SlideShare a Scribd company logo
1 of 43
Dr K M Soni
Chief Engineer, WZ-I, CPWD, Mumbai
Disputes are part of life.
Disputes are time immemorial.
Disputes are resolved through
negotiation, mediation,
arbitration, courts.
Disputes cannot be stopped
altogether.
Disputes can be avoided.
Disputes can be resolved.
Generally all the parties are
ultimately at loss involving in
disputes
 A contract is a written agreement.
 The agreement includes specifications,
items, terms and conditions and drawings.
 The employer is aware of its requirements.
 The contractor is aware of requirements as
he quotes the rates and also obtains
clarifications during pre-bid meetings.
 Thus disputes are not due to written
provisions but “not written”.
 Agreement
 In many places, even agreements do not
include complete items and dispute may not
arise.
 Employer and Contractor
 Reason of dispute is “Loss or Profit” i.e.
Money.
 The contractor quoting low and unworkable
rates.
 The contractor having quoted low/unworkable
rates carries out sub standard work.
 The contractor having quoted low/unworkable
rates for the items to be executed towards the
end of contract period wants to withdraw from
execution of those items.
 The contractor has quoted low/unworkable
rates for some items and wants to get them
substituted or does not want to execute.
Disputes due to “loss/profit” or money
• The market rates have gone up.
• The employer is not making payment in time
and contractor has to pay interest on capital.
• The employer is not making payments to some
of the items.
• The employer is delaying the payment.
• The employer is delaying the measurements or
not allowing to execute some items resulting
into idle machinery/equipment/establishment.
• Withholding money due to different reasons
like milestones, QA, approvals, EOT etc.
• The contractor expecting additional money due
to lacunae in the framing of agreement or
conditions.
Disputes due to “loss/profit” or money
• The Employer is at loss due to sub
standard work.
• The contractor refusing to execute
the items for which he has quoted
low/unworkable rates while high
profitable items executed.
• Loss due to delay in completion of
work, assets not being put to use.
Before award of work
Immediately or on award of
work
During execution
After completion of work
 Mainly from contractor’s side.
 Due to denial of issue of tender
documents
 Due to non opening of particular tender
or opening of particular tender.
 Due to rejection of particular tender.
 Rejection of technical bids.
 Forfeiture of earnest money (bid
security)
 E –tendering
 Abiding to the provisions of tender /bid
documents (No discretion).
 Transparency and equal opportunity to
all bidders.
 Intimation to bidders about the status.
Disputes Immediately or on award of work
• From contractor’s side.
• Due to low/unworkable rates quoted by
the contractor.
Disputes Immediately or on awardof work due to delay
causedby the contractor
• Due to inadequate resources
• Due to taken up works beyond the
capacity.
• To gain time to augment resources.
• To gain time to sublet the work.
• To delay the work in the
expectations not to execute the
items to be taken in the last.
Disputes Immediately or on award of work
• From contractor’s side.
• Due to encumbered site
• Due to non availability of drawings
• Due to non availability of approvals
• Due to non availability of budget.
Disputes AVOIDANCE
• From contractor’s side.
• Due to encumbered site
• Please do not invite tenders
• Due to non availability of drawings
• Please availability of drawings in
time or before time
• Due to non availability of approvals
• Please ensure all approvals from
local bodies/govt.
• Due to non availability of budget.
• Please co-ordinate with the client
 Due to non-availability of drawings
 Due to non-availability of stipulated materials
 Due to delayed payments
 Due to non completion of works by associated
agencies
 Due to delayed payments
 Due to admissibility of payments of certain
items
 Due to non approvals of payments of certain
items (deviations/EI/SI)
 Due to suspension of work
 Due to delayed decisions
 Due to non-availability of drawings
 Make available on time or before time
 Due to non-availability of stipulated materials
 Please avoid stipulation
 Due to delayed payments
 Due to non preparation/processing of bills or availability of
budget
 Due to non completion of works by associated agencies
 Please monitor the work of associated agencies or switch over
to composite tenders
 Due to admissibility of payments of certain items
 Do not throw on others or delay the decisions
 Due to non approvals of payments of certain items (deviations/EI/SI)
 Please monitor and accord approvals in time. Take prior
approvals.
 Due to suspension of work
 Due to delayed decisions
All disputes arisen during
execution
Due to idle T & P, Establishment,
liquidated damages, loss of profit,
interest etc.
Please use conciliation clause in
agreement and resolve disputes
before completion
Resolve issues which can be before
appointment of arbitrator and do
not leave on arbitrator to decide
even those which can be resolved.
Appoint arbitrator if required
within time
Disputes fromCommencement of work
Dispute after commencementof work
with or WithoutADR mechanisms
 Take right decisions at right time
 “Prevention is better than cure…The size
and complexity of many programmes of
work mean that disputes are still likely to
happen, but up front work can help avoid
as many as possible.”
The disputes can’t be eliminated,
but it can be effectively mitigated
Manage disputes as early as
possible for mitigation
If not mitigated, take effective
steps timely before arbitrator.
 “Arbitration agreement" means an agreement by the parties
to submit to arbitration all or certain disputes which have
arisen or which may arise between them in respect of a
defined legal relationship, whether contractual or not.
 An arbitration agreement may be in the form of an
arbitration clause in a contract or in the form of a separate
agreement.
 An arbitration agreement shall be in writing.
 An arbitration agreement is in writing if it is contained in-
 (a) a document signed by the parties; (b) an exchange of letters,
telex, telegrams or other means of telecommunication which
provide a record of the agreement; or (c) an exchange of
statements of claim and defence in which the existence of the
agreement is alleged by one party and not denied by the other.
 The reference in a contract to a document containing an
arbitration clause constitutes an arbitration agreement if
the contract is in writing and the reference is such as to
make that arbitration clause part of the contract.
 The parties are free to determine the number of
arbitrators, provided that such number shall not be
an even number. Failing the determination referred
here, the arbitral tribunal shall consist of a sole
arbitrator.
 Appointment of arbitrators.- (1) A person of any
nationality may be an arbitrator, unless otherwise
agreed by the parties.
 Subject to sub-section (6) of the Act, the parties are
free to agree on a procedure for appointing the
arbitrator or arbitrators.
 Failing any agreement referred to above, in an
arbitration with three arbitrators, each party shall
appoint one arbitrator, and the two appointed
arbitrators shall appoint the third arbitrator who shall
act as the presiding arbitrator.
 If a party fails to appoint an arbitrator
within thirty days from the receipt of a
request to do so from the other party; or
 the two appointed arbitrators fail to agree
on the third arbitrator within thirty days
from the date of their appointment,
 Circumstances exist that give rise to
justifiable doubts as to his independence or
impartiality, or
 he does not possess the qualifications agreed
to by the parties.
 A party may challenge an arbitrator
appointed by him, or in whose appointment
he has participated, only for reasons of
which he becomes aware after the
appointment has been made.
 Equal treatment of parties.- The parties shall be treated with
equality and each party shall be given a full opportunity to
present his case.
 Determination of rules of procedure.- (1) The arbitral tribunal
shall not be bound by the Code of Civil Procedure, 1908 or the
Indian Evidence Act, 1872. Subject to this Part, the parties are
free to agree on the procedure to be followed by the arbitral
tribunal in conducting its proceedings. Failing any agreement
referred to in the sub-section, the arbitral tribunal may, subject
to this Part, conduct the proceedings in the manner it considers
appropriate.
 The power of the arbitral tribunal includes the power to
determine the admissibility , relevance, materiality and weight
of any evidence.
 Place of arbitration.- The parties are free to agree on the place
of arbitration. Failing any agreement referred to in this sub-
section, the place of arbitration shall be determined by the
arbitral tribunal having regard to the circumstances of the case,
including the convenience of the parties.
 Definition and Meaning of conciliation-
The simplest meaning of conciliation is the settlement of
the disputes outside the court .It is a process by which the
discussion between the parties are kept going through the
participation of a conciliator. Conciliation is one of the non
binding procedures where an impartial third party, known
as the conciliator, assist the parties to a dispute in
reaching a mutually agreed settlement of the dispute. As
per the Halsbury Laws of England, conciliation is a process
of persuading parties to each an agreement. Because of its
non judicial character, conciliation is considered to be
fundamentally different from that of litigation. Generally
Judges and Arbitrators decide the case in the form of a
judgment or an award which is binding on the parties while
in the procedure of the conciliation ,the conciliator who is
often a government official gives its report in the form of
recommendations which is made public.
 Section 61 of the Arbitration and Conciliation Act of 1996
provides for the Application and Scope of Conciliation.
Section 61 points out that the process of conciliation
extends, in the first place, to disputes, whether
contractual or not. But the disputes must arise out of the
legal relationship. It means that the dispute must be such
as to give one party the right to sue and to the other party
the liability to be sued. The process of conciliation
extends, in the second place, to all proceedings relating to
it. But Part III of the Act does not apply to such disputes as
cannot be submitted to conciliation by the virtue of any
law for the time being in force.
Number and qualification of conciliators-Section 63 fixes
the number of conciliators. There shall be one conciliator.
But the parties may by their agreement provide for two or
three conciliators. Where the number of conciliator is
more than one ,they should as general rule act jointly.
 Section 64 deals with the appointment of the
conciliators.When the invitation to the conciliation is
accepted by the other party, the parties have to agree on
the composition of the conciliation tribunal. In the
absence of any agreement to the contrary ,there shall be
only one conciliator. The conciliation proceeding may be
conducted by a sole conciliator to be appointed with the
concent of both the parties, failing to which the same may
be conducted by two conciliators (maximum limit is
three), then each party appoints own conciliator ,and the
third conciliator is appointed unanimously by both the
parties. The third conciliator so appointed shall be the
presiding conciliator. The parties to the arbitration
agreement instead of appointing the conciliator
themselves may enlist the assistance of an institution or
person of their choice for appointment of conciliators. But
the institution or the person should keep in view during
appointment that, the conciliator is independent and
impartial.
 1) Independence and impartiality [Section 67(1)]-
The conciliator should be independent and impartial. He should assist the parties in an
independent and impartial manner while he is attempting to reach an amicable settlement of
their dispute.
2) Fairness and justice[Section 67(2)]-
The conciliator should be guided by the principles of fairness and justice. He should take into
consideration ,among other things , the rights and obligations of the parties, the usages of the
trade concerned ,and the circumstances surrounding the dispute ,including any previous
business practices between the parties.
3) Confidentiality [Section 70]-
The conciliator and the parties are duly bound to keep confidential all matters relating to
conciliation proceedings. Similarly when a party gives a information to the conciliator on the
condition that it be kept confidential , the conciliator should not disclose that information to
the other party.
4) Disclosure of the information[Section 70]-
When the conciliator receives a information about any fact relating to the dispute from a
party , he should disclose the substance of that information to the other party.The purpose of
this provision is to enable the other party to present an explaination which he might consider
appropriate.
5) Co-operation of the parties with Conciliator [S. 71]-
The parties should in good faith cooperate with the conciliator. They should submit the
written materials , provide evidence and attend meetings when the conciliator requests them
for this purpose.
 Commencement of the conciliation proceedings
[Section 62]-
The conciliation proceeding are initiated by one party
sending a written invitation to the other party to
conciliate. The invitation should identify the subject
of the dispute. Conciliation proceedings are
commenced when the other party accepts the
invitation to conciliate in writing. If the other party
rejects the invitation, there will be no conciliation
proceedings. If the party inviting conciliation does
not receive a reply within thirty days of the date he
sends the invitation or within such period of time as
is specified in the invitation, he may elect to treat
this as rejection of the invitation to conciliate. If he
so elects he should inform the other party in writing
accordingly.
 Submission of Statement to Conciliator [Section 65]
–
The conciliator may request each party to submit to
him a brief written statement. The statement should
describe the general nature of the dispute and the
points at issue. Each party should send a copy of such
statement to the other party. The conciliator may
require each party to submit to hima further written
statement of his position and the facts and grounds in
its support. It may be supplemented by appropriate
documents and evidence. The party should send the
copy of such statements , documents and evidence to
the other party. At any stage of the conciliation
proceedings , the conciliator may request a party to
submit to him any additional information which he
may deem appropriate.
 Conduct of Conciliation Proceedings[Section
69(1),67(3)]-
The conciliator may invite the parties to meet
him. He may communicate with the parties
orally or in writing. He may meet or
communicate with the parties together or
separately. In the conduct of the conciliation
proceedings, the conciliator has some freedom.
He may conduct them in such manner as he may
consider appropriate. But he should take in
account the circumstances of the case, the
express wishes of the parties, a party’s request
to beheard orally and the need of speedy
settlement of the dispute.
 Administrative assistance [S. 68]-
Section 68 facilitates administrative
assistance for the conduct of conciliation
proceedings. Accordingly , the parties and
the conciliator may seek administrative
assistance by a suitable institution or the
person with the consent of the parties.
 Haresh Dayaram Thakur v. State of Maharashtra and Ors. while
dealing with the provisions of Sections 73 and 74 of the Abbitration
and Conciliation Act of 1996 in paragraph 19 of the judgment as
expressed thus the court held that-
"19. From the statutory provisions noted above the position is
manifest that a conciliator is a person who is to assist the parties to
settle the disputes between them amicably. For this purpose the
conciliator is vested with wide powers to decide the procedure to be
followed by him untrammeled by the procedural law like the Code
of Civil Procedure or the Indian Evidence Act, 1872. When the
parties are able to resolve the dispute between them by mutual
agreement and it appears to the conciliator that their exists an
element of settlement which may be acceptable to the parties he is
to proceed in accordance with the procedure laid down in Section
73, formulate the terms of a settlement and make it over to the
parties for their observations; and the ultimate step to be taken by
a conciliator is to draw up a settlement in the light of the
observations made by the parties to the terms formulated by him.
The settlement takes shape only when the parties draw up the
settlement agreement or request the conciliator to prepare the
same and affix their signatures to it. Under Sub-section (3) of
Section 73 the settlement agreement signed by the parties is final
and binding on the parties and persons claiming under them. It
follows therefore that a successful conciliation proceedings comes
to end only when the settlement agreement signed by the parties
comes into existence. It is such an agreement which has the status
and effect of legal sanctity of an arbitral award under Section 74”.
 In Mysore Cements Ltd. v. Svedala Barmac Ltd it was said that
Section 73 of the Act speaks of Settlement Agreement. Sub-
section (1) says that when it appears to the Conciliator that there
exist elements of settlement which may be acceptable to the
parties, he shall formulate the terms of a possible settlement
and submit them to the parties for their observation. After
receiving the observations of the parties, the Conciliator may
reformulates the terms of a possible settlement in the light of
such observations. In the present case, we do not find there any
such formulation and reformulation by the Conciliator, under Sub-
section (2), if the parties reach a settlement agreement of the
dispute on the possible terms of settlement formulated, they
may draw up and sign a written settlement agreement. As per
Sub-section
(3) when the parties sign the Settlement Agreement, it shall be
final and binding on the parties and persons claiming under them
respectively. Under Sub-section (4), the Conciliator shall
authenticate the Settlement Agreement and furnish a copy
thereof to each of the parties. From the undisputed facts and
looking to the records, it is clear that all the requirements of
Section 73 are not complied with.
 Electronic Communication
 Copy of the Agreement by respondents
 Disclosure by the arbitrator of his relation with any party
 Commencement of arbitral proceedings within a fixed period
 Time Limit of the appointment of arbitrator
 Fee of the Arbitration
 Submission of Counter Claims
 Frequent Adjournments at cost
 Time Limit for the Award given
 Provision of Fast Track Proceedings included
 Interest on Award mentioned and linked to current
prevailing rate
 Cost of Arbitration based on circumstances and conduct of
parties
 Explanation of Public Policy
 The process of conciliation as an alternate dispute redressal mechanism
is advantageous to the parties in the sense that it is cost effective and
expeditious, it is simple,fast and convenient then the lengthy litigation
procedure and it eliminates any scope of biasness and corruption. The
parties who wish to settle their disputes they can be provided great
intensive by the process of conciliation. In order to enable the conciliator
to play his role effectively ,the parties should be brought together face
to face at a common place where they can interact face to face and with
the conciliator, separately or together without any distraction and with
only a single aim to sincerely arrive at the settlement of the dispute.
Conciliation is a boon and it is a better procedure to settle any dispute as
in this process it is the parties who by themselves only come to the
settlement of the dispute and the role of the conciliator is to bring
parties together and to make a atmosphere where parties can themselves
resolve their disputes. Conciliation tries to individualize the optimal
solution and direct parties towards a satisfactory common agreement. In
conciliation, the conciliator plays a relatively direct role in the actual
resolution of a dispute and even advises the parties on certain solutions
by making proposals for settlement. Thus I would like to conclude with a
saying: Do conciliate, therefore ,whenever there are differences ,and
sooner it is done ,the better.

More Related Content

What's hot

What's hot (20)

Dr Mohan R Bolla on Institutional arbitration
Dr Mohan R Bolla on Institutional arbitration Dr Mohan R Bolla on Institutional arbitration
Dr Mohan R Bolla on Institutional arbitration
 
064 po in adr
064 po in adr064 po in adr
064 po in adr
 
Drafting Arbitration Clause
Drafting Arbitration ClauseDrafting Arbitration Clause
Drafting Arbitration Clause
 
Arbitration
ArbitrationArbitration
Arbitration
 
Bus law arbitration
Bus law  arbitrationBus law  arbitration
Bus law arbitration
 
Arbitration act unit-7
Arbitration act unit-7Arbitration act unit-7
Arbitration act unit-7
 
Arbitration Act in Bangladesh
Arbitration Act in BangladeshArbitration Act in Bangladesh
Arbitration Act in Bangladesh
 
Arbitration
ArbitrationArbitration
Arbitration
 
Appointment of arbitrator as per The Arbitration and Conciliation (Amendment)...
Appointment of arbitrator as per The Arbitration and Conciliation (Amendment)...Appointment of arbitrator as per The Arbitration and Conciliation (Amendment)...
Appointment of arbitrator as per The Arbitration and Conciliation (Amendment)...
 
Arbitation , conciliation
Arbitation , conciliationArbitation , conciliation
Arbitation , conciliation
 
Law arbiration
Law arbirationLaw arbiration
Law arbiration
 
Arbitration
ArbitrationArbitration
Arbitration
 
Arbitration Agreements
Arbitration AgreementsArbitration Agreements
Arbitration Agreements
 
Arbitration
ArbitrationArbitration
Arbitration
 
Arbitration & its types
Arbitration & its typesArbitration & its types
Arbitration & its types
 
International commercial arbitration under the icc rules a critical view
International commercial arbitration under the icc rules  a critical viewInternational commercial arbitration under the icc rules  a critical view
International commercial arbitration under the icc rules a critical view
 
conciliation ppt
conciliation pptconciliation ppt
conciliation ppt
 
Arbitration Overview
Arbitration OverviewArbitration Overview
Arbitration Overview
 
Law of Arbitration by Niddhi Parmar
Law of Arbitration by Niddhi ParmarLaw of Arbitration by Niddhi Parmar
Law of Arbitration by Niddhi Parmar
 
Arbitration ppt mba
Arbitration ppt  mbaArbitration ppt  mba
Arbitration ppt mba
 

Viewers also liked

Crdamc civilian payroll_employee_crisis
Crdamc civilian payroll_employee_crisisCrdamc civilian payroll_employee_crisis
Crdamc civilian payroll_employee_crisisslappedsilly39
 
Comp1ad presentation
Comp1ad presentationComp1ad presentation
Comp1ad presentationjctg88
 
Accelerating Growth by moving to the cloud keynote - #TheFutureOfCloud
Accelerating Growth by moving to the cloud keynote - #TheFutureOfCloudAccelerating Growth by moving to the cloud keynote - #TheFutureOfCloud
Accelerating Growth by moving to the cloud keynote - #TheFutureOfCloudm-hance
 
power point
power pointpower point
power pointliliana
 
Pyramid Consulting Brochure
Pyramid Consulting BrochurePyramid Consulting Brochure
Pyramid Consulting BrochureSherif Farghal
 
Improve Your Understanding in German History 1
Improve Your Understanding in German History 1Improve Your Understanding in German History 1
Improve Your Understanding in German History 1liselhud
 
Waste to Resource
Waste to ResourceWaste to Resource
Waste to ResourceDr K M SONI
 
Belene – ville l`ancienne et les jeunes
Belene – ville l`ancienne et les jeunesBelene – ville l`ancienne et les jeunes
Belene – ville l`ancienne et les jeunesStefka Pavlova
 
Tourisme culturel; la concurrence. François Perroy
Tourisme culturel; la concurrence. François PerroyTourisme culturel; la concurrence. François Perroy
Tourisme culturel; la concurrence. François PerroyMONA
 
Innovation et prsopective accueil touristique otf revaccueil mopa janvier 2016
Innovation et prsopective accueil touristique otf revaccueil mopa janvier 2016Innovation et prsopective accueil touristique otf revaccueil mopa janvier 2016
Innovation et prsopective accueil touristique otf revaccueil mopa janvier 2016MONA
 
Office de tourisme et retail revaccueil mopa janvier 2016
Office de tourisme et retail revaccueil mopa janvier 2016Office de tourisme et retail revaccueil mopa janvier 2016
Office de tourisme et retail revaccueil mopa janvier 2016MONA
 
Tendances quoi de neuf depuis revaccueil saison 1 mopa janvier 2016
Tendances quoi de neuf depuis revaccueil saison 1 mopa janvier 2016Tendances quoi de neuf depuis revaccueil saison 1 mopa janvier 2016
Tendances quoi de neuf depuis revaccueil saison 1 mopa janvier 2016MONA
 
Working capital finance
Working capital financeWorking capital finance
Working capital financeVIKESH KUMAR
 
A case study on Accenture
A case study on AccentureA case study on Accenture
A case study on AccentureDeeban Babu
 
Ms dynamics 365 First Overview
Ms dynamics 365 First OverviewMs dynamics 365 First Overview
Ms dynamics 365 First OverviewSameh Senosi
 

Viewers also liked (18)

Página 15
Página 15Página 15
Página 15
 
Motivation
MotivationMotivation
Motivation
 
Crdamc civilian payroll_employee_crisis
Crdamc civilian payroll_employee_crisisCrdamc civilian payroll_employee_crisis
Crdamc civilian payroll_employee_crisis
 
Comp1ad presentation
Comp1ad presentationComp1ad presentation
Comp1ad presentation
 
Accelerating Growth by moving to the cloud keynote - #TheFutureOfCloud
Accelerating Growth by moving to the cloud keynote - #TheFutureOfCloudAccelerating Growth by moving to the cloud keynote - #TheFutureOfCloud
Accelerating Growth by moving to the cloud keynote - #TheFutureOfCloud
 
juanito.com
juanito.comjuanito.com
juanito.com
 
power point
power pointpower point
power point
 
Pyramid Consulting Brochure
Pyramid Consulting BrochurePyramid Consulting Brochure
Pyramid Consulting Brochure
 
Improve Your Understanding in German History 1
Improve Your Understanding in German History 1Improve Your Understanding in German History 1
Improve Your Understanding in German History 1
 
Waste to Resource
Waste to ResourceWaste to Resource
Waste to Resource
 
Belene – ville l`ancienne et les jeunes
Belene – ville l`ancienne et les jeunesBelene – ville l`ancienne et les jeunes
Belene – ville l`ancienne et les jeunes
 
Tourisme culturel; la concurrence. François Perroy
Tourisme culturel; la concurrence. François PerroyTourisme culturel; la concurrence. François Perroy
Tourisme culturel; la concurrence. François Perroy
 
Innovation et prsopective accueil touristique otf revaccueil mopa janvier 2016
Innovation et prsopective accueil touristique otf revaccueil mopa janvier 2016Innovation et prsopective accueil touristique otf revaccueil mopa janvier 2016
Innovation et prsopective accueil touristique otf revaccueil mopa janvier 2016
 
Office de tourisme et retail revaccueil mopa janvier 2016
Office de tourisme et retail revaccueil mopa janvier 2016Office de tourisme et retail revaccueil mopa janvier 2016
Office de tourisme et retail revaccueil mopa janvier 2016
 
Tendances quoi de neuf depuis revaccueil saison 1 mopa janvier 2016
Tendances quoi de neuf depuis revaccueil saison 1 mopa janvier 2016Tendances quoi de neuf depuis revaccueil saison 1 mopa janvier 2016
Tendances quoi de neuf depuis revaccueil saison 1 mopa janvier 2016
 
Working capital finance
Working capital financeWorking capital finance
Working capital finance
 
A case study on Accenture
A case study on AccentureA case study on Accenture
A case study on Accenture
 
Ms dynamics 365 First Overview
Ms dynamics 365 First OverviewMs dynamics 365 First Overview
Ms dynamics 365 First Overview
 

Similar to Project dispute avoidance and mitigation through conciliation and arbitration

Construction Disputes & Settlement.pptx
Construction Disputes & Settlement.pptxConstruction Disputes & Settlement.pptx
Construction Disputes & Settlement.pptxAditya Mane
 
TOT Alternative Dispute REsolution.pptx
TOT Alternative Dispute REsolution.pptxTOT Alternative Dispute REsolution.pptx
TOT Alternative Dispute REsolution.pptxMARINELORO1
 
SEMINAR_4_ALTERNATIVE_DISPUTE_ESOLUTION_MECHANISM[3].pdf
SEMINAR_4_ALTERNATIVE_DISPUTE_ESOLUTION_MECHANISM[3].pdfSEMINAR_4_ALTERNATIVE_DISPUTE_ESOLUTION_MECHANISM[3].pdf
SEMINAR_4_ALTERNATIVE_DISPUTE_ESOLUTION_MECHANISM[3].pdfJaphethK
 
Contracts.pptx
Contracts.pptxContracts.pptx
Contracts.pptxVahHoltian
 
Dispute resolution clause Overview
Dispute resolution clause OverviewDispute resolution clause Overview
Dispute resolution clause OverviewAbdelrahman Eldosh
 
Grp 1 arbitration at Chinmay Tutorials Presented by CS Professional Students
Grp 1 arbitration at Chinmay Tutorials Presented by CS Professional StudentsGrp 1 arbitration at Chinmay Tutorials Presented by CS Professional Students
Grp 1 arbitration at Chinmay Tutorials Presented by CS Professional StudentsChinmay Jain
 
Review of Boilerplate Contract Provisions: Say What You Mean and Mean What Yo...
Review of Boilerplate Contract Provisions: Say What You Mean and Mean What Yo...Review of Boilerplate Contract Provisions: Say What You Mean and Mean What Yo...
Review of Boilerplate Contract Provisions: Say What You Mean and Mean What Yo...BoyarMiller
 
Utilizing Alternative Dispute Resolution Tactics in Employment Matters
Utilizing Alternative Dispute Resolution Tactics in Employment MattersUtilizing Alternative Dispute Resolution Tactics in Employment Matters
Utilizing Alternative Dispute Resolution Tactics in Employment MattersWoodrow Glass
 
Alternative Dispute Resolution methods Level III - B.Sc QS (Salford) March ...
Alternative  Dispute Resolution methods  Level III - B.Sc QS (Salford) March ...Alternative  Dispute Resolution methods  Level III - B.Sc QS (Salford) March ...
Alternative Dispute Resolution methods Level III - B.Sc QS (Salford) March ...TheGimhan123
 
Alternative dispute resolution: Interim Measures
Alternative dispute resolution: Interim MeasuresAlternative dispute resolution: Interim Measures
Alternative dispute resolution: Interim MeasuresRittika Dattana
 
Arbitration & Conciliation Act 1996 (amdt) ordinance
Arbitration & Conciliation Act 1996 (amdt) ordinanceArbitration & Conciliation Act 1996 (amdt) ordinance
Arbitration & Conciliation Act 1996 (amdt) ordinanceMahesh Gupta
 
Arbitration Proceeding (Working Guidlines)
Arbitration Proceeding (Working Guidlines)Arbitration Proceeding (Working Guidlines)
Arbitration Proceeding (Working Guidlines)SME Technologist
 
Arbitration Of Construction Disputes
Arbitration Of Construction DisputesArbitration Of Construction Disputes
Arbitration Of Construction Disputeslouchang
 
Contract admn ajit philip
Contract admn ajit philipContract admn ajit philip
Contract admn ajit philipFarhan Moosa
 
Top 5 Methods for Resolving UK Construction Disputes
Top 5 Methods for Resolving UK Construction DisputesTop 5 Methods for Resolving UK Construction Disputes
Top 5 Methods for Resolving UK Construction DisputesSarah Fox
 

Similar to Project dispute avoidance and mitigation through conciliation and arbitration (20)

Construction Disputes & Settlement.pptx
Construction Disputes & Settlement.pptxConstruction Disputes & Settlement.pptx
Construction Disputes & Settlement.pptx
 
TOT Alternative Dispute REsolution.pptx
TOT Alternative Dispute REsolution.pptxTOT Alternative Dispute REsolution.pptx
TOT Alternative Dispute REsolution.pptx
 
Cc 2
Cc 2Cc 2
Cc 2
 
SEMINAR_4_ALTERNATIVE_DISPUTE_ESOLUTION_MECHANISM[3].pdf
SEMINAR_4_ALTERNATIVE_DISPUTE_ESOLUTION_MECHANISM[3].pdfSEMINAR_4_ALTERNATIVE_DISPUTE_ESOLUTION_MECHANISM[3].pdf
SEMINAR_4_ALTERNATIVE_DISPUTE_ESOLUTION_MECHANISM[3].pdf
 
Contracts.pptx
Contracts.pptxContracts.pptx
Contracts.pptx
 
Dispute resolution clause Overview
Dispute resolution clause OverviewDispute resolution clause Overview
Dispute resolution clause Overview
 
Grp 1 arbitration at Chinmay Tutorials Presented by CS Professional Students
Grp 1 arbitration at Chinmay Tutorials Presented by CS Professional StudentsGrp 1 arbitration at Chinmay Tutorials Presented by CS Professional Students
Grp 1 arbitration at Chinmay Tutorials Presented by CS Professional Students
 
Review of Boilerplate Contract Provisions: Say What You Mean and Mean What Yo...
Review of Boilerplate Contract Provisions: Say What You Mean and Mean What Yo...Review of Boilerplate Contract Provisions: Say What You Mean and Mean What Yo...
Review of Boilerplate Contract Provisions: Say What You Mean and Mean What Yo...
 
Utilizing Alternative Dispute Resolution Tactics in Employment Matters
Utilizing Alternative Dispute Resolution Tactics in Employment MattersUtilizing Alternative Dispute Resolution Tactics in Employment Matters
Utilizing Alternative Dispute Resolution Tactics in Employment Matters
 
Alternative Dispute Resolution methods Level III - B.Sc QS (Salford) March ...
Alternative  Dispute Resolution methods  Level III - B.Sc QS (Salford) March ...Alternative  Dispute Resolution methods  Level III - B.Sc QS (Salford) March ...
Alternative Dispute Resolution methods Level III - B.Sc QS (Salford) March ...
 
Alternative dispute resolution: Interim Measures
Alternative dispute resolution: Interim MeasuresAlternative dispute resolution: Interim Measures
Alternative dispute resolution: Interim Measures
 
LeTran.Litigation Law Review. No.5/2018
LeTran.Litigation Law Review. No.5/2018LeTran.Litigation Law Review. No.5/2018
LeTran.Litigation Law Review. No.5/2018
 
Arbitration & Conciliation Act 1996 (amdt) ordinance
Arbitration & Conciliation Act 1996 (amdt) ordinanceArbitration & Conciliation Act 1996 (amdt) ordinance
Arbitration & Conciliation Act 1996 (amdt) ordinance
 
Arbitration Proceeding (Working Guidlines)
Arbitration Proceeding (Working Guidlines)Arbitration Proceeding (Working Guidlines)
Arbitration Proceeding (Working Guidlines)
 
Arbitration Of Construction Disputes
Arbitration Of Construction DisputesArbitration Of Construction Disputes
Arbitration Of Construction Disputes
 
Contract- Vijay Suryawanshi
Contract- Vijay SuryawanshiContract- Vijay Suryawanshi
Contract- Vijay Suryawanshi
 
Contract admn ajit philip
Contract admn ajit philipContract admn ajit philip
Contract admn ajit philip
 
Arbitration notes
Arbitration notesArbitration notes
Arbitration notes
 
Top 5 Methods for Resolving UK Construction Disputes
Top 5 Methods for Resolving UK Construction DisputesTop 5 Methods for Resolving UK Construction Disputes
Top 5 Methods for Resolving UK Construction Disputes
 
Nce603 mod unit4
Nce603 mod unit4Nce603 mod unit4
Nce603 mod unit4
 

More from Dr K M SONI

Heritage Conservation
Heritage ConservationHeritage Conservation
Heritage ConservationDr K M SONI
 
Project Management
Project ManagementProject Management
Project ManagementDr K M SONI
 
You are also a leader
You are also a leaderYou are also a leader
You are also a leaderDr K M SONI
 
Contract Management
Contract Management Contract Management
Contract Management Dr K M SONI
 
Contract and agreements
Contract and agreementsContract and agreements
Contract and agreementsDr K M SONI
 
Price variation in works contracts
Price variation in works contractsPrice variation in works contracts
Price variation in works contractsDr K M SONI
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contractsDr K M SONI
 
Contract Conditions
Contract ConditionsContract Conditions
Contract ConditionsDr K M SONI
 
Anchors in civil engineering works
Anchors in civil engineering worksAnchors in civil engineering works
Anchors in civil engineering worksDr K M SONI
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in WorksDr K M SONI
 
Net zero energy building
Net zero energy buildingNet zero energy building
Net zero energy buildingDr K M SONI
 
C & D Waste Management
C & D Waste ManagementC & D Waste Management
C & D Waste ManagementDr K M SONI
 
EPC and other types of contracts
EPC and other types of contractsEPC and other types of contracts
EPC and other types of contractsDr K M SONI
 
Contract Management
Contract Management Contract Management
Contract Management Dr K M SONI
 
EPS Geofoam Blocks
EPS Geofoam BlocksEPS Geofoam Blocks
EPS Geofoam BlocksDr K M SONI
 
Aesthetics and Functionality through Glass
Aesthetics and Functionality through GlassAesthetics and Functionality through Glass
Aesthetics and Functionality through GlassDr K M SONI
 

More from Dr K M SONI (20)

Heritage Conservation
Heritage ConservationHeritage Conservation
Heritage Conservation
 
Project Management
Project ManagementProject Management
Project Management
 
You are also a leader
You are also a leaderYou are also a leader
You are also a leader
 
Contract Management
Contract Management Contract Management
Contract Management
 
Contract and agreements
Contract and agreementsContract and agreements
Contract and agreements
 
Price variation in works contracts
Price variation in works contractsPrice variation in works contracts
Price variation in works contracts
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
Anchors in civil engineering works
Anchors in civil engineering worksAnchors in civil engineering works
Anchors in civil engineering works
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Deconstruction
DeconstructionDeconstruction
Deconstruction
 
Geosynthetics
GeosyntheticsGeosynthetics
Geosynthetics
 
Net zero energy building
Net zero energy buildingNet zero energy building
Net zero energy building
 
C & D Waste Management
C & D Waste ManagementC & D Waste Management
C & D Waste Management
 
EPC and other types of contracts
EPC and other types of contractsEPC and other types of contracts
EPC and other types of contracts
 
Contract Management
Contract Management Contract Management
Contract Management
 
EPS Geofoam Blocks
EPS Geofoam BlocksEPS Geofoam Blocks
EPS Geofoam Blocks
 
Aesthetics and Functionality through Glass
Aesthetics and Functionality through GlassAesthetics and Functionality through Glass
Aesthetics and Functionality through Glass
 
EPC Contracts
EPC Contracts EPC Contracts
EPC Contracts
 

Recently uploaded

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 

Recently uploaded (20)

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 

Project dispute avoidance and mitigation through conciliation and arbitration

  • 1. Dr K M Soni Chief Engineer, WZ-I, CPWD, Mumbai
  • 2. Disputes are part of life. Disputes are time immemorial. Disputes are resolved through negotiation, mediation, arbitration, courts.
  • 3.
  • 4. Disputes cannot be stopped altogether. Disputes can be avoided. Disputes can be resolved. Generally all the parties are ultimately at loss involving in disputes
  • 5.  A contract is a written agreement.  The agreement includes specifications, items, terms and conditions and drawings.  The employer is aware of its requirements.  The contractor is aware of requirements as he quotes the rates and also obtains clarifications during pre-bid meetings.  Thus disputes are not due to written provisions but “not written”.
  • 6.  Agreement  In many places, even agreements do not include complete items and dispute may not arise.  Employer and Contractor  Reason of dispute is “Loss or Profit” i.e. Money.
  • 7.  The contractor quoting low and unworkable rates.  The contractor having quoted low/unworkable rates carries out sub standard work.  The contractor having quoted low/unworkable rates for the items to be executed towards the end of contract period wants to withdraw from execution of those items.  The contractor has quoted low/unworkable rates for some items and wants to get them substituted or does not want to execute.
  • 8. Disputes due to “loss/profit” or money • The market rates have gone up. • The employer is not making payment in time and contractor has to pay interest on capital. • The employer is not making payments to some of the items. • The employer is delaying the payment. • The employer is delaying the measurements or not allowing to execute some items resulting into idle machinery/equipment/establishment. • Withholding money due to different reasons like milestones, QA, approvals, EOT etc. • The contractor expecting additional money due to lacunae in the framing of agreement or conditions.
  • 9. Disputes due to “loss/profit” or money • The Employer is at loss due to sub standard work. • The contractor refusing to execute the items for which he has quoted low/unworkable rates while high profitable items executed. • Loss due to delay in completion of work, assets not being put to use.
  • 10. Before award of work Immediately or on award of work During execution After completion of work
  • 11.  Mainly from contractor’s side.  Due to denial of issue of tender documents  Due to non opening of particular tender or opening of particular tender.  Due to rejection of particular tender.  Rejection of technical bids.  Forfeiture of earnest money (bid security)
  • 12.  E –tendering  Abiding to the provisions of tender /bid documents (No discretion).  Transparency and equal opportunity to all bidders.  Intimation to bidders about the status.
  • 13. Disputes Immediately or on award of work • From contractor’s side. • Due to low/unworkable rates quoted by the contractor.
  • 14. Disputes Immediately or on awardof work due to delay causedby the contractor • Due to inadequate resources • Due to taken up works beyond the capacity. • To gain time to augment resources. • To gain time to sublet the work. • To delay the work in the expectations not to execute the items to be taken in the last.
  • 15. Disputes Immediately or on award of work • From contractor’s side. • Due to encumbered site • Due to non availability of drawings • Due to non availability of approvals • Due to non availability of budget.
  • 16. Disputes AVOIDANCE • From contractor’s side. • Due to encumbered site • Please do not invite tenders • Due to non availability of drawings • Please availability of drawings in time or before time • Due to non availability of approvals • Please ensure all approvals from local bodies/govt. • Due to non availability of budget. • Please co-ordinate with the client
  • 17.  Due to non-availability of drawings  Due to non-availability of stipulated materials  Due to delayed payments  Due to non completion of works by associated agencies  Due to delayed payments  Due to admissibility of payments of certain items  Due to non approvals of payments of certain items (deviations/EI/SI)  Due to suspension of work  Due to delayed decisions
  • 18.  Due to non-availability of drawings  Make available on time or before time  Due to non-availability of stipulated materials  Please avoid stipulation  Due to delayed payments  Due to non preparation/processing of bills or availability of budget  Due to non completion of works by associated agencies  Please monitor the work of associated agencies or switch over to composite tenders  Due to admissibility of payments of certain items  Do not throw on others or delay the decisions  Due to non approvals of payments of certain items (deviations/EI/SI)  Please monitor and accord approvals in time. Take prior approvals.  Due to suspension of work  Due to delayed decisions
  • 19. All disputes arisen during execution Due to idle T & P, Establishment, liquidated damages, loss of profit, interest etc.
  • 20. Please use conciliation clause in agreement and resolve disputes before completion Resolve issues which can be before appointment of arbitrator and do not leave on arbitrator to decide even those which can be resolved. Appoint arbitrator if required within time
  • 22. Dispute after commencementof work with or WithoutADR mechanisms
  • 23.  Take right decisions at right time
  • 24.  “Prevention is better than cure…The size and complexity of many programmes of work mean that disputes are still likely to happen, but up front work can help avoid as many as possible.”
  • 25. The disputes can’t be eliminated, but it can be effectively mitigated Manage disputes as early as possible for mitigation If not mitigated, take effective steps timely before arbitrator.
  • 26.  “Arbitration agreement" means an agreement by the parties to submit to arbitration all or certain disputes which have arisen or which may arise between them in respect of a defined legal relationship, whether contractual or not.  An arbitration agreement may be in the form of an arbitration clause in a contract or in the form of a separate agreement.  An arbitration agreement shall be in writing.  An arbitration agreement is in writing if it is contained in-  (a) a document signed by the parties; (b) an exchange of letters, telex, telegrams or other means of telecommunication which provide a record of the agreement; or (c) an exchange of statements of claim and defence in which the existence of the agreement is alleged by one party and not denied by the other.  The reference in a contract to a document containing an arbitration clause constitutes an arbitration agreement if the contract is in writing and the reference is such as to make that arbitration clause part of the contract.
  • 27.  The parties are free to determine the number of arbitrators, provided that such number shall not be an even number. Failing the determination referred here, the arbitral tribunal shall consist of a sole arbitrator.  Appointment of arbitrators.- (1) A person of any nationality may be an arbitrator, unless otherwise agreed by the parties.  Subject to sub-section (6) of the Act, the parties are free to agree on a procedure for appointing the arbitrator or arbitrators.  Failing any agreement referred to above, in an arbitration with three arbitrators, each party shall appoint one arbitrator, and the two appointed arbitrators shall appoint the third arbitrator who shall act as the presiding arbitrator.
  • 28.  If a party fails to appoint an arbitrator within thirty days from the receipt of a request to do so from the other party; or  the two appointed arbitrators fail to agree on the third arbitrator within thirty days from the date of their appointment,
  • 29.  Circumstances exist that give rise to justifiable doubts as to his independence or impartiality, or  he does not possess the qualifications agreed to by the parties.  A party may challenge an arbitrator appointed by him, or in whose appointment he has participated, only for reasons of which he becomes aware after the appointment has been made.
  • 30.  Equal treatment of parties.- The parties shall be treated with equality and each party shall be given a full opportunity to present his case.  Determination of rules of procedure.- (1) The arbitral tribunal shall not be bound by the Code of Civil Procedure, 1908 or the Indian Evidence Act, 1872. Subject to this Part, the parties are free to agree on the procedure to be followed by the arbitral tribunal in conducting its proceedings. Failing any agreement referred to in the sub-section, the arbitral tribunal may, subject to this Part, conduct the proceedings in the manner it considers appropriate.  The power of the arbitral tribunal includes the power to determine the admissibility , relevance, materiality and weight of any evidence.  Place of arbitration.- The parties are free to agree on the place of arbitration. Failing any agreement referred to in this sub- section, the place of arbitration shall be determined by the arbitral tribunal having regard to the circumstances of the case, including the convenience of the parties.
  • 31.  Definition and Meaning of conciliation- The simplest meaning of conciliation is the settlement of the disputes outside the court .It is a process by which the discussion between the parties are kept going through the participation of a conciliator. Conciliation is one of the non binding procedures where an impartial third party, known as the conciliator, assist the parties to a dispute in reaching a mutually agreed settlement of the dispute. As per the Halsbury Laws of England, conciliation is a process of persuading parties to each an agreement. Because of its non judicial character, conciliation is considered to be fundamentally different from that of litigation. Generally Judges and Arbitrators decide the case in the form of a judgment or an award which is binding on the parties while in the procedure of the conciliation ,the conciliator who is often a government official gives its report in the form of recommendations which is made public.
  • 32.  Section 61 of the Arbitration and Conciliation Act of 1996 provides for the Application and Scope of Conciliation. Section 61 points out that the process of conciliation extends, in the first place, to disputes, whether contractual or not. But the disputes must arise out of the legal relationship. It means that the dispute must be such as to give one party the right to sue and to the other party the liability to be sued. The process of conciliation extends, in the second place, to all proceedings relating to it. But Part III of the Act does not apply to such disputes as cannot be submitted to conciliation by the virtue of any law for the time being in force. Number and qualification of conciliators-Section 63 fixes the number of conciliators. There shall be one conciliator. But the parties may by their agreement provide for two or three conciliators. Where the number of conciliator is more than one ,they should as general rule act jointly.
  • 33.  Section 64 deals with the appointment of the conciliators.When the invitation to the conciliation is accepted by the other party, the parties have to agree on the composition of the conciliation tribunal. In the absence of any agreement to the contrary ,there shall be only one conciliator. The conciliation proceeding may be conducted by a sole conciliator to be appointed with the concent of both the parties, failing to which the same may be conducted by two conciliators (maximum limit is three), then each party appoints own conciliator ,and the third conciliator is appointed unanimously by both the parties. The third conciliator so appointed shall be the presiding conciliator. The parties to the arbitration agreement instead of appointing the conciliator themselves may enlist the assistance of an institution or person of their choice for appointment of conciliators. But the institution or the person should keep in view during appointment that, the conciliator is independent and impartial.
  • 34.  1) Independence and impartiality [Section 67(1)]- The conciliator should be independent and impartial. He should assist the parties in an independent and impartial manner while he is attempting to reach an amicable settlement of their dispute. 2) Fairness and justice[Section 67(2)]- The conciliator should be guided by the principles of fairness and justice. He should take into consideration ,among other things , the rights and obligations of the parties, the usages of the trade concerned ,and the circumstances surrounding the dispute ,including any previous business practices between the parties. 3) Confidentiality [Section 70]- The conciliator and the parties are duly bound to keep confidential all matters relating to conciliation proceedings. Similarly when a party gives a information to the conciliator on the condition that it be kept confidential , the conciliator should not disclose that information to the other party. 4) Disclosure of the information[Section 70]- When the conciliator receives a information about any fact relating to the dispute from a party , he should disclose the substance of that information to the other party.The purpose of this provision is to enable the other party to present an explaination which he might consider appropriate. 5) Co-operation of the parties with Conciliator [S. 71]- The parties should in good faith cooperate with the conciliator. They should submit the written materials , provide evidence and attend meetings when the conciliator requests them for this purpose.
  • 35.  Commencement of the conciliation proceedings [Section 62]- The conciliation proceeding are initiated by one party sending a written invitation to the other party to conciliate. The invitation should identify the subject of the dispute. Conciliation proceedings are commenced when the other party accepts the invitation to conciliate in writing. If the other party rejects the invitation, there will be no conciliation proceedings. If the party inviting conciliation does not receive a reply within thirty days of the date he sends the invitation or within such period of time as is specified in the invitation, he may elect to treat this as rejection of the invitation to conciliate. If he so elects he should inform the other party in writing accordingly.
  • 36.  Submission of Statement to Conciliator [Section 65] – The conciliator may request each party to submit to him a brief written statement. The statement should describe the general nature of the dispute and the points at issue. Each party should send a copy of such statement to the other party. The conciliator may require each party to submit to hima further written statement of his position and the facts and grounds in its support. It may be supplemented by appropriate documents and evidence. The party should send the copy of such statements , documents and evidence to the other party. At any stage of the conciliation proceedings , the conciliator may request a party to submit to him any additional information which he may deem appropriate.
  • 37.  Conduct of Conciliation Proceedings[Section 69(1),67(3)]- The conciliator may invite the parties to meet him. He may communicate with the parties orally or in writing. He may meet or communicate with the parties together or separately. In the conduct of the conciliation proceedings, the conciliator has some freedom. He may conduct them in such manner as he may consider appropriate. But he should take in account the circumstances of the case, the express wishes of the parties, a party’s request to beheard orally and the need of speedy settlement of the dispute.
  • 38.  Administrative assistance [S. 68]- Section 68 facilitates administrative assistance for the conduct of conciliation proceedings. Accordingly , the parties and the conciliator may seek administrative assistance by a suitable institution or the person with the consent of the parties.
  • 39.  Haresh Dayaram Thakur v. State of Maharashtra and Ors. while dealing with the provisions of Sections 73 and 74 of the Abbitration and Conciliation Act of 1996 in paragraph 19 of the judgment as expressed thus the court held that- "19. From the statutory provisions noted above the position is manifest that a conciliator is a person who is to assist the parties to settle the disputes between them amicably. For this purpose the conciliator is vested with wide powers to decide the procedure to be followed by him untrammeled by the procedural law like the Code of Civil Procedure or the Indian Evidence Act, 1872. When the parties are able to resolve the dispute between them by mutual agreement and it appears to the conciliator that their exists an element of settlement which may be acceptable to the parties he is to proceed in accordance with the procedure laid down in Section 73, formulate the terms of a settlement and make it over to the parties for their observations; and the ultimate step to be taken by a conciliator is to draw up a settlement in the light of the observations made by the parties to the terms formulated by him. The settlement takes shape only when the parties draw up the settlement agreement or request the conciliator to prepare the same and affix their signatures to it. Under Sub-section (3) of Section 73 the settlement agreement signed by the parties is final and binding on the parties and persons claiming under them. It follows therefore that a successful conciliation proceedings comes to end only when the settlement agreement signed by the parties comes into existence. It is such an agreement which has the status and effect of legal sanctity of an arbitral award under Section 74”.
  • 40.  In Mysore Cements Ltd. v. Svedala Barmac Ltd it was said that Section 73 of the Act speaks of Settlement Agreement. Sub- section (1) says that when it appears to the Conciliator that there exist elements of settlement which may be acceptable to the parties, he shall formulate the terms of a possible settlement and submit them to the parties for their observation. After receiving the observations of the parties, the Conciliator may reformulates the terms of a possible settlement in the light of such observations. In the present case, we do not find there any such formulation and reformulation by the Conciliator, under Sub- section (2), if the parties reach a settlement agreement of the dispute on the possible terms of settlement formulated, they may draw up and sign a written settlement agreement. As per Sub-section (3) when the parties sign the Settlement Agreement, it shall be final and binding on the parties and persons claiming under them respectively. Under Sub-section (4), the Conciliator shall authenticate the Settlement Agreement and furnish a copy thereof to each of the parties. From the undisputed facts and looking to the records, it is clear that all the requirements of Section 73 are not complied with.
  • 41.  Electronic Communication  Copy of the Agreement by respondents  Disclosure by the arbitrator of his relation with any party  Commencement of arbitral proceedings within a fixed period  Time Limit of the appointment of arbitrator  Fee of the Arbitration  Submission of Counter Claims  Frequent Adjournments at cost  Time Limit for the Award given  Provision of Fast Track Proceedings included  Interest on Award mentioned and linked to current prevailing rate  Cost of Arbitration based on circumstances and conduct of parties  Explanation of Public Policy
  • 42.
  • 43.  The process of conciliation as an alternate dispute redressal mechanism is advantageous to the parties in the sense that it is cost effective and expeditious, it is simple,fast and convenient then the lengthy litigation procedure and it eliminates any scope of biasness and corruption. The parties who wish to settle their disputes they can be provided great intensive by the process of conciliation. In order to enable the conciliator to play his role effectively ,the parties should be brought together face to face at a common place where they can interact face to face and with the conciliator, separately or together without any distraction and with only a single aim to sincerely arrive at the settlement of the dispute. Conciliation is a boon and it is a better procedure to settle any dispute as in this process it is the parties who by themselves only come to the settlement of the dispute and the role of the conciliator is to bring parties together and to make a atmosphere where parties can themselves resolve their disputes. Conciliation tries to individualize the optimal solution and direct parties towards a satisfactory common agreement. In conciliation, the conciliator plays a relatively direct role in the actual resolution of a dispute and even advises the parties on certain solutions by making proposals for settlement. Thus I would like to conclude with a saying: Do conciliate, therefore ,whenever there are differences ,and sooner it is done ,the better.