1. Blind Backfilling of Goaf and Coal
Extraction below Built-up Areas /
Surface Structures.
2. • India’s Coal Production is dominated with OPENCAST MINING which
accounts for about 80% of total production
• Future Coal mining in India needs to emphasize coal Production from
Underground Mining
• Mining with Filling can increase Percentage of Extraction from
underground mines
• Underground Mining under Built-up Areas or Important Surface
Structures is possible with Mine Filling.
Mining is a process to extract valuable
minerals from the earth’s crust.
3. Blind Backfilling
• Old abandoned underground coal mines have left the
workings unapproachable.
• Surface instability and ground subsidence above such
workings has become cause of concern for the people
residing in this area.
• Conditions are acute in some parts in Ranigunj and
Jharia Coalfields.
• There is a need
(i)To develop a suitable cost efficient
backfilling method.
5. Stages of
Failure of
Pillars leading
to Subsidence
Pot Hole Subsidence
Usually occurs over old
workings worked by
Bord and Pillar Method
6. Common Blind Backfilling Techniques
Broadly classified into two types
(A) Point Support Technique:
Support a relatively small area
Use of cement grouted columns
Point Support
7. (B) Area-wide Blind Backfilling techniques
This is of three types:
(i)Pneumatic Backfilling
• Filled material carried underground
pneumatically
• Thrown all around the inlet hole
• Good for dry mines
• Packing area from one borehole is small
8. (ii) Hydro - Pneumatic Backfilling
• Mixture of solids and water is gravity fed
through borehole
• Air is simultaneously fed through pipe
placed concentrically to the feeder pipe
• Solids used:
sand, fly ash, small sized gravel/crushed
rock or washery rejects.
• Pipe diameter: 150 to 250 mm
10. Pumped Slurry Backfilling
Mixture of solids and water is
pumped through borehole at high
pressures
Large capacity pumps with high flow
are used
Solid concentration is 10 to 20% by
weight
Pipe diameters: 150 to 355 mm.
12. The Gravity Backfilling Method
Developed and Proposed by Prof. S. K. Pal of IIT Kharagpur
after detailed Laboratory and Field Experiments
COMMON DIFFICULTIES encountered in all Blind
Backfilling Process :
JAMMING PROBLEM
• Commonly jamming of feeder borehole, is sudden
and unpredictable
• Thus, it is difficult to plan for the location of the
next borehole in advance
14. Features and Drawbacks
1. Slurry pumping method
Superior method
Quick and wider area filling at high slurry flow rate
Pumps - imported & costly
• High maintenance cost
2. The hydro-pneumatic method
Less capital intensive
Cost efficient
Spread towards rise direction is more
• Filling rate comparatively slower
• Air injection may sometimes cause ground cracks
15. So evaluation of a pre-jamming indication
parameter is necessary
Pre-jamming indication parameter would certainly
facilitate a properly planned filling work
Benefit of blind backfilling
Maximization of the filling extent from a
single borehole by methodical reduction in sand
concentration as filling progress, thereby,
reduction of the overall filling duration
16. The Project Site
Abandoned Krishnanagar
Colliery of ECL, has been
selected to verify the
findings of laboratory
scale model study
BLIND BACKFILLING by Gravity Backfilling Technique
17. Drilling of Boreholes
Fig. 5.3 The underground map of Krishnanagar Colliery marking the
positions of different types of boreholes
18. The Movable Blind
Backfilling Laboratory
Fig. 5.12 Photograph of the caravan, inlet water pipelines and the overhead tank
5000 litre
overhead tank
for hole-flushing
in case of power
failure
19. Two Submercible Pumps of 600 gpm capacity were installed
in the two boreholes drilled outside the area to be filled up
Wireless
antenna
Fig. 5.6(b) Main switches and
starters
Fig. 5.6(a) Pump room with pump
outlets
20. Sand Feeding Arrangement
SAND STORAGE – SAND BUNKER – BUCKET ELEVATOR –
MIXING VAT
Sand Bunker
Bucket
Elevator
Fig. 5.10 Photograph of sand bunker feeding sand to bucket elevator
22. Continuous Data Recording System
Fig. 5.16 A close-up view of data logger during data recording
Continuous graph of piezo head with time
23. Air Movement during filling Operation
The entrained air from the inlet hole moves along the roof of
the underground roadway and produce an effusive release
from the nearest air-release hole.
Fig. 6.2(a)Air bubbles moving along
underground mine roof
Fig. 6.2(b) Effusive release of air
bubbles and water
24. Details of sand-filling through
different Mother( Inlet) Boreholes
Sl.
No.
BoreholeNo.
Sand
deposited
(m3)
Cumulativeamount of
sand deposited (m3)
Remarks
1. 17 6689 6689 Unhindered filling
2. 23 1427 8116
Hindered filling due to
stoppings
3. 28 6236 14352 Unhindered filling
4. 29 1544 15896
Hindered filling due to
stoppings
5. 27 4223 20119 Unhindered filling
6. 3 1357 21476
Incomplete filling (no
jamming)
25. FILLING through
Boreholes
Fig. 5.3 The underground map of Krishnanagar Colliery marking the
positions of different types of boreholes
Sl.
No
.
Borehol
e No.
Sand
deposit
ed (m3)
Cumulative
amount of
sand
deposited
(m3)
Remarks
1. 17 6689 6689 Unhindered filling
2. 23 1427 8116
Hindered filling
due to stoppings
3. 27 6236 14352 Unhindered filling
4. 29 1544 15896
Hindered filling
due to stoppings
5. 28 4223 20119 Unhindered filling
6. 3 1357 21476
Incomplete filling
(no jamming)
1
2
5
4
3
6
26. Monitoring of filled-up area
Position of filled-up sand bed at the end of
Filling through the first mother borehole
Shape of filled-up sand bed at the end of
Filling in the MODEL STUDY
6,689 m3
27. Monitoring of filled-up area
Position of filled-up sand bed at the end of
filling through the second mother borehole
Position of filled-up sand bed at the end of
filling through the third mother borehole
2
1
4 3
9,660 m3
15,896 m3
28. Monitoring of filled-up area
Position of filled-up sand bed at the end of
filling through the fifth mother borehole
Position of filled-up sand bed at the end of
project when filling through the fifth
mother borehole was continuing.
5 6
20,119 m3 21,476 m3
29. Monitoring of Filled-up Area in the
Field Study
Fig. 6.7 ROV camera system with float block removed for clear
viewing of propellers
Control panel for ROV camera system contr
panel
30. Monitoring of filled-up area
Position of filled-up sand bed after the first
stage of filling through the first mother borehole
Position of filled-up sand bed after the second
stage of filling through the first mother borehole
31. Monitoring of filled-up area
Position of filled-up sand bed after the fourth
stage of filling through the first mother borehole
Position of filled-up sand bed after the seventh
stage of filling through the first mother borehole
33. Variation of maximum sand throughput
‘Vs’ with sand concentration ‘C’
Vs = 227.88e-0.1092C
Vs = 408.35e-0.1232C
s
V = 404.39e-0.0944C
Vs = 551.57e-0.1133C
Vs = 604.41e-0.0822C
0
100
50
150
200
250
300
350
400
0 5 10 15
SandConcentration C(%)
in the model study
Q=15lpm
Q=20lpm
Q=25lpm
Q=30lpm
Q=35lpm
20 25
M
axim
um
S
and
Throughput
V
s
(litres)
in the Field study
34. Relative spreads of sand in model
study and field study
Model
inclination
Multiple
regression type
Regression
coefficient(R2)
Empirical relationships Remarks
7.50 Power 0.936 A e0.0603
*L 0.378
*L1.149
U S
Model Study
3.50 Power 0.897 A e0.537
*L0.753
*L1.752
U S
4.80 Power 0.987 A e2.356
*L0.509
*L 0.764
U S
Field Study
LU
LS
An approximation of the shape of sand filled area
35. Variation of Area of the filled-up
portion ‘A’ with Slurry Flow Rate ‘Q’
and Sand Concentration ‘C’
Model
inclin
a
tion
Multiple
regressio
n type
Variable
s
involved
Regression
coefficien
t (R2
)
Empirical
relationship
s
Remarks
7.50
Power A, Q, C 0.785 A 0.2236Q1.294
C0.8
Model study
3.50
Power A, Q, C 0.837 A 0.6832Q1.234
C1.23
4.80
Power A, Q, C 0.967 A 1.041Q1.313
C2.02
Field study
A = Area of the filled out Area
Q = Slurry Flow Rate
C = Sand Concentration
37. CONCLUSIONS
Filling by Simple Gravity Backfilling Method is
an efficient method of backfilling, where filling
may start with 15 % sand concentration and
then gradually be reduced to 9 % or less, as
and when the pre jamming indication arises.
Under Favourable Geo-mining conditions about
6000 m3 of sand can be delivered through a
single mother borehole.
Sand packing in the filled-up areas occurs
tightly up to the roof as monitored by the
Underwater ROV Camera.
The shape of the filled-up area is very similar to
that obtained in the model study.
38. CONCLUSIONS
Different empirical relationships obtained in Field study are
also similar to those obtained in the Model study, but the
values of the constants are different due to the reasons
mentioned earlier.
Similar to model study the Standard deviation ratio in the
pressure signature curve may be used an indicator for pre-
jamming condition, but its magnitude should be increased
from 4 to 20.
This technique being very simple yet efficient, may be used in
future for filling existing voids in water-filled abandoned
mines with proper scientific monitoring arrangements in order
to reap the benefits of the present study.
39. Hydraulic Stowing or Hydraulic Filling
Problem at Mosboni Mine : Although High Head is available
• Slurry flow is pulsating and
• Frequent jamming and Pipe-Joint Breakage
40. Critical Velocity vc For Slurry Flow
Durand’s Equation
Slurry Density and Concentration
Prof. A. P. Ujfin’s Empirical Equation
41. Actual Flow Velocity with Recommended Flow
Velocity for 3”, 4”and 4.5” Pipe Diameters
47. Schematic details of stowing pipelines
Route C
Route D
Route B
i. e., Geometric Profile
Hydraulic Profile is drawn by using the
Pressure loss data to find equivalent
length of the horizontal pipeline that
would cause the same pressure loss as
that occurs in that part of pipeline.
Hydraulic Gradient Line is drawn by joining the feed point and the discharge point of each route
51. Some Concepts of Paste Backfilling
Paste Backfilling would be another suitable technique for
filling of active mines under built-up Area
52. Characteristics of Fill with respect to Concrete
Young’s
Modulus in
MPa
Compaction in %
Concrete 3000-9000 0
Cemented fill 300-6000 3-5
Hydraulic fill 10-60 10-20
Uncemented rockfill 10-30 15-50
53.
54. UCS with binder content
Effect of water on strength generation