This document provides information on the design and construction of a coal loading jetty and stockpile area. It includes details such as:
- The elevation difference between water and land levels of approximately 5 meters.
- A hauling road of 40 km between the mining area and loading jetty.
- Conceptual designs of the stockpile area, loading conveyor, and barge loading configuration.
- Survey results and soil condition analyses to inform the jetty and foundation designs.
- Project milestones for completing the environmental impact analysis, land acquisition, and construction activities over a 6-month period from October 2011 through March 2012.
Operation concerned Hydraulic set packer using tandem packer with mechanical set ETI-R3 for zonal isolation...in Mann Oil Field, Central basin of Myanmar.
Operation concerned Hydraulic set packer using tandem packer with mechanical set ETI-R3 for zonal isolation...in Mann Oil Field, Central basin of Myanmar.
The significance of Surface Logging For The Formation Evaluation Advance Surf...Evangelos Siskos
The significance of Surface Logging For The Formation Evaluation Advance Surface Logging Technology is a Master of Science Thesis presentation for the MSc in Oil & Gas Technology program at Eastern Macedonia and thrace Institute of Technology.
The significance of Surface Logging For The Formation Evaluation Advance Surf...Evangelos Siskos
The significance of Surface Logging For The Formation Evaluation Advance Surface Logging Technology is a Master of Science Thesis presentation for the MSc in Oil & Gas Technology program at Eastern Macedonia and thrace Institute of Technology.
An ICON OF PORTO MONTENEGRO
original and methodical, striking and practical, I always am showing how important symbolism, heritage , sculptural architecture can be- very simple in construction, while suggesting visually complex and vibrant sculpture;
in this case, porto montenegro is basically a brand new project, so, i could not rely on it’s history, besides it’s aspirations for the future.. so Design inspiration behind the idea of a metaphor through an innovative designs, to express the essence of the Porto Montenegro, its aspiration and ambitions. Our intent is to create an experience that ranges from wonder and appreciation of the surprise effect but the one that blends an effortless comfort and a perfect balance between our vision, form, function, environment and of course the budget with all of your other requirements and needs.
This project is emerging from the setting, it is shaped by water temperament, as an original solution to the provision of effortless, graceful and efficient design.
• Idea is to create an original, distinctive and innovative architectural structure as a symbol, state of the art symbiosis , that solves the function and blends in the environment, to be an icon of mne;
• One that has a wow – a surprise effect-as a unique sea welcome point that will expand Porto Montenegro in to the sea- create a physical link between water and land;
Mayaguez Seaport Redevelopment Concept Proposal - Circa 2007-8Ramon A. de Mier
Preliminary Conceptual Master Plan proposal for the "wholistic" revitalization of the Municipal Port District (Commercial Seaport, Passenger Terninal and its immediate adjacencies) for the city of Mayaguez, which is physically located upon the west coast [Costa del Sol] of Puerto Rico.
Seaport Working Group Guidelines & Principles - Community Board 1 Open HouseGale A. Brewer
SWG was formed by Manhattan Borough President Gale A. Brewer, Speaker Sheldon Silver, Councilmember Margaret Chin, and Manhattan Community Board 1 in late February, with the purpose of engaging in a candid, community-driven dialogue about development in and around the South Street Seaport Historic District - particularly the proposed mixed use development plan for the New Market Building and Tin Building site by the Howard Hughes Corporation.
Refer to the updated presentation as per PMBOK6:
https://www.slideshare.net/anandbobade/pmp-download-49-processes-chart-pmbok6-links-to-all-slides-link-to-youtube-videos
Need to try and remember the Process Groups and Knowledge Areas of PMBOK, try the mind map approach with this PDF version, you just may be surprise yourself. For all us old hands it also doesn't hurt to refresh yourself every now and again.
Sorry links don't work on slideshare uploaded version, but if you think it may be useful pop over to www.pm250.com and download your own copy.
A case study on Coastal protection structure failure. Quay failure in Port of Barcelona. The presentation describes the failure of harbour walls which occurred at Barcelona on 1st January 2007, associated with an inadequate consideration of the ground conditions in the light of the marine environment. At Barcelona, the construction of the quay wall proceeded at a faster rate than the breakwater. In this case the wharf backfill was placed rapidly on the soft muds, progressing from the inland side. The paper discusses the importance of an overview including the ground investigation, engineering design, construction method and speed of construction. KeywordsBearing capacity–Caissons–Shallow foundations–Failure modes–Study cases
8. Propose Coal Handling and stock pile, for reference only
Loading conveyor 1500 ton/hour capacity
9. Other Optional Propose Plot Plan Gadur Jetty and Mess,Housing
and other facility
Proposed
for mess
and
housing
facility
Extend
Stock Pile
Stock pile and
reclaim feeder
21. Kondisi Banjir 10 tahunan menurut data penduduk lokal elevasi tinggi kurang
lebih 2 meter dari muka tanah
Ketinggian elevasi air pada saat banjir 10 tahunan,pada posisi 1,2 km dari bibir sungai
22. Kondisi Tanah di Jetty
Tanah keras 350 m
Dari bibir sungai
Tanah lembek
berlumpur 1,2 km dari bibir
sungai
23. Contoh test beban untuk mendapatkan consolidated settlement dengan menggunakan model
PLAXIS 2 D
26. Jetty &Stock Pile Milestone
• Construction of Loading and Stock Pile / Jetty Milestone
•
• Item Job description PIC Est Completion
•
• AMDAL Yuanito October 2011
•
• Land Identification/Additional Sukadi August 2011
•
• Land Acquisition Sukadi End Of Sept
•
• Boundary identification Construction team Early Oct 2011
•
• BED/DED Of loading jetty Paul/Ardyan/Adi End Oct 2011
• Stock pile, coal handling
• Bathymetry,Geotech, Topo
• Hydrology, estimate CBM fill
•
• Set up Temporary facility Adi Sumanto Nov 2011
•
• Stacking out area for land clearing Adi Sumanto Nov 2011
• And checking final elevation
• Conveyor center line, jetty position
• Stock pile and chain feeder position
• Coal Crushing Plant,Site Facility
•
• Selected Land clearing Contractor Adi Sumanto Oct 2011
•
• Mobilization land clearing sub con Adi Sumanto Nov 2011
•
• Land Clearing Activities Adi Sumanto March 2012
•