Strategic Environmental Assessment of
National Water Plan, Nepal
BY
Ram B. Khadka
Nepal: An Introduction
Location:
Nepal is the
Himalayan Kingdom
known as the Land of
the Mt. Everest and
the birthplace of Lord
Buddha. The country
is situated in South
Asia, bordered on the
north by China and
on the south, west
and east by India.
Nepal: General Information
Topographical Features:
Nepal is a mountainous country with the Himalayan belt in the north,
the hilly region and fertile valleys in the Middle and the narrow strip
of plain in the South, all running parallel to each other from East to
West.
Climate:
The country has diverse climatic conditions. It is generally cold in the
mountainous region, mild weather in the hills, and warm in the
plains.
Rainfall: 1,500 -2,500mm (average)
Capital:
Kathmandu, a historical city with rich cultural heritage is Nepal's
capital with 1.5 million population.
Background information
• 6000 Rivers, mostly
trans-Himalayan and
snow –fed
• Drain 194,471 km2
• 225 billion cubic liters of water is available
Annually
• 15 billion cubic liters of water have been
utilized so far
Background information
• 72 percent of population have an access
to water supply
• 25 percent have access to sanitation
facility
• 0.76 million ha of agriculture land have
been irrigated
• Hydropower development potential is
83000MW, at present only 619MW has
been generated.
Background information
• Water is one of the major natural
resources for economic development
• Inspite of many efforts made in the past
water resource development is slow,
• In order to make water resource
development comprehensive,
systematized and accelerate the process
of development, Government of Nepal
issued Water Resource Strategy in 2002.
Water Resource Strategy (WRS)
for Nepal
WRS contains following 10 action programs:
• management water-Induced disaster
• management of watershed and aquatic ecosystem
• domestic water supply and sanitation
• Irrigation facilities for agriculture
• development of hydropower for electricity
• water-based cultural, recreational, and eco-tourism activities
• amendment the existing water resource policy and legal framework
• water-related information systems
• development of regional and bi-lateral co-operation and
• revision and modification of exsisting institutional procedural
mechanism.
National Water Plan for Nepal
(NWP)
In order to operationalize WRS of Nepal, a
National Water Plan was developed and
endorsed by the government (2005).The
following are the action programs contained
in the NWP
The implementation of NWP activities is to
take place within the time frame of 5,15 and
20 years.
National Water Plan (NWP)
Contd.
• Management of major types of water
induced disasters
• Improvement of water Quality and
watersheds
• Provide safe drinking water to 100%
people of Nepal
• Provide irrigation facilities to 100% arable
land
National Water Plan (NWP)
Contd.
• Develop 4000MW of hydropower
• Provide water to 100% industry, navigation
and tourism
• Enhance inland fisheries and increase the
production to 87000 MT per year
• Establish hydrometric stations to 370 at
strategic places and disseminate the
information
National Water Plan (NWP)
Contd
• Establish regional cooperation for water
sharing fully
• Revise and refine the existing legal
framework, develop policies, guidelines,
norms and standards.
• Restructure administrative institutions
revise and improve administrative
mechanism.
Application of SEA in NWP
• No legal requirement for SEA in Nepal
• Water Energy Commission of Nepal decided to
apply SEA in NWP voluntarily to make plan
environmentally sound and sustainable.
• SEA was carried out based on secondary
sources of Information and an extensive public
consultation with some field verification.
• Followed screening, scoping, baseline
information collection, impact identification and
prediction, mitigation measures and
environmental management plan.
Application of SEA in NWP
• Stakeholders consultation at different
stages
• Use of internationally recognized checklist,
interaction matrix, and Impact summary
matrix (Saddler and Verheem, 1996).
• Issues identified in scoping were classified
into i physical, ii biological iii socio-
economic/cultural and iv legal and
institutional components.
Issue Analysis and Prediction
NWP was examined whether,
• Issues were addressed in NWP
• Assessment of the status of issues included
• Mitigation measures are provided
Physical Issues
• Downstream release of water, submerging
of large amount of farmland, water logging, extraction of ground
water-lowering of water level
• Formation of new flood plain
• Water pollution due to chemical fertilizer and pesticides
• No Measures are mentioned in policies, guidelines and no
standards
Issue Analysis and Prediction
Biological Issues: effect on;
• Forest, flora, animals both aquatic and
Terrestrials
• Protected areas, wild animal habitat,
• Destruction of biodiversity
• Effect on fish and fisheries
• Production of Green House Gas (GHG)
• Downstream Pollution
Issue Analysis and Prediction
Socio-Economic/Cultural Issue
• employment opportunity,
• local market development,
• reduced drudgery in women and children,
• skilled manpower development,
• gender,
• enhancement of local organizations.
• land acquisition,
• displacement, and resettlement,
• cultural malpractices, and pressure on social services
Issue Analysis and Prediction
Legal and Institutional Component
Policy conflict
No coordination
Improper legal framework ineffective in
Implementation
No water quality standards, no code of conduct,
No waste water treatment commitment
The private sector projects are operating well
The government sector projects do not function
properly because of the financial limitation imposed
by finance act
No comprehensive legislation
Mitigation Measures /Alternative
Options
Mitigation measures at strategic level can
involves:
• rewriting the strategic actions to minimize negative
environmental effects and enhance the beneficial one,
• establishing management guidelines for implementing
strategic action,
• shifting responsibility to lower tier of strategic action or in
project level, and
• no action alternative.
Mitigation Measures /Alternative
Options
Physical Components
• Maintaining water flow down stream : release of 10% dry period flow
plus existing water requirement in downstream.
• Downstream Water Pollution and
Groundwater Quality ; Standards and policy guidelines
• Use of Inundated Upland Fields and Forest
• Cloud Burst, Glacial Lake Outburst Flood,
• and Landslide Dam Flood; Minimization
• Erosions, Landslides, and Sedimentation: minimization
• Lowering of Ground Water ;Policy guidelines
• Water logging and Soil Modification; Policy guidelines
Mitigation Measures /Alternative
Options
Forest Vegetation and Wild animals;
• Forest and Vegetation; Policy guidelines and standards
• Wildlife and Biodiversity;
• Protected Areas;
• Aquatic flora and Fauna
Mitigation Measures /Alternative
Options
Socio-economic and Cultural Issues ;Mostly to be
addressed by issuing of policy guidelines, directives, standards, and
implementation guidelines
• Employment Opportunities;
• Economic Activities
• Local Market Development Market
• Skilled manpower development;
• Reduce Drudgery to Women and Children
• Cultural Practice;
• Land Acquisition, Displacement and Resettlement
• Pressure on Social Service
• Gender Issue
Mitigation Measures /Alternative
Options
Legal and Institutional Component
• Comprehensive National Water Resource Policy
• Action Plans for Water resource and Environment Laws
• Legal Regime for Ground Water Management
• Pollution Standards for Enforcement of Environment
• Protection Act
• Strengthen Community-Based Water User Organizations
Environmental Management
Plan (EMP)
• rewriting, strategy and Action Plans, development of policy
guidelines for implementation of directives to project-level
implementations are the key strategic mitigation prescriptions.
• EMP of National Water Plan should examine whether the issues are
addressed and the corresponding gaps are identified.
• In SEA of NWP strategic EMP parameters on physical, biological,
socio-economic, and cultural components of the environment have
been identified and recommendation should be made to apply in
project level activities
• The second part in EMP is to monitor the implementation of
mitigation prescriptions. Monitoring such as (i) baseline (ii) impact
and (iii) compliance monitoring are applicable to strategic actions.
Conclusion and
Recommendation
Analysis has been carried out for the consideration of in the upper
tier of decision-making.
The key environmental issues identified were:
• downstream release of water and water use right,
• inundation,
• downstream and ground water pollution,
• issues on the loss of forests and wildlife, both aquatic and terrestrial,
• issues on boom and bust cycle related to workforce,
• land acquisition displacement and resettlement, and
• ineffective environmental laws, regulations, and standards and institutions
related to water resource development.
• Issues on human resource development and employment opportunity.
Conclusion and
Recommendation
Minimization of the adverse issues and enhancement of
beneficial issues of NWP implementation at the Strategic
Level are:
• revising and modification of existing system of legal
framework,
• revising and writing of water resource development policies, Plans
and programs, and
• Issuing policy guidelines, standards, norms, reforming existing
institutional and procedural aspects, etc.
THANK YOU

More Related Content

Similar to 329. Khadka, Strategic Environment Assessment of National Water Plan of Nepal.ppt

Large Marine Ecosystems Assessment and Management Approach 2005-2010
Large Marine Ecosystems Assessment and Management Approach 2005-2010Large Marine Ecosystems Assessment and Management Approach 2005-2010
Large Marine Ecosystems Assessment and Management Approach 2005-2010Iwl Pcu
 
Environmental Science DRRM for climate change in the philippines
Environmental Science DRRM for climate change in the philippinesEnvironmental Science DRRM for climate change in the philippines
Environmental Science DRRM for climate change in the philippinesRah yan Kim Rico
 
Integrated watershed management
Integrated watershed managementIntegrated watershed management
Integrated watershed managementSorab Sadri
 
3 dave tickner strategic water mgt china
3 dave tickner strategic water mgt china3 dave tickner strategic water mgt china
3 dave tickner strategic water mgt chinaobjectiveassociates
 
Water sector challenges in South Africa
Water sector challenges in South AfricaWater sector challenges in South Africa
Water sector challenges in South AfricaCollin Manickum
 
Lecture 2-CVS 445.ppt
Lecture 2-CVS 445.pptLecture 2-CVS 445.ppt
Lecture 2-CVS 445.pptLawrence Omai
 
6. Implementing the WFD, heritage projects and planning policy bernadette ...
6. Implementing the WFD, heritage projects and planning policy    bernadette ...6. Implementing the WFD, heritage projects and planning policy    bernadette ...
6. Implementing the WFD, heritage projects and planning policy bernadette ...Environmental Protection Agency, Ireland
 
Chapter 11-Sustainable Management of Natural Resources.pptx
Chapter 11-Sustainable Management of Natural Resources.pptxChapter 11-Sustainable Management of Natural Resources.pptx
Chapter 11-Sustainable Management of Natural Resources.pptxTenzinNamgayNidrup
 
Workshop WCP WACREP south asia_lal induruwage_1 sep
Workshop WCP WACREP south asia_lal induruwage_1 sepWorkshop WCP WACREP south asia_lal induruwage_1 sep
Workshop WCP WACREP south asia_lal induruwage_1 sepGlobal Water Partnership
 
SWaRMA_IRBM_Module1_#5, Experiences of IWRM implementation from Australia, An...
SWaRMA_IRBM_Module1_#5, Experiences of IWRM implementation from Australia, An...SWaRMA_IRBM_Module1_#5, Experiences of IWRM implementation from Australia, An...
SWaRMA_IRBM_Module1_#5, Experiences of IWRM implementation from Australia, An...ICIMOD
 
SWaRMA_IRBM_Module2_#7, Basin planning experience from Australia, Andrew Joh...
SWaRMA_IRBM_Module2_#7,  Basin planning experience from Australia, Andrew Joh...SWaRMA_IRBM_Module2_#7,  Basin planning experience from Australia, Andrew Joh...
SWaRMA_IRBM_Module2_#7, Basin planning experience from Australia, Andrew Joh...ICIMOD
 
Subcatchment management plan
Subcatchment management planSubcatchment management plan
Subcatchment management planJames Nyaga
 
Chattahoochee River Watershed Case Study
Chattahoochee River Watershed Case StudyChattahoochee River Watershed Case Study
Chattahoochee River Watershed Case StudyMichael R. Barr
 
IWRM Evaluation Result_Thailand
IWRM Evaluation Result_ThailandIWRM Evaluation Result_Thailand
IWRM Evaluation Result_ThailandGWP SOUTHEAST ASIA
 

Similar to 329. Khadka, Strategic Environment Assessment of National Water Plan of Nepal.ppt (20)

Large Marine Ecosystems Assessment and Management Approach 2005-2010
Large Marine Ecosystems Assessment and Management Approach 2005-2010Large Marine Ecosystems Assessment and Management Approach 2005-2010
Large Marine Ecosystems Assessment and Management Approach 2005-2010
 
Environmental Science DRRM for climate change in the philippines
Environmental Science DRRM for climate change in the philippinesEnvironmental Science DRRM for climate change in the philippines
Environmental Science DRRM for climate change in the philippines
 
Integrated watershed management
Integrated watershed managementIntegrated watershed management
Integrated watershed management
 
PPIMT1
PPIMT1PPIMT1
PPIMT1
 
3 dave tickner strategic water mgt china
3 dave tickner strategic water mgt china3 dave tickner strategic water mgt china
3 dave tickner strategic water mgt china
 
Water sector challenges in South Africa
Water sector challenges in South AfricaWater sector challenges in South Africa
Water sector challenges in South Africa
 
Lecture 2-CVS 445.ppt
Lecture 2-CVS 445.pptLecture 2-CVS 445.ppt
Lecture 2-CVS 445.ppt
 
6. Implementing the WFD, heritage projects and planning policy bernadette ...
6. Implementing the WFD, heritage projects and planning policy    bernadette ...6. Implementing the WFD, heritage projects and planning policy    bernadette ...
6. Implementing the WFD, heritage projects and planning policy bernadette ...
 
Business environment
Business environmentBusiness environment
Business environment
 
Chapter 11-Sustainable Management of Natural Resources.pptx
Chapter 11-Sustainable Management of Natural Resources.pptxChapter 11-Sustainable Management of Natural Resources.pptx
Chapter 11-Sustainable Management of Natural Resources.pptx
 
Water issues
Water issuesWater issues
Water issues
 
7. Cox1
7. Cox17. Cox1
7. Cox1
 
Workshop WCP WACREP south asia_lal induruwage_1 sep
Workshop WCP WACREP south asia_lal induruwage_1 sepWorkshop WCP WACREP south asia_lal induruwage_1 sep
Workshop WCP WACREP south asia_lal induruwage_1 sep
 
2015 State of the Sound
2015 State of the Sound 2015 State of the Sound
2015 State of the Sound
 
SWaRMA_IRBM_Module1_#5, Experiences of IWRM implementation from Australia, An...
SWaRMA_IRBM_Module1_#5, Experiences of IWRM implementation from Australia, An...SWaRMA_IRBM_Module1_#5, Experiences of IWRM implementation from Australia, An...
SWaRMA_IRBM_Module1_#5, Experiences of IWRM implementation from Australia, An...
 
SWaRMA_IRBM_Module2_#7, Basin planning experience from Australia, Andrew Joh...
SWaRMA_IRBM_Module2_#7,  Basin planning experience from Australia, Andrew Joh...SWaRMA_IRBM_Module2_#7,  Basin planning experience from Australia, Andrew Joh...
SWaRMA_IRBM_Module2_#7, Basin planning experience from Australia, Andrew Joh...
 
Subcatchment management plan
Subcatchment management planSubcatchment management plan
Subcatchment management plan
 
Chattahoochee River Watershed Case Study
Chattahoochee River Watershed Case StudyChattahoochee River Watershed Case Study
Chattahoochee River Watershed Case Study
 
IWRM Evaluation Result_Thailand
IWRM Evaluation Result_ThailandIWRM Evaluation Result_Thailand
IWRM Evaluation Result_Thailand
 
Session 7 Trans-boundary Perspective Volta
Session 7 Trans-boundary Perspective VoltaSession 7 Trans-boundary Perspective Volta
Session 7 Trans-boundary Perspective Volta
 

Recently uploaded

Specialize in a MSc within Biomanufacturing, and work part-time as Process En...
Specialize in a MSc within Biomanufacturing, and work part-time as Process En...Specialize in a MSc within Biomanufacturing, and work part-time as Process En...
Specialize in a MSc within Biomanufacturing, and work part-time as Process En...Juli Boned
 
obat aborsi pacitan wa 081336238223 jual obat aborsi cytotec asli di pacitan0...
obat aborsi pacitan wa 081336238223 jual obat aborsi cytotec asli di pacitan0...obat aborsi pacitan wa 081336238223 jual obat aborsi cytotec asli di pacitan0...
obat aborsi pacitan wa 081336238223 jual obat aborsi cytotec asli di pacitan0...yulianti213969
 
UIowa Application Instructions - 2024 Update
UIowa Application Instructions - 2024 UpdateUIowa Application Instructions - 2024 Update
UIowa Application Instructions - 2024 UpdateUniversity of Iowa
 
如何办理(Columbia毕业证书)哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(Columbia毕业证书)哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证如何办理(Columbia毕业证书)哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(Columbia毕业证书)哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证epyhpep
 
We’re looking for a junior patent engineer to join our Team!
We’re looking for a junior patent engineer to join our Team!We’re looking for a junior patent engineer to join our Team!
We’re looking for a junior patent engineer to join our Team!Juli Boned
 
Novo Nordisk Kalundborg. We are expanding our manufacturing hub in Kalundborg...
Novo Nordisk Kalundborg. We are expanding our manufacturing hub in Kalundborg...Novo Nordisk Kalundborg. We are expanding our manufacturing hub in Kalundborg...
Novo Nordisk Kalundborg. We are expanding our manufacturing hub in Kalundborg...Juli Boned
 
一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理F
 
Fracture design PowerPoint presentations
Fracture design PowerPoint presentationsFracture design PowerPoint presentations
Fracture design PowerPoint presentationsjitiniift
 
B.tech Civil Engineering Major Project by Deepak Kumar ppt.pdf
B.tech Civil Engineering Major Project by Deepak Kumar ppt.pdfB.tech Civil Engineering Major Project by Deepak Kumar ppt.pdf
B.tech Civil Engineering Major Project by Deepak Kumar ppt.pdfDeepak15CivilEngg
 
Jual obat aborsi Dubai ( 085657271886 ) Cytote pil telat bulan penggugur kand...
Jual obat aborsi Dubai ( 085657271886 ) Cytote pil telat bulan penggugur kand...Jual obat aborsi Dubai ( 085657271886 ) Cytote pil telat bulan penggugur kand...
Jual obat aborsi Dubai ( 085657271886 ) Cytote pil telat bulan penggugur kand...ZurliaSoop
 
Prest Reed Portfolio revamp Full Sail Presentation 2
Prest Reed Portfolio revamp Full Sail Presentation 2Prest Reed Portfolio revamp Full Sail Presentation 2
Prest Reed Portfolio revamp Full Sail Presentation 25203records
 
LinkedIn For Job Search Presentation May 2024
LinkedIn For Job Search Presentation May 2024LinkedIn For Job Search Presentation May 2024
LinkedIn For Job Search Presentation May 2024Bruce Bennett
 
如何办理(VIU毕业证书)温哥华岛大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(VIU毕业证书)温哥华岛大学毕业证成绩单本科硕士学位证留信学历认证如何办理(VIU毕业证书)温哥华岛大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(VIU毕业证书)温哥华岛大学毕业证成绩单本科硕士学位证留信学历认证gkyvm
 
b-sc-agri-course-curriculum.pdf for Karnataka state board
b-sc-agri-course-curriculum.pdf for Karnataka state boardb-sc-agri-course-curriculum.pdf for Karnataka state board
b-sc-agri-course-curriculum.pdf for Karnataka state boardramyaul734
 
一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证
一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证
一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证eqaqen
 
Mallu Aunts ℂall Girls Ahmedabad ℂall Us 6378878445 Top ℂlass ℂall Girl Servi...
Mallu Aunts ℂall Girls Ahmedabad ℂall Us 6378878445 Top ℂlass ℂall Girl Servi...Mallu Aunts ℂall Girls Ahmedabad ℂall Us 6378878445 Top ℂlass ℂall Girl Servi...
Mallu Aunts ℂall Girls Ahmedabad ℂall Us 6378878445 Top ℂlass ℂall Girl Servi...anjli garg#k09
 
如何办理(USC毕业证书)南加利福尼亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(USC毕业证书)南加利福尼亚大学毕业证成绩单本科硕士学位证留信学历认证如何办理(USC毕业证书)南加利福尼亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(USC毕业证书)南加利福尼亚大学毕业证成绩单本科硕士学位证留信学历认证gakamzu
 
一比一原版(UCI毕业证)加州大学欧文分校毕业证成绩单学位证留信学历认证
一比一原版(UCI毕业证)加州大学欧文分校毕业证成绩单学位证留信学历认证一比一原版(UCI毕业证)加州大学欧文分校毕业证成绩单学位证留信学历认证
一比一原版(UCI毕业证)加州大学欧文分校毕业证成绩单学位证留信学历认证vflw6bsde
 
Ganga Path Project (marine drive project) Patna ,Bihar .pdf
Ganga Path Project (marine drive project) Patna ,Bihar .pdfGanga Path Project (marine drive project) Patna ,Bihar .pdf
Ganga Path Project (marine drive project) Patna ,Bihar .pdfDeepak15CivilEngg
 

Recently uploaded (20)

Specialize in a MSc within Biomanufacturing, and work part-time as Process En...
Specialize in a MSc within Biomanufacturing, and work part-time as Process En...Specialize in a MSc within Biomanufacturing, and work part-time as Process En...
Specialize in a MSc within Biomanufacturing, and work part-time as Process En...
 
obat aborsi pacitan wa 081336238223 jual obat aborsi cytotec asli di pacitan0...
obat aborsi pacitan wa 081336238223 jual obat aborsi cytotec asli di pacitan0...obat aborsi pacitan wa 081336238223 jual obat aborsi cytotec asli di pacitan0...
obat aborsi pacitan wa 081336238223 jual obat aborsi cytotec asli di pacitan0...
 
UIowa Application Instructions - 2024 Update
UIowa Application Instructions - 2024 UpdateUIowa Application Instructions - 2024 Update
UIowa Application Instructions - 2024 Update
 
如何办理(Columbia毕业证书)哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(Columbia毕业证书)哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证如何办理(Columbia毕业证书)哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(Columbia毕业证书)哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证
 
We’re looking for a junior patent engineer to join our Team!
We’re looking for a junior patent engineer to join our Team!We’re looking for a junior patent engineer to join our Team!
We’re looking for a junior patent engineer to join our Team!
 
Novo Nordisk Kalundborg. We are expanding our manufacturing hub in Kalundborg...
Novo Nordisk Kalundborg. We are expanding our manufacturing hub in Kalundborg...Novo Nordisk Kalundborg. We are expanding our manufacturing hub in Kalundborg...
Novo Nordisk Kalundborg. We are expanding our manufacturing hub in Kalundborg...
 
一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理
 
Fracture design PowerPoint presentations
Fracture design PowerPoint presentationsFracture design PowerPoint presentations
Fracture design PowerPoint presentations
 
B.tech Civil Engineering Major Project by Deepak Kumar ppt.pdf
B.tech Civil Engineering Major Project by Deepak Kumar ppt.pdfB.tech Civil Engineering Major Project by Deepak Kumar ppt.pdf
B.tech Civil Engineering Major Project by Deepak Kumar ppt.pdf
 
Jual obat aborsi Dubai ( 085657271886 ) Cytote pil telat bulan penggugur kand...
Jual obat aborsi Dubai ( 085657271886 ) Cytote pil telat bulan penggugur kand...Jual obat aborsi Dubai ( 085657271886 ) Cytote pil telat bulan penggugur kand...
Jual obat aborsi Dubai ( 085657271886 ) Cytote pil telat bulan penggugur kand...
 
Prest Reed Portfolio revamp Full Sail Presentation 2
Prest Reed Portfolio revamp Full Sail Presentation 2Prest Reed Portfolio revamp Full Sail Presentation 2
Prest Reed Portfolio revamp Full Sail Presentation 2
 
LinkedIn For Job Search Presentation May 2024
LinkedIn For Job Search Presentation May 2024LinkedIn For Job Search Presentation May 2024
LinkedIn For Job Search Presentation May 2024
 
如何办理(VIU毕业证书)温哥华岛大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(VIU毕业证书)温哥华岛大学毕业证成绩单本科硕士学位证留信学历认证如何办理(VIU毕业证书)温哥华岛大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(VIU毕业证书)温哥华岛大学毕业证成绩单本科硕士学位证留信学历认证
 
b-sc-agri-course-curriculum.pdf for Karnataka state board
b-sc-agri-course-curriculum.pdf for Karnataka state boardb-sc-agri-course-curriculum.pdf for Karnataka state board
b-sc-agri-course-curriculum.pdf for Karnataka state board
 
一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证
一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证
一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证
 
Mallu Aunts ℂall Girls Ahmedabad ℂall Us 6378878445 Top ℂlass ℂall Girl Servi...
Mallu Aunts ℂall Girls Ahmedabad ℂall Us 6378878445 Top ℂlass ℂall Girl Servi...Mallu Aunts ℂall Girls Ahmedabad ℂall Us 6378878445 Top ℂlass ℂall Girl Servi...
Mallu Aunts ℂall Girls Ahmedabad ℂall Us 6378878445 Top ℂlass ℂall Girl Servi...
 
如何办理(USC毕业证书)南加利福尼亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(USC毕业证书)南加利福尼亚大学毕业证成绩单本科硕士学位证留信学历认证如何办理(USC毕业证书)南加利福尼亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(USC毕业证书)南加利福尼亚大学毕业证成绩单本科硕士学位证留信学历认证
 
一比一原版(UCI毕业证)加州大学欧文分校毕业证成绩单学位证留信学历认证
一比一原版(UCI毕业证)加州大学欧文分校毕业证成绩单学位证留信学历认证一比一原版(UCI毕业证)加州大学欧文分校毕业证成绩单学位证留信学历认证
一比一原版(UCI毕业证)加州大学欧文分校毕业证成绩单学位证留信学历认证
 
Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)
Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)
Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)
 
Ganga Path Project (marine drive project) Patna ,Bihar .pdf
Ganga Path Project (marine drive project) Patna ,Bihar .pdfGanga Path Project (marine drive project) Patna ,Bihar .pdf
Ganga Path Project (marine drive project) Patna ,Bihar .pdf
 

329. Khadka, Strategic Environment Assessment of National Water Plan of Nepal.ppt

  • 1. Strategic Environmental Assessment of National Water Plan, Nepal BY Ram B. Khadka
  • 2. Nepal: An Introduction Location: Nepal is the Himalayan Kingdom known as the Land of the Mt. Everest and the birthplace of Lord Buddha. The country is situated in South Asia, bordered on the north by China and on the south, west and east by India.
  • 3. Nepal: General Information Topographical Features: Nepal is a mountainous country with the Himalayan belt in the north, the hilly region and fertile valleys in the Middle and the narrow strip of plain in the South, all running parallel to each other from East to West. Climate: The country has diverse climatic conditions. It is generally cold in the mountainous region, mild weather in the hills, and warm in the plains. Rainfall: 1,500 -2,500mm (average) Capital: Kathmandu, a historical city with rich cultural heritage is Nepal's capital with 1.5 million population.
  • 4.
  • 5. Background information • 6000 Rivers, mostly trans-Himalayan and snow –fed • Drain 194,471 km2 • 225 billion cubic liters of water is available Annually • 15 billion cubic liters of water have been utilized so far
  • 6. Background information • 72 percent of population have an access to water supply • 25 percent have access to sanitation facility • 0.76 million ha of agriculture land have been irrigated • Hydropower development potential is 83000MW, at present only 619MW has been generated.
  • 7. Background information • Water is one of the major natural resources for economic development • Inspite of many efforts made in the past water resource development is slow, • In order to make water resource development comprehensive, systematized and accelerate the process of development, Government of Nepal issued Water Resource Strategy in 2002.
  • 8. Water Resource Strategy (WRS) for Nepal WRS contains following 10 action programs: • management water-Induced disaster • management of watershed and aquatic ecosystem • domestic water supply and sanitation • Irrigation facilities for agriculture • development of hydropower for electricity • water-based cultural, recreational, and eco-tourism activities • amendment the existing water resource policy and legal framework • water-related information systems • development of regional and bi-lateral co-operation and • revision and modification of exsisting institutional procedural mechanism.
  • 9. National Water Plan for Nepal (NWP) In order to operationalize WRS of Nepal, a National Water Plan was developed and endorsed by the government (2005).The following are the action programs contained in the NWP The implementation of NWP activities is to take place within the time frame of 5,15 and 20 years.
  • 10. National Water Plan (NWP) Contd. • Management of major types of water induced disasters • Improvement of water Quality and watersheds • Provide safe drinking water to 100% people of Nepal • Provide irrigation facilities to 100% arable land
  • 11. National Water Plan (NWP) Contd. • Develop 4000MW of hydropower • Provide water to 100% industry, navigation and tourism • Enhance inland fisheries and increase the production to 87000 MT per year • Establish hydrometric stations to 370 at strategic places and disseminate the information
  • 12. National Water Plan (NWP) Contd • Establish regional cooperation for water sharing fully • Revise and refine the existing legal framework, develop policies, guidelines, norms and standards. • Restructure administrative institutions revise and improve administrative mechanism.
  • 13. Application of SEA in NWP • No legal requirement for SEA in Nepal • Water Energy Commission of Nepal decided to apply SEA in NWP voluntarily to make plan environmentally sound and sustainable. • SEA was carried out based on secondary sources of Information and an extensive public consultation with some field verification. • Followed screening, scoping, baseline information collection, impact identification and prediction, mitigation measures and environmental management plan.
  • 14. Application of SEA in NWP • Stakeholders consultation at different stages • Use of internationally recognized checklist, interaction matrix, and Impact summary matrix (Saddler and Verheem, 1996). • Issues identified in scoping were classified into i physical, ii biological iii socio- economic/cultural and iv legal and institutional components.
  • 15. Issue Analysis and Prediction NWP was examined whether, • Issues were addressed in NWP • Assessment of the status of issues included • Mitigation measures are provided Physical Issues • Downstream release of water, submerging of large amount of farmland, water logging, extraction of ground water-lowering of water level • Formation of new flood plain • Water pollution due to chemical fertilizer and pesticides • No Measures are mentioned in policies, guidelines and no standards
  • 16. Issue Analysis and Prediction Biological Issues: effect on; • Forest, flora, animals both aquatic and Terrestrials • Protected areas, wild animal habitat, • Destruction of biodiversity • Effect on fish and fisheries • Production of Green House Gas (GHG) • Downstream Pollution
  • 17. Issue Analysis and Prediction Socio-Economic/Cultural Issue • employment opportunity, • local market development, • reduced drudgery in women and children, • skilled manpower development, • gender, • enhancement of local organizations. • land acquisition, • displacement, and resettlement, • cultural malpractices, and pressure on social services
  • 18. Issue Analysis and Prediction Legal and Institutional Component Policy conflict No coordination Improper legal framework ineffective in Implementation No water quality standards, no code of conduct, No waste water treatment commitment The private sector projects are operating well The government sector projects do not function properly because of the financial limitation imposed by finance act No comprehensive legislation
  • 19. Mitigation Measures /Alternative Options Mitigation measures at strategic level can involves: • rewriting the strategic actions to minimize negative environmental effects and enhance the beneficial one, • establishing management guidelines for implementing strategic action, • shifting responsibility to lower tier of strategic action or in project level, and • no action alternative.
  • 20. Mitigation Measures /Alternative Options Physical Components • Maintaining water flow down stream : release of 10% dry period flow plus existing water requirement in downstream. • Downstream Water Pollution and Groundwater Quality ; Standards and policy guidelines • Use of Inundated Upland Fields and Forest • Cloud Burst, Glacial Lake Outburst Flood, • and Landslide Dam Flood; Minimization • Erosions, Landslides, and Sedimentation: minimization • Lowering of Ground Water ;Policy guidelines • Water logging and Soil Modification; Policy guidelines
  • 21. Mitigation Measures /Alternative Options Forest Vegetation and Wild animals; • Forest and Vegetation; Policy guidelines and standards • Wildlife and Biodiversity; • Protected Areas; • Aquatic flora and Fauna
  • 22. Mitigation Measures /Alternative Options Socio-economic and Cultural Issues ;Mostly to be addressed by issuing of policy guidelines, directives, standards, and implementation guidelines • Employment Opportunities; • Economic Activities • Local Market Development Market • Skilled manpower development; • Reduce Drudgery to Women and Children • Cultural Practice; • Land Acquisition, Displacement and Resettlement • Pressure on Social Service • Gender Issue
  • 23. Mitigation Measures /Alternative Options Legal and Institutional Component • Comprehensive National Water Resource Policy • Action Plans for Water resource and Environment Laws • Legal Regime for Ground Water Management • Pollution Standards for Enforcement of Environment • Protection Act • Strengthen Community-Based Water User Organizations
  • 24. Environmental Management Plan (EMP) • rewriting, strategy and Action Plans, development of policy guidelines for implementation of directives to project-level implementations are the key strategic mitigation prescriptions. • EMP of National Water Plan should examine whether the issues are addressed and the corresponding gaps are identified. • In SEA of NWP strategic EMP parameters on physical, biological, socio-economic, and cultural components of the environment have been identified and recommendation should be made to apply in project level activities • The second part in EMP is to monitor the implementation of mitigation prescriptions. Monitoring such as (i) baseline (ii) impact and (iii) compliance monitoring are applicable to strategic actions.
  • 25. Conclusion and Recommendation Analysis has been carried out for the consideration of in the upper tier of decision-making. The key environmental issues identified were: • downstream release of water and water use right, • inundation, • downstream and ground water pollution, • issues on the loss of forests and wildlife, both aquatic and terrestrial, • issues on boom and bust cycle related to workforce, • land acquisition displacement and resettlement, and • ineffective environmental laws, regulations, and standards and institutions related to water resource development. • Issues on human resource development and employment opportunity.
  • 26. Conclusion and Recommendation Minimization of the adverse issues and enhancement of beneficial issues of NWP implementation at the Strategic Level are: • revising and modification of existing system of legal framework, • revising and writing of water resource development policies, Plans and programs, and • Issuing policy guidelines, standards, norms, reforming existing institutional and procedural aspects, etc. THANK YOU