Faculty of Engineering Tanta University
Ahmed Mohamed El Ashry
Prepared By:
Bill Of Quantities
Issued For Construction - Rev.00
Civil engineering Builging
December, 2022
PREAMBLE TO BILL OF QUANTITIES
PREAMBLE TO BILL OF QUANTITIES
1.1
A
B
1 Division 03:Concrete
2 Division 04: Masonry
3 Division 05:Metals
4 Division 06:Wood, Plastics
5
6
7
8 Division 10: Specialties
9 Division 31: Earthwork
1.2 PRICING PREAMBLES
A
B
C
a
b
c
d
e
E
H
List of Abbreviations:
m METER
m2 SQUARE METER
m3 CUBIC METER
The method of measurement used is POMI.
Materials and goods including all connected costs.
Preparatory works and setting out of particular item.
All equipment, tools, etc. for the proper and safe completion of the relevant item of work.
All other incidental works and necessary works which are not described in the B.O.Q but described in
the aforesaid specifications and or shown in the drawings for the proper completion of the relevant
item of work.
In addition to above, the rate for items of work shall include for cost implemented as result of complying with
Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1
Specification Sections, HSE regulations and ruling laws.
Labor and connected costs.
CONTENTS OF THE BILLS OF QUANTITIES
Bills of quantities, prepared in accordance with Construction Specifications Institute CSI
(MASTERFORMAT 2012), fully describe and accurately represent the works to be executed and this
provides a uniform basis for competitive tendering.
Specifications and Bills of Quantities may consist some or all of the followings:
Division 07: Thermal & Moisture Insulation
Division 08: Opening
Division 09: Finishes
Should any discrepancy occur between these Preambles, the descriptions, the drawings and any other Contract
Documents, the Tenderer (Contractor afterwards) shall obtain instructions from the Engineer before proceeding.
The rate for each item must be comprehensive and must include for complying in all respects with the requirements
of the aforesaid specifications, these pricing preambles, cover all the obligations/liabilities under the contract, and all
matters and things necessary for the proper construction, completion, commissioning and maintenance of the
The rates and prices entered in the Bills of Quantities shall be deemed to be the full inclusive value of the work
covered by the several items including the following unless expressly stated separately otherwise:
DIVISION 03
CONCRETE
Page 1 of 3
Rate Amount
(EGP) (EGP)
DIVISION 03 CONCRETE
The Contractor is referred to the specifications and drawings
for all details related to the works and he is to include for
complying with all the requirements contained therein, whether
or not they are specifically mentioned within the items. All
Tender documents (Drawings, Bill of quantities, Specifications)
are integrated documents and complete each other. Workshop
drawings and frames for approval before supply and
installation (as per approved sample)
* Rates for all concrete items shall include shuttering, steel
reinforcement, testing for steel reinforcement, water stop,
placing of concrete, vibrating, curing, striking, workmanship,
finish, all ducts, sleeves, opening areas and all according to
drawings, specifications, conditions and directed instructions
by the Engineer
CAST-IN-PLACE CONCRETE
1 Supply and cast plain concrete with required compressive
strength as per structure drawings; rate includes but not limited
to casting using concrete pump, formwork, construction joints,
sealant filled, finishing surface to receive waterproofing and all
necessary to complete the work as per structure drawings and
specifications.
1.1 Plain concrete footings m³ 21 ١٢٠٠ 25,200
1.2 Plain concrete below ground beams m³ 5 ١٢٠٠ 6,000
2 Supply and cast reinforced concrete with required compressive
strength as per structure drawings; rate includes but not limited
to casting using concrete pump, formwork, steel reinforcement,
expansion and construction joints, joint filler, sealant, surface
repair to receive waterproofing, rain scupper and all
accessories necessary to complete the work as per structure
drawings and specifications.
2.1 Footings m³ 638 ١٢٠٠ 765,600
2.2 Columns neck m³ 70 ١٢٠٠ 84,000
2.3 Ground beams m³ 525 ١٨٠٠ 945,000
2.4 Slab on grade,150mm thick m² 2,870 ١٨٠٠ 5,166,000
2.5 Slabs m³ 5,393 ١٨٠٠ 9,707,400
2.6 Columns m³ 979 ١٨٠٠ 1,762,092
2.7 Beams m³ 300 ١٨٠٠ 540,000
2.8 Roof parapet m³ 140 ١٢٠٠ 168,000
2.9 Stairs m³ 172 ١٨٠٠ 309,600
LIGHTWEIGHT CONCRETE ROOF INSULATION
3 Supply and cast lightweight concrete flooring with the required
slope; rate includes but not limited to joint sealants, trowel,
finish reinforcement (where required) and all accessories
necessary to complete the work as per drawings and
specifications. Refer to drawing no. (A-502)
Item Description Unit Quantity
Page 2 of 3
3.1 Lightweight concrete for roof and terraces; 130:70mm thick m² 140 260 36,400
To Collection
Amount
(EGP)
Total Division Summary
Page No 2
Total Division 03 Concrete 19,515,292
To Summary
Item Description
Page 3 of 3
DIVISION 04
MASONRY
Page 1 of 3
Rate Amount
(EGP) (EGP)
DIVISION 04 MASONRY
All items rates include supply materials, apply and / or execute
work according to contract conditions, specifications and
drawings. Also include the required construction equipment's,
samples and tests. All Tender documents (Drawings, Bill of
quantities, Specifications) are integrated documents and
complete each other
CONCRETE UNIT MASONRY
1 Supply and install concrete blocks; rate includes cement
mortar, solid jambs at openings, lintels, embedded expansion
metals, galvanized steel anchors, wall ties, metal Lath
reinforcement, stiffeners, jointing, Rockwool insulation (if
required) and all required work for completion according to
drawings and specifications. The contractor is to provide all
necessary wall reinforcements, wall supports / blocking and
necessary fixation to receive loads & weights of all ID
elements, finishes, cladding and FF&E items mounted on walls
(Like for example “Interior Plantings & Trees” – “Draperies” –
“Furniture - Artwork & Accessories” – “Television Sets &
Mounting Hardware” …etc) according to ID drawings &
documents, the contractor should also submit shop drawings
for the Engineers approval prior to installation.
1.1 Solid concrete brick for 250mm wall for underground masonry;
size (250Lx120Wx60H) mm m³ 66 450 29,700
1.2 Solid concrete brick for 250mm wall; type (W01) size
(250Lx120Wx60H) mm m³ 3,028 450 1,362,600
1.3 Hollow concrete block for 250mm wall; type (W02) size
(400Lx250Wx200H) mm m³ 3 450 1,125
1.4 Solid concrete brick for 120mm wall;type (W03), size
(250Lx120Wx60H) mm m³ 110 210 23,100
1.5 Hollow concrete block for 120mm wall; type (W04) size
(400Lx120Wx200H) mm m³ 82 210 17,220
EXTERIOR STONE CLADDING
2 Supply and install natural stone cladding; rate includes but not
limited to fixation system , waterproofing behind, filling grout,
reveal, trims, accessories, finish, approved sample and all
necessary to complete the work as per drawings and
specifications
2.1 Melly gray marble skirting; 20mm thick, 1200mm max. high,
type (ST-04) m² 1,448 240 61,920
2.2 Melly gray marble skirting; 20mm thick, 1000mm max. high
m² 258 160 41,280
To Collection
Item Description Unit Quantity
Page 2 of 3
Amount
(EGP)
Total Division Summary
Page No 2
Total Division 04 Masonry 1,519,725
To Summary
Item Description
Page 3 of 3
DIVISION 05
METALS
Page 1 of 2
Rate Amount
(EGP) (EGP)
DIVISION 05 METALS
All metal work includes fixing, finish, painting, accessories and work
required for fixation. Samples shall be submitted by the contractor and
approved by the Engineer. Complete all work according to drawings
and specification.
METAL RAILINGS
2 Supply and install aluminum handrail; rate includes but not limited to
painted rail, fixation, paint, finish and all necessary to complete the
work as per drawings and specifications.
Approved samples shall be submitted by the contractor and approved
by the Engineer. Refer to drawing no. (A-505)
2.1 Floor mounted handrial for terraces, 1000mm high kgr ٥٩٧
2.2 Floor mounted handrial above parapet, 800mm high kgr ٥٩٧
Total Division 05 Metals
To Summary
Item Description Unit Quantity
Page 2 of 2
DIVISION 06
WOOD, PLASTICS AND COMPOSITES
Page 1 of 2
Rate Amount
(EGP) (EGP)
DIVISION 06: WOOD, PLASTICS, AND COMPOSITES
All items rates include supply materials, install and / or execute
work according to contract conditions , specifications and
drawings. Also include the required construction equipment's,
samples and tests.
ARCHITECTURAL WOOD CASEWORK
1 Supply and install laminated MDF skirting; rate includes but
not limited to fixation,trims, laminate, finish, approved samples
and all necessary to complete the work as per drawings, cut
sheets and specifications. Type, color and samples shall be
submitted by the contractor and approved by the Engineer.
1.1 Oak Laminated on MDF skirting, 100mm high, Code (SK-002) m 45 26.00 1,170.00
To Collection
Total Division Summary
Total Division 06 Wood, Plastics and composites 1,170.00
To Summary
Item Description Unit Quantity
Page 2 of 2
DIVISION 07
THERMAL AND MOISTURE PROTECTION
Page 1 of 3
Rate Amount
(EGP) (EGP)
DIVISION 07 THERMAL AND MOISTURE PROTECTION
The Contractor is referred to the specifications and drawings
for all details related to the works of this division and he is to
include for complying with all the requirements contained
therein, whether or not they are specifically mentioned within
the item. Scope of work will be: shop drawings issue, systems
supply, installation and testing.
BITUMINOUS DAMPPROOFING
1 Supply and apply cold applied rubberized bituminous
dampproofing paint, rate includes but not limited to prepare
surfaces, testing, sub-base layers and any material or activity
required to complete all work according to drawings and
specifications
1.1 Cold fluid applied damp-proofing for foundations m² 254 50 12,700
THERMAL INSULATION
3 Supply and apply extruded polystyrene foam for thermal
insulation; rate includes but not limited to preparation works,
protection layer (Geotextile), testing and all necessary to
complete the work as per drawings and specifications. Refer
to drawing no. (A-502)
3.1 Thermal insulation for roof; 70mm thick m² 2,047 48 98,256
ROOF TILES
4 Supply and install cement tiles; rate includes but not limited to
cement mortar, finish and all material or activity required to
finish the work as per drawings and specification. Type, color
and samples shall be submitted by the contractor and
approved by the Engineer
4.1 Cement tiles for roof, size (300x300x30)mm m² 20 134 2,680
4.2 Ditto, but for base, 300mm high m 22 -
MODIFIED BITUMINOUS MEMBRANE
5 Supply and install waterproofing membrane, rate includes
prepare surfaces, overlap, testing, protection board as per
drawing and any material or activity required to complete work
according to drawings and specifications.
5.1 Waterproofing membrane for roof and terraces, 4mm thick m² 2,047 50 102,350
5.2 Waterproofing membrane for wet area, 4mm thick m² 559 50 27,950
To Collection
Amount
(EGP)
Total Division Summary
Page No 2
Item Description
Item Description Unit Quantity
Page 2 of 3
Total Division 07 Thermal and Moisture Protection 243,936
To Summary
Page 3 of 3
DIVISION 08
OPENINGS
Page 1 of 5
Rate Amount
(EGP) (EGP)
DIVISION 08 : OPENINGS
All items rates include supply materials, install and / or execute
work according to contract conditions, specifications and
drawings. All Tender documents (Drawings, Bill of quantities,
Specifications) are integrated documents and complete each
other
WOOD DOORS
1 Supply and install external wooden doors as per drawings; rate
includes but not limited to sub-frames, wooden frames,
architraves, leaves, fittings, joint sealant, paint, finish and all
necessary to complete the work as per drawings and
specifications.
Approved samples shall be submitted by the contractor and
approved by the Engineer.
1.1 External wooden solid flush door with natural oak veneer
coated with polyurethane finish, type (D01), size
(1200x2400)mm
No 32
340 10,880
2 Supply and install internal wooden doors as per drawings; rate
includes but not limited to sub-frames, wooden frames ,
architraves, leaves, fittings, joint sealant, paint, finish and all
necessary to complete the work as per drawings and
specifications.
Approved samples shall be submitted by the contractor and
approved by the Engineer. Refer to drawing no (GD-AF-304) &
(GD-AF-305)
2.1 Semi solid wooden door type (D01), size (900x2180)mm No 79 280 22,120
2.4 Semi solid wooden door type (D06), size (800x2200)mm No 74 420 31,080
ALUMINUM WINDOW
3 Supply and install electrostatic powder coated aluminum
windows with float glass 6mm thick as per drawing; rate
includes but not limited to fixation, insulated composite
aluminum panels, glazing panel, insect screens, hardware
sets, spacer, sealant, finish and any material or activity
required to complete work as per drawings and specification.
Type, color and samples shall be
submitted by the contractor and approved by the Engineer.
Refer to drawing no.(A-601)
3.1 Window type (AL-02), size (700x1200)mm No 5 -
3.2 Window type (AL-03), size (900x1200)mm No 18 -
To Collection 64,080
Item Description Unit Quantity
Page 2 of 5
Rate Amount
(EGP) (EGP)
ALUMINUM WINDOW CONT'
1 Supply and install electrostatic powder coated aluminum
windows with tempered glass 6mm thick as per drawing; rate
includes but not limited to fixation, insulated composite
aluminum panels, glazing panel, insect screens, hardware
sets, spacer, sealant, finish and any material or activity
required to complete work as per drawings and specification.
Type, color and samples shall be
submitted by the contractor and approved by the Engineer.
Refer to drawing no.(A-601)
1.1 Window type (AL-01), size (700x2400)mm No 28 670 18,760
1.2 Wndow door type (AL-06), size (900x2400)mm No 2 ٩٥٠ 1,900
1.6 Wndow door type (AL-10), size (1800x2400)mm No 128 ١٤٥٠ 185,600
2 Supply and install electrostatic powder coated aluminum
window door with tempered glass 6mm thick as per drawing;
rate includes but not limited to fixation, insulated composite
aluminum panels, glazing panel, insect screens, hardware
sets, spacer, sealant, finish and any material or activity
required to complete work as per drawings and specification.
Type, color and samples shall be
submitted by the contractor and approved by the Engineer.
Refer to drawing no.(A-601)
2.1 Window door type (AL-04), size (2000x2400)mm No 3 -
2.2 Wndow door type (AL-05), size (3980/1250x2400)mm No 1 -
DOORS HARDWARE
All items rates include but not limited to supply materials,
install and / or execute work according to specifications,
drawings and cut sheets. Also include the required
construction equipment's, samples and tests. All Tender
documents (Drawings, Bill of quantities, Specifications) are
integrated documents and complete each other
3 Supply door hardware sets as shown in schedule, samples
shall be submitted by the contractor and approved by the
engineer. Complete all work according to drawings, cut sheets
and specification
3.1 Door Hardware Set, Code (1) No 3 Rate Only
3.2 Door Hardware Set, Code (2) No 5 Rate Only
3.3 Door Hardware Set, Code (3) No 3 Rate Only
3.4 Door Hardware Set, Code (4) No 1 Rate Only
To Collection 206,260
Quantity
Item Description Unit
Page 3 of 5
Rate Amount
(EGP) (EGP)
DOORS HARDWARE CONT
1 Install door hardware sets as shown in schedule, rate include
but not limited to fixation, finish and all necessary to complete
the work. samples shall be submitted by the contractor and
approved by the engineer. Complete all work according to
drawings, cut sheets and specification
1.1 Door Hardware Set, Code (1) No 3 -
1.2 Door Hardware Set, Code (2) No 5 -
1.3 Door Hardware Set, Code (3) No 3 -
1.4 Door Hardware Set, Code (4) No 1 -
MIRRORS
2 Supply and install 6mm thick mirror; rate includes but not
limited to supporting system, finish, frame, and any material or
activity required to complete work as per drawings and
specification. Type, color and samples shall be submitted by
the contractor and approved by the Engineer. Ref drawing no.
(CG-V4B-AF-202), (CG-V4B-AF-204), (CG-V4B-AF-206), (CG-
V4B-AF-208), (GD-AF-305).
2.1 Mirror for toilets size (1000x1000)mm, code (GL-001) with
metal frame code (MT-003) No 10 -
2.2 Mirror for toilets size (720x1000)mm, code (GL-001) with metal
frame code (MT-003) No 10 -
2.3 Mirror for toilets size (660x1000)mm, code (GL-001) with metal
frame code (MT-003) No 10 -
2.4 Mirror for toilets size (650x1000)mm, code (GL-001) with metal
frame code (MT-003) No 10 -
2.5 Mirror for toilets size (550x1000)mm, code (GL-001) with metal
frame code (MT-003) No 10 -
Item Description Unit Quantity
Page 4 of 5
To Collection
Amount
(EGP)
Total Division Summary
Page No 2 64,080
Page No 3 206,260
Page No 4 -
Total Division 08 Openings
To Summary 270,340
Item Description
Page 5 of 5
DIVISION 09
FINISHES
Page 1 of 6
Rate Amount
(EGP) (EGP)
DIVISION 09 FINISHES
All finishes work includes prepare surface, application, accessories,
cleaning and work required to finish according to drawings,
specification and manufacturers data sheets. Shop drawings and
samples shall be submitted by the contractor and approved by the
Engineer. Complete all work according to drawings and specification.
PORTLAND CEMENT PLASTERING
1 Supply and apply plaster on concrete or masonry walls; rate includes
but not limited to angles beads,metal lath, wire mesh, accessories and
all required to complete the work as per drawings and specification.
1.1 Plaster for internal walls 15mm thick m² 586
1.2 Plaster for internal ceiling, 15mm thick m² 123
1.3 Plaster for externall walls 20mm thick m² 425
GYPSUM BOARD ASSEMBLIES
2 Supply and install gypsum board for suspended ceilings as per
drawings; rate includes but not limited to fixation system, accessories,
access panels, sealant, bulk head, light coves, pattern, finish, shadow
gab and any material or activity required to complete work as per
drawings and specification.
Type, color and samples shall be submitted by the contractor and
approved by the Engineer
2.1 Gypsum board false ceiling, m² 33
2.2 Moisture resistant gypsum board false ceiling m² 33
TILING
3 Supply and install cement tiles; rate includes but not limited to cement
mortar, finish and all material or activity required to finish the work as
per drawings and specification. Type, color and samples shall be
submitted by the contractor and approved by the Engineer
3.1 Cement tiles to receive finishes, size (300x300x30) m² 55
CERAMIC TILING
4 Supply and install porcelain/ceramic tiles from ceramica innova or
equivalent; rate includes but not limited to all required design pattern
as per finish schedule, cement mortar, grouting, adhesive material (if
required), joint spacers, accessories, finish and any material or activity
required to complete work as per drawings, cut sheets and
specification.
Flooring
4.1 Slip resistant porcelain tiles, size (1100x600)mm, code (CT-001) m² 30
4.2 Slip resistant ceramic tiles, size (450x450)mm, code (CT-003) m² 5
4.3 Porcelain tiles, size (600x600)mm, code (CT-005) m² 105
To Collection
Rate Amount
(EGP) (EGP)
Item Description Unit Quantity
Quantity
Item Description Unit
Page 2 of 6
CERAMIC TILING CONT'
1 Supply and install porcelain/ceramic tiles from ceramica innova or
equivalent; rate includes but not limited to all required design pattern
as per finish schedule, cement mortar, grouting, adhesive material (if
required), joint spacers, accessories, finish and any material or activity
required to complete work as per drawings, cut sheets and
specification.
Walls
1.1 Porcelain tiles, size (1100x600)mm, code (CT-002) m² 50
1.2 Porcelain tiles, size (450x450)mm, code (CT-004) m² 31
Skirting
1.3 Porcelain skirting,100mm high, code (SK-003) m 18
1.4 Ceramic skirting,100mm high, code (SK-004) m 10
1.5 Porcelain skirting for terraces,100mm high, code (SK-005) m 21
GLASS MOSAIC TILING
2 Supply and install mosaic tiles from Mahgoub or equivalent; rate
includes but not limited to all required design pattern as per finish
schedule, cement mortar, grouting, adhesive material (if required), joint
spacers, accessories, finish and any material or activity required to
complete work as per drawings, cut sheets and specification.
Walls
2.1 Mosaic tiles, size (20x20)mm, code (CT-006) m² 2
STONE FLOORING
3 Supply and install marble tiles; rate includes but not limited to all
required design pattern as per finish schedule, cement mortar,
grouting, self leveling screed, adhesive material (if required), joint
spacers, accessories, finish and any material or activity required to
complete work as per drawings, cut sheets and specification.
3.1 Crema Noble marble flooring, size (1200x600)mm, code (ST-001) m² 65
To Collection
Rate Amount
(EGP) (EGP)
STONE FLOORING CONT
Quantity
Item Description Unit
Page 3 of 6
1 Supply and Install stone for treads & risers fixed on concrete stair; rate
includes but not limited to adhesive mortar, accessories, finish,
approved samples, shop drawings, cut sheets and all necessary to
complete the work as per drawings and specifications.
1.1 Crema Noble marble risers for internal stairs, 20mm thickness, code
(ST-001) m 48
1.2 Crema Noble marble treads for internal stairs 40 mm thickness, code
(ST-001) m 48
1.3 Crema Noble marble for staircases for landing 20mm thick, code (ST-
001) m² 5
1.4 Melly gray marble risers for external stairs steps 20mm thickness, code (ST-
04) m 27
1.5 Melly gray marble treads for external stairs steps 40mm thickness, code (ST-
04) m 27
1.6 Melly gray marble landing for external stairs steps 20mm thickness, code (ST-
04) m² 5
Skirting
1.7 Crema Noble marble skirting,100mm high, code (SK-001) m 50
Threshold
1.8 Crema Noble marble threeshold, 250mm width code (ST-001) m 4
1.9 Crema Noble marble threeshold, 120mm width code (ST-001) m 8
WOOD FLOORING
2 Supply engineered wood flooring as per drawings, and specification.
Type, color and samples shall be submitted by the contractor and
approved by the Engineer.
2.1 Oak engineered wood flooring, code (WD-001) m² 55 Rate only
3 Install engineered wood flooring, rate include but not limited to panels,
adhesion, accessories, floor transition thresholds and any activity
required for complete delivery of product as per specification,
drawings and cut sheets .Type, color and samples shall be submitted
by the contractor and approved by the engineer.
3.1 Oak engineered wood flooring, code (WD-001) m² 55
To Collection
Rate Amount
(EGP) (EGP)
PAINTING
Item Description Unit Quantity
Page 4 of 6
Supply and paint high quality acrylic emulsion paint according to
manufacturer instructions and recommended system; rate includes all
materials and accessories required to complete according to drawings
and specification. Type, color and samples shall be submitted by the
contractor and approved by the Engineer
* The contractor should allow in his pricing that the Engineer may use as
many different colors or combination of colors to meet an approved
color scheme. No hand made color mix is allowed.
1 Supply and apply acrylic paint according to approved manufacturer
instruction; rate includes but not limited to clean surface, repair cracks
and all necessary to complete the work as per drawings, cut sheets
and specifications.
1.1 Acrylic paint for internal walls m² 440
1.2 Acrylic paint for internal ceiling m² 123
1.3 Moisture resistant acrylic paint for internal ceiling m² 44
1.4 Moisture resistant acrylic paint for walls m² 65
CEMENTITIOUS COATINGS
Supply and paint high quality cementitious paint according to
manufacturer instructions and recommended system; rate includes all
materials and accessories required to complete according to drawings
and specification. Type, color and samples shall be submitted by the
contractor and approved by the Engineer
* The contractor should allow in his pricing that the Engineer may use as
many different colors or combination of colors to meet an approved
color scheme. No hand made color mix is allowed.
2 Supply and apply cementious paint according to approved
manufacturer instruction; rate includes but not limited to clean surface,
repair cracks and all necessary to complete the work as per drawings,
cut sheets and specifications. Refer to drawing no.(A-201, A-202)
2.1 Cementitious paint for external walls & soffits, code (PT-01) & (PT-04)
& (PT-05) m² 425
To Collection
Amount
(EGP)
Total Division Summary
Item Description
Page 5 of 6
Page No 2
Page No 3
Page No 4
Page No 5
Total Division 09 Finishes
To Summary
Page 6 of 6

More Related Content

What's hot

Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavation
Al-Amin Ahmed Nabin
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
Pang Khai Shuen
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compile
Timun Loh
 
Bq preamble
Bq preambleBq preamble
Bq preambleaizat76
 
Building Construction and Tech. 3. Responsibilities of participants
Building Construction and Tech. 3. Responsibilities of participantsBuilding Construction and Tech. 3. Responsibilities of participants
Building Construction and Tech. 3. Responsibilities of participantsHamdija Velagic
 
DD STAGE COST ESTIMATE SECTION 1 (J102) (1)
DD STAGE COST ESTIMATE SECTION 1 (J102) (1)DD STAGE COST ESTIMATE SECTION 1 (J102) (1)
DD STAGE COST ESTIMATE SECTION 1 (J102) (1)Gayan Kalpitha Perera
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
sooricivil
 
Mooc smm substructure_2
Mooc smm substructure_2Mooc smm substructure_2
Mooc smm substructure_2
Azizan Supardi
 
Marshall Mix Design: Lab Report
Marshall Mix Design: Lab ReportMarshall Mix Design: Lab Report
Marshall Mix Design: Lab Report
Priyansh Singh
 
Topic 2 area & volume
Topic 2   area & volumeTopic 2   area & volume
Topic 2 area & volumekmasz kamal
 
DESIGN OF FLAT SLABS
DESIGN OF FLAT SLABSDESIGN OF FLAT SLABS
DESIGN OF FLAT SLABS
sharda university
 
Construction Materials and Engineering - Module I - Lecture Notes
Construction Materials and Engineering - Module I - Lecture NotesConstruction Materials and Engineering - Module I - Lecture Notes
Construction Materials and Engineering - Module I - Lecture Notes
SHAMJITH KM
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Eccentric connections in steel structure
Eccentric connections in steel structureEccentric connections in steel structure
Eccentric connections in steel structure
Sarvesh Sureshrao Chikte
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surfaceMinh Bui Si
 

What's hot (20)

Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavation
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compile
 
Bq preamble
Bq preambleBq preamble
Bq preamble
 
Building Construction and Tech. 3. Responsibilities of participants
Building Construction and Tech. 3. Responsibilities of participantsBuilding Construction and Tech. 3. Responsibilities of participants
Building Construction and Tech. 3. Responsibilities of participants
 
DD STAGE COST ESTIMATE SECTION 1 (J102) (1)
DD STAGE COST ESTIMATE SECTION 1 (J102) (1)DD STAGE COST ESTIMATE SECTION 1 (J102) (1)
DD STAGE COST ESTIMATE SECTION 1 (J102) (1)
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Anti termite treatment in foundation
Anti termite treatment in foundationAnti termite treatment in foundation
Anti termite treatment in foundation
 
Mooc smm substructure_2
Mooc smm substructure_2Mooc smm substructure_2
Mooc smm substructure_2
 
Marshall Mix Design: Lab Report
Marshall Mix Design: Lab ReportMarshall Mix Design: Lab Report
Marshall Mix Design: Lab Report
 
5.1 quantity take-off
5.1 quantity take-off5.1 quantity take-off
5.1 quantity take-off
 
Problem in bored pile
Problem in bored pileProblem in bored pile
Problem in bored pile
 
Topic 2 area & volume
Topic 2   area & volumeTopic 2   area & volume
Topic 2 area & volume
 
DESIGN OF FLAT SLABS
DESIGN OF FLAT SLABSDESIGN OF FLAT SLABS
DESIGN OF FLAT SLABS
 
Construction Materials and Engineering - Module I - Lecture Notes
Construction Materials and Engineering - Module I - Lecture NotesConstruction Materials and Engineering - Module I - Lecture Notes
Construction Materials and Engineering - Module I - Lecture Notes
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
Eccentric connections in steel structure
Eccentric connections in steel structureEccentric connections in steel structure
Eccentric connections in steel structure
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surface
 
Section 400
Section 400Section 400
Section 400
 

Similar to Bill Of Quantities Issued For Construction

Contract presentation
Contract presentation  Contract presentation
Contract presentation
amity university
 
Bo q for joint cuart hall block construction in pamir (3)
Bo q for joint cuart hall block construction in pamir (3)Bo q for joint cuart hall block construction in pamir (3)
Bo q for joint cuart hall block construction in pamir (3)
Stephen Nzima
 
Building Schedule Rates - 2019 N.P
Building Schedule Rates - 2019 N.PBuilding Schedule Rates - 2019 N.P
Building Schedule Rates - 2019 N.P
Vj NiroSh
 
Construction Estimating.pdf
Construction Estimating.pdfConstruction Estimating.pdf
Construction Estimating.pdf
SoniaGandhi26
 
Aluminum work
Aluminum workAluminum work
Aluminum work
Rajiva Gupta
 
A Course Material On Estimation And Quantity Surveying
A Course Material On Estimation And Quantity SurveyingA Course Material On Estimation And Quantity Surveying
A Course Material On Estimation And Quantity Surveying
Claire Webber
 
Brochure contractor registration_guidelines
Brochure contractor registration_guidelinesBrochure contractor registration_guidelines
Brochure contractor registration_guidelines
muhammad Taupik
 
Lec- 3.ppt domabd gerhjddj gedawquun bhajk
Lec- 3.ppt domabd gerhjddj gedawquun bhajkLec- 3.ppt domabd gerhjddj gedawquun bhajk
Lec- 3.ppt domabd gerhjddj gedawquun bhajk
2cd
 
Estimation and costing book
Estimation and costing bookEstimation and costing book
Estimation and costing book
Subash Pathak
 
Estimating-Costing-civil.pdf
Estimating-Costing-civil.pdfEstimating-Costing-civil.pdf
Estimating-Costing-civil.pdf
DivyaTadepalli1
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
DougDos
 
Lec - 2.ppt ganbella university quantity estimta
Lec - 2.ppt ganbella university quantity estimtaLec - 2.ppt ganbella university quantity estimta
Lec - 2.ppt ganbella university quantity estimta
2cd
 
EDUARDO H. PARE SPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKS
EDUARDO H. PARE SPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKSEDUARDO H. PARE SPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKS
EDUARDO H. PARE SPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKS
Eduardo H. Pare
 
EDUARDO H. PARE CIVIL, STRUCTURAL AND ARCHITECTURAL SPECIFICATIONS
EDUARDO H. PARE CIVIL, STRUCTURAL AND ARCHITECTURAL SPECIFICATIONSEDUARDO H. PARE CIVIL, STRUCTURAL AND ARCHITECTURAL SPECIFICATIONS
EDUARDO H. PARE CIVIL, STRUCTURAL AND ARCHITECTURAL SPECIFICATIONS
Eduardo H. Pare
 
SPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKS
SPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKSSPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKS
SPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKSEduardo H. Pare
 
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdfTender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
ssuserd43de8
 
2000v04 economy
2000v04 economy2000v04 economy
2000v04 economy
Johneey Deep
 

Similar to Bill Of Quantities Issued For Construction (20)

Contract presentation
Contract presentation  Contract presentation
Contract presentation
 
Bo q for joint cuart hall block construction in pamir (3)
Bo q for joint cuart hall block construction in pamir (3)Bo q for joint cuart hall block construction in pamir (3)
Bo q for joint cuart hall block construction in pamir (3)
 
Building Schedule Rates - 2019 N.P
Building Schedule Rates - 2019 N.PBuilding Schedule Rates - 2019 N.P
Building Schedule Rates - 2019 N.P
 
Construction Estimating.pdf
Construction Estimating.pdfConstruction Estimating.pdf
Construction Estimating.pdf
 
Aluminum work
Aluminum workAluminum work
Aluminum work
 
1200 13
1200 131200 13
1200 13
 
1200 8
1200 81200 8
1200 8
 
A Course Material On Estimation And Quantity Surveying
A Course Material On Estimation And Quantity SurveyingA Course Material On Estimation And Quantity Surveying
A Course Material On Estimation And Quantity Surveying
 
Brochure contractor registration_guidelines
Brochure contractor registration_guidelinesBrochure contractor registration_guidelines
Brochure contractor registration_guidelines
 
Lec- 3.ppt domabd gerhjddj gedawquun bhajk
Lec- 3.ppt domabd gerhjddj gedawquun bhajkLec- 3.ppt domabd gerhjddj gedawquun bhajk
Lec- 3.ppt domabd gerhjddj gedawquun bhajk
 
Estimation and costing book
Estimation and costing bookEstimation and costing book
Estimation and costing book
 
2_2._BOQ.pdf
2_2._BOQ.pdf2_2._BOQ.pdf
2_2._BOQ.pdf
 
Estimating-Costing-civil.pdf
Estimating-Costing-civil.pdfEstimating-Costing-civil.pdf
Estimating-Costing-civil.pdf
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
 
Lec - 2.ppt ganbella university quantity estimta
Lec - 2.ppt ganbella university quantity estimtaLec - 2.ppt ganbella university quantity estimta
Lec - 2.ppt ganbella university quantity estimta
 
EDUARDO H. PARE SPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKS
EDUARDO H. PARE SPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKSEDUARDO H. PARE SPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKS
EDUARDO H. PARE SPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKS
 
EDUARDO H. PARE CIVIL, STRUCTURAL AND ARCHITECTURAL SPECIFICATIONS
EDUARDO H. PARE CIVIL, STRUCTURAL AND ARCHITECTURAL SPECIFICATIONSEDUARDO H. PARE CIVIL, STRUCTURAL AND ARCHITECTURAL SPECIFICATIONS
EDUARDO H. PARE CIVIL, STRUCTURAL AND ARCHITECTURAL SPECIFICATIONS
 
SPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKS
SPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKSSPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKS
SPECS & SW_BUILDING & UNDERGROUND CABLES CIVIL WORKS
 
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdfTender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
 
2000v04 economy
2000v04 economy2000v04 economy
2000v04 economy
 

Recently uploaded

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 

Recently uploaded (20)

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 

Bill Of Quantities Issued For Construction

  • 1. Faculty of Engineering Tanta University Ahmed Mohamed El Ashry Prepared By: Bill Of Quantities Issued For Construction - Rev.00 Civil engineering Builging December, 2022
  • 2. PREAMBLE TO BILL OF QUANTITIES
  • 3. PREAMBLE TO BILL OF QUANTITIES 1.1 A B 1 Division 03:Concrete 2 Division 04: Masonry 3 Division 05:Metals 4 Division 06:Wood, Plastics 5 6 7 8 Division 10: Specialties 9 Division 31: Earthwork 1.2 PRICING PREAMBLES A B C a b c d e E H List of Abbreviations: m METER m2 SQUARE METER m3 CUBIC METER The method of measurement used is POMI. Materials and goods including all connected costs. Preparatory works and setting out of particular item. All equipment, tools, etc. for the proper and safe completion of the relevant item of work. All other incidental works and necessary works which are not described in the B.O.Q but described in the aforesaid specifications and or shown in the drawings for the proper completion of the relevant item of work. In addition to above, the rate for items of work shall include for cost implemented as result of complying with Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, HSE regulations and ruling laws. Labor and connected costs. CONTENTS OF THE BILLS OF QUANTITIES Bills of quantities, prepared in accordance with Construction Specifications Institute CSI (MASTERFORMAT 2012), fully describe and accurately represent the works to be executed and this provides a uniform basis for competitive tendering. Specifications and Bills of Quantities may consist some or all of the followings: Division 07: Thermal & Moisture Insulation Division 08: Opening Division 09: Finishes Should any discrepancy occur between these Preambles, the descriptions, the drawings and any other Contract Documents, the Tenderer (Contractor afterwards) shall obtain instructions from the Engineer before proceeding. The rate for each item must be comprehensive and must include for complying in all respects with the requirements of the aforesaid specifications, these pricing preambles, cover all the obligations/liabilities under the contract, and all matters and things necessary for the proper construction, completion, commissioning and maintenance of the The rates and prices entered in the Bills of Quantities shall be deemed to be the full inclusive value of the work covered by the several items including the following unless expressly stated separately otherwise:
  • 5. Rate Amount (EGP) (EGP) DIVISION 03 CONCRETE The Contractor is referred to the specifications and drawings for all details related to the works and he is to include for complying with all the requirements contained therein, whether or not they are specifically mentioned within the items. All Tender documents (Drawings, Bill of quantities, Specifications) are integrated documents and complete each other. Workshop drawings and frames for approval before supply and installation (as per approved sample) * Rates for all concrete items shall include shuttering, steel reinforcement, testing for steel reinforcement, water stop, placing of concrete, vibrating, curing, striking, workmanship, finish, all ducts, sleeves, opening areas and all according to drawings, specifications, conditions and directed instructions by the Engineer CAST-IN-PLACE CONCRETE 1 Supply and cast plain concrete with required compressive strength as per structure drawings; rate includes but not limited to casting using concrete pump, formwork, construction joints, sealant filled, finishing surface to receive waterproofing and all necessary to complete the work as per structure drawings and specifications. 1.1 Plain concrete footings m³ 21 ١٢٠٠ 25,200 1.2 Plain concrete below ground beams m³ 5 ١٢٠٠ 6,000 2 Supply and cast reinforced concrete with required compressive strength as per structure drawings; rate includes but not limited to casting using concrete pump, formwork, steel reinforcement, expansion and construction joints, joint filler, sealant, surface repair to receive waterproofing, rain scupper and all accessories necessary to complete the work as per structure drawings and specifications. 2.1 Footings m³ 638 ١٢٠٠ 765,600 2.2 Columns neck m³ 70 ١٢٠٠ 84,000 2.3 Ground beams m³ 525 ١٨٠٠ 945,000 2.4 Slab on grade,150mm thick m² 2,870 ١٨٠٠ 5,166,000 2.5 Slabs m³ 5,393 ١٨٠٠ 9,707,400 2.6 Columns m³ 979 ١٨٠٠ 1,762,092 2.7 Beams m³ 300 ١٨٠٠ 540,000 2.8 Roof parapet m³ 140 ١٢٠٠ 168,000 2.9 Stairs m³ 172 ١٨٠٠ 309,600 LIGHTWEIGHT CONCRETE ROOF INSULATION 3 Supply and cast lightweight concrete flooring with the required slope; rate includes but not limited to joint sealants, trowel, finish reinforcement (where required) and all accessories necessary to complete the work as per drawings and specifications. Refer to drawing no. (A-502) Item Description Unit Quantity Page 2 of 3
  • 6. 3.1 Lightweight concrete for roof and terraces; 130:70mm thick m² 140 260 36,400 To Collection Amount (EGP) Total Division Summary Page No 2 Total Division 03 Concrete 19,515,292 To Summary Item Description Page 3 of 3
  • 8. Rate Amount (EGP) (EGP) DIVISION 04 MASONRY All items rates include supply materials, apply and / or execute work according to contract conditions, specifications and drawings. Also include the required construction equipment's, samples and tests. All Tender documents (Drawings, Bill of quantities, Specifications) are integrated documents and complete each other CONCRETE UNIT MASONRY 1 Supply and install concrete blocks; rate includes cement mortar, solid jambs at openings, lintels, embedded expansion metals, galvanized steel anchors, wall ties, metal Lath reinforcement, stiffeners, jointing, Rockwool insulation (if required) and all required work for completion according to drawings and specifications. The contractor is to provide all necessary wall reinforcements, wall supports / blocking and necessary fixation to receive loads & weights of all ID elements, finishes, cladding and FF&E items mounted on walls (Like for example “Interior Plantings & Trees” – “Draperies” – “Furniture - Artwork & Accessories” – “Television Sets & Mounting Hardware” …etc) according to ID drawings & documents, the contractor should also submit shop drawings for the Engineers approval prior to installation. 1.1 Solid concrete brick for 250mm wall for underground masonry; size (250Lx120Wx60H) mm m³ 66 450 29,700 1.2 Solid concrete brick for 250mm wall; type (W01) size (250Lx120Wx60H) mm m³ 3,028 450 1,362,600 1.3 Hollow concrete block for 250mm wall; type (W02) size (400Lx250Wx200H) mm m³ 3 450 1,125 1.4 Solid concrete brick for 120mm wall;type (W03), size (250Lx120Wx60H) mm m³ 110 210 23,100 1.5 Hollow concrete block for 120mm wall; type (W04) size (400Lx120Wx200H) mm m³ 82 210 17,220 EXTERIOR STONE CLADDING 2 Supply and install natural stone cladding; rate includes but not limited to fixation system , waterproofing behind, filling grout, reveal, trims, accessories, finish, approved sample and all necessary to complete the work as per drawings and specifications 2.1 Melly gray marble skirting; 20mm thick, 1200mm max. high, type (ST-04) m² 1,448 240 61,920 2.2 Melly gray marble skirting; 20mm thick, 1000mm max. high m² 258 160 41,280 To Collection Item Description Unit Quantity Page 2 of 3
  • 9. Amount (EGP) Total Division Summary Page No 2 Total Division 04 Masonry 1,519,725 To Summary Item Description Page 3 of 3
  • 11. Rate Amount (EGP) (EGP) DIVISION 05 METALS All metal work includes fixing, finish, painting, accessories and work required for fixation. Samples shall be submitted by the contractor and approved by the Engineer. Complete all work according to drawings and specification. METAL RAILINGS 2 Supply and install aluminum handrail; rate includes but not limited to painted rail, fixation, paint, finish and all necessary to complete the work as per drawings and specifications. Approved samples shall be submitted by the contractor and approved by the Engineer. Refer to drawing no. (A-505) 2.1 Floor mounted handrial for terraces, 1000mm high kgr ٥٩٧ 2.2 Floor mounted handrial above parapet, 800mm high kgr ٥٩٧ Total Division 05 Metals To Summary Item Description Unit Quantity Page 2 of 2
  • 12. DIVISION 06 WOOD, PLASTICS AND COMPOSITES Page 1 of 2
  • 13. Rate Amount (EGP) (EGP) DIVISION 06: WOOD, PLASTICS, AND COMPOSITES All items rates include supply materials, install and / or execute work according to contract conditions , specifications and drawings. Also include the required construction equipment's, samples and tests. ARCHITECTURAL WOOD CASEWORK 1 Supply and install laminated MDF skirting; rate includes but not limited to fixation,trims, laminate, finish, approved samples and all necessary to complete the work as per drawings, cut sheets and specifications. Type, color and samples shall be submitted by the contractor and approved by the Engineer. 1.1 Oak Laminated on MDF skirting, 100mm high, Code (SK-002) m 45 26.00 1,170.00 To Collection Total Division Summary Total Division 06 Wood, Plastics and composites 1,170.00 To Summary Item Description Unit Quantity Page 2 of 2
  • 14. DIVISION 07 THERMAL AND MOISTURE PROTECTION Page 1 of 3
  • 15. Rate Amount (EGP) (EGP) DIVISION 07 THERMAL AND MOISTURE PROTECTION The Contractor is referred to the specifications and drawings for all details related to the works of this division and he is to include for complying with all the requirements contained therein, whether or not they are specifically mentioned within the item. Scope of work will be: shop drawings issue, systems supply, installation and testing. BITUMINOUS DAMPPROOFING 1 Supply and apply cold applied rubberized bituminous dampproofing paint, rate includes but not limited to prepare surfaces, testing, sub-base layers and any material or activity required to complete all work according to drawings and specifications 1.1 Cold fluid applied damp-proofing for foundations m² 254 50 12,700 THERMAL INSULATION 3 Supply and apply extruded polystyrene foam for thermal insulation; rate includes but not limited to preparation works, protection layer (Geotextile), testing and all necessary to complete the work as per drawings and specifications. Refer to drawing no. (A-502) 3.1 Thermal insulation for roof; 70mm thick m² 2,047 48 98,256 ROOF TILES 4 Supply and install cement tiles; rate includes but not limited to cement mortar, finish and all material or activity required to finish the work as per drawings and specification. Type, color and samples shall be submitted by the contractor and approved by the Engineer 4.1 Cement tiles for roof, size (300x300x30)mm m² 20 134 2,680 4.2 Ditto, but for base, 300mm high m 22 - MODIFIED BITUMINOUS MEMBRANE 5 Supply and install waterproofing membrane, rate includes prepare surfaces, overlap, testing, protection board as per drawing and any material or activity required to complete work according to drawings and specifications. 5.1 Waterproofing membrane for roof and terraces, 4mm thick m² 2,047 50 102,350 5.2 Waterproofing membrane for wet area, 4mm thick m² 559 50 27,950 To Collection Amount (EGP) Total Division Summary Page No 2 Item Description Item Description Unit Quantity Page 2 of 3
  • 16. Total Division 07 Thermal and Moisture Protection 243,936 To Summary Page 3 of 3
  • 18. Rate Amount (EGP) (EGP) DIVISION 08 : OPENINGS All items rates include supply materials, install and / or execute work according to contract conditions, specifications and drawings. All Tender documents (Drawings, Bill of quantities, Specifications) are integrated documents and complete each other WOOD DOORS 1 Supply and install external wooden doors as per drawings; rate includes but not limited to sub-frames, wooden frames, architraves, leaves, fittings, joint sealant, paint, finish and all necessary to complete the work as per drawings and specifications. Approved samples shall be submitted by the contractor and approved by the Engineer. 1.1 External wooden solid flush door with natural oak veneer coated with polyurethane finish, type (D01), size (1200x2400)mm No 32 340 10,880 2 Supply and install internal wooden doors as per drawings; rate includes but not limited to sub-frames, wooden frames , architraves, leaves, fittings, joint sealant, paint, finish and all necessary to complete the work as per drawings and specifications. Approved samples shall be submitted by the contractor and approved by the Engineer. Refer to drawing no (GD-AF-304) & (GD-AF-305) 2.1 Semi solid wooden door type (D01), size (900x2180)mm No 79 280 22,120 2.4 Semi solid wooden door type (D06), size (800x2200)mm No 74 420 31,080 ALUMINUM WINDOW 3 Supply and install electrostatic powder coated aluminum windows with float glass 6mm thick as per drawing; rate includes but not limited to fixation, insulated composite aluminum panels, glazing panel, insect screens, hardware sets, spacer, sealant, finish and any material or activity required to complete work as per drawings and specification. Type, color and samples shall be submitted by the contractor and approved by the Engineer. Refer to drawing no.(A-601) 3.1 Window type (AL-02), size (700x1200)mm No 5 - 3.2 Window type (AL-03), size (900x1200)mm No 18 - To Collection 64,080 Item Description Unit Quantity Page 2 of 5
  • 19. Rate Amount (EGP) (EGP) ALUMINUM WINDOW CONT' 1 Supply and install electrostatic powder coated aluminum windows with tempered glass 6mm thick as per drawing; rate includes but not limited to fixation, insulated composite aluminum panels, glazing panel, insect screens, hardware sets, spacer, sealant, finish and any material or activity required to complete work as per drawings and specification. Type, color and samples shall be submitted by the contractor and approved by the Engineer. Refer to drawing no.(A-601) 1.1 Window type (AL-01), size (700x2400)mm No 28 670 18,760 1.2 Wndow door type (AL-06), size (900x2400)mm No 2 ٩٥٠ 1,900 1.6 Wndow door type (AL-10), size (1800x2400)mm No 128 ١٤٥٠ 185,600 2 Supply and install electrostatic powder coated aluminum window door with tempered glass 6mm thick as per drawing; rate includes but not limited to fixation, insulated composite aluminum panels, glazing panel, insect screens, hardware sets, spacer, sealant, finish and any material or activity required to complete work as per drawings and specification. Type, color and samples shall be submitted by the contractor and approved by the Engineer. Refer to drawing no.(A-601) 2.1 Window door type (AL-04), size (2000x2400)mm No 3 - 2.2 Wndow door type (AL-05), size (3980/1250x2400)mm No 1 - DOORS HARDWARE All items rates include but not limited to supply materials, install and / or execute work according to specifications, drawings and cut sheets. Also include the required construction equipment's, samples and tests. All Tender documents (Drawings, Bill of quantities, Specifications) are integrated documents and complete each other 3 Supply door hardware sets as shown in schedule, samples shall be submitted by the contractor and approved by the engineer. Complete all work according to drawings, cut sheets and specification 3.1 Door Hardware Set, Code (1) No 3 Rate Only 3.2 Door Hardware Set, Code (2) No 5 Rate Only 3.3 Door Hardware Set, Code (3) No 3 Rate Only 3.4 Door Hardware Set, Code (4) No 1 Rate Only To Collection 206,260 Quantity Item Description Unit Page 3 of 5
  • 20. Rate Amount (EGP) (EGP) DOORS HARDWARE CONT 1 Install door hardware sets as shown in schedule, rate include but not limited to fixation, finish and all necessary to complete the work. samples shall be submitted by the contractor and approved by the engineer. Complete all work according to drawings, cut sheets and specification 1.1 Door Hardware Set, Code (1) No 3 - 1.2 Door Hardware Set, Code (2) No 5 - 1.3 Door Hardware Set, Code (3) No 3 - 1.4 Door Hardware Set, Code (4) No 1 - MIRRORS 2 Supply and install 6mm thick mirror; rate includes but not limited to supporting system, finish, frame, and any material or activity required to complete work as per drawings and specification. Type, color and samples shall be submitted by the contractor and approved by the Engineer. Ref drawing no. (CG-V4B-AF-202), (CG-V4B-AF-204), (CG-V4B-AF-206), (CG- V4B-AF-208), (GD-AF-305). 2.1 Mirror for toilets size (1000x1000)mm, code (GL-001) with metal frame code (MT-003) No 10 - 2.2 Mirror for toilets size (720x1000)mm, code (GL-001) with metal frame code (MT-003) No 10 - 2.3 Mirror for toilets size (660x1000)mm, code (GL-001) with metal frame code (MT-003) No 10 - 2.4 Mirror for toilets size (650x1000)mm, code (GL-001) with metal frame code (MT-003) No 10 - 2.5 Mirror for toilets size (550x1000)mm, code (GL-001) with metal frame code (MT-003) No 10 - Item Description Unit Quantity Page 4 of 5
  • 21. To Collection Amount (EGP) Total Division Summary Page No 2 64,080 Page No 3 206,260 Page No 4 - Total Division 08 Openings To Summary 270,340 Item Description Page 5 of 5
  • 23. Rate Amount (EGP) (EGP) DIVISION 09 FINISHES All finishes work includes prepare surface, application, accessories, cleaning and work required to finish according to drawings, specification and manufacturers data sheets. Shop drawings and samples shall be submitted by the contractor and approved by the Engineer. Complete all work according to drawings and specification. PORTLAND CEMENT PLASTERING 1 Supply and apply plaster on concrete or masonry walls; rate includes but not limited to angles beads,metal lath, wire mesh, accessories and all required to complete the work as per drawings and specification. 1.1 Plaster for internal walls 15mm thick m² 586 1.2 Plaster for internal ceiling, 15mm thick m² 123 1.3 Plaster for externall walls 20mm thick m² 425 GYPSUM BOARD ASSEMBLIES 2 Supply and install gypsum board for suspended ceilings as per drawings; rate includes but not limited to fixation system, accessories, access panels, sealant, bulk head, light coves, pattern, finish, shadow gab and any material or activity required to complete work as per drawings and specification. Type, color and samples shall be submitted by the contractor and approved by the Engineer 2.1 Gypsum board false ceiling, m² 33 2.2 Moisture resistant gypsum board false ceiling m² 33 TILING 3 Supply and install cement tiles; rate includes but not limited to cement mortar, finish and all material or activity required to finish the work as per drawings and specification. Type, color and samples shall be submitted by the contractor and approved by the Engineer 3.1 Cement tiles to receive finishes, size (300x300x30) m² 55 CERAMIC TILING 4 Supply and install porcelain/ceramic tiles from ceramica innova or equivalent; rate includes but not limited to all required design pattern as per finish schedule, cement mortar, grouting, adhesive material (if required), joint spacers, accessories, finish and any material or activity required to complete work as per drawings, cut sheets and specification. Flooring 4.1 Slip resistant porcelain tiles, size (1100x600)mm, code (CT-001) m² 30 4.2 Slip resistant ceramic tiles, size (450x450)mm, code (CT-003) m² 5 4.3 Porcelain tiles, size (600x600)mm, code (CT-005) m² 105 To Collection Rate Amount (EGP) (EGP) Item Description Unit Quantity Quantity Item Description Unit Page 2 of 6
  • 24. CERAMIC TILING CONT' 1 Supply and install porcelain/ceramic tiles from ceramica innova or equivalent; rate includes but not limited to all required design pattern as per finish schedule, cement mortar, grouting, adhesive material (if required), joint spacers, accessories, finish and any material or activity required to complete work as per drawings, cut sheets and specification. Walls 1.1 Porcelain tiles, size (1100x600)mm, code (CT-002) m² 50 1.2 Porcelain tiles, size (450x450)mm, code (CT-004) m² 31 Skirting 1.3 Porcelain skirting,100mm high, code (SK-003) m 18 1.4 Ceramic skirting,100mm high, code (SK-004) m 10 1.5 Porcelain skirting for terraces,100mm high, code (SK-005) m 21 GLASS MOSAIC TILING 2 Supply and install mosaic tiles from Mahgoub or equivalent; rate includes but not limited to all required design pattern as per finish schedule, cement mortar, grouting, adhesive material (if required), joint spacers, accessories, finish and any material or activity required to complete work as per drawings, cut sheets and specification. Walls 2.1 Mosaic tiles, size (20x20)mm, code (CT-006) m² 2 STONE FLOORING 3 Supply and install marble tiles; rate includes but not limited to all required design pattern as per finish schedule, cement mortar, grouting, self leveling screed, adhesive material (if required), joint spacers, accessories, finish and any material or activity required to complete work as per drawings, cut sheets and specification. 3.1 Crema Noble marble flooring, size (1200x600)mm, code (ST-001) m² 65 To Collection Rate Amount (EGP) (EGP) STONE FLOORING CONT Quantity Item Description Unit Page 3 of 6
  • 25. 1 Supply and Install stone for treads & risers fixed on concrete stair; rate includes but not limited to adhesive mortar, accessories, finish, approved samples, shop drawings, cut sheets and all necessary to complete the work as per drawings and specifications. 1.1 Crema Noble marble risers for internal stairs, 20mm thickness, code (ST-001) m 48 1.2 Crema Noble marble treads for internal stairs 40 mm thickness, code (ST-001) m 48 1.3 Crema Noble marble for staircases for landing 20mm thick, code (ST- 001) m² 5 1.4 Melly gray marble risers for external stairs steps 20mm thickness, code (ST- 04) m 27 1.5 Melly gray marble treads for external stairs steps 40mm thickness, code (ST- 04) m 27 1.6 Melly gray marble landing for external stairs steps 20mm thickness, code (ST- 04) m² 5 Skirting 1.7 Crema Noble marble skirting,100mm high, code (SK-001) m 50 Threshold 1.8 Crema Noble marble threeshold, 250mm width code (ST-001) m 4 1.9 Crema Noble marble threeshold, 120mm width code (ST-001) m 8 WOOD FLOORING 2 Supply engineered wood flooring as per drawings, and specification. Type, color and samples shall be submitted by the contractor and approved by the Engineer. 2.1 Oak engineered wood flooring, code (WD-001) m² 55 Rate only 3 Install engineered wood flooring, rate include but not limited to panels, adhesion, accessories, floor transition thresholds and any activity required for complete delivery of product as per specification, drawings and cut sheets .Type, color and samples shall be submitted by the contractor and approved by the engineer. 3.1 Oak engineered wood flooring, code (WD-001) m² 55 To Collection Rate Amount (EGP) (EGP) PAINTING Item Description Unit Quantity Page 4 of 6
  • 26. Supply and paint high quality acrylic emulsion paint according to manufacturer instructions and recommended system; rate includes all materials and accessories required to complete according to drawings and specification. Type, color and samples shall be submitted by the contractor and approved by the Engineer * The contractor should allow in his pricing that the Engineer may use as many different colors or combination of colors to meet an approved color scheme. No hand made color mix is allowed. 1 Supply and apply acrylic paint according to approved manufacturer instruction; rate includes but not limited to clean surface, repair cracks and all necessary to complete the work as per drawings, cut sheets and specifications. 1.1 Acrylic paint for internal walls m² 440 1.2 Acrylic paint for internal ceiling m² 123 1.3 Moisture resistant acrylic paint for internal ceiling m² 44 1.4 Moisture resistant acrylic paint for walls m² 65 CEMENTITIOUS COATINGS Supply and paint high quality cementitious paint according to manufacturer instructions and recommended system; rate includes all materials and accessories required to complete according to drawings and specification. Type, color and samples shall be submitted by the contractor and approved by the Engineer * The contractor should allow in his pricing that the Engineer may use as many different colors or combination of colors to meet an approved color scheme. No hand made color mix is allowed. 2 Supply and apply cementious paint according to approved manufacturer instruction; rate includes but not limited to clean surface, repair cracks and all necessary to complete the work as per drawings, cut sheets and specifications. Refer to drawing no.(A-201, A-202) 2.1 Cementitious paint for external walls & soffits, code (PT-01) & (PT-04) & (PT-05) m² 425 To Collection Amount (EGP) Total Division Summary Item Description Page 5 of 6
  • 27. Page No 2 Page No 3 Page No 4 Page No 5 Total Division 09 Finishes To Summary Page 6 of 6