SlideShare a Scribd company logo
BCPC LOADING JETTY AND STOCK PILE
Perbedaan ketinggian elevasi air dengan daratan ± 5 meter dari level
muka air
Survey 27 July 2011
Kondisi Lahan untuk Stock Pile
Survey Tgl 27 July 2011
Orientation of Location from mine pit to loading jetty
Hauling
Road 40 KM
Loading Jetty
Schematic Flow Diagram Stock Pile and Loading Jetty
MINING AREA ROM STOCKPILE AT MINESITE
MINE - HAUL ROAD LONG DISTANCE
HAUL ROAD
COAL TERMINAL
DUMP
STATION
EMERGENCY
STOCKPILE
CRUSHING
STATION
BARGE
LOADING
CONVEYOR
BARGE
Loading Conveyor
Stock pile and Loading conveyor conceptual
Conveyor Lay Out
Conveyor Configuration
Propose Coal Handling and stock pile, for reference only
Loading conveyor 1500 ton/hour capacity
Other Optional Propose Plot Plan Gadur Jetty and Mess,Housing
and other facility
Proposed
for mess
and
housing
facility
Extend
Stock Pile
Stock pile and
reclaim feeder
Contoh Pondasi Jetty
Dolphin to Accommodate
8000 DWT Barge
Loading jetty for 8000 DWT Barge
Coal pile configuration on 8000 DWT
barge
Loading conveyor 1500
ton/hours
Long Profile Of Loading JETTY Accommodate 8000 DWT Barge
Walkways on the trestle
Typical Tower Loading Conveyor ke Barge
CPT Location and land boundary yang dilakukan oleh GRM
Stock Pile,Loading Conveyor dan Loading Jetty untuk 8000 DWT
Survey tanggal 29 July 2011
CONE PENETRATION TEST CPT-10 DENGAN KEDALAMAN 27,4 M
Hasil Cone Penetration Test CPT-10
Contoh Laporan hasil Sondir sebagai referensi
Contoh Laporan Sondir untuk design pondasi dan tiang pancang
Contoh laporan Deep bore hole untuk piling dan pondasi
Kondisi Banjir 10 tahunan menurut data penduduk lokal elevasi tinggi kurang
lebih 2 meter dari muka tanah
Ketinggian elevasi air pada saat banjir 10 tahunan,pada posisi 1,2 km dari bibir sungai
Kondisi Tanah di Jetty
Tanah keras 350 m
Dari bibir sungai
Tanah lembek
berlumpur 1,2 km dari bibir
sungai
Contoh test beban untuk mendapatkan consolidated settlement dengan menggunakan model
PLAXIS 2 D
Indikasi tanah Lembek/Rawa-2 dari hauling road sepanjang 10,5 KM
Tanah lembek dan
berawa
Project Plan Chart
Jetty &Stock Pile Milestone
• Construction of Loading and Stock Pile / Jetty Milestone
•
• Item Job description PIC Est Completion
•
• AMDAL Yuanito October 2011
•
• Land Identification/Additional Sukadi August 2011
•
• Land Acquisition Sukadi End Of Sept
•
• Boundary identification Construction team Early Oct 2011
•
• BED/DED Of loading jetty Paul/Ardyan/Adi End Oct 2011
• Stock pile, coal handling
• Bathymetry,Geotech, Topo
• Hydrology, estimate CBM fill
•
• Set up Temporary facility Adi Sumanto Nov 2011
•
• Stacking out area for land clearing Adi Sumanto Nov 2011
• And checking final elevation
• Conveyor center line, jetty position
• Stock pile and chain feeder position
• Coal Crushing Plant,Site Facility
•
• Selected Land clearing Contractor Adi Sumanto Oct 2011
•
• Mobilization land clearing sub con Adi Sumanto Nov 2011
•
• Land Clearing Activities Adi Sumanto March 2012
•

More Related Content

What's hot

Dragline exclavator
Dragline exclavatorDragline exclavator
Dragline exclavatorVivek Kumar
 
Bucket wheel excavator
Bucket wheel excavatorBucket wheel excavator
Bucket wheel excavatorVR M
 
In-Pit Crushing and Conveying Systems
In-Pit Crushing and Conveying SystemsIn-Pit Crushing and Conveying Systems
In-Pit Crushing and Conveying Systems
shashikanth perumandla
 
Wire ropes used in mining
Wire ropes used in miningWire ropes used in mining
Wire ropes used in mining
Pankaj Kumawat
 
Transportation in underground mines
Transportation  in underground mines Transportation  in underground mines
Transportation in underground mines
vanam mareswara rao
 
Aerial ropeway
Aerial ropewayAerial ropeway
Aerial ropeway
VinaySingh650
 
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
MD.Suresh Kumar
 
Drilling methods
Drilling methodsDrilling methods
Drilling methods
Rajesh Samal
 
Wait and weight vs. driller
Wait and weight vs. drillerWait and weight vs. driller
Wait and weight vs. driller
amrhaggag
 
Rig components
Rig componentsRig components
Rig components
Elsayed Amer
 
Drilling Fluids
Drilling FluidsDrilling Fluids
Drilling Fluids
Mustafa Münir Atagun
 
Porosity
Porosity Porosity
Porosity
M.T.H Group
 
Lab 3 measurement of the viscosity of drilling mud using marsh funnel.
Lab 3 measurement of the viscosity of drilling mud using marsh funnel.Lab 3 measurement of the viscosity of drilling mud using marsh funnel.
Lab 3 measurement of the viscosity of drilling mud using marsh funnel.
Awais Qureshi
 
Drilling fluids
Drilling fluidsDrilling fluids
Drilling fluids
Seham Jalal
 
Haul road design
Haul road designHaul road design
Haul road designVR M
 
Mine transportation system
Mine transportation systemMine transportation system
Mine transportation system
ajeetkm
 
Coal Transportation Methods
Coal Transportation Methods Coal Transportation Methods
Coal Transportation Methods
Shoniza Irfan
 
The significance of Surface Logging For The Formation Evaluation Advance Surf...
The significance of Surface Logging For The Formation Evaluation Advance Surf...The significance of Surface Logging For The Formation Evaluation Advance Surf...
The significance of Surface Logging For The Formation Evaluation Advance Surf...
Evangelos Siskos
 
Introduction to Conveyors.ppt
Introduction to Conveyors.pptIntroduction to Conveyors.ppt
Introduction to Conveyors.ppt
KISHAN KUMAR
 

What's hot (20)

Dragline exclavator
Dragline exclavatorDragline exclavator
Dragline exclavator
 
Bucket wheel excavator
Bucket wheel excavatorBucket wheel excavator
Bucket wheel excavator
 
In-Pit Crushing and Conveying Systems
In-Pit Crushing and Conveying SystemsIn-Pit Crushing and Conveying Systems
In-Pit Crushing and Conveying Systems
 
Wire ropes used in mining
Wire ropes used in miningWire ropes used in mining
Wire ropes used in mining
 
Transportation in underground mines
Transportation  in underground mines Transportation  in underground mines
Transportation in underground mines
 
Aerial ropeway
Aerial ropewayAerial ropeway
Aerial ropeway
 
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
 
Drilling methods
Drilling methodsDrilling methods
Drilling methods
 
Wait and weight vs. driller
Wait and weight vs. drillerWait and weight vs. driller
Wait and weight vs. driller
 
Rig components
Rig componentsRig components
Rig components
 
Drilling Fluids
Drilling FluidsDrilling Fluids
Drilling Fluids
 
Porosity
Porosity Porosity
Porosity
 
Lab 3 measurement of the viscosity of drilling mud using marsh funnel.
Lab 3 measurement of the viscosity of drilling mud using marsh funnel.Lab 3 measurement of the viscosity of drilling mud using marsh funnel.
Lab 3 measurement of the viscosity of drilling mud using marsh funnel.
 
Working of dragline
Working of draglineWorking of dragline
Working of dragline
 
Drilling fluids
Drilling fluidsDrilling fluids
Drilling fluids
 
Haul road design
Haul road designHaul road design
Haul road design
 
Mine transportation system
Mine transportation systemMine transportation system
Mine transportation system
 
Coal Transportation Methods
Coal Transportation Methods Coal Transportation Methods
Coal Transportation Methods
 
The significance of Surface Logging For The Formation Evaluation Advance Surf...
The significance of Surface Logging For The Formation Evaluation Advance Surf...The significance of Surface Logging For The Formation Evaluation Advance Surf...
The significance of Surface Logging For The Formation Evaluation Advance Surf...
 
Introduction to Conveyors.ppt
Introduction to Conveyors.pptIntroduction to Conveyors.ppt
Introduction to Conveyors.ppt
 

Viewers also liked

Annual Report UNDP Indonesia 2011
Annual Report UNDP Indonesia 2011Annual Report UNDP Indonesia 2011
Annual Report UNDP Indonesia 2011
Anggit T A W
 
Adgeco Group Clients List
Adgeco Group Clients ListAdgeco Group Clients List
Adgeco Group Clients List
Mohamed Dekkak
 
Quy hoach he thong cang vn den nam 2020 dinh huong 2030
Quy hoach he thong cang vn den nam 2020 dinh huong 2030Quy hoach he thong cang vn den nam 2020 dinh huong 2030
Quy hoach he thong cang vn den nam 2020 dinh huong 2030Nguyen Thanh Luan
 
PORTO MONTENEGRO M2 MARINA BUILDING
PORTO MONTENEGRO M2 MARINA BUILDINGPORTO MONTENEGRO M2 MARINA BUILDING
PORTO MONTENEGRO M2 MARINA BUILDING
Tatjana Nikcevic
 
Sabang harbour presentation_eng_FH
Sabang harbour  presentation_eng_FHSabang harbour  presentation_eng_FH
Sabang harbour presentation_eng_FH
Frans Wongkaren
 
The persistent urban health challenges of migration and informal settlements...
The persistent urban health challenges of migration and informal settlements...The persistent urban health challenges of migration and informal settlements...
The persistent urban health challenges of migration and informal settlements...Jo Vearey
 
Mayaguez Seaport Redevelopment Concept Proposal - Circa 2007-8
Mayaguez Seaport Redevelopment Concept Proposal - Circa 2007-8Mayaguez Seaport Redevelopment Concept Proposal - Circa 2007-8
Mayaguez Seaport Redevelopment Concept Proposal - Circa 2007-8
Ramon A. de Mier
 
Jetty服务器架构及调优.v2 2011-5
Jetty服务器架构及调优.v2 2011-5Jetty服务器架构及调优.v2 2011-5
Jetty服务器架构及调优.v2 2011-5
lovingprince58
 
Colombia seaport maritime industry
Colombia seaport maritime industryColombia seaport maritime industry
Colombia seaport maritime industry
Carlos Andrés García Sánchez
 
Seaport Working Group Guidelines & Principles - Community Board 1 Open House
Seaport Working Group Guidelines & Principles - Community Board 1 Open HouseSeaport Working Group Guidelines & Principles - Community Board 1 Open House
Seaport Working Group Guidelines & Principles - Community Board 1 Open House
Gale A. Brewer
 
chuong 1
 chuong 1 chuong 1
chuong 1luuguxd
 
chương 3 : thiết kế
chương 3 : thiết kếchương 3 : thiết kế
chương 3 : thiết kếluuguxd
 
Knowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes ChartKnowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes Chart
Anand Bobade
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
Anand Bobade
 
PMPProcessGroupTasks
PMPProcessGroupTasksPMPProcessGroupTasks
PMPProcessGroupTasks
Anand Bobade
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
Mark Troncone MBA, PMP, CBAP, ITILv3, CSM
 
PMBOK 5th Edition Mind map
PMBOK 5th Edition Mind mapPMBOK 5th Edition Mind map
PMBOK 5th Edition Mind map
Alex Ashton
 
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
TURKI , PMP
 

Viewers also liked (20)

Annual Report UNDP Indonesia 2011
Annual Report UNDP Indonesia 2011Annual Report UNDP Indonesia 2011
Annual Report UNDP Indonesia 2011
 
Adgeco Group Clients List
Adgeco Group Clients ListAdgeco Group Clients List
Adgeco Group Clients List
 
SBC Triptico 2014_
SBC Triptico 2014_SBC Triptico 2014_
SBC Triptico 2014_
 
Quy hoach he thong cang vn den nam 2020 dinh huong 2030
Quy hoach he thong cang vn den nam 2020 dinh huong 2030Quy hoach he thong cang vn den nam 2020 dinh huong 2030
Quy hoach he thong cang vn den nam 2020 dinh huong 2030
 
PORTO MONTENEGRO M2 MARINA BUILDING
PORTO MONTENEGRO M2 MARINA BUILDINGPORTO MONTENEGRO M2 MARINA BUILDING
PORTO MONTENEGRO M2 MARINA BUILDING
 
Habour and dock engineering
Habour and dock engineeringHabour and dock engineering
Habour and dock engineering
 
Sabang harbour presentation_eng_FH
Sabang harbour  presentation_eng_FHSabang harbour  presentation_eng_FH
Sabang harbour presentation_eng_FH
 
The persistent urban health challenges of migration and informal settlements...
The persistent urban health challenges of migration and informal settlements...The persistent urban health challenges of migration and informal settlements...
The persistent urban health challenges of migration and informal settlements...
 
Mayaguez Seaport Redevelopment Concept Proposal - Circa 2007-8
Mayaguez Seaport Redevelopment Concept Proposal - Circa 2007-8Mayaguez Seaport Redevelopment Concept Proposal - Circa 2007-8
Mayaguez Seaport Redevelopment Concept Proposal - Circa 2007-8
 
Jetty服务器架构及调优.v2 2011-5
Jetty服务器架构及调优.v2 2011-5Jetty服务器架构及调优.v2 2011-5
Jetty服务器架构及调优.v2 2011-5
 
Colombia seaport maritime industry
Colombia seaport maritime industryColombia seaport maritime industry
Colombia seaport maritime industry
 
Seaport Working Group Guidelines & Principles - Community Board 1 Open House
Seaport Working Group Guidelines & Principles - Community Board 1 Open HouseSeaport Working Group Guidelines & Principles - Community Board 1 Open House
Seaport Working Group Guidelines & Principles - Community Board 1 Open House
 
chuong 1
 chuong 1 chuong 1
chuong 1
 
chương 3 : thiết kế
chương 3 : thiết kếchương 3 : thiết kế
chương 3 : thiết kế
 
Knowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes ChartKnowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes Chart
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
PMPProcessGroupTasks
PMPProcessGroupTasksPMPProcessGroupTasks
PMPProcessGroupTasks
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
PMBOK 5th Edition Mind map
PMBOK 5th Edition Mind mapPMBOK 5th Edition Mind map
PMBOK 5th Edition Mind map
 
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
 

Similar to BCPC LOADING JETTY AND STOCK PILE Presentation

Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbour
FHRahman1
 
Presentation - July 4, 2011
Presentation - July 4, 2011Presentation - July 4, 2011
Presentation - July 4, 2011newpacificmetals
 
New Pacific Metals Corporate Presentation
New Pacific Metals Corporate PresentationNew Pacific Metals Corporate Presentation
New Pacific Metals Corporate Presentationnewpacific
 
11 july-5 nux-update
11 july-5 nux-update11 july-5 nux-update
11 july-5 nux-updatenewpacific
 
Blind Backfilling.pptx
Blind Backfilling.pptxBlind Backfilling.pptx
Blind Backfilling.pptx
SureshSharma514631
 
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
AMIT SAHU
 
Earth- Our Heritage : Challenges & Opportunities
Earth- Our Heritage : Challenges & OpportunitiesEarth- Our Heritage : Challenges & Opportunities
Earth- Our Heritage : Challenges & Opportunities
IEI GSC
 
Expansion Of The Cape Town Container Terminal
Expansion Of The Cape Town Container TerminalExpansion Of The Cape Town Container Terminal
Expansion Of The Cape Town Container Terminal
Railways and Harbours
 
Libya great man made river project
Libya   great man made river projectLibya   great man made river project
Libya great man made river project
issa ibrahim
 
Ataturk dam
Ataturk damAtaturk dam
Ataturk dam
Narasimha Rao
 
Nikhil Gopi.doc.pptx
Nikhil Gopi.doc.pptxNikhil Gopi.doc.pptx
Nikhil Gopi.doc.pptx
itech2017
 
Ce154 lecture 3 reservoirs, spillways, & energy dissipators
Ce154   lecture 3 reservoirs, spillways, & energy dissipatorsCe154   lecture 3 reservoirs, spillways, & energy dissipators
Ce154 lecture 3 reservoirs, spillways, & energy dissipators
saibabu48
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
Angelo Indelicato
 
A.ÖZGÜR MISIRLIOĞLU TANITIM
A.ÖZGÜR MISIRLIOĞLU TANITIMA.ÖZGÜR MISIRLIOĞLU TANITIM
A.ÖZGÜR MISIRLIOĞLU TANITIMAhmet Ozgur
 

Similar to BCPC LOADING JETTY AND STOCK PILE Presentation (16)

Marks Sess13 102309
Marks Sess13 102309Marks Sess13 102309
Marks Sess13 102309
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbour
 
Presentation - July 4, 2011
Presentation - July 4, 2011Presentation - July 4, 2011
Presentation - July 4, 2011
 
New Pacific Metals Corporate Presentation
New Pacific Metals Corporate PresentationNew Pacific Metals Corporate Presentation
New Pacific Metals Corporate Presentation
 
11 july-5 nux-update
11 july-5 nux-update11 july-5 nux-update
11 july-5 nux-update
 
Blind Backfilling.pptx
Blind Backfilling.pptxBlind Backfilling.pptx
Blind Backfilling.pptx
 
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
 
Earth- Our Heritage : Challenges & Opportunities
Earth- Our Heritage : Challenges & OpportunitiesEarth- Our Heritage : Challenges & Opportunities
Earth- Our Heritage : Challenges & Opportunities
 
Expansion Of The Cape Town Container Terminal
Expansion Of The Cape Town Container TerminalExpansion Of The Cape Town Container Terminal
Expansion Of The Cape Town Container Terminal
 
Libya great man made river project
Libya   great man made river projectLibya   great man made river project
Libya great man made river project
 
Ataturk dam
Ataturk damAtaturk dam
Ataturk dam
 
Nikhil Gopi.doc.pptx
Nikhil Gopi.doc.pptxNikhil Gopi.doc.pptx
Nikhil Gopi.doc.pptx
 
Ce154 lecture 3 reservoirs, spillways, & energy dissipators
Ce154   lecture 3 reservoirs, spillways, & energy dissipatorsCe154   lecture 3 reservoirs, spillways, & energy dissipators
Ce154 lecture 3 reservoirs, spillways, & energy dissipators
 
AML-8
AML-8AML-8
AML-8
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
 
A.ÖZGÜR MISIRLIOĞLU TANITIM
A.ÖZGÜR MISIRLIOĞLU TANITIMA.ÖZGÜR MISIRLIOĞLU TANITIM
A.ÖZGÜR MISIRLIOĞLU TANITIM
 

BCPC LOADING JETTY AND STOCK PILE Presentation

  • 1. BCPC LOADING JETTY AND STOCK PILE Perbedaan ketinggian elevasi air dengan daratan ± 5 meter dari level muka air Survey 27 July 2011
  • 2. Kondisi Lahan untuk Stock Pile Survey Tgl 27 July 2011
  • 3. Orientation of Location from mine pit to loading jetty Hauling Road 40 KM Loading Jetty
  • 4. Schematic Flow Diagram Stock Pile and Loading Jetty MINING AREA ROM STOCKPILE AT MINESITE MINE - HAUL ROAD LONG DISTANCE HAUL ROAD COAL TERMINAL DUMP STATION EMERGENCY STOCKPILE CRUSHING STATION BARGE LOADING CONVEYOR BARGE Loading Conveyor
  • 5. Stock pile and Loading conveyor conceptual
  • 8. Propose Coal Handling and stock pile, for reference only Loading conveyor 1500 ton/hour capacity
  • 9. Other Optional Propose Plot Plan Gadur Jetty and Mess,Housing and other facility Proposed for mess and housing facility Extend Stock Pile Stock pile and reclaim feeder
  • 10. Contoh Pondasi Jetty Dolphin to Accommodate 8000 DWT Barge
  • 11. Loading jetty for 8000 DWT Barge Coal pile configuration on 8000 DWT barge Loading conveyor 1500 ton/hours
  • 12. Long Profile Of Loading JETTY Accommodate 8000 DWT Barge Walkways on the trestle
  • 13. Typical Tower Loading Conveyor ke Barge
  • 14. CPT Location and land boundary yang dilakukan oleh GRM
  • 15. Stock Pile,Loading Conveyor dan Loading Jetty untuk 8000 DWT
  • 16. Survey tanggal 29 July 2011 CONE PENETRATION TEST CPT-10 DENGAN KEDALAMAN 27,4 M
  • 17. Hasil Cone Penetration Test CPT-10
  • 18. Contoh Laporan hasil Sondir sebagai referensi
  • 19. Contoh Laporan Sondir untuk design pondasi dan tiang pancang
  • 20. Contoh laporan Deep bore hole untuk piling dan pondasi
  • 21. Kondisi Banjir 10 tahunan menurut data penduduk lokal elevasi tinggi kurang lebih 2 meter dari muka tanah Ketinggian elevasi air pada saat banjir 10 tahunan,pada posisi 1,2 km dari bibir sungai
  • 22. Kondisi Tanah di Jetty Tanah keras 350 m Dari bibir sungai Tanah lembek berlumpur 1,2 km dari bibir sungai
  • 23. Contoh test beban untuk mendapatkan consolidated settlement dengan menggunakan model PLAXIS 2 D
  • 24. Indikasi tanah Lembek/Rawa-2 dari hauling road sepanjang 10,5 KM Tanah lembek dan berawa
  • 26. Jetty &Stock Pile Milestone • Construction of Loading and Stock Pile / Jetty Milestone • • Item Job description PIC Est Completion • • AMDAL Yuanito October 2011 • • Land Identification/Additional Sukadi August 2011 • • Land Acquisition Sukadi End Of Sept • • Boundary identification Construction team Early Oct 2011 • • BED/DED Of loading jetty Paul/Ardyan/Adi End Oct 2011 • Stock pile, coal handling • Bathymetry,Geotech, Topo • Hydrology, estimate CBM fill • • Set up Temporary facility Adi Sumanto Nov 2011 • • Stacking out area for land clearing Adi Sumanto Nov 2011 • And checking final elevation • Conveyor center line, jetty position • Stock pile and chain feeder position • Coal Crushing Plant,Site Facility • • Selected Land clearing Contractor Adi Sumanto Oct 2011 • • Mobilization land clearing sub con Adi Sumanto Nov 2011 • • Land Clearing Activities Adi Sumanto March 2012 •