SlideShare a Scribd company logo
February
Analysis of life-cycle
costs
The Roseau Dam infrastructure, Saint Lucia
2022
Context
• Climate change models have predicted that St.
Lucia will undergo a warming and drying trend and
is expected to endure more frequent heat waves
and droughts, rainfalls with increased intensity,
and rising sea levels as predicted for the rest of the
Caribbean consistent with the projected global
median. Probable climate change impacts in St.
Lucia include higher temperatures, higher storm
intensities and, possibly, more frequent El Niño-
Southern Oscillation (ENSO) events, exacerbating
existing health, social and economic challenges
affecting St. Lucia. (ref. WB Global Facility for
Disaster Reduction and Recovery GFDRR Country
Notes – Saint Lucia)
2
Roseau Dam
• Construction on the dam began in April 1993
but was substantially delayed when Tropical
Storm Debby struck the island on 10 September
1994. Rainfall from the storm exceeded the
1000 - year estimate and ensuing floods
breached the incomplete dam. The dam was
eventually completed in October 1995 and
commissioned in 1996. The dam's reservoir,
Roseau Reservoir, is experiencing heavily
siltation and studies are currently underway to
remediate the problem. Hurricane Tomas in
2010 and a severe December 2013 storm
created large landslides in the reservoir that
have reduced its capacity by at least 30 percent.
(https://en.wikipedia.org/?curid=48936020)
3
Location
4
Dam rehabilitation
St. Lucia ‘The Voice’ newspaper
• The dam rehabilitation
project is aimed at increasing
Saint Lucia’s water collection,
storage and distribution
capacity.
ADD A FOOTER 5
Phases 1 and 2 of Dam Infras.
Project
• Phase one of the project saw the
construction of a sediment disposal area
including reforestation and stabilisation of
60 ha of land in one year and 98ha in the
second year in order to reduce land
siltation (building of disposal pit) and soil
erosion at the dam site. It was funded
exclusively by the State-owned Water and
Sewerage Company (WASCO) from a
drenching fee introduced in 2012. The fee
was part of consumers’ bills, and has
accumulated to approximately EC$25.95
million dollars.
• The second phase of the project includes
the installation of pipes and the removal of
sediment, thus expanding the water
treatment plant from 0.4 m gallons to 1.4
m gallons per day, in order to increase the
water supply and quality to residents. That
phase will be financed through a loan
secured from the Caribbean Development
Bank. The overall cost of the project now
stands at EC$54 million (Ministry of
Infrastructure website). Currently, this
second phase of the project was awarded
to Vinci Construction Maritime et Fruvial
via international competitive bidding in
July 2018 and was followed by a “no
objection” from the Caribbean
Development Bank (CDB) and dredging
commenced in early October 2020 and is
ongoing.
6
Sectoral Adaptation
Plan
• The timely Saint Lucia 10-year Sectoral Adaptation Plan for
Water was developed in 2017, just before the second phase
of the project. It consists of 70 adaptation measures deemed
critical for improving water infrastructure and service
management and reducing water-mediated climate change
impacts in the country. The measures, endorsed by relevant
stakeholders, offer solutions to information, technical,
institutional, financial, regulatory and policy limitations
hampering adaptation in the water sector. These guide the
goals of, inter alia, increased water access, availability
and quality; water efficiency and conservation;
Strengthened preparedness to climate variability and
extremes. This allows them to follow the Quality
Infrastructure Investment (QII) Principles along the life-cycle
of the projects. 7
Life-cycle costing issues
• Non-revenue water loss at a high of 42% - 60%
• High involvement of State-owned stakeholder who does the price-
making.
• Increase in water tariffs for consumer; though outages and
shortages are common.
• No control over weather patterns causing, as we have seen, severe
damage and high costs for repair, operation and maintenance.
• Mitigation and adaptation become an ever-moving goal post and
uncertainty of climate change makes it almost impossible to
predict the damage, scale and effects of the damage. What is clear
is that they will impact water supply for 100 000 people and
reduce water quality and infrastructure reliability.
• Lack of local technical capacity to respond to major threats and
potential damage, therefore seeking international expertise,
bringing them into the country in a time of a health pandemic, and
training of local staff to continue the highly technical work, all
become an additional costs to the project.
• Seismic hazards: The seismic hazard at the site of
the dam in Saint Lucia is evaluated probabilistically
for engineering design purposes. The assessment
takes advantage of recent high quality regional
seismological data, reappraised older instrumental
catalogues and current tectonic interpretations.
Saint Lucia stands at a position in the Lesser Antilles
island arc where two distinct, seismically active,
subduction zones appear to converge at different
depths. As a result, the seismic hazard is critically
dependent on site position relative to the
boundaries of these major source zones, which each
exhibit different activity rates. The ground motion
hazard at the damsite is computed using the
probabilistic logic-tree program PRISK (ref. Lancaster
University research directory)
8
Recommendations
- Pursue collaboration with international agencies such as the
UN Office for Project Services and universities such as
University of Oxford-led Infrastructure Transitions Research
Consortium (ITRC) to facilitate evidence-based decision
making, while also aligning recommendations with the Paris
Agreement and the SDGs and the Paris Agreement on
Climate Change. The first such joint approach resulted in a
National Infrastructure Assessment completed in 2020. They
developed a National Infrastructure Systems Model
(NISMOD) composed of a series of analysis steps, which has
been designed to assess a country’s current and future
infrastructure needs and to provide recommendations on
how those needs can best be met (ref. National
Infrastructure Assessment Report). Though this
comprehensive model analysis was developed after the dam
was built, it can assist in recalibrating and adapting the dam
infrastructure project so that it reduces costs during the
second phase of the project, and also maintenance costs
and any other costs to the community, including resulting in
lower tariffs/ user fees.
9
Recommendations
- It is not clear whether the life cycle costing approach
was used in procurement process for the maintenance of
the dam. The documents for bidding and bid evaluation
are not always publicly available as the government may
have considered that relevant expertise is not available
in-country. However, the cross-departmental input
approach used to develop the terms of reference is one
way to ensure that quality and value for money is being
considered in the bidding process. Transparency in
procurement is essential.
- Evidence-based planning for climate-compatible
investment and development, facilitated by the
cooperation of numerous different ministries and
departments, can help Saint Lucia apply and benefit
from global adaptation funds to ensure long-term
sustainable growth.
- Building institutional capacity is also essential
for risk management and cost effectiveness:
Institutional capacity is pivotal to ensuring asset
management before, during, and after a
hazard. This includes the ability to use hazard
exposure modelling to inform decisions,
incorporate early warning systems, and to
develop emergency and evacuation plans.
- Resilient design of infrastructure maintenance
systems: Changing the design of infrastructure
supply can provide a relatively inexpensive and
adaptive way to adapt to erosion.
10
Recommendations
- Climate change has and will amplify existing
hazards, and have damaging effects on the dam as
it is in an exposed area (see photos). Disruptions to
basic infrastructure services (outages, reduced
water supply, silted water and reduced quality)
may have cascading socio-economic
consequences, particularly for the surrounding
communities, for hygiene, disease transmission,
education, or community services. Nature-based
solutions such as replanting of vegetation and
protection of the reservoir basin are a requirement
to prevent or limit future siltation related to
natural hazards such as erosion. Revegetating is a
simple, cost-effective, and community-based risk-
reduction solution.
- Private investment mobilisation can also be
considered, as mainly institution financial
mechanisms has been used thus far. Investors can
recuperate funds from affordable tariffs that may
be set once the water service is provided on a
more regular basis to an increasing consumer base
in a more reliable manner.
- Performance-based contracts could be considered
where remuneration is based on performance,
rather than long-term contacts that the
administration in Saint Lucia is accustomed to, as
the private party will then bear a significant
amount of risk and management responsibility,
which is currently mainly in the hand of the
national Water authorities.
11
Recommendations
- Seek ways to maximise the positive impact of the
infrastructure on communities, such as promoting
sustainable development , and community involvement
in observing and reporting damage to the dam and
reforestation awareness.
- Pursue predictive maintenance or preventative measures
as far as possible, based on optimal timing of events so
that the actors are not merely reactive when disaster
strikes, and this will contribute to reduced costs and
possibly its extended life as well as increased reliability.
- Greater effort is required in terms of safety and security
to further boost the production quality and capacity of
the dam, in light of an increasing population as well as
increasing usage by increased tourist arrivals. Smarter
technology may be utilised to model the dam and
observe virtual risks that may arise and that may hamper
operation and maintenance.
- Regulation on the safety and security of
surrounding terrain must also be included in the
maintenance of the dam as it remains accessible
to wandering members of the public and may cost
lives because of exposed high voltage wires.
- Resilience of the dam must also be clearly
addressed as such capacity building including
engineers within the water authority’s staff …
- It is necessary to design and put in place a
monitoring plan for the implementation of the
Water Adaptation Plan itself and for the dam
infrastructure, to ensure that the activities
conducted are completed and contribute to the
achievement of the established objectives and
outcomes. The monitoring and evaluation (M&E)
plan will also help to determine corrective actions
when changes, due to existing and new
circumstances occur, and will ease reporting.
12
Recommendations
- The dam could be used to produce hydroelectricity,
and though the cost may be high at initial stages, it
has potential to contribute further to carbon dioxide
reduction and reduce the use of GHGs on the Island
as well as reduce overall cost of energy. Energy
consumption and pollution can be limited by the use
of solar energy along the dam site.
- Regional integration in infrastructure
management (on the operation and
maintenance of the dam) is an option to
be considered as other Islands in the
Caribbean have dams have been using
hydropower and geothermal energy as a
means of compensating for a reduction in
fossil fuel options.
13
THANK YOU!

More Related Content

Similar to Analysis of life cycle costs - Roseau Dam - final project

assignmenttutorhelp.com
assignmenttutorhelp.comassignmenttutorhelp.com
assignmenttutorhelp.com
Sudeshna Sen Gupta
 
Community engagement on adaptation to sea level change
Community engagement on adaptation to sea level changeCommunity engagement on adaptation to sea level change
Community engagement on adaptation to sea level change
Neil Dufty
 
2011 12-15 -report_to_spc_acm_final
2011 12-15 -report_to_spc_acm_final2011 12-15 -report_to_spc_acm_final
2011 12-15 -report_to_spc_acm_final
Naoise
 
Understanding Climate Change Adaptation in the Saint Lucia Context
Understanding Climate Change Adaptation in the Saint Lucia ContextUnderstanding Climate Change Adaptation in the Saint Lucia Context
Understanding Climate Change Adaptation in the Saint Lucia Context
NAP Global Network
 
Wetlands and Stormwater Management
Wetlands and Stormwater ManagementWetlands and Stormwater Management
Wetlands and Stormwater Management
Andrew T. Der & Associates, LLC
 
Flood management systems
Flood management systemsFlood management systems
Flood management systems
CKMCforstudents
 
Nguyen dinh khoa's assignment adaptation - the city of cape town
Nguyen dinh khoa's assignment   adaptation - the city of cape townNguyen dinh khoa's assignment   adaptation - the city of cape town
Nguyen dinh khoa's assignment adaptation - the city of cape town
Nguyễn Khoa
 
EA - Business Case for Adaption - May 15 - v12 Low res FINAL
EA - Business Case for Adaption - May 15 - v12 Low res FINALEA - Business Case for Adaption - May 15 - v12 Low res FINAL
EA - Business Case for Adaption - May 15 - v12 Low res FINALKit England
 
Covering Natural Disaster Losses for Water Utilities - An insurance mutual fo...
Covering Natural Disaster Losses for Water Utilities - An insurance mutual fo...Covering Natural Disaster Losses for Water Utilities - An insurance mutual fo...
Covering Natural Disaster Losses for Water Utilities - An insurance mutual fo...
CAWASA
 
Critical water shortages disaster plan summary
Critical water shortages disaster plan summaryCritical water shortages disaster plan summary
Critical water shortages disaster plan summary
Fanus van Straten
 
TR0288.pdf
TR0288.pdfTR0288.pdf
TR0288.pdf
aloknayak47
 
ADB,GWP and Water Security presented by Dr. Thomas Panella at GWP Network Me...
ADB,GWP and Water Security presented by Dr. Thomas  Panella at GWP Network Me...ADB,GWP and Water Security presented by Dr. Thomas  Panella at GWP Network Me...
ADB,GWP and Water Security presented by Dr. Thomas Panella at GWP Network Me...
Global Water Partnership
 
Showcasing Successful Green Stormwater Infrastructure - Lessons from Implemen...
Showcasing Successful Green Stormwater Infrastructure - Lessons from Implemen...Showcasing Successful Green Stormwater Infrastructure - Lessons from Implemen...
Showcasing Successful Green Stormwater Infrastructure - Lessons from Implemen...
Amy Greenwood
 
GreenStormwaterInfrastructure_CaseStudyReport_LR
GreenStormwaterInfrastructure_CaseStudyReport_LRGreenStormwaterInfrastructure_CaseStudyReport_LR
GreenStormwaterInfrastructure_CaseStudyReport_LRAmy Greenwood
 
Climate Change Adaptation Strategy
Climate Change Adaptation StrategyClimate Change Adaptation Strategy
Climate Change Adaptation Strategy
Turlough Guerin GAICD FGIA
 
Net Impact Case Competition Urban Infrastructure Strategy
Net Impact Case Competition Urban Infrastructure StrategyNet Impact Case Competition Urban Infrastructure Strategy
Net Impact Case Competition Urban Infrastructure Strategy
Yoni Sarason
 
Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...
Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...
Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...
Robert Muir
 
Sanders, Richard: The Integrated Ocean Carbon Observing System
Sanders, Richard: The Integrated Ocean Carbon Observing SystemSanders, Richard: The Integrated Ocean Carbon Observing System
Sanders, Richard: The Integrated Ocean Carbon Observing System
Integrated Carbon Observation System (ICOS)
 

Similar to Analysis of life cycle costs - Roseau Dam - final project (20)

backgrounder_lmfls
backgrounder_lmflsbackgrounder_lmfls
backgrounder_lmfls
 
assignmenttutorhelp.com
assignmenttutorhelp.comassignmenttutorhelp.com
assignmenttutorhelp.com
 
Community engagement on adaptation to sea level change
Community engagement on adaptation to sea level changeCommunity engagement on adaptation to sea level change
Community engagement on adaptation to sea level change
 
2011 12-15 -report_to_spc_acm_final
2011 12-15 -report_to_spc_acm_final2011 12-15 -report_to_spc_acm_final
2011 12-15 -report_to_spc_acm_final
 
Understanding Climate Change Adaptation in the Saint Lucia Context
Understanding Climate Change Adaptation in the Saint Lucia ContextUnderstanding Climate Change Adaptation in the Saint Lucia Context
Understanding Climate Change Adaptation in the Saint Lucia Context
 
Wetlands and Stormwater Management
Wetlands and Stormwater ManagementWetlands and Stormwater Management
Wetlands and Stormwater Management
 
Flood management systems
Flood management systemsFlood management systems
Flood management systems
 
Nguyen dinh khoa's assignment adaptation - the city of cape town
Nguyen dinh khoa's assignment   adaptation - the city of cape townNguyen dinh khoa's assignment   adaptation - the city of cape town
Nguyen dinh khoa's assignment adaptation - the city of cape town
 
Lgu services amp
Lgu services ampLgu services amp
Lgu services amp
 
EA - Business Case for Adaption - May 15 - v12 Low res FINAL
EA - Business Case for Adaption - May 15 - v12 Low res FINALEA - Business Case for Adaption - May 15 - v12 Low res FINAL
EA - Business Case for Adaption - May 15 - v12 Low res FINAL
 
Covering Natural Disaster Losses for Water Utilities - An insurance mutual fo...
Covering Natural Disaster Losses for Water Utilities - An insurance mutual fo...Covering Natural Disaster Losses for Water Utilities - An insurance mutual fo...
Covering Natural Disaster Losses for Water Utilities - An insurance mutual fo...
 
Critical water shortages disaster plan summary
Critical water shortages disaster plan summaryCritical water shortages disaster plan summary
Critical water shortages disaster plan summary
 
TR0288.pdf
TR0288.pdfTR0288.pdf
TR0288.pdf
 
ADB,GWP and Water Security presented by Dr. Thomas Panella at GWP Network Me...
ADB,GWP and Water Security presented by Dr. Thomas  Panella at GWP Network Me...ADB,GWP and Water Security presented by Dr. Thomas  Panella at GWP Network Me...
ADB,GWP and Water Security presented by Dr. Thomas Panella at GWP Network Me...
 
Showcasing Successful Green Stormwater Infrastructure - Lessons from Implemen...
Showcasing Successful Green Stormwater Infrastructure - Lessons from Implemen...Showcasing Successful Green Stormwater Infrastructure - Lessons from Implemen...
Showcasing Successful Green Stormwater Infrastructure - Lessons from Implemen...
 
GreenStormwaterInfrastructure_CaseStudyReport_LR
GreenStormwaterInfrastructure_CaseStudyReport_LRGreenStormwaterInfrastructure_CaseStudyReport_LR
GreenStormwaterInfrastructure_CaseStudyReport_LR
 
Climate Change Adaptation Strategy
Climate Change Adaptation StrategyClimate Change Adaptation Strategy
Climate Change Adaptation Strategy
 
Net Impact Case Competition Urban Infrastructure Strategy
Net Impact Case Competition Urban Infrastructure StrategyNet Impact Case Competition Urban Infrastructure Strategy
Net Impact Case Competition Urban Infrastructure Strategy
 
Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...
Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...
Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...
 
Sanders, Richard: The Integrated Ocean Carbon Observing System
Sanders, Richard: The Integrated Ocean Carbon Observing SystemSanders, Richard: The Integrated Ocean Carbon Observing System
Sanders, Richard: The Integrated Ocean Carbon Observing System
 

Recently uploaded

PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
ClaudioTebaldi2
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
ahcitycouncil
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
Get Government Grants
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
RIDPRO11
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
SERUDS INDIA
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
JSchaus & Associates
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
ahcitycouncil
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
ehbuaw
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
Paul Smith
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
Mohammed325561
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
ehbuaw
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
ukyewh
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
ehbuaw
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
ahcitycouncil
 
Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023
ARCResearch
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
oklahomajudicialproc1
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
AjayVejendla3
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
ILC- UK
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
GrantManagementInsti
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
SERUDS INDIA
 

Recently uploaded (20)

PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
 
Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
 

Analysis of life cycle costs - Roseau Dam - final project

  • 1. February Analysis of life-cycle costs The Roseau Dam infrastructure, Saint Lucia 2022
  • 2. Context • Climate change models have predicted that St. Lucia will undergo a warming and drying trend and is expected to endure more frequent heat waves and droughts, rainfalls with increased intensity, and rising sea levels as predicted for the rest of the Caribbean consistent with the projected global median. Probable climate change impacts in St. Lucia include higher temperatures, higher storm intensities and, possibly, more frequent El Niño- Southern Oscillation (ENSO) events, exacerbating existing health, social and economic challenges affecting St. Lucia. (ref. WB Global Facility for Disaster Reduction and Recovery GFDRR Country Notes – Saint Lucia) 2
  • 3. Roseau Dam • Construction on the dam began in April 1993 but was substantially delayed when Tropical Storm Debby struck the island on 10 September 1994. Rainfall from the storm exceeded the 1000 - year estimate and ensuing floods breached the incomplete dam. The dam was eventually completed in October 1995 and commissioned in 1996. The dam's reservoir, Roseau Reservoir, is experiencing heavily siltation and studies are currently underway to remediate the problem. Hurricane Tomas in 2010 and a severe December 2013 storm created large landslides in the reservoir that have reduced its capacity by at least 30 percent. (https://en.wikipedia.org/?curid=48936020) 3
  • 5. Dam rehabilitation St. Lucia ‘The Voice’ newspaper • The dam rehabilitation project is aimed at increasing Saint Lucia’s water collection, storage and distribution capacity. ADD A FOOTER 5
  • 6. Phases 1 and 2 of Dam Infras. Project • Phase one of the project saw the construction of a sediment disposal area including reforestation and stabilisation of 60 ha of land in one year and 98ha in the second year in order to reduce land siltation (building of disposal pit) and soil erosion at the dam site. It was funded exclusively by the State-owned Water and Sewerage Company (WASCO) from a drenching fee introduced in 2012. The fee was part of consumers’ bills, and has accumulated to approximately EC$25.95 million dollars. • The second phase of the project includes the installation of pipes and the removal of sediment, thus expanding the water treatment plant from 0.4 m gallons to 1.4 m gallons per day, in order to increase the water supply and quality to residents. That phase will be financed through a loan secured from the Caribbean Development Bank. The overall cost of the project now stands at EC$54 million (Ministry of Infrastructure website). Currently, this second phase of the project was awarded to Vinci Construction Maritime et Fruvial via international competitive bidding in July 2018 and was followed by a “no objection” from the Caribbean Development Bank (CDB) and dredging commenced in early October 2020 and is ongoing. 6
  • 7. Sectoral Adaptation Plan • The timely Saint Lucia 10-year Sectoral Adaptation Plan for Water was developed in 2017, just before the second phase of the project. It consists of 70 adaptation measures deemed critical for improving water infrastructure and service management and reducing water-mediated climate change impacts in the country. The measures, endorsed by relevant stakeholders, offer solutions to information, technical, institutional, financial, regulatory and policy limitations hampering adaptation in the water sector. These guide the goals of, inter alia, increased water access, availability and quality; water efficiency and conservation; Strengthened preparedness to climate variability and extremes. This allows them to follow the Quality Infrastructure Investment (QII) Principles along the life-cycle of the projects. 7
  • 8. Life-cycle costing issues • Non-revenue water loss at a high of 42% - 60% • High involvement of State-owned stakeholder who does the price- making. • Increase in water tariffs for consumer; though outages and shortages are common. • No control over weather patterns causing, as we have seen, severe damage and high costs for repair, operation and maintenance. • Mitigation and adaptation become an ever-moving goal post and uncertainty of climate change makes it almost impossible to predict the damage, scale and effects of the damage. What is clear is that they will impact water supply for 100 000 people and reduce water quality and infrastructure reliability. • Lack of local technical capacity to respond to major threats and potential damage, therefore seeking international expertise, bringing them into the country in a time of a health pandemic, and training of local staff to continue the highly technical work, all become an additional costs to the project. • Seismic hazards: The seismic hazard at the site of the dam in Saint Lucia is evaluated probabilistically for engineering design purposes. The assessment takes advantage of recent high quality regional seismological data, reappraised older instrumental catalogues and current tectonic interpretations. Saint Lucia stands at a position in the Lesser Antilles island arc where two distinct, seismically active, subduction zones appear to converge at different depths. As a result, the seismic hazard is critically dependent on site position relative to the boundaries of these major source zones, which each exhibit different activity rates. The ground motion hazard at the damsite is computed using the probabilistic logic-tree program PRISK (ref. Lancaster University research directory) 8
  • 9. Recommendations - Pursue collaboration with international agencies such as the UN Office for Project Services and universities such as University of Oxford-led Infrastructure Transitions Research Consortium (ITRC) to facilitate evidence-based decision making, while also aligning recommendations with the Paris Agreement and the SDGs and the Paris Agreement on Climate Change. The first such joint approach resulted in a National Infrastructure Assessment completed in 2020. They developed a National Infrastructure Systems Model (NISMOD) composed of a series of analysis steps, which has been designed to assess a country’s current and future infrastructure needs and to provide recommendations on how those needs can best be met (ref. National Infrastructure Assessment Report). Though this comprehensive model analysis was developed after the dam was built, it can assist in recalibrating and adapting the dam infrastructure project so that it reduces costs during the second phase of the project, and also maintenance costs and any other costs to the community, including resulting in lower tariffs/ user fees. 9
  • 10. Recommendations - It is not clear whether the life cycle costing approach was used in procurement process for the maintenance of the dam. The documents for bidding and bid evaluation are not always publicly available as the government may have considered that relevant expertise is not available in-country. However, the cross-departmental input approach used to develop the terms of reference is one way to ensure that quality and value for money is being considered in the bidding process. Transparency in procurement is essential. - Evidence-based planning for climate-compatible investment and development, facilitated by the cooperation of numerous different ministries and departments, can help Saint Lucia apply and benefit from global adaptation funds to ensure long-term sustainable growth. - Building institutional capacity is also essential for risk management and cost effectiveness: Institutional capacity is pivotal to ensuring asset management before, during, and after a hazard. This includes the ability to use hazard exposure modelling to inform decisions, incorporate early warning systems, and to develop emergency and evacuation plans. - Resilient design of infrastructure maintenance systems: Changing the design of infrastructure supply can provide a relatively inexpensive and adaptive way to adapt to erosion. 10
  • 11. Recommendations - Climate change has and will amplify existing hazards, and have damaging effects on the dam as it is in an exposed area (see photos). Disruptions to basic infrastructure services (outages, reduced water supply, silted water and reduced quality) may have cascading socio-economic consequences, particularly for the surrounding communities, for hygiene, disease transmission, education, or community services. Nature-based solutions such as replanting of vegetation and protection of the reservoir basin are a requirement to prevent or limit future siltation related to natural hazards such as erosion. Revegetating is a simple, cost-effective, and community-based risk- reduction solution. - Private investment mobilisation can also be considered, as mainly institution financial mechanisms has been used thus far. Investors can recuperate funds from affordable tariffs that may be set once the water service is provided on a more regular basis to an increasing consumer base in a more reliable manner. - Performance-based contracts could be considered where remuneration is based on performance, rather than long-term contacts that the administration in Saint Lucia is accustomed to, as the private party will then bear a significant amount of risk and management responsibility, which is currently mainly in the hand of the national Water authorities. 11
  • 12. Recommendations - Seek ways to maximise the positive impact of the infrastructure on communities, such as promoting sustainable development , and community involvement in observing and reporting damage to the dam and reforestation awareness. - Pursue predictive maintenance or preventative measures as far as possible, based on optimal timing of events so that the actors are not merely reactive when disaster strikes, and this will contribute to reduced costs and possibly its extended life as well as increased reliability. - Greater effort is required in terms of safety and security to further boost the production quality and capacity of the dam, in light of an increasing population as well as increasing usage by increased tourist arrivals. Smarter technology may be utilised to model the dam and observe virtual risks that may arise and that may hamper operation and maintenance. - Regulation on the safety and security of surrounding terrain must also be included in the maintenance of the dam as it remains accessible to wandering members of the public and may cost lives because of exposed high voltage wires. - Resilience of the dam must also be clearly addressed as such capacity building including engineers within the water authority’s staff … - It is necessary to design and put in place a monitoring plan for the implementation of the Water Adaptation Plan itself and for the dam infrastructure, to ensure that the activities conducted are completed and contribute to the achievement of the established objectives and outcomes. The monitoring and evaluation (M&E) plan will also help to determine corrective actions when changes, due to existing and new circumstances occur, and will ease reporting. 12
  • 13. Recommendations - The dam could be used to produce hydroelectricity, and though the cost may be high at initial stages, it has potential to contribute further to carbon dioxide reduction and reduce the use of GHGs on the Island as well as reduce overall cost of energy. Energy consumption and pollution can be limited by the use of solar energy along the dam site. - Regional integration in infrastructure management (on the operation and maintenance of the dam) is an option to be considered as other Islands in the Caribbean have dams have been using hydropower and geothermal energy as a means of compensating for a reduction in fossil fuel options. 13