 The present ACME Distribution Center was having constraint with future throughput capacity
with respect to the forecasted growth.
 Growth was expected to be 7% in unit capacity, 2% in orders for every consecutive year, for a
five year design period.
 ACME’s Distribution Center is re-designed with the growth data and brain stormed with
different alternatives.
 Analysis and design has been done with respect to space utilization, labor, material handling,
and cost expenditure.
 Comparison was done between the alternatives and the alternative with the highest MARR
(Minimum Acceptable Rate of Return ) was selected.
Existing DC is at capacity with no room to expand and an expiring lease
Experiencing high annual unit growth
Seeking new, justified alternative operational processes, and a right sized facility to support
future business
Current operation has little to no automation
Design philosophy
Product flow
Space utilization
Human resources
Equipment selection
Information technology
Product Flow
Receiving Put-Away Order Fulfillment Staging Shipping
Unload trailer/
container
300 CPH
Check ASN,
Verify BOL, and
scan RFID Tag
Sort as per SKU
Velocity
category
Palletize
Forward or
Reserve
Put-away to
reserve area
30 PPH
Put-away to
forward area
60 CPH
Generate
orders by
customers
ReserveForward
Full pallet
orders
Pick from
reserve area
Pick from
forward area
Orders Cases/
Eaches
Staging
Load on to
trailer
Dispatch
Is there
enough
quantity?
Replenish from
reserve area
No
Yes
Crossdock
receipt?
Label outbound
details
No
Print Outbound
Label
Cases/pallets
10 %
Q/A
240
CPH
SKU Velocity
Order from A, B
& C
Yes
No
 CPH- Cases per
hour
 PPH- Pallet per
Hour
 ASN- Advance
Shipment Notice
 RFID- Radio
Frequency
Identification
Device
 BOL- Bill of Lading
 Q/A- Quality
Assurance
Yes
Classification Equipment Location Data Used
Containers & Unitizing  Pallets  Receiving
Projected growth in
the next five years
Storage and Retrieval  Pallet Jack
 Pick to Light System
 Single Selective Racks with
Wide Aisles (10’)
 Forward Area
 Reserve Area
Material Transport
Equipment
 Automated Roller Conveyor
 Counterbalanced Lift Truck
 Order Picker
 Sortation Conveyor
 Storage to Shipping
 Storage
 Storage cum Retrieval
 Shipping
Automatic Data
Collection &
Communication
Equipment
 Radio Frequency Data Terminal
 Voice Headsets
 Entire Distribution
Center
Alternative 1
Classification Equipment Location Data Used
Containers & Unitizing  Pallets
 Palletizer
 Receiving
Projected growth in
the next five years
Storage and Retrieval  Pick to Light System
 Single Selective Racks with
Wide Aisles (10’)
 Forward Area
 Reserve Area
Material Transport
Equipment
 Expandable/Portable
Conveyors
 Automated Roller Conveyor
 Counterbalanced Lift Truck
 Order Picker
 Sortation Conveyor
 Receiving and
Shipping
 Storage to Shipping
 Storage
 Storage cum Retrieval
 Shipping
Automatic Data
Collection &
Communication
Equipment
 Radio Frequency Data Terminal
 Voice Headsets
 Entire Distribution
Center
Alternative 2
Space Block Dimension in Ft Area in Sq ft
Distribution Center 771.36 x 410.05 x 30 316,292
Receiving 325.5 x 76.8 25,000
Storage 611 x 320 195,520
FReceiving 378 x 320 120,960
RShipping 233 x 320 74,560
Shipping 325.5 x 76.8 25,000
Admin Office Space 37.2 x 25 930
Receiving Office 12.25 x 12.5 150
Shipping Office 12.25 x 12.5 150
Cafeteria 111.9 x 40 4,476
Locker Rooms 96 x 24 2,304
Restroom 21 x 12 252
Parking Space 360 x 400 144,000
Space Utilization
Space Calculations - Approach
 The growth in annual units sold per year is 7%.
 Annual units in year 2021 is calculated by using 7% growth over the 5
years of planning horizon.
 From the data of daily volumes, the deviations in the units sold per year
and the maximum outbound units in 249 days is obtained.
 The unit quantities sold for the 1st, 2nd, 3rd std deviations and the
maximum are observed.
 The annual units sold as per 2nd std deviations is equal to the annual
units sold in year 2021.
 Analysis and calculation for space requirements are based on the 2nd std
deviations quantity.
Space Calculations - Approach Contd.
 If we design our facility as per max volumes, it will be under utilized about
half of the year and if we design as per the average volume it will not have
enough space for the max volume.
 To have a possible solution for the above problem it is necessary to take
the seasonality factor into consideration.
 Hence we design our facility based on the monthly volumes obtained
taking into account the volume for peak month.
 In each month the above three variables have different values due to the
seasonality effect.
 As seen from the table in next slide we observe that the peak season for
the sale of shoes is before Christmas through spring and early summers
with the most units sold in December and June.
 The next slide shows the monthly orders, quantities of units sold and on
hand inventories.
Space Calculations – Data Analysis Contd.
Facility
Layout
 All the labor calculations has been done based on the growth
and the actual requirement for the respective year.
 Each year labor requirement is calculated for both direct and
indirect labor.
 Since the facility is designed based on the maximum
utilization of its capacity, all the amenities has been designed
with respect to it.
 With respect to Alternatives designed, respective analysis in
cost, requirement has been done and presented.
Baseline Alternative 1 Alternative 2
Receiving 19 24 16
Put-Away 15 27 27
Order Fulfillment 182 332 332
Staging & QA 17 32 32
Shipping 9 13 13
Total 242 428 420
Cost per hour $22.50 $27 $27
Cost per month $871,200 $1,848,960 $1,814,400
Alternative 1
Alternative 2
Alternative 1
MARR = 15.098
Alternative 2
MARR = 14.82
Alternative 1
is selected
Abc inc.  Facilities Planning and Design
Abc inc.  Facilities Planning and Design

More Related Content

Similar to Abc inc. Facilities Planning and Design

Layout
LayoutLayout
Layout
FNian
 
Ch09
Ch09Ch09
Ch09
FNian
 
Data Warehouse
Data WarehouseData Warehouse
Data Warehouse
ganblues
 
Datawarehousing
DatawarehousingDatawarehousing
Datawarehousing
work
 

Similar to Abc inc. Facilities Planning and Design (20)

Spring 2017 Sage 300 (Accpac) Users Group
Spring 2017 Sage 300 (Accpac) Users GroupSpring 2017 Sage 300 (Accpac) Users Group
Spring 2017 Sage 300 (Accpac) Users Group
 
SAP BO Xcelsius Dashboard Case Study
SAP BO Xcelsius Dashboard   Case StudySAP BO Xcelsius Dashboard   Case Study
SAP BO Xcelsius Dashboard Case Study
 
ITReady DW Day2
ITReady DW Day2ITReady DW Day2
ITReady DW Day2
 
Ch09
Ch09Ch09
Ch09
 
Production planning and control module 3 (OM)
Production planning and control module 3 (OM)Production planning and control module 3 (OM)
Production planning and control module 3 (OM)
 
Scm
ScmScm
Scm
 
Layout
LayoutLayout
Layout
 
Ch09(2)
Ch09(2)Ch09(2)
Ch09(2)
 
Ch09
Ch09Ch09
Ch09
 
Expert talk
Expert talkExpert talk
Expert talk
 
Big Data and Analytics on Amazon Web Services: Building A Business-Friendly P...
Big Data and Analytics on Amazon Web Services: Building A Business-Friendly P...Big Data and Analytics on Amazon Web Services: Building A Business-Friendly P...
Big Data and Analytics on Amazon Web Services: Building A Business-Friendly P...
 
Data Warehouse
Data WarehouseData Warehouse
Data Warehouse
 
Real-time data integration to the cloud
Real-time data integration to the cloudReal-time data integration to the cloud
Real-time data integration to the cloud
 
Supply Chain Management
Supply Chain ManagementSupply Chain Management
Supply Chain Management
 
SAP An Introduction
SAP An IntroductionSAP An Introduction
SAP An Introduction
 
Big Data Analytics and Artifical Intelligence
Big Data Analytics and Artifical IntelligenceBig Data Analytics and Artifical Intelligence
Big Data Analytics and Artifical Intelligence
 
Datawarehousing
DatawarehousingDatawarehousing
Datawarehousing
 
S&OP as a Service.pdf
S&OP as a Service.pdfS&OP as a Service.pdf
S&OP as a Service.pdf
 
Cost Optimization on AWS
Cost Optimization on AWSCost Optimization on AWS
Cost Optimization on AWS
 
Cost Optimization on AWS
Cost Optimization on AWSCost Optimization on AWS
Cost Optimization on AWS
 

Recently uploaded

21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx
rahulmanepalli02
 
Artificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdfArtificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdf
Kira Dess
 
Seizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networksSeizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networks
IJECEIAES
 

Recently uploaded (20)

Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx
 
Raashid final report on Embedded Systems
Raashid final report on Embedded SystemsRaashid final report on Embedded Systems
Raashid final report on Embedded Systems
 
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
 
analog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptxanalog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptx
 
Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...
 
Independent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging StationIndependent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging Station
 
Artificial Intelligence in due diligence
Artificial Intelligence in due diligenceArtificial Intelligence in due diligence
Artificial Intelligence in due diligence
 
Autodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxAutodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptx
 
Insurance management system project report.pdf
Insurance management system project report.pdfInsurance management system project report.pdf
Insurance management system project report.pdf
 
Artificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdfArtificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdf
 
Seizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networksSeizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networks
 
Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1
 
Intro to Design (for Engineers) at Sydney Uni
Intro to Design (for Engineers) at Sydney UniIntro to Design (for Engineers) at Sydney Uni
Intro to Design (for Engineers) at Sydney Uni
 
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdfInstruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdflitvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
 
15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon
 
Working Principle of Echo Sounder and Doppler Effect.pdf
Working Principle of Echo Sounder and Doppler Effect.pdfWorking Principle of Echo Sounder and Doppler Effect.pdf
Working Principle of Echo Sounder and Doppler Effect.pdf
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 

Abc inc. Facilities Planning and Design

  • 1.
  • 2.
  • 3.  The present ACME Distribution Center was having constraint with future throughput capacity with respect to the forecasted growth.  Growth was expected to be 7% in unit capacity, 2% in orders for every consecutive year, for a five year design period.  ACME’s Distribution Center is re-designed with the growth data and brain stormed with different alternatives.  Analysis and design has been done with respect to space utilization, labor, material handling, and cost expenditure.  Comparison was done between the alternatives and the alternative with the highest MARR (Minimum Acceptable Rate of Return ) was selected.
  • 4. Existing DC is at capacity with no room to expand and an expiring lease Experiencing high annual unit growth Seeking new, justified alternative operational processes, and a right sized facility to support future business Current operation has little to no automation
  • 5. Design philosophy Product flow Space utilization Human resources Equipment selection Information technology
  • 6. Product Flow Receiving Put-Away Order Fulfillment Staging Shipping Unload trailer/ container 300 CPH Check ASN, Verify BOL, and scan RFID Tag Sort as per SKU Velocity category Palletize Forward or Reserve Put-away to reserve area 30 PPH Put-away to forward area 60 CPH Generate orders by customers ReserveForward Full pallet orders Pick from reserve area Pick from forward area Orders Cases/ Eaches Staging Load on to trailer Dispatch Is there enough quantity? Replenish from reserve area No Yes Crossdock receipt? Label outbound details No Print Outbound Label Cases/pallets 10 % Q/A 240 CPH SKU Velocity Order from A, B & C Yes No  CPH- Cases per hour  PPH- Pallet per Hour  ASN- Advance Shipment Notice  RFID- Radio Frequency Identification Device  BOL- Bill of Lading  Q/A- Quality Assurance Yes
  • 7. Classification Equipment Location Data Used Containers & Unitizing  Pallets  Receiving Projected growth in the next five years Storage and Retrieval  Pallet Jack  Pick to Light System  Single Selective Racks with Wide Aisles (10’)  Forward Area  Reserve Area Material Transport Equipment  Automated Roller Conveyor  Counterbalanced Lift Truck  Order Picker  Sortation Conveyor  Storage to Shipping  Storage  Storage cum Retrieval  Shipping Automatic Data Collection & Communication Equipment  Radio Frequency Data Terminal  Voice Headsets  Entire Distribution Center Alternative 1
  • 8. Classification Equipment Location Data Used Containers & Unitizing  Pallets  Palletizer  Receiving Projected growth in the next five years Storage and Retrieval  Pick to Light System  Single Selective Racks with Wide Aisles (10’)  Forward Area  Reserve Area Material Transport Equipment  Expandable/Portable Conveyors  Automated Roller Conveyor  Counterbalanced Lift Truck  Order Picker  Sortation Conveyor  Receiving and Shipping  Storage to Shipping  Storage  Storage cum Retrieval  Shipping Automatic Data Collection & Communication Equipment  Radio Frequency Data Terminal  Voice Headsets  Entire Distribution Center Alternative 2
  • 9. Space Block Dimension in Ft Area in Sq ft Distribution Center 771.36 x 410.05 x 30 316,292 Receiving 325.5 x 76.8 25,000 Storage 611 x 320 195,520 FReceiving 378 x 320 120,960 RShipping 233 x 320 74,560 Shipping 325.5 x 76.8 25,000 Admin Office Space 37.2 x 25 930 Receiving Office 12.25 x 12.5 150 Shipping Office 12.25 x 12.5 150 Cafeteria 111.9 x 40 4,476 Locker Rooms 96 x 24 2,304 Restroom 21 x 12 252 Parking Space 360 x 400 144,000 Space Utilization
  • 10.
  • 11.
  • 12.
  • 13. Space Calculations - Approach  The growth in annual units sold per year is 7%.  Annual units in year 2021 is calculated by using 7% growth over the 5 years of planning horizon.  From the data of daily volumes, the deviations in the units sold per year and the maximum outbound units in 249 days is obtained.  The unit quantities sold for the 1st, 2nd, 3rd std deviations and the maximum are observed.  The annual units sold as per 2nd std deviations is equal to the annual units sold in year 2021.  Analysis and calculation for space requirements are based on the 2nd std deviations quantity.
  • 14.
  • 15. Space Calculations - Approach Contd.  If we design our facility as per max volumes, it will be under utilized about half of the year and if we design as per the average volume it will not have enough space for the max volume.  To have a possible solution for the above problem it is necessary to take the seasonality factor into consideration.  Hence we design our facility based on the monthly volumes obtained taking into account the volume for peak month.  In each month the above three variables have different values due to the seasonality effect.  As seen from the table in next slide we observe that the peak season for the sale of shoes is before Christmas through spring and early summers with the most units sold in December and June.  The next slide shows the monthly orders, quantities of units sold and on hand inventories.
  • 16. Space Calculations – Data Analysis Contd.
  • 17.
  • 19.  All the labor calculations has been done based on the growth and the actual requirement for the respective year.  Each year labor requirement is calculated for both direct and indirect labor.  Since the facility is designed based on the maximum utilization of its capacity, all the amenities has been designed with respect to it.  With respect to Alternatives designed, respective analysis in cost, requirement has been done and presented.
  • 20. Baseline Alternative 1 Alternative 2 Receiving 19 24 16 Put-Away 15 27 27 Order Fulfillment 182 332 332 Staging & QA 17 32 32 Shipping 9 13 13 Total 242 428 420 Cost per hour $22.50 $27 $27 Cost per month $871,200 $1,848,960 $1,814,400
  • 21.
  • 24. Alternative 1 MARR = 15.098 Alternative 2 MARR = 14.82 Alternative 1 is selected