The document provides an update on the Davis Landings Affordable Housing Project, including construction progress, budget details, and change orders. Construction began in November 2011 and is now over 90% complete, with interior build out, landscaping, and installation of cabinets and AC nearing completion. The budget shows actual costs invoiced through July 2012 compared to projected balances. Total project spending is tracking close to budget, with a remaining contingency of 1.6% to cover additional change orders for security and site management costs through project completion in August 2012.