Spring 2009 Town Meeting Article 40  Birch Road Water Treatment Facility   May 2009 Town of Framingham Department of Public Works "Preserving Your Investment in the Public Infrastructure "
Presentation Agenda Birch Road Water Treatment Facility Background and Rationale Preliminary Concept Plans Key Milestones
Background Project identified by DPW - 2003 Preliminary testing of site geology - 2004 Aquifer testing -  Spring 2006 Pilot water quality testing - Summer 2006 State permitting 2006 – present
Project Rationale 2004 –water purchased from MWRA cost  $4.1M  2008 – water purchased from MWRA cost  $6.3M  2014 –MWRA’s Projected Water Cost  for Framingham  -  $9.3M
Project Rationale
Project Rationale Birch Road Water Treatment Facility Project - $40M  Designed to treat 4 + million gallons per day 2008 - MWRA cost for water is $1M more than BRWTF would have been 2013 - BRWTF water costs approximately 60% of MWRA cost  2030 - Annual savings in excess of $5M, with a cumulative savings  to date of over $60M
Approximate Capital Expenditure by Fiscal Year ($ Millions) FY 2009 FY 2010 FY 2011 FY 2012 FY 2013 Total $2.9 $5.5 $13.4 $11.4 $7.1 $40.3
Project Rationale While reallocating and keeping financial resources local is a  primary benefit, there are other important  advantages…. Reduced reliance on MWRA as a sole source of water  Increased control of a critical utility and resource Community’s ability to have more control over their  direction (50-100 year planning cycle)  Optimization of DPW staff   Local policy decision opportunities   Preservation of open space, a natural resource and unusually high yield groundwater supply Preservation of a watershed
Project Description State-of-the-art membrane water treatment process Administrative space for treatment operations and certain adjunct Department functions  Energy efficient plant  Active and passive solar technology Energy efficient lighting Innovative geothermal heating and cooling system Sustainable design principles incorporated throughout
Birch Road Water Quality Facility PRELIMINARY
Project Description - What might the Facility Look Like? PRELIMINARY
Conceptual Interior Space PRELIMINARY Post Treatment Treatment Pre Treatment
Schedule of Key Milestones Retained Engineering Design Firm – Oct ‘08 Procurement of Membranes – June ’09 100% Design – Spring 2010 Contractor Selection – Summer 2010 Groundbreaking – Fall 2010 Plant Operational – 2013

Birch Rd Presentation 05-11-09 Tm

  • 1.
    Spring 2009 TownMeeting Article 40 Birch Road Water Treatment Facility May 2009 Town of Framingham Department of Public Works "Preserving Your Investment in the Public Infrastructure "
  • 2.
    Presentation Agenda BirchRoad Water Treatment Facility Background and Rationale Preliminary Concept Plans Key Milestones
  • 3.
    Background Project identifiedby DPW - 2003 Preliminary testing of site geology - 2004 Aquifer testing - Spring 2006 Pilot water quality testing - Summer 2006 State permitting 2006 – present
  • 4.
    Project Rationale 2004–water purchased from MWRA cost $4.1M 2008 – water purchased from MWRA cost $6.3M 2014 –MWRA’s Projected Water Cost for Framingham - $9.3M
  • 5.
  • 6.
    Project Rationale BirchRoad Water Treatment Facility Project - $40M Designed to treat 4 + million gallons per day 2008 - MWRA cost for water is $1M more than BRWTF would have been 2013 - BRWTF water costs approximately 60% of MWRA cost 2030 - Annual savings in excess of $5M, with a cumulative savings to date of over $60M
  • 7.
    Approximate Capital Expenditureby Fiscal Year ($ Millions) FY 2009 FY 2010 FY 2011 FY 2012 FY 2013 Total $2.9 $5.5 $13.4 $11.4 $7.1 $40.3
  • 8.
    Project Rationale Whilereallocating and keeping financial resources local is a primary benefit, there are other important advantages…. Reduced reliance on MWRA as a sole source of water Increased control of a critical utility and resource Community’s ability to have more control over their direction (50-100 year planning cycle)  Optimization of DPW staff   Local policy decision opportunities  Preservation of open space, a natural resource and unusually high yield groundwater supply Preservation of a watershed
  • 9.
    Project Description State-of-the-artmembrane water treatment process Administrative space for treatment operations and certain adjunct Department functions Energy efficient plant Active and passive solar technology Energy efficient lighting Innovative geothermal heating and cooling system Sustainable design principles incorporated throughout
  • 10.
    Birch Road WaterQuality Facility PRELIMINARY
  • 11.
    Project Description -What might the Facility Look Like? PRELIMINARY
  • 12.
    Conceptual Interior SpacePRELIMINARY Post Treatment Treatment Pre Treatment
  • 13.
    Schedule of KeyMilestones Retained Engineering Design Firm – Oct ‘08 Procurement of Membranes – June ’09 100% Design – Spring 2010 Contractor Selection – Summer 2010 Groundbreaking – Fall 2010 Plant Operational – 2013