6, Arvin park Soc, B/h
Ranchhodpark,
V.I.P.road, Karelibaug,
Baroda, Gujarat.
Phone -9879103798 /
7567029344
E-mail
-new10me@gmail.com
ABHISHEK RATHOD
Career
Objective :
To become part of an esteemed organization and contribute myself with
my best potential and knowledge to excel in life.
Professional
experience :
Bachelor of Engineering in Mechanical discipline with thought out first
class grade in all semesters
A successful, highly results oriented Rotating Equipment Maintenance
& Reliability Engineer with 12 years of experience in Engineering,
Erection, Commissioning, Maintenance, Trouble shooting and Reliability
improvement of rotating equipment with reputed Oil & Gas (Godrej
Petrochemical Complex).
Working exposure to equipment condition monitoring tools - Vibration
analysis, Lube oil analysis, performance evaluation
Capital project execution from datasheet & design document review,
commissioning & operating spares, BOM preparation, Inspection,
Preservation, installation, pre-commissioning and start up of plant
equipments.
Versatile with various relevant international codes & standards related
to rotating equipment such as API, ISO, NACE etc
JOB PROFILE – Rotating Equipment Engineer.
Professional Skill:
Maintenance related:
 Work experience in specification, review of equipment
drawing, maintenance, trouble-shooting & spares planning of
various rotating equipments like centrifugal compressor, steam
turbine compressor, Reciprocating compressor, screw compressor,
Centrifugal pump, gearbox, positive displacement pump, ID/FD
fan, fin fan, agitator etc:
• Centrifugal compressors – Split type having capacity of 7000 CFM
(Make – Atlas Copco, Model-GA 7000-6).
• Special Purpose Steam turbine (Make – GE) – Condensing as well
as back pressure type.
• Screw compressor (Make –Atlas Copco, khosla).
• Double acting Reciprocating Compressor (Make –Ingersoll Rand).
• Mechanical Seals of M/s John Crane & M/S Flowserve.
• Various types of multistage & single stage centrifugal pumps (Make
– KSB, Kirloskar, Sulzer etc).
• ID & FD fan for reformer & fired heater.
• Air fin-fan cooler.
• Various types of positive displacement pumps.
 Preparation & Execution of maintenance job of rotating
equipment in co-ordination with turnaround section:
• Job scope preparation
• Material & Manpower planning
• Technical evaluation for service and material purchase requisition
• Job pack preparation
• Task-list preparation
• Job scheduling
• Job Safety Analysis and Risk assessment
• Job execution and progress monitoring
• Handle surprises during equipment inspection
• Release equipment inspection and overhauling report with
recommendation
Reliability related:
• Evaluation of equipment condition monitoring by various technique
such as,
- Vibration Analysis (GE - System1 for online & CSI 2130, Entek
IRD – Data Pac 1500 analyzer for offline vibration monitoring
system).
- Oil analysis as per RCM practices.
- Critical equipment – Centrifugal compressor, pump & steam
turbine performance evaluation.
• Rotating equipment section representative for various such as RCM,
RCA, and FEMA & MTBF analysis.
• Identifying the ‘bad actor’ which affects equipment availability &
maintenance cost and initiate action plan to resolve them
• Carry out root cause analysis of failures of mechanical equipment by
use of scientific technique like Why tree analysis, Fish-bone analysis
methods
• Developing maintenance plan, procedure and inspection checklist
• Resolve technical problems in consultation with OEM and operation
dept
Planning related:
• Planning, scheduling, Monitoring and execution of breakdown &
major overhauling in given time-frame
• Carrying out maintenance processing tasks on SAP-PM module
• Ensure spare availability of critical equipments and non-stock
materials in co-ordination with material department
• Preparation of budget for maintenance and minor capex project
Safety related:
• Compliance with organization EHSS rules and procedures &
promoting awareness about them among subordinates and
contractors through tool box talk, risk assessment sheet
Project Handled in ESSAR STEEL – (Feb-2003 to Aug-2008)
• Prepared plan for Cooling water system, DM water plant, Compressed
air system, Steam generation and distribution, Chillers plant, and
Effluent treatment plant (Cold rolling mill and Pickling effluents).
• Successfully commissioned low pressure boilers (15 TPH and 16 TPH).
Prepared conceptual design, specification, general arrangement
drawing, review of piping drawing and iso metric drawings, supervision
for erection and commissioning activities.
• Planning for erection and commissioning of 20 m3/hr DM Water plant.
• Prepared plan of 2 KM Sch40 SML pipe line for NG transportation.
Drawing review, BOQ Preparation, contract finalization for erection and
commissioning.
• Successful installation of Effluent treatment plant (240 m3/day).
• Successful completion of energy saving projects like condensate
recovery.
• Successful planning of Boiler Annual Shutdown and License renewal
activities.
• Handling operation and Maintenance of Boiler, Pump house,
Compressor house, Chiller plant, DM Plant and Effluent Treatment
plant.
Project Handled in Godrej Industries-(Sept-2008 to Aug-2010)
I was rotating section representative for major revamping project in
Utilities plant for its design data review to plant commissioning stage. In
this project, four centrifugal compressor, multistage centrifugal pumps and
ID/FD fan have been replaced.
• Review and approval of Rotating Equipment data sheets, ,
specifications and design guides as per API / ISO / ANS.
• Review of vendor’s technical bid.
• Technical evaluation of FAT / SAT performance of major
rotating equipment.
• Review commissioning & two years spares.
• New equipment BOM creation.
• Involve in the inspection / testing, erection, alignment, pre-
commissioning & commissioning of rotating equipments
• Passed BOILER PROFICIENCY EXAM in 2007.
• Best rated candidate in Utility department in 2007-2008.
• Prepare the documents for ISO-900,ISO-14001,OHSAS-18001
Qualification: TECHNICAL
QUALIFICATIO
N
Course
Diploma
Engineer
(Mechanical)
Institute M.S. University University
Aggregate % 70% Year of passing
Institute
BE in
Mechanical
Engineering University
Aggregate 68.5 % Year of passing
ACADEMIC QUALIIFICATION
Course %
Year of
passing
S.S.C. 86.71 June, 1999
SOFTWARE EXPOUSER
SOFTWARE PROFICIENCY EXPERIENCE
AutoCAD 2002 Expert 3 years
SAP- PM Module Proficient 1 year
MS OFFICE Expert 3 years
Training &
Other
Qualification:
• Training of Boiler operation from India Boiler .com.
• Training for Screw Compressors at Kirlosker Pneumatic division, Pune.
• Industrial training at GIPCL, Baroda.
Extracurricula
r Activities
and Hobbies:
• Playing Cricket, football and volleyball.
• Listening to music and watch movies.
• Like travelling and make friends.
Personal
Detail:
• Date of Birth 30-08-1983
• Nationality INDIAN
• Languages Known Hindi, English and Gujarati
Abhishek
Abhishek

Abhishek

  • 1.
    6, Arvin parkSoc, B/h Ranchhodpark, V.I.P.road, Karelibaug, Baroda, Gujarat. Phone -9879103798 / 7567029344 E-mail -new10me@gmail.com ABHISHEK RATHOD Career Objective : To become part of an esteemed organization and contribute myself with my best potential and knowledge to excel in life.
  • 2.
    Professional experience : Bachelor ofEngineering in Mechanical discipline with thought out first class grade in all semesters A successful, highly results oriented Rotating Equipment Maintenance & Reliability Engineer with 12 years of experience in Engineering, Erection, Commissioning, Maintenance, Trouble shooting and Reliability improvement of rotating equipment with reputed Oil & Gas (Godrej Petrochemical Complex). Working exposure to equipment condition monitoring tools - Vibration analysis, Lube oil analysis, performance evaluation Capital project execution from datasheet & design document review, commissioning & operating spares, BOM preparation, Inspection, Preservation, installation, pre-commissioning and start up of plant equipments. Versatile with various relevant international codes & standards related to rotating equipment such as API, ISO, NACE etc JOB PROFILE – Rotating Equipment Engineer. Professional Skill: Maintenance related:  Work experience in specification, review of equipment drawing, maintenance, trouble-shooting & spares planning of various rotating equipments like centrifugal compressor, steam turbine compressor, Reciprocating compressor, screw compressor, Centrifugal pump, gearbox, positive displacement pump, ID/FD fan, fin fan, agitator etc: • Centrifugal compressors – Split type having capacity of 7000 CFM (Make – Atlas Copco, Model-GA 7000-6). • Special Purpose Steam turbine (Make – GE) – Condensing as well as back pressure type. • Screw compressor (Make –Atlas Copco, khosla). • Double acting Reciprocating Compressor (Make –Ingersoll Rand). • Mechanical Seals of M/s John Crane & M/S Flowserve. • Various types of multistage & single stage centrifugal pumps (Make – KSB, Kirloskar, Sulzer etc). • ID & FD fan for reformer & fired heater. • Air fin-fan cooler. • Various types of positive displacement pumps.  Preparation & Execution of maintenance job of rotating equipment in co-ordination with turnaround section: • Job scope preparation • Material & Manpower planning • Technical evaluation for service and material purchase requisition • Job pack preparation • Task-list preparation
  • 3.
    • Job scheduling •Job Safety Analysis and Risk assessment • Job execution and progress monitoring • Handle surprises during equipment inspection • Release equipment inspection and overhauling report with recommendation Reliability related: • Evaluation of equipment condition monitoring by various technique such as, - Vibration Analysis (GE - System1 for online & CSI 2130, Entek IRD – Data Pac 1500 analyzer for offline vibration monitoring system). - Oil analysis as per RCM practices. - Critical equipment – Centrifugal compressor, pump & steam turbine performance evaluation. • Rotating equipment section representative for various such as RCM, RCA, and FEMA & MTBF analysis. • Identifying the ‘bad actor’ which affects equipment availability & maintenance cost and initiate action plan to resolve them • Carry out root cause analysis of failures of mechanical equipment by use of scientific technique like Why tree analysis, Fish-bone analysis methods • Developing maintenance plan, procedure and inspection checklist • Resolve technical problems in consultation with OEM and operation dept Planning related: • Planning, scheduling, Monitoring and execution of breakdown & major overhauling in given time-frame • Carrying out maintenance processing tasks on SAP-PM module • Ensure spare availability of critical equipments and non-stock materials in co-ordination with material department • Preparation of budget for maintenance and minor capex project Safety related: • Compliance with organization EHSS rules and procedures & promoting awareness about them among subordinates and contractors through tool box talk, risk assessment sheet Project Handled in ESSAR STEEL – (Feb-2003 to Aug-2008) • Prepared plan for Cooling water system, DM water plant, Compressed air system, Steam generation and distribution, Chillers plant, and Effluent treatment plant (Cold rolling mill and Pickling effluents). • Successfully commissioned low pressure boilers (15 TPH and 16 TPH). Prepared conceptual design, specification, general arrangement
  • 4.
    drawing, review ofpiping drawing and iso metric drawings, supervision for erection and commissioning activities. • Planning for erection and commissioning of 20 m3/hr DM Water plant. • Prepared plan of 2 KM Sch40 SML pipe line for NG transportation. Drawing review, BOQ Preparation, contract finalization for erection and commissioning. • Successful installation of Effluent treatment plant (240 m3/day). • Successful completion of energy saving projects like condensate recovery. • Successful planning of Boiler Annual Shutdown and License renewal activities. • Handling operation and Maintenance of Boiler, Pump house, Compressor house, Chiller plant, DM Plant and Effluent Treatment plant. Project Handled in Godrej Industries-(Sept-2008 to Aug-2010) I was rotating section representative for major revamping project in Utilities plant for its design data review to plant commissioning stage. In this project, four centrifugal compressor, multistage centrifugal pumps and ID/FD fan have been replaced. • Review and approval of Rotating Equipment data sheets, , specifications and design guides as per API / ISO / ANS. • Review of vendor’s technical bid. • Technical evaluation of FAT / SAT performance of major rotating equipment. • Review commissioning & two years spares. • New equipment BOM creation. • Involve in the inspection / testing, erection, alignment, pre- commissioning & commissioning of rotating equipments • Passed BOILER PROFICIENCY EXAM in 2007. • Best rated candidate in Utility department in 2007-2008. • Prepare the documents for ISO-900,ISO-14001,OHSAS-18001
  • 5.
    Qualification: TECHNICAL QUALIFICATIO N Course Diploma Engineer (Mechanical) Institute M.S.University University Aggregate % 70% Year of passing Institute BE in Mechanical Engineering University Aggregate 68.5 % Year of passing ACADEMIC QUALIIFICATION Course % Year of passing S.S.C. 86.71 June, 1999 SOFTWARE EXPOUSER SOFTWARE PROFICIENCY EXPERIENCE AutoCAD 2002 Expert 3 years SAP- PM Module Proficient 1 year MS OFFICE Expert 3 years Training & Other Qualification: • Training of Boiler operation from India Boiler .com. • Training for Screw Compressors at Kirlosker Pneumatic division, Pune. • Industrial training at GIPCL, Baroda. Extracurricula r Activities and Hobbies: • Playing Cricket, football and volleyball. • Listening to music and watch movies. • Like travelling and make friends. Personal Detail: • Date of Birth 30-08-1983 • Nationality INDIAN • Languages Known Hindi, English and Gujarati