SlideShare a Scribd company logo
1 of 36
Download to read offline
Presented By:
11/15/16
Releasing the Full Capacity of DERs through Flexibility
Speakers:
Jeffrey	Norman,	Vice	President	of	Industry	Solutions,	AutoGrid Systems
Adam	Todorski,	Senior	Director	Product	Technology,	AutoGrid Systems
Moderator:
Elta Kolo,	Analyst,	Grid	Edge,	GTM	Research
2GTM Research
Audience	Console	Overview
Submit
Questions Speaker
Bios
Download
Slides
Share
Webinar
Enlarge
Slide
Area
3GTM Research
Today’s	Speakers
4GTM Research
Agenda
Distributed	Energy	Resources	Evolving	in	Demand	Response	Programs1
Releasing	the	Full	Capacity	of	DERs	through	Flexibility2
Q&A3
GTM Research
Distributed	Energy	Resources	Evolving	in	Demand	
Response	Programs
6GTM Research
Building	Electricity	Markets	of	the	Future	
Innovation for Market—Based Deployments of DERs
Aggregation	is	a	key	for	DER	integration	at	a	system	and	
distribution	level,	in	this	way	increasing	the	value	of	the	offering.	
Animating	Markets	for	
Distributed	Energy	
Resources	
Regulatory	
Guidance
Electricity	Market	
(Re)design	
Third	Party	
Technology	and	
Service	Providers
Empowering	customers	to	become	
active	electric	system	participates	
will	come	from	appropriate	adoption	
of	Distributed	Energy	Resources(	
DERs)
Affordable	and	reliable	electricity		system
7GTM Research
Value	of	Flexibility	from	DERs
Flexibility	Capability Grid	Value
Capacity	
Can	reduce	the	grid’s	peak	load	and	flatten	the	
aggregate	demand	profile	of	customers
• Avoided	generation,	transmission,	and	distribution	
investment	
• Minimize	grid	losses
• Reduce the	rate	of	equipment	degradation
Energy Can	shift	load	from	high-price	to	low-price	times Avoided	production	from	high-marginal-cost	resources
DER	integration
Can	reshape load	profiles	to	better	match	
renewable	energy	production	profiles
Mitigated	renewable	integration	challenges	(e.g.,	ramping,	
minimum	load)
Source: Rocky Mountain Institute
Value of Flexibility
Aggregated DER flexibility is valued under existing demand response program schemes for ISOs/RTOs and utilities. With DERs available at
different levels of the grid, opportunities and challenges arise with respect to markets and market design in addition monetization
strategies for capacity and energy.
8GTM Research
61%
23%
16%
Demand	Response	Allocation	in	ISO/RTO	Territories	
Behind-the-Meter Generation in MISO, PJM and SPP in Delivery Year 2016/2017 Makes up 21.2% of the System-Wide Flexibility
Source: MIS, PJM, ERCOT, CAISO, NYISO, ISONE, SPP
1
MW include maximum availability not maximum
activation.
31.3 GW1
6.6 GW
Total DR Available per ISO/RTO BTMG in MISO, SPP and PJM
38%
37%
8%
6%
5%
4%2%
9GTM Research
System	Needs	Are	Changing	
January	,	140,510
June,	141,678
February,	143,129 July,	143,633
80,000
90,000
100,000
110,000
120,000
130,000
140,000
150,000
160,000
1 3 5 7 9 11
MW
Month
2010 2011 2012 2013 2014 2015 2016
Although PJM has traditionally been a summer peaking system, it is evident that this fact is slowly changing. For 2015, the winter peak in February and
summer peak in July were nearly equal in the RTO territory.
PJM Monthly RTO Peaks 2010 to 2016
Source: PJM
10GTM Research
For the July 25th peaking summer day, between the hours of 14:00 to 19:00 there was approximately 600
MW of economically scheduled DR flexibility that provided relief in the BGE territory.
Heat	Day	Peak	Load	Triggers	Economic	Demand	Response	in	BGE	Territory	on	July	25,	2016
Load in PJM Territory During Heat Days Load in BGE Territory During PJM Declared Heat Days
7/25/2016,	
75,000
85,000
95,000
105,000
115,000
125,000
135,000
145,000
155,000
1:00 3:00 5:00 7:00 9:00 11:00 13:00 15:00 17:00 19:00 21:00 23:00
MW
Hour
7/21/2016 7/22/2016 7/23/2016 7/24/2016
PJM issued hot weather alerts for July 21 to July 27. System capacity peaked on July 25, reaching a
maximum load of over 150,000 MW in the RTO territory at 16:00 on July 25.
2,800
7,800
1:00 3:00 5:00 7:00 9:00 11:00 13:00 15:00 17:00 19:00 21:00 23:00
MW
Hour
7/21/2016
7/22/2016
7/23/2016
Source:	PJM
*Actual	reductions	achieved	will	be	known	after	all	individual	customer	meter	data	is	provided	for	settlements	– submission	deadline	for	economic	energy	settlements	is	60	days	following	event.
Source:	PJM
Releasing the Full Capacity of
DERs through Flexibility
Jeff Norman, VP Industry Solutions, AutoGrid
Adam Todorski, Senior Director Product Technology, AutoGrid
Rise of the DERs at Grid Edge
A complex, real-time energy network
(aka the Energy Internet)
§ Distributed energy resources
§ Renewables
§ Customers as consumers
and suppliers
§ Value through optimization
12
Inherent Challenges with DERs
New
Technologies
Intermittency
Integration with
Existing Grid
Communications Business Model
New Approach: Flexibility Management
14
Solar, DG
HVAC, Lighting
Combined Heat &
Power Plants
Thermostats,
Water Heaters
Battery Storage
Energy Resources
Electric Vehicles
Transmission
& Distribution
Wholesale
Energy
Markets
Value Streams
Behind-the-
Meter Cost
Reduction
$$
Resource
Flexibility
Unleashing That Potential Requires Challenging
Some Common Assumptions
NEW THINKINGMYTHS
Distributed generation, storage, and
demand response are separate categories
with different purposes
MYTH #1
New Thinking: All Are DERs
18
Solar HVAC, LightingCombined Heat
& Power Plants
Thermostats,
Water Heaters
Distributed Energy Resources
Distributed Generation Energy Storage Demand Response
Battery Storage
Other DERs
Electric Vehicles
What others have said…
Yes,
20%
No,
80%
Is the electricity industry prepared for
how the surge of DERs at the grid edge
will change utility business models?
Source: GTM Squared “Annual Survey Report 2016: The Future of Global Electricity Systems”
19
DERs are a threat to grid stability
MYTH #2
What others have said…
33.9%
26.5%
9.2%
15.8%
4.6%
To what extent do you
believe distributed
generation represents a
threat to your business?
Source: Black & Veatch 2015 Strategic Directions: U.S. Electric Industry Report
Major/
moderate
threat
Minor threat, but with
significant long-term
repercussions
Minor threat,
but with limited
long-term
repercussions
No threat
Don’t know
21
Do you:
• Get ready to pay millions or tens of millions for your new seasonal
capacity peak?
• Spin up a peaker plant?
• Curse your customers for having deployed solar, which has pushed
your daily load curve into the early evening and threatens to wreak all
sorts of other havoc?
Scenario: it’s the third day of a late July heat wave and
you’re about to eclipse your seasonal peak by 3%!
New Thinking
Or, do you help your customers buy batteries and:
• Have a reliable load-shifting capacity resource right where demand is
• Facilitate the integration of rooftop PV and leverage it as a distribution
asset
• Opportunistically self-supply or sell ancillary services
Scenario: it’s the third day of a late July heat wave and
you’re about to eclipse your seasonal peak by 3%!
<1 s2-4 s
10-30
mins
Hours/D
ays
Months/
Years
System
Planning
Governor
Response
RegulationReservesCapacity
Event Based DR
DR in Capacity
Auctions/Resourc
e Adequacy
Programs
Managed
Smart
Inverters
DERs with
Real-time
Controls
24
New Thinking: What Can’t You Do with DERs?
§ Active utility interaction with customer
sited storage and generation can be the
norm – just like DR
§ Good customer engagement tools can
help expand DR programs and integrate
DER programs
§ Existing DR resources can be forecast
and controlled alongside storage and DG
to respond at all time scales
Response Time of Resources
You can’t do much more with old assets like
window A/C units and water heaters
MYTH #3
New Thinking: Sometimes a Cigar Isn’t Just a Cigar
With good software, these assets
can deliver predictable, precise,
targeted, and fast-acting load relief
26
Flexibility Management
Predictable, flexible capacity
You can’t count on voluntary DR
for grid operations
MYTH #4
New Thinking: “Dispatch-Grade” Load Shed Forecasts
28
Forecast vs. Actual Curtailed Load
Actual Load AutoGrid Forecast Single Methodology Forecast
kWCurtailedLoad
1.5
2
2.5
3
3.5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
-0.4
-0.3
-0.2
-0.1
0.0
0.1
0.2
0.3
0.4
0.5
Error(kW)
DR Event
Load Forecasting Error Single Methodology Error
AutoGrid Forecasting Error
Data from 20 Behavior DR events at a major utility
What others have said
Source: Utility Dive, State of the Electric Utility 2016
The best way to integrate these DERs is
asset-by-asset to reduce risk
MYTH #5
New Thinking: It’s not about each asset or program, it’s about
the network
C&I DR
BYOT
Smart
Thermostat
Residential DLC
Building
Optimization
Interruptible Gas
Programs
MISO
Registration
Storage
DERs
EVSEs
Flexibility Management
C&I DR
BYOT
Smart
Thermostat
Residential DLC
Interruptible
Gas Programs
MISO
Registration
Flexibility Management: All Assets, All Services, All Customers
32
Storage Mgmt
Behavioral DR
Bring-Your-Own-Thing
C&I Direct Load Control
Demand Charge Mgmt
All Services
DERMS
All Customer Classes
Residential Commercial Industrial
Virtual Power Plant
All Assets
Flexibility
Management
Solar
Thermostats
CHP
Water Heaters, HVAC
Storage
EV/EVSE
Lighting
DER
DR
All Services
Capacity Energy Ancillary
ABOUT AUTOGRID
33
AutoGrid Company Overview
Company Facts
§ Established in 2011 at Stanford University
§ Headquartered in Silicon Valley
§ Operations in North America, Europe, APAC
§ ~50 employees
§ Strategic Investors include regulated and
deregulated global energy companies
Leading Provider of
Flexibility Management Applications
25+
Global Energy Customers
2000MW
DERs Contracted Globally
50 Million
End Customers
34
AutoGrid Flex
• DERMS
• Demand Response
• Virtual Power Plants
• Storage Optimization
Use Cases
35
Solar, DG
HVAC, Lighting
Combined Heat &
Power Plants
Thermostats,
Water Heaters
Battery Storage
Energy Assets
Electric Vehicles
$$
Resource
Flexibility
Wholesale
Markets
Transmission
& Distribution
Value Streams
Behind-the-
Meter
To Learn More
§ Contact us
§ jeffrey.norman@auto-grid.com
§ adam.tordorski@auto-grid.com
§ Go to our website www.auto-grid.com for:
§ White paper: “The Economic Value of Next-Generation DR”
§ Lots of other info!
§ Meet with us at Energy Storage Summit (12/7) or DistribuTECH (1/31)
1
2
3

More Related Content

What's hot

3M Electrical Catalogue - Low & High Voltage Cable Accessories (Scotchcast & ...
3M Electrical Catalogue - Low & High Voltage Cable Accessories (Scotchcast & ...3M Electrical Catalogue - Low & High Voltage Cable Accessories (Scotchcast & ...
3M Electrical Catalogue - Low & High Voltage Cable Accessories (Scotchcast & ...Thorne & Derrick International
 
Zxsdr bs8906 e product description(configured with b8100) 20100825
Zxsdr bs8906 e product description(configured with b8100) 20100825Zxsdr bs8906 e product description(configured with b8100) 20100825
Zxsdr bs8906 e product description(configured with b8100) 20100825Adeep Asaad
 
Preventive Maintenance Strategies for Power Distribution Systems- Charles Alvis
Preventive Maintenance Strategies for Power Distribution Systems- Charles AlvisPreventive Maintenance Strategies for Power Distribution Systems- Charles Alvis
Preventive Maintenance Strategies for Power Distribution Systems- Charles AlvisSchneider Electric
 
Nexans Euromold - Medium Voltage Compact Separable Connectors Interface C.
Nexans Euromold - Medium Voltage Compact Separable Connectors Interface C.Nexans Euromold - Medium Voltage Compact Separable Connectors Interface C.
Nexans Euromold - Medium Voltage Compact Separable Connectors Interface C.Thorne & Derrick International
 
Acionamentos elétricos ventiladores
Acionamentos elétricos   ventiladoresAcionamentos elétricos   ventiladores
Acionamentos elétricos ventiladoresAngelo Hafner
 
TL_Cons_present_Kishanpur_20[1].08.09.ppt
TL_Cons_present_Kishanpur_20[1].08.09.pptTL_Cons_present_Kishanpur_20[1].08.09.ppt
TL_Cons_present_Kishanpur_20[1].08.09.pptAshokKumar561399
 
Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...
Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...
Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...Thorne & Derrick International
 
ZTE BTS Cards Description
ZTE BTS Cards DescriptionZTE BTS Cards Description
ZTE BTS Cards Descriptionibrahimnabil17
 
Original Mosfet AP09N70I 09N70I 09N701 TO-220 New
Original Mosfet AP09N70I 09N70I 09N701 TO-220 NewOriginal Mosfet AP09N70I 09N70I 09N701 TO-220 New
Original Mosfet AP09N70I 09N70I 09N701 TO-220 NewAUTHELECTRONIC
 
Cable Ladder Bonding with Earth Wire, Is it Necessary?
Cable Ladder Bonding with Earth Wire, Is it Necessary?Cable Ladder Bonding with Earth Wire, Is it Necessary?
Cable Ladder Bonding with Earth Wire, Is it Necessary?Mike Hamilton
 
Catalog busbar ls 06. busduct presentation e series rev 2
Catalog busbar ls 06. busduct presentation e series rev 2Catalog busbar ls 06. busduct presentation e series rev 2
Catalog busbar ls 06. busduct presentation e series rev 2Dien Ha The
 
Awg to mm2
Awg to mm2Awg to mm2
Awg to mm2cwva
 
T distribution table
T distribution tableT distribution table
T distribution tableRaja Rosenani
 
146661638 configuring-rbs-6201-gsm-with-rus
146661638 configuring-rbs-6201-gsm-with-rus146661638 configuring-rbs-6201-gsm-with-rus
146661638 configuring-rbs-6201-gsm-with-rusSyed Ahmad
 
ETAP - Transient stability
ETAP - Transient stabilityETAP - Transient stability
ETAP - Transient stabilityHimmelstern
 
Codan 8800 Presentation Overview
Codan 8800 Presentation OverviewCodan 8800 Presentation Overview
Codan 8800 Presentation Overviewgueste402ad
 
3M cable and electrical products catalogue and 3M Cable Price List - Shopelect
3M cable and electrical products catalogue and 3M Cable Price List - Shopelect3M cable and electrical products catalogue and 3M Cable Price List - Shopelect
3M cable and electrical products catalogue and 3M Cable Price List - Shopelecttwinkleerai
 

What's hot (20)

3M Electrical Catalogue - Low & High Voltage Cable Accessories (Scotchcast & ...
3M Electrical Catalogue - Low & High Voltage Cable Accessories (Scotchcast & ...3M Electrical Catalogue - Low & High Voltage Cable Accessories (Scotchcast & ...
3M Electrical Catalogue - Low & High Voltage Cable Accessories (Scotchcast & ...
 
Zxsdr bs8906 e product description(configured with b8100) 20100825
Zxsdr bs8906 e product description(configured with b8100) 20100825Zxsdr bs8906 e product description(configured with b8100) 20100825
Zxsdr bs8906 e product description(configured with b8100) 20100825
 
Preventive Maintenance Strategies for Power Distribution Systems- Charles Alvis
Preventive Maintenance Strategies for Power Distribution Systems- Charles AlvisPreventive Maintenance Strategies for Power Distribution Systems- Charles Alvis
Preventive Maintenance Strategies for Power Distribution Systems- Charles Alvis
 
Nexans Euromold - Medium Voltage Compact Separable Connectors Interface C.
Nexans Euromold - Medium Voltage Compact Separable Connectors Interface C.Nexans Euromold - Medium Voltage Compact Separable Connectors Interface C.
Nexans Euromold - Medium Voltage Compact Separable Connectors Interface C.
 
Acionamentos elétricos ventiladores
Acionamentos elétricos   ventiladoresAcionamentos elétricos   ventiladores
Acionamentos elétricos ventiladores
 
Cable sizing.pptx
Cable sizing.pptxCable sizing.pptx
Cable sizing.pptx
 
TL_Cons_present_Kishanpur_20[1].08.09.ppt
TL_Cons_present_Kishanpur_20[1].08.09.pptTL_Cons_present_Kishanpur_20[1].08.09.ppt
TL_Cons_present_Kishanpur_20[1].08.09.ppt
 
HV/ MV SWG basics
HV/ MV SWG basicsHV/ MV SWG basics
HV/ MV SWG basics
 
Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...
Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...
Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...
 
ZTE BTS Cards Description
ZTE BTS Cards DescriptionZTE BTS Cards Description
ZTE BTS Cards Description
 
Original Mosfet AP09N70I 09N70I 09N701 TO-220 New
Original Mosfet AP09N70I 09N70I 09N701 TO-220 NewOriginal Mosfet AP09N70I 09N70I 09N701 TO-220 New
Original Mosfet AP09N70I 09N70I 09N701 TO-220 New
 
zte mobilink bts swap
zte mobilink bts swapzte mobilink bts swap
zte mobilink bts swap
 
Cable Ladder Bonding with Earth Wire, Is it Necessary?
Cable Ladder Bonding with Earth Wire, Is it Necessary?Cable Ladder Bonding with Earth Wire, Is it Necessary?
Cable Ladder Bonding with Earth Wire, Is it Necessary?
 
Catalog busbar ls 06. busduct presentation e series rev 2
Catalog busbar ls 06. busduct presentation e series rev 2Catalog busbar ls 06. busduct presentation e series rev 2
Catalog busbar ls 06. busduct presentation e series rev 2
 
Awg to mm2
Awg to mm2Awg to mm2
Awg to mm2
 
T distribution table
T distribution tableT distribution table
T distribution table
 
146661638 configuring-rbs-6201-gsm-with-rus
146661638 configuring-rbs-6201-gsm-with-rus146661638 configuring-rbs-6201-gsm-with-rus
146661638 configuring-rbs-6201-gsm-with-rus
 
ETAP - Transient stability
ETAP - Transient stabilityETAP - Transient stability
ETAP - Transient stability
 
Codan 8800 Presentation Overview
Codan 8800 Presentation OverviewCodan 8800 Presentation Overview
Codan 8800 Presentation Overview
 
3M cable and electrical products catalogue and 3M Cable Price List - Shopelect
3M cable and electrical products catalogue and 3M Cable Price List - Shopelect3M cable and electrical products catalogue and 3M Cable Price List - Shopelect
3M cable and electrical products catalogue and 3M Cable Price List - Shopelect
 

Similar to Releasing Full Capacity of DERs through Flexibility

Day 1 june 20 morning and track 1
Day 1 june 20 morning and track 1Day 1 june 20 morning and track 1
Day 1 june 20 morning and track 1Nicole Green
 
Five market trends that are re-shaping C&I energy management and procurement
Five market trends that are re-shaping C&I energy management and procurementFive market trends that are re-shaping C&I energy management and procurement
Five market trends that are re-shaping C&I energy management and procurementOmar Saadeh
 
Five market trends that are re-shaping C&I energy management and procurement
Five market trends that are re-shaping C&I energy management and procurementFive market trends that are re-shaping C&I energy management and procurement
Five market trends that are re-shaping C&I energy management and procurementOmar Saadeh
 
Case Study – Demand Side Response and How it Can Work for you
Case Study – Demand Side Response and How it Can Work for youCase Study – Demand Side Response and How it Can Work for you
Case Study – Demand Side Response and How it Can Work for youEMEX
 
Power management for a changing world
Power management for a changing worldPower management for a changing world
Power management for a changing worldBassam Gomaa
 
Power Responsive DSR Conference 18th June - Summary Paper
Power Responsive DSR Conference 18th June - Summary PaperPower Responsive DSR Conference 18th June - Summary Paper
Power Responsive DSR Conference 18th June - Summary PaperPower Responsive
 
Steven hauser presentation
Steven hauser presentationSteven hauser presentation
Steven hauser presentationGreen17Creative
 
Energy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyEnergy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyTransGrid AU
 
Track 1 intro presentation
Track 1 intro presentationTrack 1 intro presentation
Track 1 intro presentationNicole Green
 
Grid Software solutions smart grids
Grid Software solutions smart gridsGrid Software solutions smart grids
Grid Software solutions smart gridsalexa842003
 
ARC's Larry O'Brien Process Automation Presentation @ ARC Industry Forum 2010
ARC's Larry O'Brien Process Automation Presentation @ ARC Industry Forum 2010ARC's Larry O'Brien Process Automation Presentation @ ARC Industry Forum 2010
ARC's Larry O'Brien Process Automation Presentation @ ARC Industry Forum 2010ARC Advisory Group
 
2013 us grid storage report executive summary
2013 us grid storage report   executive summary2013 us grid storage report   executive summary
2013 us grid storage report executive summaryJon Winberg
 
Abb whitepaper final 022316 integrating renewables into microgrids
Abb whitepaper final 022316 integrating renewables into microgridsAbb whitepaper final 022316 integrating renewables into microgrids
Abb whitepaper final 022316 integrating renewables into microgridsSteve Wittrig
 
Andrew Ritch: Interruption in the Utility Industry
Andrew Ritch: Interruption in the Utility IndustryAndrew Ritch: Interruption in the Utility Industry
Andrew Ritch: Interruption in the Utility IndustryEnergyTech2015
 
Smart Grid - Concept to Reality 21.09.22.pptx
Smart Grid - Concept to Reality  21.09.22.pptxSmart Grid - Concept to Reality  21.09.22.pptx
Smart Grid - Concept to Reality 21.09.22.pptxshivarajCSRaj
 
Clean energy microgrids - Hype or Reality?
Clean energy microgrids - Hype or Reality?Clean energy microgrids - Hype or Reality?
Clean energy microgrids - Hype or Reality?Daniel Schwab
 

Similar to Releasing Full Capacity of DERs through Flexibility (20)

Day 1 june 20 morning and track 1
Day 1 june 20 morning and track 1Day 1 june 20 morning and track 1
Day 1 june 20 morning and track 1
 
Five market trends that are re-shaping C&I energy management and procurement
Five market trends that are re-shaping C&I energy management and procurementFive market trends that are re-shaping C&I energy management and procurement
Five market trends that are re-shaping C&I energy management and procurement
 
Five market trends that are re-shaping C&I energy management and procurement
Five market trends that are re-shaping C&I energy management and procurementFive market trends that are re-shaping C&I energy management and procurement
Five market trends that are re-shaping C&I energy management and procurement
 
Case Study – Demand Side Response and How it Can Work for you
Case Study – Demand Side Response and How it Can Work for youCase Study – Demand Side Response and How it Can Work for you
Case Study – Demand Side Response and How it Can Work for you
 
Power management for a changing world
Power management for a changing worldPower management for a changing world
Power management for a changing world
 
Power Responsive DSR Conference 18th June - Summary Paper
Power Responsive DSR Conference 18th June - Summary PaperPower Responsive DSR Conference 18th June - Summary Paper
Power Responsive DSR Conference 18th June - Summary Paper
 
Steven hauser presentation
Steven hauser presentationSteven hauser presentation
Steven hauser presentation
 
Energy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyEnergy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering Sydney
 
Track 1 intro presentation
Track 1 intro presentationTrack 1 intro presentation
Track 1 intro presentation
 
Grid Software solutions smart grids
Grid Software solutions smart gridsGrid Software solutions smart grids
Grid Software solutions smart grids
 
Uk approach – Matching demand to inflexible generation
Uk approach – Matching demand to inflexible generationUk approach – Matching demand to inflexible generation
Uk approach – Matching demand to inflexible generation
 
ARC's Larry O'Brien Process Automation Presentation @ ARC Industry Forum 2010
ARC's Larry O'Brien Process Automation Presentation @ ARC Industry Forum 2010ARC's Larry O'Brien Process Automation Presentation @ ARC Industry Forum 2010
ARC's Larry O'Brien Process Automation Presentation @ ARC Industry Forum 2010
 
Dsm bses
Dsm bsesDsm bses
Dsm bses
 
2013 us grid storage report executive summary
2013 us grid storage report   executive summary2013 us grid storage report   executive summary
2013 us grid storage report executive summary
 
PowerSecure
PowerSecurePowerSecure
PowerSecure
 
Abb whitepaper final 022316 integrating renewables into microgrids
Abb whitepaper final 022316 integrating renewables into microgridsAbb whitepaper final 022316 integrating renewables into microgrids
Abb whitepaper final 022316 integrating renewables into microgrids
 
Andrew Ritch: Interruption in the Utility Industry
Andrew Ritch: Interruption in the Utility IndustryAndrew Ritch: Interruption in the Utility Industry
Andrew Ritch: Interruption in the Utility Industry
 
Smart Grid - Concept to Reality 21.09.22.pptx
Smart Grid - Concept to Reality  21.09.22.pptxSmart Grid - Concept to Reality  21.09.22.pptx
Smart Grid - Concept to Reality 21.09.22.pptx
 
Transformer Smart Grid
Transformer Smart GridTransformer Smart Grid
Transformer Smart Grid
 
Clean energy microgrids - Hype or Reality?
Clean energy microgrids - Hype or Reality?Clean energy microgrids - Hype or Reality?
Clean energy microgrids - Hype or Reality?
 

More from Jeffrey Norman

4Q16 Navigant Research Leaderboard Report - Demand Response Management System...
4Q16 Navigant Research Leaderboard Report - Demand Response Management System...4Q16 Navigant Research Leaderboard Report - Demand Response Management System...
4Q16 Navigant Research Leaderboard Report - Demand Response Management System...Jeffrey Norman
 
MCE AutoGrid DR DER WF Oct2016 FINAL
MCE AutoGrid DR DER WF Oct2016  FINALMCE AutoGrid DR DER WF Oct2016  FINAL
MCE AutoGrid DR DER WF Oct2016 FINALJeffrey Norman
 
Capgemini_SmartGrid_RenewableEnergySurvey_0209
Capgemini_SmartGrid_RenewableEnergySurvey_0209Capgemini_SmartGrid_RenewableEnergySurvey_0209
Capgemini_SmartGrid_RenewableEnergySurvey_0209Jeffrey Norman
 
Capgemini_NARUC_EnergySurvey_DetailedAnalysis2008
Capgemini_NARUC_EnergySurvey_DetailedAnalysis2008Capgemini_NARUC_EnergySurvey_DetailedAnalysis2008
Capgemini_NARUC_EnergySurvey_DetailedAnalysis2008Jeffrey Norman
 
Platts_Capgemini_UtilityExecutiveStudy_ExecSummary_051810
Platts_Capgemini_UtilityExecutiveStudy_ExecSummary_051810Platts_Capgemini_UtilityExecutiveStudy_ExecSummary_051810
Platts_Capgemini_UtilityExecutiveStudy_ExecSummary_051810Jeffrey Norman
 
Capgemini_Smart Meter POV_2009
Capgemini_Smart Meter POV_2009Capgemini_Smart Meter POV_2009
Capgemini_Smart Meter POV_2009Jeffrey Norman
 
20141031 CPS AEEI Bios FINAL
20141031 CPS AEEI Bios FINAL20141031 CPS AEEI Bios FINAL
20141031 CPS AEEI Bios FINALJeffrey Norman
 
Autovation_2012_Slide_Template_Norman FINAL_Post Conference
Autovation_2012_Slide_Template_Norman FINAL_Post ConferenceAutovation_2012_Slide_Template_Norman FINAL_Post Conference
Autovation_2012_Slide_Template_Norman FINAL_Post ConferenceJeffrey Norman
 
SGN Webinar March 14 2013 Norman_SAIC
SGN Webinar March 14 2013 Norman_SAICSGN Webinar March 14 2013 Norman_SAIC
SGN Webinar March 14 2013 Norman_SAICJeffrey Norman
 
DTECH Preso 2013 Norman-SAIC_FINAL
DTECH Preso 2013 Norman-SAIC_FINALDTECH Preso 2013 Norman-SAIC_FINAL
DTECH Preso 2013 Norman-SAIC_FINALJeffrey Norman
 
DTECH_ Norman _Benefits of Modular SG_FINAL x
DTECH_ Norman _Benefits of Modular SG_FINAL xDTECH_ Norman _Benefits of Modular SG_FINAL x
DTECH_ Norman _Benefits of Modular SG_FINAL xJeffrey Norman
 
TPPA Grid of the Future
TPPA Grid of the FutureTPPA Grid of the Future
TPPA Grid of the FutureJeffrey Norman
 

More from Jeffrey Norman (14)

4Q16 Navigant Research Leaderboard Report - Demand Response Management System...
4Q16 Navigant Research Leaderboard Report - Demand Response Management System...4Q16 Navigant Research Leaderboard Report - Demand Response Management System...
4Q16 Navigant Research Leaderboard Report - Demand Response Management System...
 
MCE AutoGrid DR DER WF Oct2016 FINAL
MCE AutoGrid DR DER WF Oct2016  FINALMCE AutoGrid DR DER WF Oct2016  FINAL
MCE AutoGrid DR DER WF Oct2016 FINAL
 
TRC Executive Summary
TRC Executive SummaryTRC Executive Summary
TRC Executive Summary
 
Capgemini_SmartGrid_RenewableEnergySurvey_0209
Capgemini_SmartGrid_RenewableEnergySurvey_0209Capgemini_SmartGrid_RenewableEnergySurvey_0209
Capgemini_SmartGrid_RenewableEnergySurvey_0209
 
Capgemini_NARUC_EnergySurvey_DetailedAnalysis2008
Capgemini_NARUC_EnergySurvey_DetailedAnalysis2008Capgemini_NARUC_EnergySurvey_DetailedAnalysis2008
Capgemini_NARUC_EnergySurvey_DetailedAnalysis2008
 
Platts_Capgemini_UtilityExecutiveStudy_ExecSummary_051810
Platts_Capgemini_UtilityExecutiveStudy_ExecSummary_051810Platts_Capgemini_UtilityExecutiveStudy_ExecSummary_051810
Platts_Capgemini_UtilityExecutiveStudy_ExecSummary_051810
 
Capgemini_Smart Meter POV_2009
Capgemini_Smart Meter POV_2009Capgemini_Smart Meter POV_2009
Capgemini_Smart Meter POV_2009
 
UPLC
UPLCUPLC
UPLC
 
20141031 CPS AEEI Bios FINAL
20141031 CPS AEEI Bios FINAL20141031 CPS AEEI Bios FINAL
20141031 CPS AEEI Bios FINAL
 
Autovation_2012_Slide_Template_Norman FINAL_Post Conference
Autovation_2012_Slide_Template_Norman FINAL_Post ConferenceAutovation_2012_Slide_Template_Norman FINAL_Post Conference
Autovation_2012_Slide_Template_Norman FINAL_Post Conference
 
SGN Webinar March 14 2013 Norman_SAIC
SGN Webinar March 14 2013 Norman_SAICSGN Webinar March 14 2013 Norman_SAIC
SGN Webinar March 14 2013 Norman_SAIC
 
DTECH Preso 2013 Norman-SAIC_FINAL
DTECH Preso 2013 Norman-SAIC_FINALDTECH Preso 2013 Norman-SAIC_FINAL
DTECH Preso 2013 Norman-SAIC_FINAL
 
DTECH_ Norman _Benefits of Modular SG_FINAL x
DTECH_ Norman _Benefits of Modular SG_FINAL xDTECH_ Norman _Benefits of Modular SG_FINAL x
DTECH_ Norman _Benefits of Modular SG_FINAL x
 
TPPA Grid of the Future
TPPA Grid of the FutureTPPA Grid of the Future
TPPA Grid of the Future
 

Releasing Full Capacity of DERs through Flexibility

  • 1. Presented By: 11/15/16 Releasing the Full Capacity of DERs through Flexibility Speakers: Jeffrey Norman, Vice President of Industry Solutions, AutoGrid Systems Adam Todorski, Senior Director Product Technology, AutoGrid Systems Moderator: Elta Kolo, Analyst, Grid Edge, GTM Research
  • 6. 6GTM Research Building Electricity Markets of the Future Innovation for Market—Based Deployments of DERs Aggregation is a key for DER integration at a system and distribution level, in this way increasing the value of the offering. Animating Markets for Distributed Energy Resources Regulatory Guidance Electricity Market (Re)design Third Party Technology and Service Providers Empowering customers to become active electric system participates will come from appropriate adoption of Distributed Energy Resources( DERs) Affordable and reliable electricity system
  • 7. 7GTM Research Value of Flexibility from DERs Flexibility Capability Grid Value Capacity Can reduce the grid’s peak load and flatten the aggregate demand profile of customers • Avoided generation, transmission, and distribution investment • Minimize grid losses • Reduce the rate of equipment degradation Energy Can shift load from high-price to low-price times Avoided production from high-marginal-cost resources DER integration Can reshape load profiles to better match renewable energy production profiles Mitigated renewable integration challenges (e.g., ramping, minimum load) Source: Rocky Mountain Institute Value of Flexibility Aggregated DER flexibility is valued under existing demand response program schemes for ISOs/RTOs and utilities. With DERs available at different levels of the grid, opportunities and challenges arise with respect to markets and market design in addition monetization strategies for capacity and energy.
  • 8. 8GTM Research 61% 23% 16% Demand Response Allocation in ISO/RTO Territories Behind-the-Meter Generation in MISO, PJM and SPP in Delivery Year 2016/2017 Makes up 21.2% of the System-Wide Flexibility Source: MIS, PJM, ERCOT, CAISO, NYISO, ISONE, SPP 1 MW include maximum availability not maximum activation. 31.3 GW1 6.6 GW Total DR Available per ISO/RTO BTMG in MISO, SPP and PJM 38% 37% 8% 6% 5% 4%2%
  • 9. 9GTM Research System Needs Are Changing January , 140,510 June, 141,678 February, 143,129 July, 143,633 80,000 90,000 100,000 110,000 120,000 130,000 140,000 150,000 160,000 1 3 5 7 9 11 MW Month 2010 2011 2012 2013 2014 2015 2016 Although PJM has traditionally been a summer peaking system, it is evident that this fact is slowly changing. For 2015, the winter peak in February and summer peak in July were nearly equal in the RTO territory. PJM Monthly RTO Peaks 2010 to 2016 Source: PJM
  • 10. 10GTM Research For the July 25th peaking summer day, between the hours of 14:00 to 19:00 there was approximately 600 MW of economically scheduled DR flexibility that provided relief in the BGE territory. Heat Day Peak Load Triggers Economic Demand Response in BGE Territory on July 25, 2016 Load in PJM Territory During Heat Days Load in BGE Territory During PJM Declared Heat Days 7/25/2016, 75,000 85,000 95,000 105,000 115,000 125,000 135,000 145,000 155,000 1:00 3:00 5:00 7:00 9:00 11:00 13:00 15:00 17:00 19:00 21:00 23:00 MW Hour 7/21/2016 7/22/2016 7/23/2016 7/24/2016 PJM issued hot weather alerts for July 21 to July 27. System capacity peaked on July 25, reaching a maximum load of over 150,000 MW in the RTO territory at 16:00 on July 25. 2,800 7,800 1:00 3:00 5:00 7:00 9:00 11:00 13:00 15:00 17:00 19:00 21:00 23:00 MW Hour 7/21/2016 7/22/2016 7/23/2016 Source: PJM *Actual reductions achieved will be known after all individual customer meter data is provided for settlements – submission deadline for economic energy settlements is 60 days following event. Source: PJM
  • 11. Releasing the Full Capacity of DERs through Flexibility Jeff Norman, VP Industry Solutions, AutoGrid Adam Todorski, Senior Director Product Technology, AutoGrid
  • 12. Rise of the DERs at Grid Edge A complex, real-time energy network (aka the Energy Internet) § Distributed energy resources § Renewables § Customers as consumers and suppliers § Value through optimization 12
  • 13. Inherent Challenges with DERs New Technologies Intermittency Integration with Existing Grid Communications Business Model
  • 14. New Approach: Flexibility Management 14 Solar, DG HVAC, Lighting Combined Heat & Power Plants Thermostats, Water Heaters Battery Storage Energy Resources Electric Vehicles Transmission & Distribution Wholesale Energy Markets Value Streams Behind-the- Meter Cost Reduction $$ Resource Flexibility
  • 15.
  • 16. Unleashing That Potential Requires Challenging Some Common Assumptions NEW THINKINGMYTHS
  • 17. Distributed generation, storage, and demand response are separate categories with different purposes MYTH #1
  • 18. New Thinking: All Are DERs 18 Solar HVAC, LightingCombined Heat & Power Plants Thermostats, Water Heaters Distributed Energy Resources Distributed Generation Energy Storage Demand Response Battery Storage Other DERs Electric Vehicles
  • 19. What others have said… Yes, 20% No, 80% Is the electricity industry prepared for how the surge of DERs at the grid edge will change utility business models? Source: GTM Squared “Annual Survey Report 2016: The Future of Global Electricity Systems” 19
  • 20. DERs are a threat to grid stability MYTH #2
  • 21. What others have said… 33.9% 26.5% 9.2% 15.8% 4.6% To what extent do you believe distributed generation represents a threat to your business? Source: Black & Veatch 2015 Strategic Directions: U.S. Electric Industry Report Major/ moderate threat Minor threat, but with significant long-term repercussions Minor threat, but with limited long-term repercussions No threat Don’t know 21
  • 22. Do you: • Get ready to pay millions or tens of millions for your new seasonal capacity peak? • Spin up a peaker plant? • Curse your customers for having deployed solar, which has pushed your daily load curve into the early evening and threatens to wreak all sorts of other havoc? Scenario: it’s the third day of a late July heat wave and you’re about to eclipse your seasonal peak by 3%!
  • 23. New Thinking Or, do you help your customers buy batteries and: • Have a reliable load-shifting capacity resource right where demand is • Facilitate the integration of rooftop PV and leverage it as a distribution asset • Opportunistically self-supply or sell ancillary services Scenario: it’s the third day of a late July heat wave and you’re about to eclipse your seasonal peak by 3%!
  • 24. <1 s2-4 s 10-30 mins Hours/D ays Months/ Years System Planning Governor Response RegulationReservesCapacity Event Based DR DR in Capacity Auctions/Resourc e Adequacy Programs Managed Smart Inverters DERs with Real-time Controls 24 New Thinking: What Can’t You Do with DERs? § Active utility interaction with customer sited storage and generation can be the norm – just like DR § Good customer engagement tools can help expand DR programs and integrate DER programs § Existing DR resources can be forecast and controlled alongside storage and DG to respond at all time scales Response Time of Resources
  • 25. You can’t do much more with old assets like window A/C units and water heaters MYTH #3
  • 26. New Thinking: Sometimes a Cigar Isn’t Just a Cigar With good software, these assets can deliver predictable, precise, targeted, and fast-acting load relief 26 Flexibility Management Predictable, flexible capacity
  • 27. You can’t count on voluntary DR for grid operations MYTH #4
  • 28. New Thinking: “Dispatch-Grade” Load Shed Forecasts 28 Forecast vs. Actual Curtailed Load Actual Load AutoGrid Forecast Single Methodology Forecast kWCurtailedLoad 1.5 2 2.5 3 3.5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 -0.4 -0.3 -0.2 -0.1 0.0 0.1 0.2 0.3 0.4 0.5 Error(kW) DR Event Load Forecasting Error Single Methodology Error AutoGrid Forecasting Error Data from 20 Behavior DR events at a major utility
  • 29. What others have said Source: Utility Dive, State of the Electric Utility 2016
  • 30. The best way to integrate these DERs is asset-by-asset to reduce risk MYTH #5
  • 31. New Thinking: It’s not about each asset or program, it’s about the network C&I DR BYOT Smart Thermostat Residential DLC Building Optimization Interruptible Gas Programs MISO Registration Storage DERs EVSEs Flexibility Management C&I DR BYOT Smart Thermostat Residential DLC Interruptible Gas Programs MISO Registration
  • 32. Flexibility Management: All Assets, All Services, All Customers 32 Storage Mgmt Behavioral DR Bring-Your-Own-Thing C&I Direct Load Control Demand Charge Mgmt All Services DERMS All Customer Classes Residential Commercial Industrial Virtual Power Plant All Assets Flexibility Management Solar Thermostats CHP Water Heaters, HVAC Storage EV/EVSE Lighting DER DR All Services Capacity Energy Ancillary
  • 34. AutoGrid Company Overview Company Facts § Established in 2011 at Stanford University § Headquartered in Silicon Valley § Operations in North America, Europe, APAC § ~50 employees § Strategic Investors include regulated and deregulated global energy companies Leading Provider of Flexibility Management Applications 25+ Global Energy Customers 2000MW DERs Contracted Globally 50 Million End Customers 34
  • 35. AutoGrid Flex • DERMS • Demand Response • Virtual Power Plants • Storage Optimization Use Cases 35 Solar, DG HVAC, Lighting Combined Heat & Power Plants Thermostats, Water Heaters Battery Storage Energy Assets Electric Vehicles $$ Resource Flexibility Wholesale Markets Transmission & Distribution Value Streams Behind-the- Meter
  • 36. To Learn More § Contact us § jeffrey.norman@auto-grid.com § adam.tordorski@auto-grid.com § Go to our website www.auto-grid.com for: § White paper: “The Economic Value of Next-Generation DR” § Lots of other info! § Meet with us at Energy Storage Summit (12/7) or DistribuTECH (1/31) 1 2 3