SlideShare a Scribd company logo
CAPTIVE POWER POLICY
Presented BY:-
NAVAJYOTI MARTHA
HISTORY
• Captive generation “concept”& “activity” was
recognized under the repealed law prior to
Electricity Act-2003.
• In section 44 of Electricity (Supply) Act,1948
there was the provision for captive generation.
• The provision enabled that any licensee/person
(other than central govt. body) can set up captive
generation by taking the permission of SEB.
• Also the SEB need to consult with CEA before
giving any consent if the capacity of generation
exceeds 25 MW.
• The restrictions & controls on captive generation
have been scrapped under the EA-2003.
• The new act allows any person to set up captive
generating plant.
PROVISION FOR CAPTIVE GENERATION
UNDER ELECTRICITY ACT-2003
• Under section 2(8), the expression “captive
generating plant” has been defined as a
generating plant set up by any
person/society/association to generate
electricity primarily for his/their own use .
• Section 9(1) stipulates that the person need to
construct, maintain “DEDICATED” transmission
lines primarily for his own use & that can sell the
“surplus power” available to the grid.
• They can avail “open access” to the existing
transmission lines subjected to availability of
adequate transmission capacity determined by
STU/CTU.
• Also the person shall not required to obtain license
for setup,operating,maintaining a “dedicated T/L”
if the person complies with the followings
(1)Grid code,
(2)Technical standards,
(3)system of operation as per the norms of the
concerned SLDC/RLDC
• Also “CESS” & “EXCISE DUTY” levied at
different stages of Production or at the stage of
Retail Sale.
• Also both the taxes are leviable for different
purposes. “CESS” charged on consumption of
electricity & “EXCISE DUTY” charged on the
consumption of electricity on the installed
capacity within the premises.
• To the extent of sale the captive plants treated at
par with the regulations applicable to the
generating companies.
• Under section 9,the person owning captive
generating plant has also been allowed “OPEN
ACCESS” for conveyance of energy to a destination
for his own use without paying any “SURCHARGE”.
• The objective of the act to create “Competitive
Pressure” on the utilities to prevent charging
industrial consumers with high Cross subsidy.
REALITY ISSUES
• Most of the available capacity may not available to
Grid because of 2 reasons
(1) Open Access
(2)Transmission Tariff
Because the open access linked to the attitude of the
state & RLDC/SLDC.
In case of postage transmission tariff captive capacity
has to pay the “entire transmission cost”
THE ELECTRICITY RULE-2005
• According to the rule in case of a power plant-
(1) Captive users shall not hold less than 26% of
the ownership of the plant.
(2) Such Captive users shall not consume less than
51% of the electricity generated.
• NEP spells the use of the “SPARE CAPACITY”
of the Captive Generators for contributing to
the GRID.
• So that the “Quality of power supply” &
“Competitive” environment will be enhanced.
ACCORDING TO NTP
• A two-part tariff structure should be adopted for all
long term contracts to facilitate “Merit Order
dispatch”.
• “Availability Based Tariff (ABT)” framework would be
extended to generating stations (including grid
connected captive plants of capacities as determined
by the SERC).
• Appropriate Commission may also introduce
differential rates of fixed charges for peak and off
peak hours for better management of load.
• The basic focus is to Harnessing captive generation .
CAPTIVE POLICY OF ORISSA
• The Commission through a consultative process
followed by Public Hearing on 03.01.2008 had
issued a “Policy on harnessing of Surplus Power”
from Captive Generating Plants.
(1)Firm Power:
Those captive generators who give a commitment
for supply of power for a period of more than 3
months & up to 1 year shall be considered as
supplier of firm power of electricity form their
Captive Generating Plants.
• The procurement of power through the
Competitive Bidding route as per provision under
Section-63 of Electricity Act, 2003.
• To avoid cartelization of a few large CGPs artificially
boosting the pricing of surplus power from CGPs
Commission has capped .
• The “Acceptable Cost” determined through the
competitive bidding route should be within 10% of
the Maximum of cost of generation which can be
certified by reputed firm of CAs.
• State Utilities are free to purchase Power at a
higher rate than 110 % of the cost of
generation through the competitive route for
purpose of “TRADING”.
• CGPs selling power to GRIDCO will have the
indirect advantage of saving in “Transmission
charge and Transmission loss” which at 2007-
08 level will be around 34 to 35 paisa/ unit.
(2) Non-firm Power:
• Those of the captive generators who are
capable of giving day ahead schedule but are
not in a position to give supply continuously for a
period up to three months.
• If a CGP is in a position to give its day ahead
schedule for 21 days, 35 days, 40 days etc. during
a period of three months shall be considered as
non-firm supplier of electricity in a block period
of 3 months.
• It has to declare at the beginning of the
period of three months about the volume of
energy that they would be supplying to the
state grid.
• In case of failure to supply the declared
volume, they may have to pay penalty at
double the rate.
(3) Inadvertent Power:
• Power injected by the Captive Generators
without giving day ahead schedule.
• It would be priced equal to the pooled cost of
hydro power of the State.
• However, there shall be no payment for any kind
of injection firm, non-firm or inadvertent at
frequency of 50.4 HZ or more as a matter of grid
discipline.
• CGPs are given the facilities like land at
concessional rate, water supply and other benefits
by the state for setting up the industries If they
enter into an agreement for sale of their surplus
power to the state.
• The Captive Generating Plants are free to sell their
power through Open Access if they do not want to
participate in a bidding process for determination
of tariff for sale of power inside Orissa to GRIDCO.
THANK U

More Related Content

What's hot

Mo p electricity rules, 2005
Mo p electricity rules, 2005Mo p electricity rules, 2005
Mo p electricity rules, 2005
Anil Kumar
 
Electricity policies
Electricity policiesElectricity policies
Electricity policies
Vedium Vasanthkumar
 
Electricity act 2003
Electricity act 2003Electricity act 2003
Electricity act 2003
Sanket Samantray
 
Electricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forwardElectricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forward
IPPAI
 
Indian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorIndian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power Sector
Vijay Menghani
 
Electricity laws and regulations
Electricity laws and regulationsElectricity laws and regulations
Electricity laws and regulations
Akshat Goel
 
Elec act
Elec actElec act
Elec act
Pedagogueseven
 
Electricity act 2003 INDIA
Electricity act 2003 INDIAElectricity act 2003 INDIA
Electricity act 2003 INDIA
Arpan Khanra
 
Electricity Act 2003 and its proposed amendments
Electricity Act 2003 and its proposed amendmentsElectricity Act 2003 and its proposed amendments
Electricity Act 2003 and its proposed amendments
Amitava Nag
 
Proposed Amendments to Electricity Act, 2003
Proposed Amendments to Electricity Act, 2003Proposed Amendments to Electricity Act, 2003
Proposed Amendments to Electricity Act, 2003
Gensol Engineering Limited
 
Open access ppt
Open access pptOpen access ppt
Open access ppt
Vinay Yaduka
 
Abt meter
Abt meterAbt meter
Abt meter
Jay Ranvir
 
Restructuring of power grid
Restructuring of power gridRestructuring of power grid
Restructuring of power grid
Saravanan Sivamani
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra
Gensol Engineering Limited
 
Environmental show of the south 2014 new entrants in electricity generation
Environmental show of the south 2014 new entrants in electricity generationEnvironmental show of the south 2014 new entrants in electricity generation
Environmental show of the south 2014 new entrants in electricity generation
TNenergy
 
Tariff policy of India: Salient Points
Tariff policy of India: Salient Points Tariff policy of India: Salient Points
Tariff policy of India: Salient Points
Amitava Nag
 
Restructuring and Privatization
Restructuring and PrivatizationRestructuring and Privatization
Restructuring and Privatization
Sushant Kumar Sinha
 
14.10.2019 proposed framework for real time market for electricity
14.10.2019 proposed framework for real time market for electricity14.10.2019 proposed framework for real time market for electricity
14.10.2019 proposed framework for real time market for electricity
Vijay Menghani
 

What's hot (20)

Mo p electricity rules, 2005
Mo p electricity rules, 2005Mo p electricity rules, 2005
Mo p electricity rules, 2005
 
Electricity policies
Electricity policiesElectricity policies
Electricity policies
 
Electricity act 2003
Electricity act 2003Electricity act 2003
Electricity act 2003
 
Elecact2003
Elecact2003Elecact2003
Elecact2003
 
Electricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forwardElectricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forward
 
Electricity act2003
Electricity act2003Electricity act2003
Electricity act2003
 
Indian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorIndian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power Sector
 
Electricity laws and regulations
Electricity laws and regulationsElectricity laws and regulations
Electricity laws and regulations
 
Elec act
Elec actElec act
Elec act
 
Electricity act 2003 INDIA
Electricity act 2003 INDIAElectricity act 2003 INDIA
Electricity act 2003 INDIA
 
Electricity Act 2003 and its proposed amendments
Electricity Act 2003 and its proposed amendmentsElectricity Act 2003 and its proposed amendments
Electricity Act 2003 and its proposed amendments
 
Proposed Amendments to Electricity Act, 2003
Proposed Amendments to Electricity Act, 2003Proposed Amendments to Electricity Act, 2003
Proposed Amendments to Electricity Act, 2003
 
Open access ppt
Open access pptOpen access ppt
Open access ppt
 
Abt meter
Abt meterAbt meter
Abt meter
 
Restructuring of power grid
Restructuring of power gridRestructuring of power grid
Restructuring of power grid
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra
 
Environmental show of the south 2014 new entrants in electricity generation
Environmental show of the south 2014 new entrants in electricity generationEnvironmental show of the south 2014 new entrants in electricity generation
Environmental show of the south 2014 new entrants in electricity generation
 
Tariff policy of India: Salient Points
Tariff policy of India: Salient Points Tariff policy of India: Salient Points
Tariff policy of India: Salient Points
 
Restructuring and Privatization
Restructuring and PrivatizationRestructuring and Privatization
Restructuring and Privatization
 
14.10.2019 proposed framework for real time market for electricity
14.10.2019 proposed framework for real time market for electricity14.10.2019 proposed framework for real time market for electricity
14.10.2019 proposed framework for real time market for electricity
 

Viewers also liked

Wind project cost & financing
Wind project cost & financingWind project cost & financing
Wind project cost & financing
SusDevIndia
 
National solar mission
National solar missionNational solar mission
National solar mission
SusDevIndia
 
Energizing roofs using Solar Energy for Captive Consumption
Energizing roofs using Solar Energy for Captive ConsumptionEnergizing roofs using Solar Energy for Captive Consumption
Energizing roofs using Solar Energy for Captive ConsumptionAmit Barve
 
NTPC Dadri Gas plant
NTPC Dadri Gas plantNTPC Dadri Gas plant
NTPC Dadri Gas plant
Ayush Srivastava
 
Ramgarh Gas Power Plant, Jaisalmer
Ramgarh Gas Power Plant, JaisalmerRamgarh Gas Power Plant, Jaisalmer
Ramgarh Gas Power Plant, Jaisalmer
Saurabh Tiwari
 
Captive Power Plants India - For Sealing Compounds for Power Stations Call +9...
Captive Power Plants India - For Sealing Compounds for Power Stations Call +9...Captive Power Plants India - For Sealing Compounds for Power Stations Call +9...
Captive Power Plants India - For Sealing Compounds for Power Stations Call +9...
Project Sales Corp
 
Training power exchanges_18-may-2014
Training power exchanges_18-may-2014Training power exchanges_18-may-2014
Training power exchanges_18-may-2014
PRIYANK JAIN
 
POWER SYSTEM INTRODUCTION priyank pulkit rads praveer
POWER SYSTEM INTRODUCTION  priyank pulkit rads praveerPOWER SYSTEM INTRODUCTION  priyank pulkit rads praveer
POWER SYSTEM INTRODUCTION priyank pulkit rads praveer
PRIYANK JAIN
 
Gas power plant
Gas power plantGas power plant
Gas power plant
Amit Sinha
 
Hydal power plant
Hydal power plantHydal power plant
Hydal power plant
JUNAID SK
 
Combined operation of power plants
Combined operation of power plantsCombined operation of power plants
Combined operation of power plants
Nishkam Dhiman
 
Siemens - Power Generation Power Plants
Siemens - Power Generation Power PlantsSiemens - Power Generation Power Plants
Siemens - Power Generation Power Plants
Siemens
 
Steam Power Plants
Steam Power PlantsSteam Power Plants
Steam Power Plants
Geo Jovin Vinister
 
MET 401 Chapter 7 -_combined_cycle_power_plant
MET 401 Chapter 7 -_combined_cycle_power_plantMET 401 Chapter 7 -_combined_cycle_power_plant
MET 401 Chapter 7 -_combined_cycle_power_plantIbrahim AboKhalil
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
Nishkam Dhiman
 
Combined Cycle Power Plant
Combined Cycle Power PlantCombined Cycle Power Plant
Combined Cycle Power Plant
Md. Rimon Mia
 
Hydroelectric power
Hydroelectric power Hydroelectric power
Hydroelectric power
Bibhabasu Mohanty
 
Ppt combined cycle power plant
Ppt combined cycle power plantPpt combined cycle power plant
Ppt combined cycle power plantDavid Grenier
 
Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1
Anurak Atthasit
 

Viewers also liked (20)

Wind project cost & financing
Wind project cost & financingWind project cost & financing
Wind project cost & financing
 
National solar mission
National solar missionNational solar mission
National solar mission
 
Energizing roofs using Solar Energy for Captive Consumption
Energizing roofs using Solar Energy for Captive ConsumptionEnergizing roofs using Solar Energy for Captive Consumption
Energizing roofs using Solar Energy for Captive Consumption
 
NTPC Dadri Gas plant
NTPC Dadri Gas plantNTPC Dadri Gas plant
NTPC Dadri Gas plant
 
Ramgarh Gas Power Plant, Jaisalmer
Ramgarh Gas Power Plant, JaisalmerRamgarh Gas Power Plant, Jaisalmer
Ramgarh Gas Power Plant, Jaisalmer
 
Captive Power Plants India - For Sealing Compounds for Power Stations Call +9...
Captive Power Plants India - For Sealing Compounds for Power Stations Call +9...Captive Power Plants India - For Sealing Compounds for Power Stations Call +9...
Captive Power Plants India - For Sealing Compounds for Power Stations Call +9...
 
Training power exchanges_18-may-2014
Training power exchanges_18-may-2014Training power exchanges_18-may-2014
Training power exchanges_18-may-2014
 
POWER SYSTEM INTRODUCTION priyank pulkit rads praveer
POWER SYSTEM INTRODUCTION  priyank pulkit rads praveerPOWER SYSTEM INTRODUCTION  priyank pulkit rads praveer
POWER SYSTEM INTRODUCTION priyank pulkit rads praveer
 
Gas power plant
Gas power plantGas power plant
Gas power plant
 
Hydal power plant
Hydal power plantHydal power plant
Hydal power plant
 
A presentation on steam power plant1
A presentation on steam power plant1A presentation on steam power plant1
A presentation on steam power plant1
 
Combined operation of power plants
Combined operation of power plantsCombined operation of power plants
Combined operation of power plants
 
Siemens - Power Generation Power Plants
Siemens - Power Generation Power PlantsSiemens - Power Generation Power Plants
Siemens - Power Generation Power Plants
 
Steam Power Plants
Steam Power PlantsSteam Power Plants
Steam Power Plants
 
MET 401 Chapter 7 -_combined_cycle_power_plant
MET 401 Chapter 7 -_combined_cycle_power_plantMET 401 Chapter 7 -_combined_cycle_power_plant
MET 401 Chapter 7 -_combined_cycle_power_plant
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Combined Cycle Power Plant
Combined Cycle Power PlantCombined Cycle Power Plant
Combined Cycle Power Plant
 
Hydroelectric power
Hydroelectric power Hydroelectric power
Hydroelectric power
 
Ppt combined cycle power plant
Ppt combined cycle power plantPpt combined cycle power plant
Ppt combined cycle power plant
 
Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1
 

Similar to Captive gen

Electricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptxElectricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptx
msounak95
 
New Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee ValleyNew Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee Valley
TNenergy
 
Ee09 801 eed ppt
Ee09 801 eed pptEe09 801 eed ppt
Ee09 801 eed ppt
manickaasagam
 
roof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptxroof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptx
sonu1811
 
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNADay-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
IPPAI
 
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Headway Solar
 
brief policies.pptx
brief policies.pptxbrief policies.pptx
brief policies.pptx
ssuser9f2ad7
 
Glen Wright - Legal and Regulatory Aspects of RE
Glen Wright - Legal and Regulatory Aspects of REGlen Wright - Legal and Regulatory Aspects of RE
Glen Wright - Legal and Regulatory Aspects of REANUECI
 
Tapping potential of waste heat to power and energy conservation
Tapping potential of waste heat to power and energy conservationTapping potential of waste heat to power and energy conservation
Tapping potential of waste heat to power and energy conservation
IPPAI
 
Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013Spark Network
 
Wind Force Newsletter Feb, Edition, 2012
Wind Force Newsletter   Feb, Edition, 2012Wind Force Newsletter   Feb, Edition, 2012
Wind Force Newsletter Feb, Edition, 2012rupeshsingh_1
 
Energy policy northeast
Energy policy northeastEnergy policy northeast
Energy policy northeast
Rohil Kumar
 
PM_kusum_yojna.pdf
PM_kusum_yojna.pdfPM_kusum_yojna.pdf
PM_kusum_yojna.pdf
bhupesh Dave
 
1 final com.sum
1 final com.sum1 final com.sum
1 final com.sum
Naman Kumar
 
2012 Reenergize the Americas 4A: Alejando Peraza Garcia
2012 Reenergize the Americas 4A: Alejando Peraza Garcia2012 Reenergize the Americas 4A: Alejando Peraza Garcia
2012 Reenergize the Americas 4A: Alejando Peraza GarciaReenergize
 
Captive Power Plants.pdf
Captive Power Plants.pdfCaptive Power Plants.pdf
Captive Power Plants.pdf
Sourav Bhunia
 
Net energy metering manual for three schemes
Net energy metering manual for three schemesNet energy metering manual for three schemes
Net energy metering manual for three schemes
Private Consultants
 
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
Dr. Oliver Massmann
 

Similar to Captive gen (20)

Electricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptxElectricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptx
 
New Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee ValleyNew Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee Valley
 
Ee09 801 eed ppt
Ee09 801 eed pptEe09 801 eed ppt
Ee09 801 eed ppt
 
roof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptxroof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptx
 
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNADay-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
 
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
 
brief policies.pptx
brief policies.pptxbrief policies.pptx
brief policies.pptx
 
Glen Wright - Legal and Regulatory Aspects of RE
Glen Wright - Legal and Regulatory Aspects of REGlen Wright - Legal and Regulatory Aspects of RE
Glen Wright - Legal and Regulatory Aspects of RE
 
Tapping potential of waste heat to power and energy conservation
Tapping potential of waste heat to power and energy conservationTapping potential of waste heat to power and energy conservation
Tapping potential of waste heat to power and energy conservation
 
Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013
 
Wind Force Newsletter Feb, Edition, 2012
Wind Force Newsletter   Feb, Edition, 2012Wind Force Newsletter   Feb, Edition, 2012
Wind Force Newsletter Feb, Edition, 2012
 
Energy policy northeast
Energy policy northeastEnergy policy northeast
Energy policy northeast
 
PM_kusum_yojna.pdf
PM_kusum_yojna.pdfPM_kusum_yojna.pdf
PM_kusum_yojna.pdf
 
1 final com.sum
1 final com.sum1 final com.sum
1 final com.sum
 
DSM.pptx
DSM.pptxDSM.pptx
DSM.pptx
 
2012 Reenergize the Americas 4A: Alejando Peraza Garcia
2012 Reenergize the Americas 4A: Alejando Peraza Garcia2012 Reenergize the Americas 4A: Alejando Peraza Garcia
2012 Reenergize the Americas 4A: Alejando Peraza Garcia
 
Captive Power Plants.pdf
Captive Power Plants.pdfCaptive Power Plants.pdf
Captive Power Plants.pdf
 
Ppt nep n ntp
Ppt nep n ntpPpt nep n ntp
Ppt nep n ntp
 
Net energy metering manual for three schemes
Net energy metering manual for three schemesNet energy metering manual for three schemes
Net energy metering manual for three schemes
 
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
 

Captive gen

  • 1. CAPTIVE POWER POLICY Presented BY:- NAVAJYOTI MARTHA
  • 2. HISTORY • Captive generation “concept”& “activity” was recognized under the repealed law prior to Electricity Act-2003. • In section 44 of Electricity (Supply) Act,1948 there was the provision for captive generation. • The provision enabled that any licensee/person (other than central govt. body) can set up captive generation by taking the permission of SEB.
  • 3. • Also the SEB need to consult with CEA before giving any consent if the capacity of generation exceeds 25 MW. • The restrictions & controls on captive generation have been scrapped under the EA-2003. • The new act allows any person to set up captive generating plant.
  • 4. PROVISION FOR CAPTIVE GENERATION UNDER ELECTRICITY ACT-2003 • Under section 2(8), the expression “captive generating plant” has been defined as a generating plant set up by any person/society/association to generate electricity primarily for his/their own use . • Section 9(1) stipulates that the person need to construct, maintain “DEDICATED” transmission lines primarily for his own use & that can sell the “surplus power” available to the grid.
  • 5. • They can avail “open access” to the existing transmission lines subjected to availability of adequate transmission capacity determined by STU/CTU. • Also the person shall not required to obtain license for setup,operating,maintaining a “dedicated T/L” if the person complies with the followings (1)Grid code, (2)Technical standards, (3)system of operation as per the norms of the concerned SLDC/RLDC
  • 6. • Also “CESS” & “EXCISE DUTY” levied at different stages of Production or at the stage of Retail Sale. • Also both the taxes are leviable for different purposes. “CESS” charged on consumption of electricity & “EXCISE DUTY” charged on the consumption of electricity on the installed capacity within the premises.
  • 7. • To the extent of sale the captive plants treated at par with the regulations applicable to the generating companies. • Under section 9,the person owning captive generating plant has also been allowed “OPEN ACCESS” for conveyance of energy to a destination for his own use without paying any “SURCHARGE”. • The objective of the act to create “Competitive Pressure” on the utilities to prevent charging industrial consumers with high Cross subsidy.
  • 8. REALITY ISSUES • Most of the available capacity may not available to Grid because of 2 reasons (1) Open Access (2)Transmission Tariff Because the open access linked to the attitude of the state & RLDC/SLDC. In case of postage transmission tariff captive capacity has to pay the “entire transmission cost”
  • 9. THE ELECTRICITY RULE-2005 • According to the rule in case of a power plant- (1) Captive users shall not hold less than 26% of the ownership of the plant. (2) Such Captive users shall not consume less than 51% of the electricity generated.
  • 10. • NEP spells the use of the “SPARE CAPACITY” of the Captive Generators for contributing to the GRID. • So that the “Quality of power supply” & “Competitive” environment will be enhanced.
  • 11. ACCORDING TO NTP • A two-part tariff structure should be adopted for all long term contracts to facilitate “Merit Order dispatch”. • “Availability Based Tariff (ABT)” framework would be extended to generating stations (including grid connected captive plants of capacities as determined by the SERC). • Appropriate Commission may also introduce differential rates of fixed charges for peak and off peak hours for better management of load. • The basic focus is to Harnessing captive generation .
  • 12. CAPTIVE POLICY OF ORISSA • The Commission through a consultative process followed by Public Hearing on 03.01.2008 had issued a “Policy on harnessing of Surplus Power” from Captive Generating Plants. (1)Firm Power: Those captive generators who give a commitment for supply of power for a period of more than 3 months & up to 1 year shall be considered as supplier of firm power of electricity form their Captive Generating Plants.
  • 13. • The procurement of power through the Competitive Bidding route as per provision under Section-63 of Electricity Act, 2003. • To avoid cartelization of a few large CGPs artificially boosting the pricing of surplus power from CGPs Commission has capped . • The “Acceptable Cost” determined through the competitive bidding route should be within 10% of the Maximum of cost of generation which can be certified by reputed firm of CAs.
  • 14. • State Utilities are free to purchase Power at a higher rate than 110 % of the cost of generation through the competitive route for purpose of “TRADING”. • CGPs selling power to GRIDCO will have the indirect advantage of saving in “Transmission charge and Transmission loss” which at 2007- 08 level will be around 34 to 35 paisa/ unit.
  • 15. (2) Non-firm Power: • Those of the captive generators who are capable of giving day ahead schedule but are not in a position to give supply continuously for a period up to three months. • If a CGP is in a position to give its day ahead schedule for 21 days, 35 days, 40 days etc. during a period of three months shall be considered as non-firm supplier of electricity in a block period of 3 months.
  • 16. • It has to declare at the beginning of the period of three months about the volume of energy that they would be supplying to the state grid. • In case of failure to supply the declared volume, they may have to pay penalty at double the rate.
  • 17. (3) Inadvertent Power: • Power injected by the Captive Generators without giving day ahead schedule. • It would be priced equal to the pooled cost of hydro power of the State. • However, there shall be no payment for any kind of injection firm, non-firm or inadvertent at frequency of 50.4 HZ or more as a matter of grid discipline.
  • 18. • CGPs are given the facilities like land at concessional rate, water supply and other benefits by the state for setting up the industries If they enter into an agreement for sale of their surplus power to the state. • The Captive Generating Plants are free to sell their power through Open Access if they do not want to participate in a bidding process for determination of tariff for sale of power inside Orissa to GRIDCO.