Top down
Top downTop down
Top down
 
Purpose
PurposePurpose
Purpose
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
PM3 ARTICALS
PM3 ARTICALSPM3 ARTICALS
PM3 ARTICALS
 
Specific experience criteria in contractor selection
Specific experience criteria in contractor selectionSpecific experience criteria in contractor selection
Specific experience criteria in contractor selection
 
Forecasting the final cost of iraqi public school projects using regression a...
Forecasting the final cost of iraqi public school projects using regression a...Forecasting the final cost of iraqi public school projects using regression a...
Forecasting the final cost of iraqi public school projects using regression a...
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
International Journal of Engineering Inventions (IJEI),
International Journal of Engineering Inventions (IJEI), International Journal of Engineering Inventions (IJEI),
International Journal of Engineering Inventions (IJEI),
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 

Viewers also liked

Xxxxx sub contractor_mgmnt
Xxxxx sub contractor_mgmntXxxxx sub contractor_mgmnt
Xxxxx sub contractor_mgmntGhada Gattouch
 
CONS6817_S04'16
CONS6817_S04'16CONS6817_S04'16
CONS6817_S04'16
Lara Tookey
 
M Sc Pm Lecture No 4 Risk
M Sc Pm Lecture No 4    RiskM Sc Pm Lecture No 4    Risk
M Sc Pm Lecture No 4 RiskHoang Vuong
 
Contract management procedure
Contract management procedureContract management procedure
Contract management procedure
Self-employed
 
Clean Development Mechanism
Clean Development MechanismClean Development Mechanism
Clean Development Mechanism
Nayan Bhatia
 
The Ultimate Review of Construction Project Management Methodologies
The Ultimate Review of Construction Project Management Methodologies The Ultimate Review of Construction Project Management Methodologies
The Ultimate Review of Construction Project Management Methodologies
Capterra
 
Contractor Relationship OPS405
Contractor Relationship OPS405Contractor Relationship OPS405
Contractor Relationship OPS405kahogan62
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
Daniel Ross
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project managementAli Heydari
 

Viewers also liked (10)

Xxxxx sub contractor_mgmnt
Xxxxx sub contractor_mgmntXxxxx sub contractor_mgmnt
Xxxxx sub contractor_mgmnt
 
CONS6817_S04'16
CONS6817_S04'16CONS6817_S04'16
CONS6817_S04'16
 
M Sc Pm Lecture No 4 Risk
M Sc Pm Lecture No 4    RiskM Sc Pm Lecture No 4    Risk
M Sc Pm Lecture No 4 Risk
 
Contract management procedure
Contract management procedureContract management procedure
Contract management procedure
 
Clean Development Mechanism
Clean Development MechanismClean Development Mechanism
Clean Development Mechanism
 
The Ultimate Review of Construction Project Management Methodologies
The Ultimate Review of Construction Project Management Methodologies The Ultimate Review of Construction Project Management Methodologies
The Ultimate Review of Construction Project Management Methodologies
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Contractor Relationship OPS405
Contractor Relationship OPS405Contractor Relationship OPS405
Contractor Relationship OPS405
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project management
 

Similar to CEE526 Paper for Group 33 (Bowen, Bhanu)

Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
Muthanna Abbu
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and scheduling
smumbahelp
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916George Wilkinson
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignment
wendyteosy
 
Sm presentation
Sm presentationSm presentation
Comparison of available Methods to Estimate Effort, Performance and Cost with...
Comparison of available Methods to Estimate Effort, Performance and Cost with...Comparison of available Methods to Estimate Effort, Performance and Cost with...
Comparison of available Methods to Estimate Effort, Performance and Cost with...
International Journal of Engineering Inventions www.ijeijournal.com
 
11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing Costshttpsleo11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing Costshttpsleo
SantosConleyha
 
11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing Costshttpsleo11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing Costshttpsleo
BenitoSumpter862
 
CHAPTER Modeling and Analysis Heuristic Search Methods .docx
CHAPTER Modeling and Analysis Heuristic Search Methods .docxCHAPTER Modeling and Analysis Heuristic Search Methods .docx
CHAPTER Modeling and Analysis Heuristic Search Methods .docx
tiffanyd4
 
CHAPTER Modeling and Analysis Heuristic Search Methods .docx
CHAPTER Modeling and Analysis Heuristic Search Methods .docxCHAPTER Modeling and Analysis Heuristic Search Methods .docx
CHAPTER Modeling and Analysis Heuristic Search Methods .docx
mccormicknadine86
 
Assignment Of Trainees To Software Project Requirements A Stable Matching Ba...
Assignment Of Trainees To Software Project Requirements  A Stable Matching Ba...Assignment Of Trainees To Software Project Requirements  A Stable Matching Ba...
Assignment Of Trainees To Software Project Requirements A Stable Matching Ba...
Miranda Anderson
 
COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES
COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES
COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES
ijseajournal
 
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
IOSR Journals
 
Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...
Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...
Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...
TELKOMNIKA JOURNAL
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
MoncefMakni1
 
Take The Highway To A Successful It Project
Take The Highway To A Successful It ProjectTake The Highway To A Successful It Project
Take The Highway To A Successful It Projectsantosh singh
 
Suvarna consultancy services
Suvarna consultancy services Suvarna consultancy services
Suvarna consultancy services
Ashok Tundare
 
Project Planning, Execution And Closure Essay
Project Planning, Execution And Closure EssayProject Planning, Execution And Closure Essay
Project Planning, Execution And Closure Essay
Jennifer Letterman
 
IRJET- Decision Making in Construction Management using AHP and Expert Ch...
IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...
IRJET- Decision Making in Construction Management using AHP and Expert Ch...
IRJET Journal
 

Similar to CEE526 Paper for Group 33 (Bowen, Bhanu) (20)

Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and scheduling
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignment
 
Sm presentation
Sm presentationSm presentation
Sm presentation
 
Comparison of available Methods to Estimate Effort, Performance and Cost with...
Comparison of available Methods to Estimate Effort, Performance and Cost with...Comparison of available Methods to Estimate Effort, Performance and Cost with...
Comparison of available Methods to Estimate Effort, Performance and Cost with...
 
11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing Costshttpsleo11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing Costshttpsleo
 
11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing Costshttpsleo11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing Costshttpsleo
 
CHAPTER Modeling and Analysis Heuristic Search Methods .docx
CHAPTER Modeling and Analysis Heuristic Search Methods .docxCHAPTER Modeling and Analysis Heuristic Search Methods .docx
CHAPTER Modeling and Analysis Heuristic Search Methods .docx
 
CHAPTER Modeling and Analysis Heuristic Search Methods .docx
CHAPTER Modeling and Analysis Heuristic Search Methods .docxCHAPTER Modeling and Analysis Heuristic Search Methods .docx
CHAPTER Modeling and Analysis Heuristic Search Methods .docx
 
Assignment Of Trainees To Software Project Requirements A Stable Matching Ba...
Assignment Of Trainees To Software Project Requirements  A Stable Matching Ba...Assignment Of Trainees To Software Project Requirements  A Stable Matching Ba...
Assignment Of Trainees To Software Project Requirements A Stable Matching Ba...
 
COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES
COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES
COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES
 
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
 
Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...
Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...
Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
Take The Highway To A Successful It Project
Take The Highway To A Successful It ProjectTake The Highway To A Successful It Project
Take The Highway To A Successful It Project
 
Suvarna consultancy services
Suvarna consultancy services Suvarna consultancy services
Suvarna consultancy services
 
Project Planning, Execution And Closure Essay
Project Planning, Execution And Closure EssayProject Planning, Execution And Closure Essay
Project Planning, Execution And Closure Essay
 
IRJET- Decision Making in Construction Management using AHP and Expert Ch...
IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...
IRJET- Decision Making in Construction Management using AHP and Expert Ch...
 
Practitioner class 3: Contract strategy
Practitioner class 3: Contract strategyPractitioner class 3: Contract strategy
Practitioner class 3: Contract strategy
 

CEE526 Paper for Group 33 (Bowen, Bhanu)

  • 1. 1 OPTIMIZING SUB-CONTRACTOR SELECTION BY BRANCH AND BOUND ALGORITHM Bowen Deng Bhanu Pratap Singh Sandu (Group 33) Graduate Students, Department of Civil and Environmental Engineering, University of Illinois, Urbana-Champaign Email: bowend3@illinois.edu , bsandu2@illinois.edu Khaled A El-Rayes Professor University of Illinois, Urbana-Champaign Email: elrayes@illinois.edu
  • 2. 2 ABSTRACT Obviously it is a good news for a construction company to win the bid for a huge potential amount of profit. However, when they lack the capability to finish the construction activities by themselves it would be another story. Usually they have to choose appropriate subcontractors to do the unfinished job. Subcontractors may be various from experience, cost, time, quality and many other factors which can have impacts on the selection by a main contractor on a certain project. How to choose subcontractors wisely has become a hotspot issue to many construction companies. Many literatures have recorded the attempts to select subcontractors with a consideration of as many possible factors as they can. Some of them are connected with mathematical models and algorithms. This paper is on the purpose of optimizing the selection of subcontractors on the basis of existing methods---the Branch and Bound algorithm. So a literature review is given after stating the problem. And a numerical example is also included to better explain the optimization process. PROBLEM STATEMENT Nowadays construction companies are working so hard to make a living through the fierce competition. It is always a good news for a construction company to win a bid by defeating all the
  • 3. 3 competitors. However, as the rapid development of construction industry, construction projects nowadays are becoming bigger and harder than before. Main contractors in today’s construction industry cannot complete the entire construction projects on their own. Some projects are so complicated that they need contractors with specific previous working experience. So it is necessary to subcontract some parts of the construction projects to competitive subcontractors. Here comes the question, how to choose subcontractors wisely? Many literatures have already recorded attempts to assisting the selection of subcontractors by using various mathematical algorithms and computer models. But they all have their limitations. Some of them are not as accurate as people think. So in this paper, the main purpose is to optimize the existing method by doing literature review and modifications. To optimize the selection process is so important that it should catch people’s attention. It is known that there are so many candidates in the market with different construction background and experience. If the main contractor chooses an appropriate subcontractor, the construction activity could be completed ahead of schedule and under the budget. Instead, a wrong candidate may result
  • 4. 4 in various possible troubles like short of experience, poor construction quality or some other potential conflicts. Therefore, the optimization of subcontractor selection is of great significance to all the main contractors. This paper selects a branch and bond algorithm as a basis to explore the further optimization of subcontractors in construction industry. The issue is to review the original models and equations, and find out which part of the original model can be improved. Although there are many possible factors which may have impacts on the selection like the relationship between contractors, the working experience and construction quality, the paper only chooses the most important factors to do the optimization, project schedule and overall cost. Construction quality is not discussed here because it is too subjective to get a quantitative measure. OBJECTIVES The objective of this paper is to study the existing subcontractor selection method by doing literature review. After that try to optimize it by make some modifications to the original models and develop a new model to solve the problem.
  • 5. 5 BRANCH AND BOUND ALGORITHM (BB) In this paper, a Branch and Bound algorithm is selected as the basis of optimization. The Branch and Bound algorithm (BB) is an algorithm designed for optimization problems. As it is named, the Branch and Bound algorithm (BB) is used to present all the feasible solutions of a problem into branches of a tree. And the optimal solution could be found through those branches. The basic idea of the Branch and Bound algorithm (BB) is the solution space reduction. A problem which has several constraints can be treated like a certain space. The solution is in that space. To find out the solution among other options rapidly, the space should be reduced. When operating the Branch and Bound algorithm (BB), the space of all the feasible solutions is divided into many subsets like branches. And calculate the thresholds or the upper and lower bounds for those feasible solutions in each branch. After that, abandon those branches whose bonds are already out of the range. Then the solution space will be decreased. Keep doing this until find out the optimal solution. The selection of subcontractors can be transferred into this Branch and Bound algorithm (BB) problem. Each subcontractor has a construction time and project cost. They are put into the Space. After solution space reduction, the optimal subcontractor can be found by using different bonds.
  • 6. 6 LITERATURE REVIEW 1. The paper by (Talluri, Baker, & Sarkis, 1999) first realize the importance of selecting appropriate partner for the job and propose a two phase quantitative framework to optimize the partner selection problems. In the first phase, data envelopment analysis is utilized to determine possible candidates for each type of work. Then in the second phase, an integer goal programming model is introduced to select which possible candidate is the most appropriate. But there are some limitations exposed during the optimization process. When imputing initial data, the data may not be that accurate because it is obtained via an optimization which makes the solution a sub-optimal one. Also when considering the factors affecting the partner selection, the realistic situation seems more complicated than the assumptions. So this model needs further modifications to be applied to the current situation. 2. The paper by (Ip, Yung, & Wang, 2003) presents a branch and bound algorithm solution for sub-contractor selection in agile manufacturing environment. They embed the project
  • 7. 7 schedule into the branch and bound algorithm models. To solve this problem, they separate it into two levels. The first level is to use branch and bonds to choose optimal subcontractors. Then the second level is to schedule the project and minimize the loan interest. At the beginning they define a concept called objective value Z(x) considering both money requirement and project completion time. Then they sequence the activities according to the means of the bid costs. After initial bounds and search index are set, they start to use Branch and Bound Algorithm to search for the optimal solution. The principle of Branch and Bound Algorithm (BB) is the solution space reduction by cutting branches. In each branch, one activity is assigned to a candidate contractor. After calculating the objective value Z(x) they compare it with the Bound. The branch would be abandoned if the objective value Z(x) is more than the Bound. If it is not, the branch would go on and go to the next step.
  • 8. 8 PROPOSED METHODOLOGY The proposed methodology incorporates two new performance indices for cost and time namely Cost performance index (Cpi) and Time performance index (Tpi). The way these indices would be quantified is purely based on past performances of the subcontractors. Now this past information is really important for our factors. Generally, if a contractor has a working experience with multiple subs, the contractor can easily acquire this information. Even if there is a sub-contractor who is working for the first time with the contractor, this would not necessarily mean that the sub-contractor is new to the field, just that it is the first time the duo is working together. Even for sub-contractors like this the historical data can be obtained by analyzing their past construction works. This way no assumptions would have to be made and all the data would be easily available too. But if a sub-contractor is however new to the construction field, this model cannot be applied to them. But it is very unlikely that a contractor will even consider an inexperienced sub-contractor for such a huge project, almost all the sub- contractors considered would be highly experienced professionals. And therefore we do not need to worry about applying our model to brand new sub-contractors.
  • 9. 9 The concept is that, for every 1% increase or decrease in the scheduled cost or time of the subcontractors, based on the past performances, we would assign them an increased or decreased Cpi and Tpi. Now these past records taken would be averaged and used. For example, if the subcontractor has been delayed by 10% time for one project and 5% time for another, the average taken would be 7.5%. And thus an increase in the bid time for this subcontractor would be made by 7.5%. The same would be done for the cost aspect based on their cost performances. The main objective here is to select the optimal combination of subcontractors so that we can minimize the time and cost for all the jobs in the project. For example, if we were to select one of three subcontractors for an activity (say excavation) we would have the following information: Subcontractor 1 2 3 Job Excavation Excavation Excavation Time 5 days 4 days 3 days Cost $20,000 $22,500 $25,000
  • 10. 10 However, after applying Cpi and Tpi, these numbers will change: Subcontractor 1 2 3 Job Excavation Excavation Excavation Time 5 days 4 days 3 days Cost $20,000 $22,500 $25,000 Past performances Avg time delay of 10% Avg cost increase by 10% Avg time cut short by 5% Avg cost increase by 5% Avg time cut short by 10% On average always on budget Cpi influenced Cost value 20k x Cpi = 20k x 1.1 = 22k 22k x Cpi = 22k x 1.05 = 23.1k 25k x Cpi = 25k x 1 = 25k Tpi influence Time value 5 x Tpi = 5 x 1.1 = 5.5 days 4 x Tpi = 4 x 0.95 = 3.8 days 3 x Tpi = 3 x 0.9 = 2.7 days Now that we have seen what the factors are about, we will look into the existing model proposed by Ip, Yung and Wang and how we influence and further optimize it. Since sub-projects contracted by partners consist of an activity network with precedence, each partner works in the project as a ring in a chain (Elmaghraby, 1977). Because the main contractor
  • 11. 11 gets paid in installments, this can be considered as the cash flow. This investment cannot always meet the requirements from the sub-project contractors and thus the main contractor often takes a loan of certain amount from the bank and pay them interest. Because of the complexity of the selection of the sub-contractor, it is not easily solved by general mathematical programming methods. However, Branch and Bound method is powerful tool to solve this kind of combinatorial optimizations (Taha, 1975). The model proposed by Ip, Yung and Wang is described as follows: 1. Problem and model of sub-contractor selection 2. Inefficient and ideal candidates 3. Branch and bound algorithm embedded project scheduling 4. Numerical analysis Problem and model of sub-contractor selection: All the notations are listed below: n = number of jobs included in project D = due-date of project
  • 12. 12 b = penalty cost for tardiness of a period a = rate of first payment to sub-contractors r = interest rate of loan from bank f(t) = cash flow paid to the main contractor by the project owner in period t F = total investment for the project from owner (i.k) = connected job pair H = set of all connected job pairs mi = number of candidates bidding for job i bij = bid cost of candidate j for job i pij = bid completion time of candidate j for job i Cpij = cost performance index of candidate j for job i Tpij = time performance index of candidate j for job i (The above mentioned factors are what we plan to introduce to the model). cn = completion time of final job, i.e. the completion time of the project xij = 0–1 assignment variable. xij = 1 means the job i is contracted to j
  • 13. 13 x = matrix variable for all xij: It is a completed selection Z(x) = objective value achieved by selection x si = beginning time of job i in selection x ci = completion time of job i in selection x Ok = index of job sequenced at kth place with the kth larger mean cost I(Ok) = assigned candidate index of job Ok (the job at the k-place in the sequence) (Ip, Yung, & Wang, 2003) The sub-contractor selection problem is stated as: say the main contractor wins a bid for a big project and is not able to complete the whole project by its own capacity and resources, therefore subcontracting a number of sub projects. The objective here is to select an optimal combination of sub-contractors for all the jobs such as to minimize the total cost and time. Defining the variables, xij(t) = 1, job i is contracted to candidate j and begins at period t 0, otherwise
  • 14. 14 Then the problem can be described by the following model (adding Cpij and Tpij where needed) (Ip, Yung, & Wang, 2003) The factors Cpij and Tpij have been added to the existing models and were not a part of the model before. So whenever the model uses a cost factor, we multiply the cost performance index to modify and further optimize the solution. Same is done for the time factor. Inefficient and ideal candidates: Since the size of the solution space is, It clearly shows that even for a small scale problem with 10 jobs and 3 candidates the solution min x Z(x) = bijCpij xij t=1 cn ∑ j=1 mi ∑ i=1 n ∑ (t) +r α bijCpij xij (τ )+ (1−α) bijCpij xij (τ − pijTpij )− f (τ ) τ =1 t ∑ τ =1 t ∑ j=1 mi ∑ i=1 n ∑ τ =1 t ∑ j=1 mi ∑ i=1 n ∑ ⎡ ⎣ ⎢ ⎤ ⎦ ⎥ t=1 cn ∑ + + β cn − D[ ]+ s.t. xij (t) = 1,i = 1,2,...,n, t=1 cn ∑ j=1 mi ∑ (t + pijTpij )xij (t) t=1 cn ∑ j=1 mi ∑ ≤ txkj (t),∀(i,k) ∈H t=1 cn ∑ j=1 mk ∑ (t + pnjTpij )xnj (t) = cn t=1 cn ∑ j=1 mn ∑ , xij (t) = 1or0,∀i, j,t, N = i=1 n Πmi
  • 15. 15 space is very large, 310 = 59,049. This is too high a number and therefore a reduction in the solution space is required. This reduction comes in the format of a theorem used by Ip et al, which says, the candidate j of job I is inefficient if there exists a candidate k for the same job with, bik £ bij, pik < pij or bik < bij, pik £ pij (Ip, Yung, & Wang, 2003). Using this theorem, we can ignore all inefficient candidates without the loss of an optimal solution and thus the solution space is reduced considerably. Branch and bound algorithm embedded project scheduling: The idea of the proposed branch and bound algorithm is to select the optimal partner combination by branch and bound at the first level of algorithm and to schedule all jobs with a fixed partner combination at the second level (Ip, Yung, & Wang, 2003). Numerical Analysis: The algorithm was coded by Ip et al on FORTRAN and run on a Pentium II/366 machine and satisfactory results were achieved. The example they took was a real life construction problem of the construction of a coal-fire power station. Atotal of 16 jobs were set and a due date of 36 months was also set. Additional details are: loan interest rate = 0.6% per month, 55% payment for all jobs
  • 16. 16 will be made in advance and the rest of the payment when the job was done. A total investment of $72.75 million was to be made. Table 1: The job list and the cost and time values for each job Number Job Cost (million $) Time (months) 1 Total design of system 2.75 6 2 Design of railway for coal 0.3 4 3 Construction of railway 3.75 10 4 Design of boiler system 1.75 6 5 Manufacturing of boilers 18.5 12 6 Design of buildings 2 6 7 Construction of buildings 6.5 10 8 Design of generators 1.5 6 9 Design of electric transmission 1.5 6 10 Manufacturing of generators 13.5 12 11 Assembling of boilers 1 3 12 Manufacturing of transmission equipment 6.75 12 13 Design and assembly of computer control system 7 16 14 Assembling of generators 1.25 3 15 Assembling of transmission system 1.75 3 16 System inspection and test running 3 5
  • 17. 17 Table 2: Number of candidates for the job Job Number of candidates 1 4 2 6 3 5 4 2 5 2 6 7 7 4 8 8 9 3 10 4 11 5 12 3 13 6 14 3 15 4 16 2 Table 3: List of candidates for each job Job number Candidate code Cost (million $) Time (months) A1 2.7 4 A2 2.4 5 1 A3 2.175 5 A4 1.8 6
  • 18. 18 B1 0.285 4 B2 0.3 3 B3 0.375 3 2 B4 0.27 5 B5 0.225 6 B6 0.33 3 C1 3 12 C2 3.375 11 3 C3 3.75 10 C4 4.05 8 C5 2.775 13 4 D1 1.5 6 D2 1.8 4 5 E1 18 12 E2 19.5 10 F1 1.8 4 F2 2.1 4 F3 1.5 5 6 F4 2.175 3 F5 1.2 7 F6 1.35 6 F7 1.05 8 G1 1.8 5 7 G2 2.1 4
  • 19. 19 G3 1.5 7 G4 1.2 8 H1 5.25 12 H2 4.5 13 H3 5.7 11 8 H4 6 10 H5 7.2 8 H6 6.75 8 H7 6.3 10 H8 6.45 10 I1 1.65 5 9 I2 1.2 7 I3 1.8 4 J1 14.7 10 10 J2 13.2 12 J3 12 13 J4 15.75 8 K1 0.9 3 K2 0.75 3 11 K3 1.05 2 K4 0.6 4 K5 0.825 3 L1 6 12 12 L2 5.7 14
  • 20. 20 L3 7.2 10 M1 4.5 18 M2 5.7 17 M3 7.5 12 13 M4 8.25 10 M5 9 8 M6 7.2 15 N1 1.2 4 14 N2 1.8 2 N3 1.5 3 P1 1.8 2 15 P2 1.5 3 P3 1.2 3 P4 0.9 5 16 Q1 2.4 6 Q2 3 5 Now, the model runs the mentioned values and tries to optimize the sub-contractor selection based on the values of their individual cost and time of completion. We can clearly see here how much focused this model is on these time-cost values. So when run by the model, an optimal selection of sub-contractors for respective jobs is achieved.
  • 21. 21 Table 4: The sub-contractors of optimal solution The solution by Ip et al of above data set with the model resulted in the following optimal solution: Job number Sub- contractor Cost (million $) Proc. Time Beginning time Time of completion 1 A1 2.7 4 1 5 2 B2 0.3 3 1 4 3 C5 2.775 13 4 17 4 D2 1.8 4 5 9 5 E1 18 12 13 25 6 F7 1.05 8 9 17 7 G2 2.1 4 9 13 8 H6 6.75 8 17 25 9 I3 1.8 4 13 17 10 J3 12 13 14 27 11 K3 1.05 2 25 27 12 L1 6 12 17 29 13 M3 7.5 12 19 31 14 N2 1.8 2 27 29 15 P1 1.8 2 29 31 16 Q2 3 5 31 36 In this solution we can see that the optimal selection of sub-contractors is satisfactory since all the jobs are completed within the duration of 36 months and with a budget of $70.5 million. So the contractor makes a profit of $2.25 million.
  • 22. 22 But imagine if some of these sub-contractors fail to deliver on time or within the budget. If that happens, and there is a reasonable probability that it could happen, the contractor’s profit will end up being reduced and he might have to pay the tardiness penalty as well. This would seriously impact the profit of the project and make the entire project a failed venture. Now here is where our factors for cost and time performance (Cpi and Tpi) come in. We multiply the existing time and cost promised by each sub-contractor by their individual cost and time performance index. This gives us their updated cost and time for completion of the activity. For example, for job 1 four sub-contractors had submitted their cost and time values as below: Job number Candidate code Cost (million $) Time (months) A1 2.7 4 A2 2.4 5 1 A3 2.175 5 A4 1.8 6 But this model did not consider their past performance, and now if we do, suppose for example, all four candidates have the following past performances:
  • 23. 23 Candidate code Time performance Cost performance A1 On average the candidate has been 5% behind schedule; Tpi = 1.05 On average the candidate has always been on budget; Cpi = 1 A2 On average the candidate has been 10% behind schedule; Tpi = 1.10 On average the candidate has been 5% over budget; Cpi = 1.05 A3 On average the candidate has been 5% ahead of schedule; Tpi = 0.95 On average the candidate has been 3% over budget; Cpi = 1.03 A4 On average the candidate has been 10% ahead of schedule; Tpi = 0.9 On average the candidate has been 10% over budget; Cpi = 1 And thus the new values for time and cost of the four candidates will be: Job number Candidate code Cost (million $) Cpi Influenced cost Time (months) Tpi influenced time A1 2.7 x 1 = 2.7 4 x 1.05 = 4.2 1 A2 2.4 x 1.05 = 2.52 5 x 1.10 = 5.5 A3 2.175 x 1.03 = 2.24 5 x 0.95 = 4.75 A4 1.8 x 1.1 = 1.98 6 x 0.9 = 5.4
  • 24. 24 Now if these values are used to optimize the selection, it will definitely influence the results and new sub-contractors may get selected based on their efficient past performances. This is because the model heavily focuses on the cost and time performance of each candidate, and if those values are influenced, the result will undoubtedly be influenced and further optimized because these new values would be more realistic and accurate. By using these factors to update the model, we somewhat eliminate any surprises that might come from the sub-contractors and make sure that our end profit is secure and maximum. This is the whole idea behind our updated model. Because the model is so heavily focused on the values of cost and time, if we influence those values, we will influence the result. Similarly, if we can further optimize the time and cost values, we will further optimize the model and thus the final solution.
  • 25. 25 EXPECTED CONTRIBUTION The existing model is designed to select an optimal group of sub-contractors based on their time and cost bids for the job. However, the model doesn’t take into account the historical data of the past performances of these individual candidates. That is what this paper proposes. The contribution we expect to impart is that when optimizing such models to get such a group of sub- contractors, each of them be judged on the past performances too. This way many judgmental errors and time delays can be avoided even before the construction starts. If we look at the industry at large, this would be beneficial to any party which tries to optimize its sub-contractor selection by updating their model with cost and time performance indices. It would result in a huge amount of cost savings and more importantly the saving of time.
  • 26. 26 References Elmaghraby, S. E. (1977). Activity Networks - Project Planning and control by Network Models. New York, NY, USA: Wiley, New York. Ip, W., Yung, K., & Wang, D. (2003). Branch and Bound algorithm for sub-contractor selection in agile manufacturing environment. The Hong Kong Polytechnic Unversity , Department of Manufacturing Engineering. Hong Kong: Elsevier. Taha, H. (1975). Integer Programming Theory, Applications and Computations. New York, NY, USA: Academic Press. Talluri, S., Baker, R., & Sarkis, J. (1999). A framework for designing efficient value chain networks. International Journal of Production Economics, Elsevier.