OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
TL_Cons_present_Kishanpur_20[1].08.09.ppt
1. OVER VIEW ON TRANSMISSION LINE
CONSTRUCTION
KISHANPUR 20/08/2009
By.
MAN MOHAN RAINA
MANAGER T/L
PANIPAT
2. INTRODUCTION
Different Stages of Transmission Line Construction
a) Planning a Transmission Line Project
b) Approval of the Scheme by Government
c) Preparation of Feasibility Report and BOQ
d) Framing of estimate for tentative cost of project
e) Issuance of NIT for competitive bidding
f) Award of Project to the lowest bidder
Once contract is awarded, the execution part starts.
3. INTRODUCTION
Main components of a Transmission Line
for successful completion of project:
a) Foundation
b) Tower Parts
c) Conductor
d) Earth Wire
e) Insulator
f) Hardware & Accessories
4. INTRODUCTION
Main activities of a Transmission Line during
execution stage:
a) Route Alignment
b) Detail Survey
c) Check Survey
d) Soil Investigation
e) Casting of Foundations
f) Erection of Towers
g) Stringing of Conductor and Earth Wire
h) Testing and commissioning of project.
5. INTRODUCTION
For next few hours we will be mainly discussing the following
components of Transmission Line Project:
a) Soil Investigation
b) Tower Foundations
c) Earthing of Towers
d) Tower Erection
f) Stringing
h) Statutory Clearances
i) Right of Way Issues.
6. SOIL INVESTIGATION
Why required?
To provide designer with sufficiently accurate
information about the substrata profile and
relevant soil and rock parameters at site on the
basis of which the foundation of transmission
towers can be classified and designed
rationally
When required?
Carried out after Detailed Survey
7. SOIL INVESTIGATION
Purpose:-
- Technical: -Inadequate design/conservative
choice of foundation may cause failure
-To carry out pre-design of foundation
as large variety of soil encountered in
long line with voltage going up
- Economic: -Foundation costs a major portion
- Considerable saving by way of
devolving a Techno/ Economic
foundation design as per actual soil
8. Field Investigation:-
1. Boring
Required to have knowledge of sub-soil profile, its
nature & strength etc.
To collect soil samples for strata identification and for
conducting laboratory tests
Minimum diameter of bore 150 mm
Depth of 7/10 mtr for normal soil conditions
Depth of 40 mtr for river crossing/ spl locations
9. Type of Boring
Augur Boring
For soft to stiff cohesive soil above water table
Shell & Augur Boring
All types of soil free from boulders
Rotary Boring
For all types of soil below water table
13. Standard Penetration Test
To be conducted in all types of soil deposits
encountered within borehole to find variation
in soil strata by correlating with number of
blows required for unit penetration of a
standard penetrometer
To be conducted at depths:-
Location Depth (mtr)
Normal Soil 2, 3, 5, 7, 10
River X-ing/ 2, 3, 5, 7, 10 and every 3
Special Loc mtr intervals up to 40 mtr
14. Standard Penetration Test
The test is carried out by driving a standard split spoon
sampler in the bore hole by means of a 65 KG hammer having
a free fall of 750 centimeters.
The sampler shall be driven using the hammer for 450 mm
recoding the number of blows for every 150 mm.
The number of blows for last 300 mm drive shall be reported
as N value
This test shall be discontinued when the blow count (N value)
is 100
The level where test is discontinued to be reported
15. Sampling
Disturbed Sample-
Jar sample of 1 Kg for every 0.5 mtr intervals starting from 0.5 mtr
from GL & every change of strata
Undisturbed Sample-
To be collected at change of strata & at depths:-
Location Depth (mtr)
Normal loc 1, 4, 6, 8 & 10
River X-ing/ Spl 1, 4, 5, 8, 10 & every 3 mtr up to 38 mtr
Location
Ground Water Level
To be recorded after 24 hours of drilling.
16. Tests
Undisturbed & Disturbed Sample
- Visual
- Sieve analysis
- Liquid, Plastic & Shrinkage limits
- Specific gravity
- Chemical analysis
- Swell pressure
Undisturbed Sample
- Bulk density & moisture content
- Physical bearing capacity settlement properties
Chemical Analysis of Sub-Soil water
17. SOIL INVESTIGATION RESULTS
Grain Size analysis
Nomenclature of soils as per IS
Attenburg limit (Liquid & plastic)
Angle of Internal friction
Specific Gravity
Analysis of SPT results
Consolidation tests
Presence of organic matters & chemicals which are harmful to
RCC (e.g. Sulphates, Carbonates, Chloride)
Chemical analysis of subsoil water, presence of organic matter
Unconfined Compression test
Crushing Strength of rock
Bearing Strength at 3, 4, 5 meter depth
18. SOIL INVESTIGATION
Detailed soil investigation for normal location.
Depth – 10 M
N > 100 after then 3 mtr.
SPT normal soil = 2.0, 3.0, 5.0, 7.0 & 10 mtr.
River X-ing and special = 2.0, 3.0, 5.0, 7.0, 10.0 &
thereafter at the rate of 3 mtr. interval.
65 KG hammer fall 75 CM
Blows to be recorded 450 MM, & every 150 MM
number of blows for last 300 MM is called N value.
20. Soil Resistivity
- Depends upon type of soil
(alluvium dry<clay<sandstone<lime
stone<fossil rock)
- Depends upon moisture content
& that is why values vary from
season to season
- Moisture content ranges from
10% in dry season to 35% in wet
season
- To be measured in dry season
- Soil Resistivity varies with salt
content
- Measured in ohm-meter
21. Soil Resistivity
A typical Connection of megger by
four electrode method for
measurement of Soil resistivity is
shown
Value is 2 x 22/7 x a x r
where, a= distance bet the
electrodes, r= megger reading
22. LIST OF CODES FOR SOIL INVESTIGATION
Sl.No. Indian Standards Title
1. IS : 1498 Classification and identification of soils for General Engineering purpose
2. IS : 1892 Code of practice for subsurface investigation for foundation
3. IS : 1904 Code of practice for design and construction of foundation in soils – general
requirements
4. IS : 2131 Method of Standard Penetration Test for soils
5. IS : 2132 Code of practice for Thin Walled Tube Sampling of soils
6. IS : 2720 Methods of test for soil (relevant section)
7. IS : 2809 Glossary of Terms and Symbols relating to Soil Engineering
8. IS : 3025 Methods of Sampling and Testing (Physical & Chemical) for water used in
Industry
9. IS : 4078 Code of practice for Indexing and storage of Drill cores.
10. IS : 4434 Code of practice for In-situ Vane-shear test
11. IS :4453 Code of practice for exploration of pits, trenches, drifts and shaft
23. LIST OF CODES FOR SOIL INVESTIGATION
Sl.No. Indian
Standards
Title
12. IS : 4464 Code of practice for presentation of drilling information and core description in
foundation investigation
13. IS : 4968 (Part-
II)
Method of subsurface sounding of soils, dynamic method using cone and
bentonite slurry
14. IS : 5313 Guide for core drilling observations
15. IS : 6403 Code of practice for determination of allowable bearing pressure on shallow
foundation
16. IS : 6926 Code of practice for Diamond core drilling for site investigation for river valley
projects
17. IS : 6935 Method of Determination of Water level in bore hole
18. IS : 8009 (Part
– I)
Code of practice for calculation of settlements of foundations (shallow
foundations subject to symmetrical vertical loads)
19. IS : 8764 Method of determination of point load strength index of rocks
20. IS : 9143 Method of determination of unconfined compressive strength of rock materials
21. IS : 9179 Method of preparation of rock specimen for lab. testing
25. General Design Criteria
Design of safe & economical foundation is based on
soil properties, knowledge of soil structure &
settlement analysis
Loads on Tower Foundation:-
- Downward load
- Uplift load
- Lateral Load (Horizontal thrust)
- Overturning moments
26. Downward load- Mainly due to deadweight of
tower, conductor, Insulators &^ Acc.
Uplift load - Primary concern in design
- Due angle of deviation, difference in level,
dead ending
Lateral Load - Due to wind
Wind produces both lateral as well as uplift
on the windward side of structure and down
thrust on the other side
Factor of Safety - 2.2 for normal condition
- 1.65 for broken wire condition
27. What to do before casting of
Tower Foundation
Finalize Route of Transmission line
Carry out Detailed Survey
Carry out Soil Investigation
Finalize Tower Schedule (Part/Full)
Carry out Check Survey
28. CLASSIFICATION OF FOUNDATION
1. Tower Foundation depends upon:-
Type of Soil
Sub Soil water level
Presence of surface water
2. Classification of Foundation:-
Normal Dry - where normal dry cohesive or non-cohesive soils are met
NC/ Sandy Dry – where cohesion less pure sand or negligible cohesion
sand mixed with soil are met in dry condition
Wet- where sub-soil water is met at 1.5 mtr or below
- which may remain submerged in surface water for long periods with
water penetration not exceeding 1 mtr below GL, e,g, Paddy Fields
29. CLASSIFICATION OF FOUNDATION
Partially Submerged:- Where subsoil water table is met
between 0.75 mtr to 1.5 mtr
Fully Submerged:- Where subsoil water table is met at
less than 0.75 mtr below GL
Black Cotton Soil- Where soil is clayey type which shrinks
when dry & swells when wet resulting
in differential movement
Fissured Rock- Where decomposed or fissured rock, hard
gravel, kankar, limestone are met.
Undercut type foundation is used for
fissured rock
Hard Rock- Where chiseling, drilling & blasting is
required for excavation
30. TYPE OF FOUNDATION
Type of Foundation:-
- PCC Pyramid type
- RCC Pad & Step type
a) Stepped Footing
b) Under cut type
c) Block type with under cut
- Rock Anchor type
- Augur type
- Well type
- Pile type
31. Site Activities in Tower Foundation
Pit Marking & Excavation
Shuttering for Excavation, if required
Transportation of Construction Material
Dewatering (if required)
Stub Setting
Checking of Levels & Diagonals
Reinforcement Bar Fixing
Concreting
Back Filling & Removal of Template
32. Site Activities in Tower Foundation
Pit Marking & Excavation
- Carried out as per tower foundation drawing
- For estimation purpose, excavation wall shall
be vertical & pit dimensions with clearance of
150 mm on all sides
Shuttering for Excavation
- Required when the soil condition is so bad &
there is likelihood of accident due to pit
collapsing / falling of the earth
34. Site Activities in Tower Foundation
Transportation of Construction Materials
- Coarse aggregates, Fine aggregates,
Cement, water, machineries (mixer,
vibrator etc)
Dewatering
- Required for wet locations both during concreting &
24 hrs after placing concrete
Stub Setting Method
a) Template method
b) Individual Stub Setting method
c) Bottom section method
35. Site Activities in Tower Foundation
Reinforcement Bar Fixing
- Check type of bar as per specifications.
- Fixing of RF bar is carried out after lean concrete (pad)
- Size, number, bending etc to be used as per approved
drawing
- Shall be properly placed according to drawing with min.
concrete cover of 50 mm
- Shall be placed clear of stubs & cleats
- Iron wire not less than 0.9 mm to be used for binding
- Each crossing point to be bound with the help of binding
wire.
- Sufficient number of Chairs to be provided to maintain cover.
36. Concreting
RF Steel
- To be procured only from main producers, i,e, SAIL,
RINL, TISCO, IISCO or as per specifications
- Samples to test at approved laboratory & review of
100% MTC
- To be free from loose mill scales, loose rust, coats
of paints, oil, mud or any other substance to reduce bond
- Sand blasting to clean RF steel
- During storage in saline atmosphere, cement wash may
be applied on the surface before use
37. Concreting
Concreting:-
- Plain concrete pad
- Reinforced concrete for Slab (pyramid), Chimney
- Form Boxes
- Type of concrete mix
- Pouring of concrete & vibration
- Testing of concrete
- Removal of form work & repair
- Curing
Plain concrete pad
- Required to avoid possibility of RF steel exposed to earth
- M-10 (1 cement :3 fine aggregates : 6 coarse agg)
38. Concreting
Form Boxes
- Shall be as per shape, lines and dimensions shown in
drawing
- Should be rigid & sufficiently tight
- Should be of light design, easily removable
- Shall be of steel, hardwood or framed plywood
- Inner surface to be smooth
- Shall be used for casting of all type of foundations
except at undercut foundations. No form box is required
for undercut foundations.
- Inner surface should be clean, coated with approved
surface finishing compound, before every use.
39. Concreting
Nominal Mix Concrete
- M-20 (1 cement :1.5 fine aggregates :3 coarse agg)
- 20 mm coarse aggregates for Chimney
- 40 mm coarse aggregates for Slab
- M-10 (1 cement :3 fine aggregates :6 coarse agg)
- for pad (lean concrete) to avoid possibility of RF steel
exposed to earth.
40mm size aggregate to be used
40. Cement
Cement generally used in TL foundation:-
- 43 grade Ordinary Portland Cement
(IS:8112)
- 53 grade Ordinary Portland Cement (IS
12269)
- Portland Pazzolana Cement (IS 1489)
- curing time to be ascertained from a reputed laboratory
41. Concreting
Type of Concrete
- Design Mix
- mix be designed to achieve required workability & strength
not less than appropriate value
- Nominal Mix
- proportion of materials prefixed
- used for M-20 or lower
- Used in normal foundation of TL
Proportion of Nominal Mix Concrete
Grade Fine + Coarse Agg Fine :Coarse Agg Water
(Max in Kg/bag cement) Max in liter/bag cement
M-10 480 1:2 34
M-15 330 1:2 32
M-20 250 1:2 30
42. Concreting
Transportation
- Concrete to be brought to form work as fast as possible to
prevent segregation of ingredients or setting of concrete,
- special care to be taken during very hot or cold weather
Placing
- To be placed & compacted before start of setting to avoid
segregation
- Care to be taken to avoid displacement of reinforcement
or movement of formwork
- Freefall not to be more than 1.5 meter
43. Concreting
Compaction
- To compact thoroughly & fully around reinforcement,
embedded fixtures & into corners of formwork, 16 mm
poking bar rounded at the end may be used.
- By mechanical vibrator. Manually in difficult terrain
- Over vibration & under vibration are harmful & to be
avoided
Curing
- Process of preventing loss of moisture from concrete &
maintaining a satisfactory temperature regime.
- Concrete to be kept continuously wet by ponding/
covering with sacks, canvas, hessian or similar materials
- To be done for at least 10 days
44. Concreting
Form Work
- To remain sufficiently rigid during placing &
compaction of concrete
- To prevent loss of slurry from concrete
- Insides to be cleaned from all rubbish, i,e, chippings,
shavings before concreting.
- Insides to be treated with form release agent.
- To be removed after at least 24 hrs of concreting
45. Concreting
Pouring of concrete & vibration
- Use a measurement box of internal size 30x30x30 cm equivalent
to 35 liters (= 1 bag cement)
- To be mixed in mechanical mixer. In difficult terrain hand mixing
may be permitted with 10% extra cement (after approval)
- Water to be fresh, clean & free from oil, acids, alkalis
- Hard/ Salty water not to be used. Preferably portable water to be
used
- Mixing to carry out at least for 2 minutes. Check uniform
distribution of material
- Shall be laid in 150 mm layers & consolidated
- Compaction by a mechanical vibrator. In difficult terrain manually
- Copping of top surface of Chimney
- Curing for 10 days
46. Concreting
Testing of concrete
- Slump Test
- To determine consistency of concrete/work ability (water
/cement ratio.
Apparatus for slump test
- A cone of metal with following
internal dimensions
Bottom dia - 20 cm
Top dia - 10 cm
Height - 30 cm
47. Concreting
Compressive Strength
- To be tested for 28 days compressive strength
- 3 samples of 15 cm cube shall be taken
- 28 days compressive strength for
a) for M-20 – 265 km/cm2
b) for M-15 – 210 km/cm2
- Average strength to be accepted provided strength
of each cube not < 70% or > 130% of above
specified strength
48. Site Activities in Tower Foundation
Back Filling & Removal of Template
- Shall be started after repair, if any, of foundation concrete after a setting
period of 24 hrs
- Generally done by excavated soil
- Clay type, black cotton soil & large boulders (>80mm) not allowed
- Should be clean & free from organic materials
- Shall be deposited in max. 200 mm layers & compacted
- Carried out about 75 mm above finished GL
- 50 mm earthen embankment along the sides of excavation pits & to pour
water for 24 hrs
- Stub template to be removed only after completion of back
filling
49. Unit rate & Measurement for Foundation
Excavation:-
- Measurement shall be made as per actual type of soil
encountered so that total payment for excavation shall not
exceed amount as payable for excavation considering the soil
type same as that of foundation classification
Concreting:-
-Unit rate includes all allied activities, i.e, dewatering,
shuttering, form box etc
Reinforcement:-
- Unit rate includes supply, cutting, bending as per
design & placement
55. Wind Zone and Basic wind speed
Wind Zone Basic wind speed
m/ sec
1 33
2 39
3 44
4 47
5 50
6 55
56. TOWER ERECTION
Activity that starts next to the completion of
foundation.
This activity normally starts after 14days of
the foundation completion to allow the curing
time of concrete.
58. GENERAL DESCRIPTION OF TOWER
The towers shall be of the following types:
Single circuit (types A/P B/Q C/R & D/S)
Double circuit (types DA,DB,DC & DD)
Special towers
Type of tower Deviation limit Remarks
A, DA 0 – 2 Tangent tower
B, DB 2 - 15
Also Used as section
tower with 0 deviation
C, DC 15 - 30
Also used as section
tower with 0 deviation or
trans position tower
D, DD 30 - 60
Can be used for X-ing,
anchoring. Dead end
tower with maximum 15
angle of deviation
59. Standard Body & Leg Extensions
Type of Tower Body Extension Leg Extension
A, DA +3,+6, +9, +18,
+25
-4.5,-3, -1.5, 0,
+1.5,+3,+4.5,
+6,+7.5,+9
B, DB +3,+6,+9 -Do-
C, DC +3,+6,+9 -Do-
D, DD +3,+6, +9, +18,
+25
-Do-
60. Determination of Tower Heights
Main Factors:-
Minimum permissible
ground clearance (h1)
Maximum Sag (h2)
Vertical spacing bet
conductor (h3)
Vertical clearance bet
ground wire & top
conductor (h4)
61. Tower Configuration
Tower has two faces
- Longitudinal face
- Transverse face
Tower legs/faces are
designated as A, B, C & D
or 1,2,3 & 4
67. Loads on Tower
Transverse Load
i) Wind on structure, conductor, insulator & hard
wares
ii) Deviation in the angle
Longitudinal Load
- Dye to unbalanced tension in conductor, produced
either due to dead-ending of conductor on the structure or
due to broken wire conditions. It acts along the direction
of the line and the component at right angle to the
longitudinal axis of the X-arm is considered for design
68. Loads on Tower
Vertical Load
- Loads due to:-
i) weight of conductor, ground wire, insulator strings,
hard wares, accessories
ii) Unbalanced vertical loads under broken wire
conditions
iii) Dead weight of the structure and the provision for the
weight of the maintenance crew
Torsional Load
- Produced either due to dead-ending of conductor on the two
sides, e.g, due to broken wire or due to dead ending of the
conductor on single circuit lines
69. CHECKLIST BEFORE TOWER ERECTION
AVAILABILITY OF DRGS
CHECKING OF FOUNDATION
CHECK DIGONALS OF STUB
CHECK STRENGTH OF CONCRETE
ENSURE PROPER BACK FILLING
CHECKING OF TOWER PARTS FOR ANY VISUAL
DEFECTS
CHECKING OF TOOLS AND PLANTS
71. PIECEMEAL METHOD
Place members on ground serially as per erection sequence
Erection from bottom upwards
Fix four main corner members of the first section and guy
them
Raise assembled unit of the cross braces of the first section &
bolt to leg angle
First section of tower & horizontal struts bolted in position
Place 2 derricks, one on each top of diagonal legs for raising
tower parts of second section
Progressively shift derrick upwards to the corner leg members
on top of second section for raising parts of third section &
continue till completion of tower erection
Assembled cross-arm members are raised up & fixed to the
main body of the tower
72. Section & Helicopter Method
Section Method:-
- Major sections of tower are assembled on ground & same
are erected as units
- Mobile crane is required
Helicopter Method:-
- Tower can be assembled in approachable area
- Tower is erected in section or in complete shape in yards
with help of guy
73. METHODS OF TOWER ERECTION
Merits of Piecemeal Method:-
- Tower material can be supplied to site in knocked down
condition facilitating easier & cheaper transportation
- Crane/heavy equipments is not required
- Erection of tower can be done in any kind of terrain &
throughout the year
- Workmen at available at cheaper rates
74. TOWER ERECTION – INDIAN
CONDITIONS
In India due to the prevailing tough terrains
and the availability of cheaper manpower we
are erecting the towers by using the built-up
method.
75. CHECKING OF TOWER ERECTION
Verticality Check:-
- Tower shall be checked for verticality with help of
theodolite both in longitudinal & transverse direction.
- Tower shall not be out of vertical by more than 1 in
360 before stringing
76. Tower Erection
Erection to start after 14 days of concreting
Examine tower members for defects, if any
In case of minor galvanizing defects, apply 2 coats of zinc-rich
paint having at least 90% zinc content
Sort out all members sequentially
Assembling
- Straining of members not permitted for bringing them in
position. Tommy bar of max 450 mm long may be used
for the purpose.
- Lower section to be completely braced before start of
upper section
- Complete all plan diagonals of a section before start of
upper section
77. Tower Erection
- Nuts shall be facing
- outside of tower for horizontal bolts
- downwards for vertical bolts
- Cross arms are assembled at ground
- Top cross arms are lifted first, followed by middle &
bottom
- Tips of cross arms are fully tightened before lifting
- Fill up all blank holes with bolts & nuts of correct size
after completion of erection
Tightening & Punching of Bolts & Nuts
- Spring washers are to be placed under each nut
- Nuts to be tightened properly using correct size spanners
78. CHECKING OF TOWER ERECTION
TIGHTNESS OF BOLTS AS PER THE
RECOMMENDED TORQUE
BOLT HEAD SHALL BE FACING TOP AND NUTS
LAPPING DOWN
PUNCHING OF TIGHTEND BOLTS
CHECKING OF TOWER ASSEMBLY
INCORPORATION OF ALL MEMBERS AS PER
APPROVED DRAWINGS
TACK WELDING OF BOLTS
79. Checking of Tower Erection
- Tightening to carry out from top to downward
direction attending all bolts at every level
simultaneously engaging persons at all 4 faces of
tower
- Threads of bolts projecting outside nuts are punched
at 3 places on the diameter
- Threads of bolts projecting outside nuts are tack welded
at 2 diametrically opposite places
- Length of each welding is 10 mm
- Tack welding is done up to bottom X-arm for D/C &
waist level for S/C tower from GL
- 2 coats of Zinc rich paint is applied to welded portion
80. TOWER ERECTION – TOOLS
AND PLANTS
In Built-up method of tower erection the following tools and
plants are normally kept with the erection gang.
Gin pole/Derrick pole of75/100mm dia and length 8.5 to 9m
-2No
Polypropylene Rope 25mm dia – 700m
19mm dia – 1000m
Single sheave pulley - 8No
(Closed Type)
81. TOWER ERECTION – TOOLS
AND PLANTS
Spanners both ring & Flat), Hammers, slings(16mm x
1m), hooks(12mm dia) D shackle, Tommy bars -
As required
Crow Bars(25mm dia1.8m length)– 16No
Tents, Buckets, Water drums, camping cots, tables,
chairs and Petromax/ rechargeable torch – As required
82. TOWER ERECTION – TOOLS
& PLANTS
D Shackle (3”) - 6No
Hexagonal box spanner with fixed liver and
end of the liver pointed to use hole bar
(Tommy bar) - Reqd. sizes
84. TOOLS AND PLANTS-
HEALTHINESS
All the tools and plants shall be tested as per
approved safety norms and relevent test certificates
shall be available.
Periodic testing of the tools shall be carried out.
Safe working capacity shall be worked out and if the
capacity is at doubt they shall be discarded.
85.
86.
87. Tower Earthing
Required:-
- To minimize over voltage hazards due to:-
- lightning
- Switching surges
- Line-to-ground fault
- Restricting ground faults
Each tower requires Earthing
88. Tower Earthing
Earthing in TL
1) Pipe Type Earthing
- Used in dry, wet, black cotton,
submerged soil where soil
resistivity is less
- Earth strips are fixed to the
stub during concreting of the
chimney & taken out
horizontally below GL
- Generally provided in one leg,
i.e, leg A
- A galvanized flat of size
around
3 mtr is fixed during casting
- A perforated MS galv pipe of
25 mm dia, 3 mtr long is buried
in 300 mm dia hole with
89. Tower Earthing
2) Counterpoise Earthing
- Used where soil resistivity is
high, i.e, lime stone, laterite,
rocks etc
- For < 1500 ohm-mtr, with 4 nos
30 mtr long galvanized wire
- For > 1500 ohm-mtr, with 4 nos
70 mtr long galvanized wire
- A galvanized flat of size around
3 mtr is fixed during casting
similar to pipe type
- All 4 are buried 1 meter below
ground radially away
90. Tower Earthing
To study the effect of earthing it is mandatory to record
Tower Footing Resistance (TFR), before and after earthling
After earthing, Tower Footing Resistance in all the cases
should be less than 10 ohm.
92. TOWER SCHEDULE
S.No. Loc. No.
Type Of
T
o
w
e
r
Angle Of
Deviati
on
Span In
m
t
s
Cummu-lative
Span
In
Mts
Section Length
In
Mts.
Weight Span - HOT Weight Span - COLD
Remarks
Left Right Total Left Right Total
Kaitkal GANTRY 02 ° 45 ' 24 '' LT 0 30 30 0 27 27
155 155
1 AP 1/0 DDE+9 12 ° 22 ' 48 '' LT 155 50 156 206 53 157 210 Inside PGCIL Sub Station
245 400 2 No Tar Road, 2No. 11KV, CT
2 AP 2/0 DB+0 11 ° 29 ' 34 '' RT 245 152 178 330 151 174 325 Near PGCIL Sub Station
327 727 Canal, 11 KV
3 2/1 DA+0 202 207 409 206 211 417
385 1112 CT
4 2/2 DA+0 183 178 361 179 170 349
400 1512
5 2/3 DA+3 222 213 435 230 217 447
350 1862 2No. CT , 5 No 11 KV
6 2/4 DA+0 187 200 387 183 199 382
400 2262 2 Nos.LT, 2 Nos. 11KV & Gas Line
7 2/5 DA+3 200 190 390 201 194 395
400 2662 11 KV ,CT
8 2/6 DA+3 170 192 362 166 188 354
390 3052
9 2/7 DA+3 198 174 372 202 174 376
93. STRINGING - METHODS
Basically there are two methods of stringing
Manual Stringing Method
Tension Stringing Method
94. TENSION STRINGING –
TOOLS AND PLANTS
The following tools and plants are normally
used.
TSE Set (Tensioner & Puller of 8t/9t capacity.
Running block for conductor
Running block for Earthwire
Head Board
Pilot wire each of 800m length
Pilot wire joint
Ground roller for tension/Manual stringing
95. TENSION STRINGING –
TOOLS AND PLANTS
Wire mesh Pulling grip (One end open) for conductor
Wire mesh pulling grip (One end open for Earthwire)
Wire mesh pulling Grip*Both ends open) for
Conductor
Articulated joints
Drum Mounting jack for conductor drum of 10T
capacity
Turn Table (5t capacity)
96. TENSION STRINGING –
TOOLS AND PLANTS
Anchor plate with Anchor pins
Hydraulic compressor machine of 100t capacity with
die sets
Traveling Ground
Dynamometer(10t, 2t)
Pilot wire reel stand
Four sheave pulley with wire rope.
Equiliser pulley
97. TENSION STRINGING –
TOOLS AND PLANTS
Conductor lifting Tackle
Winch machine (Motorized /Manual)
Come along clamp for conductor (Bolted &
Automatic)
Come along clamp for Earthwire (Bolted &
Automatic)
Turn Buckle (10T, 3T)
Sag Board
98. Marking Roller
Mismatch Roller
Joint protector
Walkie Talkie set
Theodalite with stand
Hydraulic conductor cutter
Flags(Red & Green)
Crow bar (1.8m length)
TENSION STRINGING –
TOOLS AND PLANTS
99. Steel wire rope
Polypropylene rope
D shackle
Bull dog clamp
Hammers, spanners , slings and other
accessories.
TENSION STRINGING –
TOOLS AND PLANTS
100. SAFETY GADGETS
Safety helmets
Safety belts
Safety Shoe
First Aid Box
TENSION STRINGING –
TOOLS AND PLANTS
103. STRINGING
Steps involved
After ensuring the tightness of all the bolts and
nuts the following activities will be started.
Insulator hoisting along with aerial rollers
Earthwire stringing
Paying out the pilot wire
Positioning of Stringing equipment
104. STRINGING – ROUGH
SAGGING
Pilot wire is connected to the conductor through
running board.
Pilot wire will be pulled with the help of puller by
maintaining required tension on the conductor with
the help of tensioner.
Conductor will be pulled upto the rough sag level.
Will be allowed at rough sag level for 24 hours.
105. STRINGING – FINAL
SAGGING
Sag boards are tied.
Final sagging will be carried out with the help
of winch machine.
Check the final sag.
Mark the conductor.
Connect to the tower with the help of tension
clamp
106. STRINGING – CLIPPING &
SPACERING
After completion of final sagging.
Clipping work will be carried out at all the
suspension towers.
Spacers will be placed as per the spacer
placement chart.
107. Final Testing
a) Pre-commissioning of lines:
Readiness of lines for pre-commissioning
i) Completeness of line.
ii) Meggar test of line
b) Commissioning of lines:
Readiness of lines for commissioning
108. Final Testing
i) Digital photograph of each tower to ascertain
the completeness of tower.
ii) Electrical Inspectors clearance from CEA.
110. Statutory Clearances For Transmission Line
Project
Prior to commissioning of a Transmission Line
project, various Statutory Clearances are required
to be obtained by the field unit.
Without these Statutory Clearances the project can
not be commissioned even if construction activity
of the project are completed ahead of schedule.
111. Statutory Clearances For Transmission Line
Project
That is why it becomes necessary to submit the proposal
in time, with respective bodies so that required NOC is
obtained within a limited time frame of the project.
The different proposals are required to be submitted with
proper documentation and relevant enclosures, without
which respective bodies may nor process the proposals,
resulting in precious time loss.
112. Statutory Clearances For Transmission Line Project
Following Statutory Clearances are required to be obtained before
commissioning of a T/L Project.
1 NOC from Railway (in case Railway Crossing is involved).
2 NOC from all the forest divisions in the route of T/L
3 NOC from Air Force Department.
4 NOC from Aviation Authorities.
5 NOC from National Highway Authorities (if crossing NH)
6 NOC from PWD of respective PWD departments.
7 NOC from Irrigation/ Canals Department (if crossing any)
8 NOC from respective Electricity Boards for Power Line crossing.
9 PTCC Clearance of the project.
10 CEA Clearance of the project.
With such a large number of clearances involved in commissioning of a
Transmission Line project, all out efforts and tremendous follow-up is
required so that all is obtained within the construction schedule of the
project.
113. Statutory Clearances For Transmission Line Project
1 Procedure and Documentation required for obtaining NOC
from Railway Department.
A QUESTIONNAIRE FINALISED BY THE RAILWAY BOARD VIDE
THEIR RESEARCH DESIGNS AND STANDARD ORGANISATION
SIMLA’S LETTER NO. CW/EE/IB/I DATED 28.09.1961
B AGREMENT FOR ERECTING AND MAINTAINING AN
OVERHEAD POWER LINE CROSSING OVER AND ACROSS
RAILWAY TRACKS.
C DETAILED DRAWING OF CROSSING ARRANGEMENT
SHOWING ALL THE DETAILS. THE DRAWING HAS TO BE
PREPARED ON TRACING CLOTH ALONG WITH ALL
REQUIRED DOCUMENTS DETAILED IN QUESTIONNARE.
D MINIMUM TIME PERIOD REQUIRED FOR OBTAINING NOC IS
6 MONTHS.
114. Statutory Clearances For Transmission Line Project
1 Procedure and Documentation required for
obtaining NOC from Railway Department.
E Initially the proposal complete in all respects is submitted with Sr. DE/
DE Electrical, which happens to be the nodal officer for such cases.
F He intern forwards the proposal to other departments such as Civil,
Signals, Traction etc. for their internal NOC/ Comments (if any)
G Last of all final NOC is granter by DRM after depositing of the charges
levied by Railway department.
H After completion of the job final acceptance has to be obtained from
Railway Department which is issued by them after joint verification of
the work in accordance with the approved drawing.
I The complete process is time consuming, so it is necessary to submit the
complete and correct proposal well in time.
116. Statutory Clearances For Transmission Line Project
2 Procedure and Documentation required for obtaining NOC from Forest
Department.
Forest Land : Sec.-II, FC Act 1980, all RF, PF or any other area
recorded as forest in Govt. records and land notified u/s -IV and V
under this act termed as forest land even it is privately owned.
Reserve Forest : Natural forests having rich bio-diversity, no activity
is permitted without specific approval.
Protected Forest : Thru’ plantation and regeneration, activities
permitted unless something is specifically prohibited.
Dense Forest : Canopy density- more than 40%.
Open/Degraded Forest : Canopy density < 40%. Plantation carried
out under SF Scheme or under CA Scheme covered under PF
117.
A
B
Road Xing
Hill , No trees, Forest area
National Park/Wild life area
Social forestry
Forest area with trees
River flowing between forest ( No trees in river
bed)
Bird sanctuary
Typical Constraints in Routing of TL
118. Statutory Clearances For Transmission Line Project
2 Procedure and Documentation required for obtaining NOC from
Forest Department.
FOREST CLEARANCE IS CONVEYED
IN TWO STAGES
1st stage/In-principle clearance (Conditional)
Cost of CA, NPV, Lease Rent, dwarf tree plantation
cost etc. I.e. compliance of conditions to St. Govt.
2nd stage clearance/ Final Clearance
After Compliance from St. Govt. to MOEF/RMOEF
119. Statutory Clearances For Transmission Line Project
2 Procedure and Documentation required for obtaining NOC from
Forest Department.
STEPS INVOLVED IN FOREST CLEARANCE
Survey in forest area
Submission of details to DFO of the respective forest division.
Scrutiny & processing of case by DFO
Joint inspection by Power Grid and DFO
Tree enumeration in the selected route
Identification of non forest/degraded forest land for C.A by forest Deptt.
Preparation of CA scheme by DFO
Formulation of forest proposal
Submission/recommendation of case to DFO/CF/NO
NO scrutinize & recommend to PCCF
Recommendation of Principal Chief Conservator of Forests
Recommendation of State Government
Processing & approval by RMOEF & MOEF
120. Statutory Clearances For Transmission Line Project
2 Procedure and Documentation required for obtaining
NOC from Forest Department.
DELIGATION OF POWERS
Forest area involvement
> 5Ha.(Processing & Approval by RMOE&F)
>5Ha.-40Ha.(Processing & recommendation by RMOE&F &
Approval by Hon’ble Minister MOE&F)
>40 Ha. Processing and approval by Hon’ble Minister MOE&F
Site Inspection
Up to 40Ha. DFO inspection report
>40Ha.-100Ha. CF inspection report
>100Ha. Site inspection by RMOE&F
*FOREST CLEARANCE APPROVAL -ONLY BY CENTRAL GOVT.
PROPOSAL PROCESS & RECOMMEND- ST. GOVT. / USER AGENCY .
121. Statutory Clearances For Transmission Line Project
2 Procedure and Documentation required for obtaining
NOC from Forest Department.
FOREST ADVISORY COMMITTEE (FAC) OF MOEF
I. Director General of Forests, MOEF - Chairperson
II. Addl. DG (Forests), MOEF - Member
III. Addl. Commissioner (Soil Conservation), - Member
Ministry of Agriculture
IV. 3 non-official experts one each in Mining, - Members
V. Civil Eng. and Dev. Economics - Members
VI. Inspector General (FC), MOEF - Member Sect.
Addl. DG (Forests) shall act as Chairperson in the absence of DG (Forests)
FAC meets at least once in every month (3rd/4th week) to discuss/
recommend proposals to Hon’ble minister for approval under FC Act 1980
involving forest > 40 ha.
122. Statutory Clearances For Transmission Line Project
2 Procedure and Documentation required for obtaining NOC from
Forest Department.
REGIONAL EMPOWERED COMMITTEE (REC)
(EARLIER SAG)
COMPOSITION :-
I. Regional PCCF (Central)-Chairperson
II. 3 Non-official members - experts one each in Mining,
III. Civil Engineering and Development Economics – Members
IV. CF or DCF of Regional Office – Member Secretary
SCHEDULE FOR REC MEETING(S)
MEETING(S) OF REC IS CONVENED BY REGIONAL CHIEF
CONSERVATOR OF FORESTS/CONSERBATOR OF FORESTS AS &
WHEN REQUIRED
123. 2 Procedure and Documentation required for obtaining NOC from Forest
Department.
REGIONAL MOE&F’s OFFICES
REGIONAL OFFICES CONCERNED STATE
Chief Conservator of Forest
(Central) Southern Zone, Bangalore
Kerala, Tamil, Andhra Pradesh, Karnataka,
Pondicherry, Lakshwadeep & Goa
CCF (Central), Western Zone,
Bhopal
Gujarat, Madhya Pradesh, Maharashtra,
D&N Haveli, Daman & Diu & Chh’garh
CCF (Central), Eastern Zone,
Bhubaneswar
Bihar, West Bengal, Orissa, A&N Island &
Jharkhand
CF (Central), Northern Zone,
Chandigarh
Haryana, Punjab, Himachal and Jammu &
Kashmir
CCF(Central), Central Zone,
Lucknow
Uttaranchal, U.P., Delhi & Rajasthan
CCF(Central), North-Eastern Region,
Shillong
Assam, Tripura, Mizoram, Manipur,
Meghalaya, Arunachal Pradesh , Nagaland
Sikkim
124. Statutory Clearances For Transmission Line Project
2 Procedure and Documentation required for obtaining
NOC from Forest Department.
Time Limit for forest proposal Approval
St. Govt. (Total) : 210 days
Nodal officer : 10 days
DFO : 90 days
Nodal Officer (NO) : 30 days
St. Govt. (Sectt.) : 60 days
Central Govt. : 90 days
TOTAL TIME : 300 DAYS.
125. Statutory Clearances For Transmission Line Project
2 Procedure and Documentation required for obtaining NOC from
Forest Department.
ROUTE SELECTION
Does not involve any human rehabilitation
Monuments of cultural or historical importance
Threat to survival of any community
Public utility services
Avoid WL Sanctuary, National Park, Biosphere Zone etc.
No Infringement with area of natural resources
Minimum Involvement of Road/canal/River/Railway X-ing.
Minimum Involvement of RF/Forests etc.
126. Statutory Clearances For Transmission Line Project
2 Procedure and Documentation required for obtaining NOC from Forest
Department.
RIGHT OF WAY FOR CALCULATION OF DIVERSION AREA
Transmission line Voltage (KV) ROW (Mtrs.)
Maximum
11 7
33 15
66 18
110 22
132 27
220 35
400 46
+/- 500 KV HVDC/400 S/C 52
800 64-85
127. Statutory Clearances For Transmission Line Project
2 Procedure and Documentation required for obtaining NOC from
Forest Department.
FORMULATION OF FOREST PROPOSAL
State wise & line wise
Tree enumeration/Joint inspection
Certification of Minimum Involvement of forest with 3
alternatives marked in Forest topo-maps / Rev. map
Identification of Degraded reserved/ protected forestland
double the area of forest land to be diverted for our
purpose for Compensatory Afforestation
Cost benefit Analysis for diversion above 5 hac.
Compensatory Afforestation (CA) Scheme
128.
129.
130. Statutory Clearances For Transmission Line Project
3 & 4 Procedure and Documentation required for obtaining NOC from Air Force & Aviation
Authorities.
The purpose of NOC is to notify the aviation and Air Force authorities the
exact location of towers along the line route.
Exact location has to be supported by providing tower schedule depicting
details of Latitude, Longitude and top elevation of each and every tower.
Route marked on survey sheets has also to be enclosed.
The correctness of data is most important as the information given by user
agency is incorporated on the flight map of said authorities for flight safety.
The proposal supported with a Questionnaire, undertaking and supporting
documents are required to be submitted at nearest Airport in case of
Aviation and at Vayu Bhawan, New Delhi, in case of Air Force.
Time period for issuance of NOC is +6Months.
131. Statutory Clearances For Transmission Line Project
5,6&7 Procedure and Documentation required for obtaining
NOC from National Highway, PWD, canals etc.
The purpose of NOC is to notify the these departments about
the project so that the concerned department gets the
knowledge of the project and in case of any proposed scheme
in process may advise accordingly, which otherwise can result
into shifting of a part of the route causing loss of investment..
Exact location of the crossing points has to be supported by
providing tower schedule and profile of the crossing area.
The proposal has to be submitted with concerned authorities
along with an undertaking regarding safety responsibility and
for shifting at user agency cost in case need arises.
132. Statutory Clearances For Transmission Line Project
8 Procedure and Documentation required for obtaining NOC from
Respective Electricity Boards.
The purpose of NOC is to notify the these departments about the project so
that the concerned department gets the knowledge of the project and in case
of any proposed scheme in process may advise accordingly, which
otherwise can result into shifting of a part of the route causing loss of
investment..
Exact location of the crossing points has to be supported by providing
tower schedule and profile of the crossing area.
Cross profile of the existing Power Line has also to be generated and
minimum clearance under worst conditions ahs to be guaranteed
The proposal has to be submitted with concerned authorities along with
profile showing the minimum clearance will shall be available after
crossing the existing TL. The approval is conveyed by concerned board
with the condition that the drawing parameters are available after execution
and subject to final joint inspection before energizing the Transmissions
Line.
133. 9 Procedure and Documentation required for
obtaining PTCC Clearance
1. Initially it is required to send Application/ Intimation to the
following:
a) Director (PTCC), CEA, New Delhi.
b) DET(PTCC), New Delhi-(Depending upon region)
Copies to:
c) GM (S&T) Concern Railways .
d) GM (Telecom District) of all the districts where line is
passing through .
With request to mark the existing/proposed railway telecom circuits/
P&T circuits/ Co-axial cables on the route map submitted by us.
134. 9 Procedure and Documentation required for obtaining PTCC
Clearance
1 Though it is the responsibility of BSNL and PTCC
department to get the lines marked in GT Sheets, but site has
to meet the concern GM of Telecom District for following
up for issuing the instructions to the DE’s (Telecom) of the
areas ( Territorial Officers) under his control.
2 Site has to follow up with the DE of the region for clarifying
the doubts and corrections to be made by concern telecom
districts and for resubmission.
135. 9 Procedure and Documentation required for obtaining PTCC
Clearance
3 With this copy site has to meet the concern Divisional Engineers and get marked
the P&T ckts/ Co-axial cables on the route map submitted by us on the width of
8 Kilometers on the both sides of our line under construction.
4 Same will be forwarded by the Divisional Engineer to their GM/ Telecom
District.
5 As per CEA Directives PTCC case is routed through ED office only.
6. After compilation of the reports received from the GMs of all the Telecom
Districts Divisional Engineer Telecom/ PTCC, T &D CIRCLE of the Region
will forward the same to the DIRECTOR (PTCC), CEA, NEW DELHI
a) For the comments regarding LF Induction on the paralleling Telecom Lines
under worst fault conditions due to proposed power line.
b) In Case of Railway Block Circuits, the break up figures of the L.F. Induced
voltage on station-to –station basis and the value of the mutual coupling for each
section).
136. 9 Procedure and Documentation required for obtaining PTCC
Clearance
7 On receipt of the details at PTCC/CEA , New Delhi , the concern
Director will calculate the INDUCED Voltages and forward the same
details to the Divisional Engineer Telecom/ PTCC of the region and GM
of the Railways for the necessary action.
8 Divisional Engineer Telecom/ PTCC of the region in turn gives
instructions to the concern GMs/ POWERGRID for providing the
protection to the telecom equipment / cables if the induced voltage is
more than the 650V by providing GD Tubes , Magazines etc.
a If the IV is Less than 650 Volts Telecom department themselves has
to provide Protection.
b If the IV is More than 650 Volts POWERGRID has pay cost the
equipment required for providing the protection to Telecom
department for installation.
137. 9 Procedure and Documentation required for obtaining PTCC
Clearance
9. DE Telecom /PTCC of the region will give the conditional
provisional clearance after the protections installed/ under
progress.
List of Documents required with the PTCC case:
1 Route Map of Transmission Line
2 Line diagram of Connecting Sub-Stations.
3 Detail of Transformers likely to be put in use.
4 Tower Drawing.
5 Questionnaire
6 Detail of Telecom Lines.
7 Soil Resistivity of entire TL.
138. 10 Procedure and Documentation required for obtaining CEA
Clearance
It is mandatory to obtain clearance from Electrical Inspector prior
to energizing any electrical installation.
For Government of India projects the Electrical Inspector is ,
Superintending Engineer, Central Elect6ricitry Authority.
The complete case has to be submitted to Electrical Inspector,
under Intimation to CE, Inspection Cell, when installation is
complete in all respects and is ready for energizing.
As the schedule of Electrical is very busy the proposal is required
to be submitted in anticipation of completion date.
Once the date of inspection is fixed the inspector inspects the
installation and may ask for compliance of the observations (if
observed any).
On submission of compliance report, final charging clearance is
issued by Electrical Inspector.
139. 10 Procedure and Documentation required for obtaining CEA
Clearance
Documents required to be submitted with CEA Case:
1 Application enclosed with the required documents for
approval of the Electrical Inspector to Energize the
HV/EHV Overhead Transmission Lines and Underground
Cables etc. Under Rule 63 of Indian Electricity Rules, 1961.
2 Line diagram of Sub-Stations and Transformer
Specifications.
3 Complete Tower Schedule of the Transmission Line.
4 Detail of Crossings and the available clearance.
5 Payment calculation detail with respect to the laid
down charges.
140. With all the above at stake of a Transmission
Line Project, you yourself can decide how fast
and effective you have to be to complete the
project in time.
Give a thought to it and start re-planning your
time module else you will be late by miles..